Professional Documents
Culture Documents
TPPRD104 Installation Instruction
TPPRD104 Installation Instruction
, LTD
全自动数控冲床安装简述
Instruction of installation for plate punching machine
1. 1 地基 Foundation
根据厂家提供地基图做好地基 Make the foundation according to the foundation drawing provide by the seller.
示例 Case 1
1
SHANDONG SUNRISE CNC MACHINE CO., LTD
示例 Case 2
2
SHANDONG SUNRISE CNC MACHINE CO., LTD
1.2 设备安装需求准备 Installation requirements before install the machine:
Installation Preparation
1. Installation time required for one set punching machine: 2-4 days.
1.1 The buyer should make ready foundation of machine according to the foundation drawing sent from our
side. Please note, the foundation base plates for machine are not supplied by us. The buyer should make
1.2 Number 46# anti-wearing hydraulic oil, appx. 800L for angle line.
1.3 Oil filter is required before infuse oil into hydraulic oil tank.
1.4 Power supply and incoming line should be 50Hz, 380V, three phase. The coming line can be cable or
1.5 Air supply is required the air compressor also required for machine.
2.1 Two operators, one maintainer. Arrange some people to accept training. They have to stay with our
It is better that the people who accept training can know computer and electrical knowledge.
If the temperature of oil is too high, density of the oil becomes smaller, and affecting normal operation of
machine, and even causing oil leakage, so the oil need cooling device, the best way of cooling for oil is
water cooling, client just need to weld one water tank (size about: 2x1.5x1.8m, this size just for reference,
picture as below:), when you welded the water tank, buy one pump (Requirements of the pump: power
more than 0.5KW, pump head 10m, if bigger it’s better, picture for reference as below:)
3
SHANDONG SUNRISE CNC MACHINE CO., LTD
Our machine need air pressure, so in client’s factory need the air compressor, requirements for our machine
of air compressor: pressure 0.8Mpa, capacity 1m³, this is ok, if bigger, will be better. Picture for reference
as below
4
SHANDONG SUNRISE CNC MACHINE CO., LTD
二.客户现场安装 Installation in customer’s site:
除去各部分包装,按设备标牌指示逐一吊装放到已做好的基础上面,并检查各部分是否完好。
Take off all packaging and put all main parts on top of ready foundation and make sure all parts complement and
in good condition.
2.1.1 把主机放到已做好的地基上,用框式水平仪放到主机冲孔缸上方,调整主机前后左右水平,水平高度与工作
台高度相对应。
2.1.1 Put the machine host to the foundation, put the frame level to the top of punching cylinder, adjust the Before,
After, Right and Left level of the host. The level of the host should correspond to work table height.
5
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.2 工作台安装 Installation of worktable.
2.2.1 对接工作台,如下图。先插入定位销,然后将螺丝轻微压紧,把框式水平仪放到直线导轨上调节工作台水平,
高度与主机部分相对应。
Second, Then tighten the screws slightly (Promise the between two connections plates no gap);
Third, put the frame level to the linear guides, adjust the level of worktable. The level of work table height should
Last, fasten the connection screws, and the base plates bolts (At this time, the base plates are in a stressed
state).
6
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.2.2. Adjust the base plates and bolts. After installation, all the base plates and bolts are in a stressed state, can’t
overhead.
2.2.3. If all prepared, weld the base plates to the foundation plates:
7
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.3 动力头安装 Installation of Power head
吊起动力头,插入定位销,拧紧固定螺母
Lift the power head, insert the locating pin and tighten the fixing nut
8
SHANDONG SUNRISE CNC MACHINE CO., LTD
9
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.4.3 根据编号连接油管(标号 1、2、3)Connect oil pipe of Clamp device(Marking No. 1, No. 2, No. 3)
1 号油管控制夹钳 No. 1 control clamp
2 跟 3 号油管控制侧挡料 No. 2 & 3 control
10
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.4. 4 主轴油管(一长一短,长油管接顶端 1,短油管接下端 2)Connect oil pipe of spindle
One long pipe is for No. 1, one short pipe is for No. 2
11
SHANDONG SUNRISE CNC MACHINE CO., LTD
12
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.5 电气部分 Electric connection: According to electric diagram.
13
SHANDONG SUNRISE CNC MACHINE CO., LTD
14
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.5.5 连接 X 轴驱动器电线(两股),原理同 Y 轴一样;电线位置,跟 2 号分线盒一起缠绕在操作按钮上
Connect the X-axis drive wire (two strands), the principle is the same as the Y-axis; the wires shall be wrapped on the
operation button together with the No. 2 junction box
2.5.6 根据线号,连接润滑泵电线;电线位置,缠绕在通润滑泵上
Connect the lubricating pump wire according to the wire number; the wire is wound on the lubricating pump
15
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.5.8 根据线号,连接空调电线(2 根)
Connect the air conditioner wire (2 pieces) according to the wire number
2.5.9 根据标号,连接电气柜外部三大分线盒,
Connect the three external junction boxes(No. 1, No. 2, No. 3) of the electrical cabinet.
16
SHANDONG SUNRISE CNC MACHINE CO., LTD
1 号冲孔缸分线盒 No. 1 Connect punch cylinder junction box
2 号工作台分线盒(注意,安装时需要从主机上方穿入)No.2 Connect worktable junction box(Note: this wire shall be
threaded in from above the host machine during installation )
3 号液压分线盒 No. 3 Connect hydraulic junction box
17
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.5.10 安装主轴圆柱开关(2 个),2 代表侧,1 代表下。 下为工进开关,需要准确调节其位置(开关顶端与支撑板
顶端位置距离为 15mm), 侧为原点开关(开关顶端与支撑板顶端位置距离为 3-5mm);
Install cylinder switches (2pcs) of the spindle, No. 2 for side, No. 1 for bottom. The bottom part(No. 1) is the working
switch, which needs to be adjusted accurately (the distance between the top of the switch and the top of the support plate
is 15mm), and the side part(No. 2) is the origin switch (the distance between the top of the switch and the top of the
support plate is 15mm);
18
SHANDONG SUNRISE CNC MACHINE CO., LTD
2.5.11 接车间总电源 Workshop power supply
19