UNIVERSITI MALAYSIA SARAWAK

FACULTY OF ENGINEERING
CIVIL ENGINEERING DEPARTMENT

KNS 4713
PROJECT MANAGEMENT

Name Ting Aik Seng (58176)


Date of Submission 11/10/19
Lecturer Ir Dr Ting Sim Nee
Group 2
ID Activity Duration Immediately
(weeks) Preceding Activity
(IPA)
2 Project Start 0 -
4 Retaining System 3 2
5 Soil Improvement 5 4
6 Excavation 1 5
8 Piling 6 6
10 Pile Cap and Stump 4 8
11 Ground Beam and Slab 6 10
12 Column 4 11
13 Roof Beam and Flat Roof 6 12
15 Brick Laying 4 13
16 Plastering 6 15
17 Painting 4 18
18 Tiling 3 16
20 Plumbing 2 17
21 Lightning 2 17
22 Ventilation 2 20,21
23 Fire Protection 2 22
25 Drains 5 18FS+5 days
26 Access Road 4 25SS+ 4 days
28 RI Inspection 2 26,23
29 Certificate of Statutory Completion (CSC) 0 28FS+7 days
30 Project Finish 0 29
-3 means there is a float in the logic network as shown below. The critical path is highlighted.

52 54
-3 20 -3 3

29 54 56 56 58 61 63 70 70 70 70
3

0 0 0 3 3 8 8 9 9 15 15 19 19 25 25 29 35 35 39 39 45 45 48 48 52 55 2 57
-3
2 4 5 6 8 10 11 25 25 1225 25 13 25 15 25 25 16 25 18 17 -3 52 54 22 -3 23 -3 28 29 30
3 3
3

2 61 61 2 63 70 0 70 70 0 70
0 0 0 0 3 3 3 5 8 8 1 9 9 6 15 15 4 19 19 6 25 25 4 29 29 6 35 35 4 39 39 6 45 45 3 48 51 4 55 -3 57 2 59 59 3

25 25 25 25 25 25 25 25 25 25 21
55 2 57
25
53 58 57 61
25 25 26
53 5 58 57 4 61
25 25