Professional Documents
Culture Documents
Cepm Module1 PPT
Cepm Module1 PPT
Leading
Controlling Planning
Staffing Organizing
8
INTRODUCTION
• Construction from dawn of civilization
CONSTRUCTION PROJECT
• A project is a temporary endeavour designed to produce a
unique product, service with a defined beginning and ending
Idea / Project
Feasibility
Initiation Concept
Phase
Phase Phase
• Conceptual
• Project Strategy
• Estimate and
Approval
15
(b)Project Concepts
• As many project concepts as possible are identified and using
some selection procedure, some concepts are selected
• Greatest degree of uncertainty about the future is encountered
• Selected ones used as inputs for the feasibility phase
16
(c)Feasibility
• Aims to analytically appraise project concepts in the context of
the organization
• Decision makers decide whether or not to go ahead with the
project concept
• Market feasibility, technical feasibility, environmental
feasibility and environmental feasibility
PROJECT PHASE
(c)Tendering phase
• Includes preparing specifications and agreement conditions,
preparing bill of quantities and estimating the contract value
19
(a)Utilization Phase
• Client makes use of the finished project
• Performance is monitored and maintenance provided at
regular intervals
Objectives of DPR :
• Should be with sufficient details to indicate the possible fate of
the project when implemented
Contract Design
Utilization and
Construction /
maintenance
Execution
26
CONSTRCUTION PLANNING
• Plans simply list the goals (events) and define the means of
achieving them (activities)
• Process of determining what is to be done, where, when and by
whom
• Plan should be flexible, realistic, basis for project monitoring
and control, provide information in a readily understandable
form
• Schedule, cost, quality and safety – success of a construction
project is evaluated
29
(b)Manpower Plan
• Focuses on estimating the size of workforce, division in
functional teams and scheduling the deployment of manpower
(c)Material Plan
• Involves identification of required materials, estimation of
required quantities, procurement plans and monitoring the
usage
31
BAR CHARTS
• Graphical representation of a project with its duration of tasks
against the progression of time
NETWORK METHODS
• Outcome of improvements in Gantt and Milestone charts
Elements of Network
• Network is a flow diagram consisting of activities and
events connected logically and sequentially
• Activities : Breaking up the entire project into a number
of distinct, well defined jobs or tasks (represented by
arrows)
• Events : Beginning and ending of an activity (represented
by circles)
43
EVENT
• Particular instant of time at which some specific part of a
plan has been or is to be achieved
• Completion or commencement of an activity
• Act as control points in a project
• Does not consume any time or resources
• TAIL EVENT
• HEAD EVENT
• DUAL ROLE EVENT
44
(b)Predecessor events
➢ The event that occurs before another event
➢ Event that immediately come before another event
without any intervening ones : Immediate Predecessor
49
CEPM / MOD 1 / CE /
SJCET / austin
50
ACTIVITY
• Actual performance of a task
• Consumes time and resources
• Represented by arrows in network diagrams
• Not a vector quantity
51
Predecessor activity
• Activity required to be performed before another activity /
job can begin
• Immediate predecessor
Successor activity
• Activity to be performed after the performance of another
activity
• Immediate successor
53
CEPM / MOD 1 / CE /
SJCET / austin
54
CEPM / MOD 1 / CE /
SJCET / austin
55
CEPM / MOD 1 / CE /
SJCET / austin
57
CEPM / MOD 1 / CE /
SJCET / austin
Common Situations
58
• Construction projects
62
CEPM / MOD 1 / CE /
SJCET / austin
63
FREQUENCY DISTRIBUTION
• Curve plotted between time of completion and number
of jobs completed
66
• If more than one activity paths leads to that event, then the
maximum of the sum of tE’s along the various paths will
give the Earliest Expected Time
CEPM / MOD 1 / CE /
SJCET / austin
77
SLACK
• Difference between the latest allowable time and earliest
expected time of an event
S = TL – TE “TIME TO SPARE”
POSITIVE SLACK
• TL is more than TE for an event (excess resources)
ZERO SLACK
• TL is equal to TE (adequate resources)
NEGATIVE SLACK
• TS (hence TL ) is less than TE (lack of resources)
78
CRITICAL PATH
• Longest path (time wise) connecting the initial and end
event
• Path which connects the events having zero or minimum
slack times
• Events are critical that any delay in their occurrence will
result in the delay in the scheduled completion of project
80
CEPM / MOD 1 / CE /
SJCET / austin
81
STEP 2
• Knowing the scheduled time of completion (Ts) and the
earliest expected time of completion (TE), find the time
distance (slack) in terms of Probability Factor Z :
Step 3
• Find % probability with respect to the Probability factor
82
CEPM / MOD 1 / CE /
SJCET / austin
83
CEPM / MOD 1 / CE /
SJCET / austin
87
CEPM / MOD 1 / CE /
SJCET / austin
89
FLOAT
• Associated with activity times and analogous to slack
TOTAL FLOAT
• Difference between maximum time available and the
actual time required
• Total Float = LST – EST
FREE FLOAT
• Positive total float used by an activity without delaying
the succeeding activity
93
CEPM / MOD 1 / CE / SJCET / austin
INDEPENDENT FLOAT
• Excess time that exists if the preceding activity ends as
late as possible and succeeding activity starts as early
as possible
• Minimum available time over the required activity
duration
INTERFERING FLOAT
• Difference between total float and free float
94
CRITICAL PATH
• Longest path through the network and time along this
path gives the project duration
CEPM / MOD 1 / CE /
SJCET / austin