Chen Et Al. - 2018 - Thermal Monitoring and Analysis of The Large-Scale

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

Environ Monit Assess (2018) 190:483

https://doi.org/10.1007/s10661-018-6869-y

Thermal monitoring and analysis of the large-scale field


earth-dam breach process
Chien-Yuan Chen & Su-Chin Chen & Kuan-Hua Chen &
Zhe-Ho Liu

Received: 6 April 2018 / Accepted: 12 July 2018


# Springer Nature Switzerland AG 2018

Abstract Thermal imaging is a nondestructive testing modes of dams. Dam surfaces with large temperature
method for monitoring internal material changes that are variations may be potential failure areas. If confirmed,
indicated by changes in an object’s surface temperature. this fact may prove useful for failure-mode prediction.
In this study, field observation using thermographs was This paper proposes a monitoring index to reflect the
applied to monitor and analyze the breach process of temperature changes in a given period, and this study
large-scale earth dams. The earth dam test site was verified it empirically.
Landao Creek in Nantou County, Taiwan. Four field
tests were performed to monitor and analyze a single Keywords Infrared thermography . Earth dam .
earth dam and two successive earth dams. Ponding first Monitoring . Field test
occurred at the lowland of the riverbed upstream, and
base seepage occurred at the base of the dam down-
stream; overtopping failure soon followed. Earth-dam
Introduction
failure mode is affected by the topographic characteris-
tics of the riverbed; specifically, lowland areas are prone
Infrared thermal imaging, based on Planck’s blackbody
to ponding upstream, which causes piping and seepage
radiation law (Planck 1901), involves detecting an object’s
downstream as well as subsequent breaches. Ponding
thermographic projection and converting it into a digital
and piping cause water seepage and soil wetting, which
thermogram. Thermal imaging is a noncontact and nonde-
are reflected in lower surface temperatures recorded on
structive screening technique that can quickly detect the
thermographs. Thermographs can monitor changes in
surface-radiation temperature of objects. Temperature can
surface temperature to evaluate the potential failure
be easily identified from colorful thermal images.
Thermal imaging was first used for military applica-
Electronic supplementary material The online version of this tions. It has been extended to daily uses such as machine
article (https://doi.org/10.1007/s10661-018-6869-y) contains maintenance (Boglietti et al. 2009) and medical moni-
supplementary material, which is available to authorized users. toring (Janssens et al. 2017). Thermal imagers can con-
duct nondestructive surface detection quickly for a large
C.<Y. Chen (*) : K.<H. Chen : Z.<H. Liu
Department of Water and Resources Engineering, National Chiayi
area. They have the camera-like advantage of effective
University, 60004 Chiayi City, Taiwan, Republic of China use at a distance and facilitate both long-term monitor-
e-mail: chienyuc@mail.ncyu.edu.tw ing and short-term inspection of surface-temperature
changes. Thermal imaging has been used to monitor
S.<C. Chen
Department of Soil and Water Conservation, National
landslides (Frodella et al. 2014; Martino and Mazzanti
Chung-Hsing University, 402 Taichung City, Taiwan, Republic of 2014; Mineo et al. 2015) and to map tunnel discontinu-
China ity (Barla et al. 2016).
483 Page 2 of 17 Environ Monit Assess (2018) 190:483

Fig. 1 Location of the earth-dam


field tests at Landao Creek in
Nantou County, Taiwan (Image
taken on 5 October, 2015 by
Google Earth)

Surface-temperature changes reflect the interior con- 1. Overtopping failure


struction quality of spray concrete-protected slopes (Wu
et al. 2005). Thermal images taken in the field show that Overtopping failure occurs in dams with low perme-
surface-temperature changes are larger in hollow areas ability, high shear strength, and large upstream dis-
than in solid areas. Hollow areas can be detected by charge. Water velocity becomes excessively fast, wet-
subtracting the lowest temperature from the highest ting the front dam material; the water level increases,
temperature recorded through thermal imaging. This is overtopping occurs, and the dam subsequently fails
because hollow-area temperatures fluctuate more than through progressive erosion.
those in structurally robust areas after sun exposure. The
existence of hollow areas inside spray concrete- 2. Slope failure
protected slopes can be detected and monitored using
thermal images from different periods. Thermal images Slope failure occurs in dams with high permeability
can be employed to quickly evaluate rock, crack, and and low shear strength. The ponding water level in-
rockfall distribution over a large area (Baroň et al. 2012; creases with water from upstream, and the flow overtops
Gigli et al. 2014; Teza et al. 2015). the dam before the wetting front of the phreatic line
Evaluation of natural-dam stability is necessary for reaches the downstream slope face.
dam breach disaster prevention and mitigation. Natural-
dam formation is dictated by topographic and geologic 3. Progressive erosion failure
conditions. A natural-dam breach can bury buildings
beneath the slope, and secondary effects are caused by Progressive erosion failure occurs when the soil
ponding upstream and flooding downstream. An exam- has higher permeability and weaker shear strength
ple is Xiaolin (Shaolin) Village in Taiwan (Lo et al. than those in either of the previously mentioned
2011; Feng 2012; Wu et al. 2014). Most natural dams failure modes. The rising ponding water level in-
are created by rainfall- and earthquake-induced failure creases with water from upstream, and the flow
of bank slopes as well as the subsequent landslides and overtops the dam before the wetting front of the
debris flows that block rivers. In 2009, Typhoon phreatic line reaches the downstream slope face.
Morakot created 18 landslide dams (Forest Bureau The piping-induced surface-water flow erodes the
2009), which are difficult to reach to perform stability slope toe downstream, causing small landslides and
analysis. Nondestructive detection at a suitable distance finally breaching the dam.
for preliminary evaluation of stability and potential fail-
ure modes could help in preventing and mitigating dam- 4. Complex failure
breach disasters.
The failure modes of natural dams include the fol- This failure mode combines two or three of the other
lowing (Schuster 1986; Chai et al. 2000; Korup 2005): failure modes.
Environ Monit Assess (2018) 190:483 Page 3 of 17 483

Table 1 Dimensions and purposes of artificial trapezoidal earth dams

Test date Downstream Upstream Purposes

26 September, 2012 Height = 2.5 m None Failure-mode monitoring


Top width = 2 m
Length = 27 m
Side slope = 45°
Volume = 300 m3
Capacity = 855 m3
Riverbed slope = 7°
16 October, 2012 Height = 2.5 m Height = 2 m Failure-mode monitoring under
Top width = 2 m Top width = 2 m flash flood (induced by dam breach)
Length = 27 m Length = 15.5 m
Side slope = 45° Side slope = 45°
Volume = 300 m3 Volume = 125 m3
Capacity = 855 m3 Capacity = 207 m3
Riverbed slope = 7° Riverbed slope = 7°
7 November, 2012 Height = 2.5 m Height = 2 m Comparisons
Top width = 2 m Top width = 2 m
Length = 27 m Length = 15.5 m
Side slope = 45° Side slope = 45°
Volume = 300 m3 Volume = 125 m3
Capacity = 855 m3 Capacity = 207 m3
Riverbed slope = 7° Riverbed slope = 7°
10 April, 2014 Height = 2.5 ma None Monitoring-index verification
Top width = 2 m
Length = 27 m
Side slope = 45o
Volume = 300 m3
Capacity = 855 m3
Riverbed slope = 7°
a
Lower elevation in the middle

Fig. 2 Average surface-


temperature changes of earth
materials over time (Chen and
Chen 2014)
483 Page 4 of 17 Environ Monit Assess (2018) 190:483

Fig. 3 Artificial earth dam and corresponding thermal images. a, b Piping area in the downstream dam (September 21, 2012); the arrow
highlights the piping area. c, d 08:22 on the day of the test (September 26, 2012); the arrow highlights the ponding area

More than half of natural dams are breached through Dam breaches have proved dangerous to downstream
overflow erosion (Korup 2005); some natural dams have residents and can inundate the upstream reaches during
been breached through piping and slope failure in Taiwan ponding. Earth embankment failures result from a combi-
(Chen and Hsu 2009). The failure modes of natural dams nation of flooding, hydraulic weakness, and geotechnical
are determined by the dam material, soil shear strength, weakness. Weakness of the embankment induced by
soil permeability, and discharge conditions of source water flooding and seepage is a neglected source of hazards
upstream (Chen 1999). A series of model tests enhanced (Polemio and Lollino 2011). The lifetime of natural dams
the understanding of the earth-dam breach process (Chen from formation to breach is generally short and just over
et al. 2015a), but real-scale field tests remain scant. 0.01 day at minimum (Korup 2004). Most natural dams are
Various methodologies are used to monitor the inaccessibly high and dangerous, and short emergency-
surface and internal erosion of natural dams, includ- response times are necessary to prevent disaster. A noncon-
ing nonintrusive geophysical techniques (Lum and tact, long-distance, nondestructive method of evaluating
Sheffer 2005; Lin et al. 2013; Lai et al. 2014), visual natural-dam stability could mitigate dam-breach disasters.
observation (Moffat et al. 2011), and passive seismic
interferometry using ambient seismic noise (Planes
et al. 2016). Using fiber optic-distributed tempera- Study area and methodology
ture sensing (Bersan et al. 2018) in dams proved
effective for detecting leakages and internal erosion The test site was Landao Creek at Huisun Forest Farm in
(Cuong et al. 2017). Nantou County, Taiwan (Fig. 1). Landao Creek is a branch
Environ Monit Assess (2018) 190:483 Page 5 of 17 483

(a) (b)

(c) (d)

(e) (f)

Fig. 4 Dam breach process during the test on September 26, ponding side; the arrows highlight the discharge overtopped areas.
2012. a, b At 9:36, base seepage and piping occurred at the e, f At 9:57, the dam was breached in the middle and on the initial
downstream face; the arrows highlight the piping area. c, d At ponding side; the arrows highlight the dam breached areas
9:55, discharge overtopped the dam in the middle and on the initial

of the Peikong Stream in the upper stream of the Wuxi that involved observing the downstream inundation area
River. Its watershed area is 536.33 km2. The test is the first following breach. Landao Creek is prone to debris flow,
earth-dam breach test with adjustable upstream discharge with a length of 2792 m and a basin slope of between 44°
483 Page 6 of 17 Environ Monit Assess (2018) 190:483

(a) (b)

(c) (d)

(e) (f)

(g) (h)
Environ Monit Assess (2018) 190:483 Page 7 of 17 483

R Fig. 5 Breach process of the upstream dam on October 16, 2012. areas of the earth dams (Chen et al. 2016; Chen and Liu
a, b At 10:04, ponding water occurred in front of the upstream 2017). The calculation is performed by first subtracting
dam; the arrow highlights the ponding area. c, d At 10:52, the dam
the temperature on the thermograph at a given time (T1)
started to breach on the initial ponding side; the arrow highlights
the dam breached area. e, f At 11:00, water flow overtopped the from the temperature at the next monitoring time (T2) to
dam. g, h At 11:03, the dam breached on the initial ponding side obtain T; subsequently, the monitoring index is T (T2 −
and in the middle T1) divided by the time period Δt (t2 − t1).

and 55°. Debris flows occurred in 2001 during Typhoon Thermograph characteristics of earth materials
Toraji; two bridges across the creek were buried under
masses of debris. Another debris flow occurred in 2004 Surficial thermal images of earth materials were cap-
during Typhoon Mindulle; debris masses buried the brid- tured to enhance the characteristics of earth materials
ges, blocked the outreach road, stopped the creek, diverted with different particle sizes in dry and wet conditions.
the stream flow, and damaged nearby buildings. Coarse aggregate more than 4.75 mm in diameter and
The construction sites of dams were located both up- fine aggregate between 150 μm and 4.75 mm in diam-
stream and downstream of the bridge for effective visual eter were mixed with soil and clay. Potted earth mate-
monitoring using a thermal imager. The earth dams were rials were exposed to sunlight, and thermal images were
constructed using an excavator to block the creek. The captured every 30 min to observe the temperature
distance between the two dams was 100 m. The dam sizes changes over time (Fig. 2).
are listed in Table 1. Field tests were conducted on Sep- The fine aggregate exhibited the highest surface-
tember 26, October 16, and November 7, 2012, as well as temperature changes, and wet soils exhibited the lowest
on April 10, 2014. The dam tested on September 26, 2012 surface-temperature changes. This was attributed to the
was constructed on September 21, 5 days before the test. small void ratio and large surface area of the fine aggregate
The others were constructed on the test date. The con- after exposure to sunlight. Wet soils have higher water
structed dams were unstable (Yang et al. 2015). Thermal content than do dry soils and show a lower surface tem-
imaging began following formation of the earth dams and perature because of the existence of water. Figure 2 shows
continued through to the release of water from upstream the surface-temperature changes and environmental-
until breach. The stream discharge was sourced from an temperature changes for the captured images. Surface-
irrigation ditch upstream with a controllable gate. temperature changes over time and the monitoring index,
The single-dam breach test was designed to explore T/Δt, could be used for long-distance monitoring to dis-
modes of failure caused by upstream impoundment. The tinguish wet soils from dry soils by water content.
two subsequent tests monitored changes in the failure A preliminary test of earth material was conducted
mode of downstream dams under flash floods induced after the construction of a downstream dam was com-
by breaching of an upstream dam. Dam materials were pleted on September 21, 2012. The different surface
sourced from the riverbed. The dam surface was lined temperatures of dry and wet soils and ponding water
with several grids for monitoring. The riverbed sedi- exhibited different thermal characteristics in the thermo-
ments are cohesionless soils with the following particle graph (Fig. 3). Ponding was caused by the lower topo-
size distribution: 10th percentile diameter d10 = 0.9 mm, graphic characteristics on the left side of the dam. The
median diameter d50 = 30 mm, and 90th percentile di- surface temperature on the left side of the dam was low
ameter d90 = 95 mm (Chen et al. 2015b). because of the high water content.
An NEC G100D infrared thermal imager was used for
analysis. Its measurable range is from − 4 to 500 °C with
precision to 0.01 °C. The visible spectrum was imaged at Results
the same time as the thermogram for comparison.
Postprocessing software was used for thermogram anal- Single earth dam (September 26, 2012)
ysis and image fusion in dual mode. Zonal temperature
was analyzed to indicate the average, maximum, and The earth dam was constructed on September 21, 2012
minimum regional temperatures in the images. The mon- downstream from the bridge for clear visual observa-
itoring index T/Δt for changes in temperature (T) during tion. The thermal imager was implemented on the
the time period (Δt) was used to monitor potential piping bridge and moved to both sides of the dam to capture
483 Page 8 of 17 Environ Monit Assess (2018) 190:483

(a) (b)

(c) (d)

(e) (f)

Fig. 6 Breach process of the downstream dam on October 16, area downstream. e, f At 11:12, the dam breached on the initial
2012. a, b Initial state of the upstream face at 9:50; the arrows ponding side; the arrow highlights the dam discharge overtopping
highlight the lower temperature zones. c, d At 11:07, piping breached area
occurred at the downstream face; the arrow highlights the piping

the images successively. Upstream discharge was re- corresponding to the initial ponding side (Fig. 4a, b).
leased 5 days after the dam was constructed, and the The upstream face showed a higher surface temperature
test started at 08:21 on September 26, 2012. Piping and than the downstream face because seepage occurred
subsequent erosion occurred at the downstream face downstream.
Environ Monit Assess (2018) 190:483 Page 9 of 17 483

(a) (b)

(c) (d)

(e) (f)

(g) (h)
483 Page 10 of 17 Environ Monit Assess (2018) 190:483

R Fig. 7 Breach process of the upstream dam on November 7, 2012. (Fig. 7a, b). The surface temperature was lower on
a, b At 10:03, ponding occurred in front of the dam; the arrow the ponding side than on the other side of the dam
highlights the ponding area. c, d At 11:27, base seepage occurred
top. Upstream water was released at 11:20, and base
downstream; the arrow highlights the base seepage area down-
stream. e, f At 11:31, the dam breached on the initial ponding side; seepage was shown downstream at 11:27 (Fig. 7c,
the arrow highlights the discharge overtopping area. g, h At 11:58, d). At 11:31, the dam was breached on the initial
the breached dam reached its final state; the arrow highlights the ponding side (Fig. 7e, f). The upstream dam failed
dam breached area
in the overtopping mode after only 11 min.
Figure 7g, h shows the final state of the breached
With the increase in discharge, the amount of seepage dam at 11:58.
water increased, and the erosion area increased. At Following the breach of the upstream dam at 11:31,
09:55, discharge overtopped the dam in the middle and the ponding water level increased at 11:34 at the down-
on the initial ponding side (Fig. 4c, d). The water level stream dam (Fig. 8a, b). One minute later at 11:35, base
rose faster than the wetting front of the dam material; seepage occurred downstream (Fig. 8c, d). At 11:36,
with the increased water level, overtopping occurred, piping and progressive erosion occurred downstream
and the dam was breached through progressive erosion. (Fig. 8e, f). At 11:38, creek discharge overtopped the
The dam was breached in the middle and on the initial dam, and it was breached shortly after at 11:41 in the
ponding side at 09:57 (Fig. 4e, f). middle (Fig. 8g, h). The dam was breached in the
The dam withstood 96 min of upstream discharge overtopping mode.
from 08:21 until the breach at 09:57. The dam failed in The downstream dam was breached 21 min after
the overtopping mode with base seepage and piping. upstream discharge was released at 11:20 and only
10 min after parts of the upstream dam were breached
Two earth dams (October 16, 2012) at 11:31.

In the next test, two dams were tested immediately after


construction on October 16, 2012. The test started at Discussion
10:04 following the release of upstream discharge.
Ponding water soon formed in front of the upstream Dam breach process
dam (Fig. 5a, b). At 10:52, the ponding area started to
breach the dam with the increasing water level (Fig. 5c, The dam breach processes during the three tests are
d). The water flow overtopped the dam at 11:00 (Fig. 5e, summarized in Table 2. Statistics indicate that 89% of
f), and at 11:03, the dam was breached on the initial landslide dams fail by overtopping, 10% by piping, and
ponding side and in the middle (Fig. 5g, h). The dam only 1% by other modes (Costa and Schuster 1988). The
endured for 59 min from 10:04 until 11:03. five earth dams in the three field tests all failed in the
Ponding water was present in front of the downstream overtopping mode. Phases of the dam breach process
dam, and the thermograph showed lower temperatures in were observed. At the beginning of the test, ponding
zones 1 and 3 (Fig. 6a, b). The downstream ponding level first occurred at the lowland of the riverbed upstream,
increased quickly at 11:04 upon the breach of the upstream and base seepage occurred at the base of the dam down-
dam. At 11:07, piping occurred at zone 3 of the down- stream. Shortly after, overtopping failure occurred.
stream face (Fig. 6c, d). The dam failed in the overtopping The topographic characteristics of the riverbed
mode on the initial ponding side of the dam and was caused ponding at the dam upstream. The piping down-
breached at 11:12 (Fig. 6c). The downstream dam lasted stream was attributed to the lowland ponding upstream,
for 68 min from the release of upstream water at 10:04 as indicated in Fig. 3. The ponding side of the dam
until it was breached at 11:12 (Fig. 6e, f). upstream in zone 1 (Fig. 3d) and at the top of the dam
(Fig. 4a) showed a low temperature on the thermo-
Two earth dams (November 7, 2012) graphs. The lower temperature indicates higher soil
water content on the initial ponding side. The dam was
The third test was similar to the second test (October shown to be breached first where ponding occurred on
16) with two earth dams constructed. Ponding oc- September 26, 2012. Similarly, during the tests on Oc-
curred in front of the upstream dam at 10:03 tober 16, 2012, the dam was first breached on the
Environ Monit Assess (2018) 190:483 Page 11 of 17 483

(a) (b)

(c) (d)

(e) (f)

(g) (h)
483 Page 12 of 17 Environ Monit Assess (2018) 190:483

R Fig. 8 Breach process of the downstream dam on November 7, attributed to the fact that it was constructed on an
2012. a, b At 11:34, the ponding water increased upon the up- existing check dam (Fig. 5a), and the soil–concrete
stream dam being breached; the arrows highlight the lower tem-
interface was prone to separation after seepage of
perature zones. c, d At 11:35, base seepage occurred downstream;
the arrows highlight the base seepage area downstream. e, f At ponding water. Additionally, the creek width was con-
11:36, piping and progressive erosion occurred downstream. g, h fined by the check dam, and leading water flow was
At 11:41, the dam was breached in the middle; the arrows high- concentrated to the creek center. This dam was breached
light the dam piping downstream and breached areas
first in the main channel and where ponding occurred.
Piping of two types is common for earth dams: piping
ponding side of the upstream dam (Fig. 5a) and on the through the body (internal erosion) and piping through
ponding side and piping area of the downstream dam the foundation (base seepage) (Omofunmi et al. 2017).
(Fig. 6a). The test on November 7, 2012 exhibited the Internal erosion failures are most common in areas
same failure mode at the upstream dam (Fig. 7a). These where hydraulic fracturing can occur (Flores-Berrones
results show that the failure mode of earth dams is et al. 2011). Base seepage on September 26, 2012 and
affected by the topographic characteristics of the river- on November 7, 2012 was captured by the thermo-
bed; lowland areas are vulnerable to ponding upstream, graphs. The downstream dam test on November 7,
which causes piping downstream and subsequent 2012 showed a low temperature on thermographs at
breaches. the dam base downstream (Fig. 8a). The tests show that
Soil erodibility is a critical parameter of the breach low temperatures at the dam surface indicate vulnerabil-
process (Zhong et al. 2018). The breach processes of the ity to seepage downstream and piping, which could lead
dams were all similar in the tests. Base seepage occurred to dam breaching.
quickly with piping and subsequent progressive erosion, Time parameters are critical to numerical models of
leading to dam breaching or overtopping. However, the dam breaches (Wahl 2004; Froehlich 2008). In an anal-
breach locations were different. Most of the dams were ysis of 204 landslide dams, 87% were shown to be
breached at one location, but some failed at two loca- breached in less than 1 year, 83% in less than 6 months,
tions. In the test on September 26, 2012, the upstream 71% in less than 1 month, 51% in less than 1 week, and
dam was breached in the middle and on the initial 34% in less than 1 day (Peng and Zhang 2012). The
ponding side of the dam. Others were breached only upstream dam on November 7 was breached after only
on the initial ponding side. In the November 7 test, the 11 min, which is far shorter than the time for the dam
downstream dam was breached in the middle. This was tested on October 16 (59 min). This is attributed to the

Table 2 Comparisons of the dam breach processes

Date Location Lifetime Failure mode /breach Breach process Thermograph changes
(min) area

26 Upstream – – – –
September, Downstream 96 Overtopping/initial Base seepage and piping, Lower temperature on ponding
2012a ponding side then overtopping failure side of the dam (Figs. 3d and 4b)
16 October, Upstream 59 Overtopping/initial Dam was breached through Lower temperature on ponding
2012 ponding side progressive erosion on the side of the dam (Fig. 5b)
and middle initial ponding side first
and failed through overtopping
Downstream 68 (8b) Overtopping/initial Piping first then breach on Lower temperature on ponding
ponding side the initial ponding side of the side and in piping areas of the
dam dam (Fig. 6b)
7 November, Upstream 11 Overtopping/initial Base seepage, then overtopping Lower temperature on ponding
2012 ponding side failure side of the dam (Fig. 7b)
Downstream 21 (10b) Overtopping/middle Base seepage and piping, then Lower temperature at the dam base
overtopping failure downstream (Fig. 8b)
a
Test was 5 days after construction
b
Lifetime after the upstream dam breach
Environ Monit Assess (2018) 190:483 Page 13 of 17 483

(a) (b)

1 2
4 5 3
6 7 8
12 9 10 11
13 14 15 16
20 21 17 18 19
22 23
24 25 26 27

(d)
(c)

(f)
(e)

(h)
(g)
483 Page 14 of 17 Environ Monit Assess (2018) 190:483

R Fig. 9 Dam breach process during the test on April 10, 2014. (a, induced by the breach of the upstream dam reduced
b) at 14:18, the earth dam was in its initial state. (c, d) At 14:19, the time to breach the downstream dam.
base seepage occurred; the arrow highlights the base seepage area
downstream. (e, f) At 14:33, piping occurred; the arrows highlight
the piping areas downstream. (g, h) At 14:35, the dam was Validation of the monitoring index
breached in the middle
An earth dam was constructed downstream on April 10,
different discharge rate; it took 1 h to overtop the dam on 2014 and tested for validation of the monitoring index
October 16 and only 10 min on November 7. Water (T/Δt). The dam surface downstream was divided into
discharge and flow rate from upstream affect the dam 27 grids for monitoring (Fig. 9a, b). The upstream water
breach process. A small discharge in a short time from was released at 14:00, and base seepage first occurred at
upstream is prone to causing piping and seepage; a large 14:19 (Fig. 9c, d). Dam surface temperatures dropped
discharge at a high rate causes ponding water to rise abruptly on the thermograph at 14:33 when piping oc-
faster and water to overtop the dam before the wetting curred at grids 7, 9, 15, 17, and 25 in the middle of the
front of the phreatic line reaches the slope face down- dam (Fig. 9e, f). At 14:35, the dam was overtopped and
stream. The area overtopped is first breached through breached in the middle (Fig. 9g, h).
progressive erosion. The thermographs indicated lower temperatures for
The existence of an upstream dam can affect the grids 7, 9, 15, 17, and 25 than for others at 14:33, and
failure process of a downstream dam. The down- they subsequently extended into the progressive erosion
stream dam was breached after 21 min on November zone at 14:34 (Fig. 10). However, the data shown were
7, which is far shorter than the times for the down- not sensitive to the rate of temperature change. For
stream dams on October 16 (68 min) and September continual abrupt changes in temperature, an index to
26 (96 min). The downstream dam was breached provide the rate of temperature changes could be useful
only 8 min after parts of the upstream dam were for monitoring purposes.
breached on October 16 and only 10 min after the The index T/Δt was used for dam breach process
upstream breach on November 7. The flash flood monitoring. The index was high at 14:21 but

Fig. 10 Surface-temperature
changes on thermographs for the
test on April 10, 2014
Environ Monit Assess (2018) 190:483 Page 15 of 17 483

Fig. 11 Variations of the


monitoring index (T/Δt) for the
test on April 10, 2014

suddenly dropped at 14:23 because of rising characteristics of the stream bed, the initial water
ponding water (Fig. 11). No notable changes were content of the soil, and the discharge conditions
observed until 14:28 and 14:31 when the index affected the failure mode and breach process of the
abruptly changed for grids 1 and 25, respectively. earth dams in field tests.
Finally, at 14:33, grid piping occurred and abruptly Areas with high soil water content display lower
reduced the index for grids 7, 9, 15, 17, and 25. The temperatures and could be prone to piping and pro-
results showed favorable agreement with the dam gressive seepage. With the aid of thermographs, a
breach process (Fig. 9), and the index can accurately monitoring index (T/Δt) is proposed for monitoring
reflect the trend of temperature changes over time. surface-temperature changes over time. The moni-
The applications of thermal imaging for dam failure toring index T/Δt decreased at grids where soil
mode monitoring could be limited to sparsely vege- piping occurred. This methodology should be ap-
tated soil surfaces above the water table. Thermal plied to safety monitoring of natural-dam stability
imaging cannot monitor the internal erosion process- and failure mode prediction for dam breach and
es of a dam. This would be useful for evaluating the disaster mitigation.
stability of natural (landslide) dams.
Funding information Parts of this work were supported by the
Ministry of Science and Technology in Taiwan, under contracts
NSC 99-2625-M-415-003-MY3 and MOST 106-2625-M-415-
003.
Conclusions

A noncontact, nondestructive, long-distance method References


of monitoring the earth-dam breach process using
thermal imaging was tested. In four real-scale breach Barla, G., Antolini, F., & Gigli, G. (2016). 3D laser scanner and
tests, the dam breach process started with ponding at thermography for tunnel discontinuity mapping.
the lowland of the riverbed upstream; piping and Geomechanics and Tunnelling, 9, 29–36.
base seepage occurred downstream; and the dam Baroň, I., Bečkovský, D., & Míča, I. L. (2012). Application of
infrared thermography for mapping open fractures in deep-
soon failed by overtopping. The overtopping failure seated rockslides and unstable cliffs. Landslides, 36, 265–275.
mode was observed in the main channel location and Bersan, S., Koelewijn, A. R., & Simonini, P. (2018). Effectiveness
on the initial ponding side first. The topographic of distributed temperature measurements for early detection
483 Page 16 of 17 Environ Monit Assess (2018) 190:483

of piping in river embankments. Hydrology and Earth System Gigli, G., Frodella, W., Garfagnoli, F., Morelli, S., Mugnai, F.,
Sciences, 22, 1491–1508. Menna, F., & Casagli, N. (2014). 3-D geomechanical rock
Boglietti, A., Cavagnino, A., Staton, D., Shanel, M., Mueller, M., mass characterization for the evaluation of rockslide suscep-
& Mejuto, C. (2009). Evolution and modern approaches for tibility scenarios. Landslides, 11, 131–140.
thermal analysis of electrical machines. IEEE Transactions Janssens, O., Van de Walle, R., Loccufier, M., & Van Hoecke, S.
on Industrial Electronics, 56, 871–882. (2017). Deep learning for infrared thermal image based ma-
Chai, H. J., Liu, H. C., Zhang, Z. Y., & Xu, Z. W. (2000). The chine health monitoring. IEEE/ASME Transactions on
distribution, causes and effects of damming landslides in Mechatronics, 23(1), 151–159.
China. Journal of Chengdu University of Technology, 27, Korup, O. (2004). Geomorphometric characteristics of New
302–307. Zealand landslide dams. Engineering Geology, 73, 13–35.
Chen, S. C. (1999). Failure mechanism and disaster mitigation on Korup, O. (2005). Geomorphic hazard assessment of landslide
landslide dammed lakes. Journal of Chinese Soil and Water dams in South Westland, New Zealand: Fundamental prob-
Conservation, 30, 299–312 (in Chinese with English lems and approaches. Geomorphology, 66, 167–188.
abstract). Lai, S. L., Lee, D. H., Wu, J. H., & Dong, Y. M. (2014). Detecting
Chen, G. H., & Chen, C. Y. (2014). Applications of thermal the cracks and seepage line associated with an earthquake in
images for highway slopeland monitoring and analysis. an earth dam using the nondestructive testing technologies.
Taiwan Highway Engineering, 40(4), 25–57 (in Chinese). Journal of the Chinese Institute of Engineers, Transactions of
Chen, S. C., & Hsu, C. L. (2009). Landslide dams induced by the Chinese Institute of Engineers, Series A, 37(4), 428–437.
typhoon Morakot and its risk assessment. Sino-Geotechnics, Lin, C. P., Hung, Y. C., Yu, Z. H., & Wu, P. L. (2013).
122, 77–86 (in Chinese with English abstract). Investigation of abnormal seepages in an earth dam using
Chen, C. Y., & Liu, Z. H. (2017). Applications of thermal images resistivity tomography. Journal of GeoEngineering, 8(2),
for monitoring surficial temperature changes of naked slope. 61–70.
Proceedings of Engineering Technology and Innovation, 5, Lo, C. M., Lin, M. L., Tang, C. L., & Hu, J. C. (2011). A kinematic
37–40. model of the Hsiaolin (a.k.a. Shaolin) landslide calibrated to
Chen, S. C., An, S. P., Hsu, T. Y., & Wang, C. (2015a). High the morphology of the landslide deposit. Engineering
precision and adjusted discharge sediment, the experimental Geology, 123, 22–39.
station in Landao Creek, Huisun Forest. Journal of Chinese Lum, K. Y., & Sheffer, M. R. (2005). Dam safety: review of
Soil and Water Conservation, 46, 1–6 (in Chinese with geophysical methods to detect seepage and internal erosion
English abstract). in embankment dams. Tulsa, OK: PennWell Corporation.
Chen, S. C., Lin, T. W., & Chen, C. Y. (2015b). Modeling of Martino, S., & Mazzanti, P. (2014). Integrating geomechanical
natural dam failure modes and downstream riverbed morpho- surveys and remote sensing for sea cliff slope stability anal-
logical changes with different dam materials in a flume test. ysis: the Mt. Pucci case study (Italy). Natural Hazards and
Engineering Geology, 188, 148–188. Earth System Sciences, 14, 831–848.
Chen, C. Y., Chen, S. C., & Chen, K. H. (2016). Earth dam Mineo, S., Pappalardo, G., Rapisarda, F., Cubito, A., & Di Maria,
monitoring by using infrared thermography detection. G. (2015). Integrated geostructural, seismic and infrared ther-
Proceedings of Engineering Technology and Innovation, 4, mography surveys for the study of an unstable rock slope in
40–42. the Peloritani chain (NE Sicily). Engineering Geology, 195,
Costa, J. E., & Schuster, R. L. (1988). The formation and failure of 225–235.
natural dams. Geological Society of America Bulletin, Moffat, R., Fannin, R. J., & Garner, S. J. (2011). Spatial and
100(7), 1054–1068. temporal progression of internal erosion in cohesionless soil.
Cuong, B. Q., Thai, N. C., Yihong, Z., & Chunju, Z. (2017). Canadian Geotechnical Journal, 48, 399–412.
Estimating seepage in embankment dams based on tempera- Omofunmi, O. E., Kolo, J. G., Oladipo, A. S., Diabana, P. D., &
ture measurement: a review paper. International Journal of Ojo, A. S. (2017). A review on effects and control of seepage
Engineering Research and Technology, 6, 106–113. through earth-fill dam. Current Journal of Applied Science
Feng, Z. Y. (2012). The seismic signatures of the surge wave from and Technology, 22(5), 1–11.
the 2009 Xiaolin landslide-dam breach in Taiwan. Peng, M., & Zhang, L. M. (2012). Breaching parameters of
Hydrological Processes, 26, 1342–1351. landslide dams. Landslides, 9(1), 13–31.
Flores-Berrones, R., Ramirez-Reynaga, M., & Macari, E. J. Planck, M. (1901). On the law of distribution of energy in the
(2011). Internal erosion and rehabilitation of an earth dam. normal spectrum. Annalen der Physik, 4, 553–559.
Journal of Geotechnical and Geoenvironmental Planes, T., Mooney, M. A., Rittgers, J. B. R., Parekh, M. L., Behm,
Engineering, 137(2), 150–160. M., & Snieder, R. (2016). Time-lapse monitoring of internal
Forest Bureau (2009). Council of Agriculture, Executive Yuan, erosion in earthen dams and levees using ambient seismic
Luodong Forest District Office, http://luodong.forest.gov. noise. Géotechnique, 66, 301–312.
tw/public/. (Accessed 27 October 2017). Polemio, M., & Lollino, P. (2011). Failure of infrastructure em-
Frodella, W., Morelli, S., Gigli, G., & Casagli, N. (2014). Contribution bankments induced by flooding and seepage: a neglected
of infrared thermography to the slope instability characterization. source of hazard. Natural Hazards and Earth System
Proceedings of World Landslide Forum, 3, 2–6. Sciences, 11, 3383–3396.
Froehlich, D. C. (2008). Embankment dam breach parameters and Schuster, R. L. (1986). Landslide dams: processes, risk, and
their uncertainties. Journal of Hydraulic Engineering, mitigation. In Geotechnical Special Publication. New
134(12), 1708–1721. York: American Society of Civil Engineers.
Environ Monit Assess (2018) 190:483 Page 17 of 17 483

Teza, G., Marcato, G., Pasuto, A., & Galgaro, A. (2015). Wu, C. H., Chen, S. C., & Feng, Z. Y. (2014). Formation, failure,
Integration of laser scanning and thermal imaging in moni- and consequences of the Xiaolin (a.k.a Shaolin) landslide
toring optimization and assessment of rockfall hazard: a case dam, triggered by extreme rainfall from typhoon Morakot,
history in the Carnic Alps (northeastern Italy). Natural Taiwan. Landslides, 11, 357–367.
Hazards, 76, 1535–1549. Yang, M. D., Chen, W. T., & Huang, K. S. (2015). Establishment
Wahl, T. L. (2004). Uncertainty of predictions of embankment of a 3D on-site model of landslide dam using UAV images.
dam breach parameters. Journal of Hydraulic Engineering, Journal of Chinese Soil and Water Conservation, 46, 88–95
130, 389–397. (in Chinese with English abstract).
Wu, J. H., Lin, H. M., Lee, D. H., & Fang, S. C. (2005). Integrity Zhong, Q. M., Chen, S. S., Mei, S. A., & Cao, W. (2018).
assessment of rock mass behind the shotcreted slope using Numerical simulation of landslide dam breaching due to
thermography. Engineering Geology, 80, 164–173. overtopping. Landslides, 15(6), 1183–1192.

You might also like