19-JMS - Installation Cable Tray or Cable Ladder and Support Installatio...

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 10

Doc. No.

P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

TITLE:
CABLE TRAY OR CABLE LADDER AND
SUPPORT INSTALLATION

1 22.06.17 MSY KKH MSI FINAL ISSUE

0 21-06-17 MSY KKH MSI ISSUE FOR AUTHORITY SUBMISSION

DPSSB DPSSB LGT-2


rev Date Description
Prepared by Reviewed by Approved by

This document and the information herein describe the company practices and are for internal use only. It shall not be
reproduced in whole or in parts or released to a third party without prior written consent from the approving
authority
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

TABLE OF CONTENTS

Item Description

1.0 SCOPE OF WORK AND DESCRIPTION

2.0 JOB METHOD AND SEQUENCE(LGT-2 And Jetty Area)

3.0 SAFETY PRECAUTION – (REFER TO HIRADC)

4.0 EQUIPMENT AND TOOLS

5.0 ACCESS AND EGRESS ROUTES

6.0 FALL PROTECTION MEASURES

7.0 OTHER ESSENTIAL TOOLS

8.0 HAZARDOUS SUBSTANCES

9.0 SPECIAL TRAINING REQUIREMENT

10.0 SAFE WORKING LOAD-Not Aplicable

11.0 PERSONAL PROTECTIVE EQUIPMENT (PPE)

12.0 MANPOWER

13.0 SAFETY CONCERNS

14.0 ATTACHMENTS

1. SCOPE OF WORK

The purpose of this job method statement is to establish the safe work method for Cable tray
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

or cable ladder and support installation, support and accessories works along the pipeline
structure for the EPCC of 24 inch pipeline extension from LgT-2 to LgT-1 pipe rack T-
junction. Refer figure 1 And Figure 2 for work location.

Date of work : 15th August 2017 – 01th October 2017


Description : Cable tray or cable ladder and support installation
Location : Lgt-2,Berth 1 And Berth-5 To Berth 8

Figure 1
Lgt-2
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

Figure 2
Berth-1,Berth 5 To Berth 8

2. JOB METHOD STATEMENT AND SEQUENCE

LGT-2 Area -

2.1 Apply the PTW prior to start work.

2.2 Mobilization of material,handtool and equipment

2.3 Determine the support installation location agains drawing

2.4 Install support of cable ladder with hot work(Welding)

2.5 New cable ladder and trays will be installed in accordance with the layout
drawings.

2.6 As far as possible cable ladders and trays will be fully accessible from at least one
side along the complete route length.
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

2.7 Manufacturer’s standard items will be used for changes of direction and elevation
of runs. Where items are unobtainable and fabrication on site is necessary, the
quality will not be less than that required for manufactured items.

2.8 Cable link ladder system will be installed to ensure electrical earth continuity
throughout the run.

2.9 Supports for horizontal cable ladders and trays will be spaced according to the type
and width of cables and trays and weight of cables run on it.

2.10 Supports for vertical cable ladders and trays will be spaced at approximately 1
meter intervals.

2.11 Cable ladders will be bolted or clamped to support.

2.12 Install all the accessories, earth cable and cover of the new cable ladder.

2.13 Where any treated or coated material is cut, or drilled the exposed surfaces will be
treated immediately with zinc primer and epoxy topcoat.

2.14 Care will be taken to ensure that water will not collect or remain in any part of the
cable ladder system.

2.15 Site inspection and housekeeping are carried out to ensure conformance of the
installation work.

2.16 Inform to LGT project owner when work completed and closed PTW.

Jetty Area-

2.17 Apply the PTW prior to start work.

2.18 Mobilization of material,handtool and equipment

2.19 Determine the support installation location agains drawing

2.20 Install support of cable ladder with hot work(Welding)

2.21 New cable ladder and trays will be installed in accordance with the layout
drawings.

2.22 As far as possible cable ladders and trays will be fully accessible from at least one
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

side along the complete route length.

2.23 Manufacturer’s standard items will be used for changes of direction and elevation
of runs. Where items are unobtainable and fabrication on site is necessary, the
quality will not be less than that required for manufactured items.

2.24 Cable link ladder system will be installed to ensure electrical earth continuity
throughout the run.

2.25 Supports for horizontal cable ladders and trays will be spaced according to the type
and width of cables and trays and weight of cables run on it.

2.26 Supports for vertical cable ladders and trays will be spaced at approximately 1
meter intervals.

2.27 Cable ladders will be bolted or clamped to support.

2.28 Install all the accessories, earth cable and cover of the new cable ladder.

2.29 Where any treated or coated material is cut, or drilled the exposed surfaces will be
treated immediately with zinc primer and epoxy topcoat.

2.30 Care will be taken to ensure that water will not collect or remain in any part of the
cable ladder system.

2.31 Site inspection and housekeeping are carried out to ensure conformance of the
installation work.

2.32 Inform to LGT project owner when work completed and closed PTW.

3. SAFETY PRECAUTION

3.1 PPE
a. All workers shall wear proper PPE such as white color safety helmet, safety glass and
safety shoes at all time.
b. Only double lanyard safety harness is allowed. Use of safety belt is prohibited.
c. All workers shall wear the life jacket while work at jetty area.

3.2 Communication
a. Pre briefing shall in form of daily tool box and pre task meeting
b. All contractor will provide with own radio communication to ensure all parties are
well communicated, especially when working at height at pipe rack over than 2 m
height.
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

3.3 Environment
a. Work at height shall be stop/suspend upon confirmation with the Project Owner if
weather conditions, such as heavy rain, haze or glaze will impact the visibility.

3.4 Protection against falling materials/object


a. When working at height at the pipe rack, protection shall be made against falling
materials, such as hand tools, cable tray, etc.
 Close or barricade the area during work.

3.5 General safety measures


a. Report any incident or near-miss to LgT-1 HSSEQ personnel.
b. Daily safety toolbox to be executed before start any work.
c. Risk assessment (HIRADC) shall be reviewed and approved before start any work.
d. Daily permit to work (PTW) to be obtained and approved.

4. EQUIPMENT AND TOOLS

a. Non-spark hand tools


b. Rope

5. ACCESS AND EGRESS ROUTE

The Cable tray or cable ladder and support installation are being carried out at LgT-2 And
Berth 8. Refer to Figure 3 and 4 below for the access and egress location of work.
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

Figure 3
LGT-2

Figure 4
Berth 1 And Berth 5 To Berth 8
Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

6. FALL PROTECTION MEASURES

Working at height at the pipe rack shall wear double lanyard safety harness. No safety belt is
allowed to be used for this work.

7. OTHER ESSENTIAL TOOLS

Not applicable for this type of work.

8. HAZARDOUS SUBSTANCES – MSDS attached

Chemicals: Not Applicable

9. SPECIFIC TRAINING REQUIRED

Working at height (WAH)

10. SAFE WORKING LOAD

Not applicable for the type of work.

11. PERSONA PROTECTIVE EQUIPMENT (PPE)

Additional PPE required: Double lanyard safety harness


Doc. No. P17385-LGT2-JMS-019
JOB METHOD STATEMENT Rev. No.
Date
0
15 August 2017
(JMS) Project EPCC of 24 Inch Pipeline
Extension from LgT-2 to Berth 8

12. MANPOWER

12.1 Site Supervisor


12.2 Site Safety Supervisor (SSS)
12.3 Work Leader
12.4 Workers

13. SAFETY CONERN - Highlighted and analyzed in HIRADC

13.1 Working at height


13.2 Falling of cable tray or materials onto the working area
13.3 Vehicles movement
13.4 Finger injury
13.5 Ergonomics – poor body posture
13.6 Slip, trip and fall
13.7 Dehydration
13.8 Strong wind
13.9 Uncertain weather condition
13.10 Fall to sea (Working at jetty area)

14. ATTACHMENT

Risk assessment form (HIRADC)

You might also like