33kV Bus Duct Structure Design & Drawing Doc. No.

Rev. : 00 Date :26-05-2021


Checks for 33kV Bus Duct Structure Design & Drawing
Reference 01 : Bureau of Indian Standards ( IS:800, IS:802(ALL PARTS)) & Other relavent IS Standards
Reference 02 : Suzlon Technical Specification No.: ENG:PEV:T-012 , CEA Technical
Standards for Construction of Electrical Plants and Electric Lines Regulations, 2010.
Sl.No Parameters to be Checked OK NOT OK Remarks, if any
A DESIGN UNITS
1 All Design units are as per Standard International (SI) Metric System
B DESIGN ASSUMPTIONS
1 General design Methodology is provided
2 All Design assumptions are clearly described
C STANDARDS & DESIGN PARAMETERS
1 IS: 800 - Code of practice for general construction in steel
2 IS: 802 (All Parts): Code of practice for use of structural steel in overhead
Transmission Line Towers
3 IS :'1161 : Steel tubes for structuralpurpose.
As the Bureau of Indian Standards have adopted IS : 802 (Part 1/ Sec 1): 1995
(Third Revision) and IS : 802 (Part 1 / Sec 2) : 1992 (Third Revision) these codes
4 shall supersede ,IS: 802 (Part 1) : 1977 (Second Revision). The Contractor shall
adopt-the design concepts as per the revised standards,

5 Structural Steel Grade


6 Unit mass of steel,
7 Modulus of elasticity,
8 Poisson ratio,
9 Modulus of rigidity,
10 Co-efficient of thermal expansion
D DESIGN LOADS
1 Design Loads are as per Project Design Basis /IS Codes
2 Dynamic loads are as Per Vendor Data for Heavy Rotating Equipment
3 Thermal loads are as per Project Design Basis
Load combinations for Allowable Stress Design are as per Project Design Basis ,
4 IS Codes

Load combinations for Ultimate Strength Design are as per Project Design
5 Basis , IS Codes
E 33kV BUS DUCT STRUCTURE DESIGN
Permissible stresses, sle~derness ratios o(member~; mi~imum thickness of
steel members, net sectional area of tension members and bolting and framing
1 shall be as per IS : 802 (Part 1 !Sec 2) : 1992.

Allswltchvard structures shall be designed for: the worst.ccmbination of dead


loads, liveloads, wind "loads and thermal loads as per IS: 802 {latest), Seismic
forces as per IS : 1893 (latest), loads due to deviation of conductor, load due to
unbalanced tension in conductor, torsional load due to unbalanced vertical and
horizontal forces, erection 'loads, short circuit forces including 'Snap' In the
2 case of bundled conductors, forces due to differential settlement and any other
loading condition which can occur during the design life ofthe structure.

3 The minimum thickness of structural sections shall as given below;


Trusses/bracings 6 mm
Purlins, side girts/runners 6 mm
Columns, beams 7 mm
Gussets in trusses & girders
Up to & inclusive of 12 m span 8 mm
Above 12 m span 10 mm
Stiffeners 8 mm
Base-plates 12 mm
i Chequered plates 6 mm on plain
Grating 25 mm
Grout for structural columns As required but min. 25 mm
Grout for equipments As required but min. 40 mm

Wind & Seismic forces shall not be.considered simultaneously in any load
4 combination.
The design of structure shall be based on the condition where stringing is done
only on one side i.e. aHthe three conductors broken on the other side. A factor
of safety of 2.0 under normal and broken' wire condition and 1;5 under
5 combined short circuit and broken wire conditions shall be adopted for design.
Short circuit forces and wind forces shall not be considered simultaneously.

Minimum distance from hole center to edge to adjacent hole shall be minimum
1.5 X bolt diameter. Minimum distance between center to center of holes shall
6 be 2.5 x bolt diameter.

7 The minimum bolt diameter shall be 16 mm.


Three-dimensional analysis shall be carried out for structures like towers and'
girders while two­dimensional analysis may be adopted for equipment support
structures; using standard software package like STAADPro. Any non-
8 standardsoftware used shan be validated with manual calculations and shall
beused only with the approval of Owner .

Vertical load of half the span of conductors/ string and the earth wires on
either side of the beam shall be taken into account for the purpose of design.
Weight of man with the tools. shall be considered as 150 kgs for the design of
9 structures.

10 The girders shall be connected with lattice columns by bolted joints.


Vertical load of half the span of conductors/string and the earth wires on either
side of the beam shall be taken into account for the purpose of design. Weight
11 of man with tools shall be considered as 150KGs for the design of structures.

Terminal / line take off girders shall be designed for a minimum conductor
tension of 1000Kg per sub conductor per phase for 66KV. The distance between
12 terminal girders and the dead end tower shall be taken as per standard.

The design of these terminal girders shall also be checked considering +/- 30
deg deviation of conductor in both vertical and horizontal planes. For other
13 girders the structural layout requirements shall be adopted in design.

14 The girders shall be connected with lattice columns be bolted joints.


All support structures used for supporting equipments shall be designed for the
worst combination of dead loads, erection load. Wind load/seismic forces,
15 short circuit forces. Short circuit forces shall be calculated considering a fault
level of 31.5KA for 3 seconds.

The fabrication and erection works shall be carried out generally in accordance
with IS 802. A reference however may be made to IS 800 in case of non-
stipulation of some particular provision in IS 802. All materials shall be
16 completely shop fabricated and finished with proper
connection material and erection marks for ready assembly in the field.

Foundation bolts shall be designed for maximum tensiori occ~rring'when 0.9


17 times minimum Dead Loads are combined with lateral loads

Lightning mastof required height shall be provided. Lighting masts shall be


provided with a structural steel ladder. The ladder shall be provided with
protection rings. Two platforms shall be provided for mounting of lighting
fixture. The platforms shall also have protection railing. the details for
18 mounting lighting fixtures would be as per the approved drawings of lighting
fixtures

Eachtower shall be provided with step bolts not less than 16 mm diameter and
175 mmlong spaced not more that 4.50mm apart, staggered on faces on one
leg extending from about 0.5 meters above ground level to the tower. The step
19 bolt shall conform to IS:I0238. Ladders.on towers with lighting appliances shall
be provided with safety guards.

Foundation bolts.for the towers and equipment supporting structures and


elsewhere shall be ".embedded in first stage concrete while the foundation is
20 cast. The Contractor shall ensure, the proper alignment of these bolts to match
the holes in the base plate,

Every bolt shall be provided with two flat and one spring washer under the nut
so that no part of the threaded portion of the bolt is within the thickness of the
21 parts bolted together. Locking nut shall be provided with each grouting bolt.
22 All steel items, bolts, nuts and washers shall be hot dip galvanized.
The work shall be done as per approved fabrication drawings, which clearly
indicate various details of joints to be welded, type of weld, length and size of
weld, whether shop or site weld etc. Symbols for welding on erection and shop
drawings shall be according to IS 813. Efforts shall be made to reduce site
23 welding so as to avoid improper joints due to constructional difficulties.

All structural steel works and support shall be galvanized after fabrication.
24

Zinc required for galvanizing shall have to be arranged by the manufacturer.


25 Purity of zinc to be used shall be 99.95% as per IS 209.

F FOUNDATION BOLTS
Foundation bolts for the towers and equipment supporting structures and
elsewhere shall be embedded in first stage concrete while the foundation is
1 cast. The contractor shall ensure the proper alignment of these bolts to match
the holes in the base plate.

The contractor shall be responsible for the correct alignment and leveling of all
2 steel work on site to ensure that the towers/structures are plumb.

All foundation bolts shall be fully galvanized so as to achieve 0.610 kg. Per
3 Sq.m. of Zinc coating as per specifications.

All foundation bolts shall conform to IS 5624 but the material shall be MS
4 conforming to IS 2062.
Anchor bolts shall be designed to resist the applied tensile loads and shear.
5

Anchor bolts that resist tensile loads shall be designed with an anchor head or
6 plate to transfer the load through tension in the concrete.

Anchor bolts for all equipments viz. vertical vessels/tanks & structural steel
structures like columns of pipe-racks, sheds, trestles, portals shall have double
7 nuts.

Anchor bolts on horizontal vessels shall have 1 nut per anchor bolt at the fixed
end and 2 nuts per anchor bolt at the sliding end, 1 loose nut and 1 locknut.
8

G CALCULATION PRESENTATION
Calculations Cover Sheet with Document Number, Project title, Caculation
1 Subject, Date, etc. is provided
2 Name of calculation originator/Checker on Claculation Sheets
3 Subject of Structural Calculations
Reference drawing number,Table of contents , List of appilcable coded,&
4 Standards .
General description of Structure design Methodology/Design Criteria /Primary
5 Loads Definition

H DRAWING
1 Check North Direction, Check Scale, Check units, Check Grid Dimensions
The information within the Title Block of each drawing has been reviewed for
2 accuracy including the “Designed By”, “Drawn By”, “Checked By” and “File No.”
fields.

The Index Sheet has been coordinated with the current list of
3 architectural drawings with respect to drawing number and title.

A drawing has been included to identify abbreviations and symbols utilized on


4 the project drawings and have been coordinated with the other architectural
drawings for compliance.

5 Loading plans, vertical loads layout


Deviations, if any
1
2
3
4

Verification team
Reviewed & Verfied by Approved & Accepted by
Remarks
Name
Date
Sign.

Prepared by Reviewed by Accepted by


Rupesh Khandekar Jagadish Ghogare Pravinkumar Patil