Professional Documents
Culture Documents
Schedule Under July Final 2020
Schedule Under July Final 2020
Schedule Under July Final 2020
MIDTERM EXAMINATION
Name:
INSTRUCTIONS:
1. This is an open book examination.
2. Use of calculator is allowed; discussion and material transfer are strictly prohibited.
PART I (100 %)
Question 1: (30 points)
Consider 4 machines and Minimum Part Set of 4 jobs corresponding with flow shop model where each
job follows the sequence: 1234
Job 1 2 3 4
P1j 1 1 2 0
P2j 2 2 2 2
P3j 1 2 3 1
P4j 2 2 1 0
a) Apply the Profile Fitting Heuristic Algorithm for the above Data. (20pts)
b) Now assumed that a buffer with capacity 1 is inserted between machine 1 and 2. As a result of this
when job is finished on machine 1 and machine 2 is busy, it can move to buffer and stay at here not block
the machine 1. Apply the 1st iteration of Profile Fitting Heuristic Algorithm to find the job at the 2nd
position in the sequence (10pts)
Machine 2 1 1 2
Activit 1 2 3 4 5 6 7
y
Tool 1 1 0 1 0 0 1 1
Tool 2 1 1 1 0 0 0 0
Tool 3 0 1 0 0 1 1 0
Tool 4 1 0 1 1 0 0 1
Month Demand
1 30 000
2 20 000
3 40 000
4 10 000
5 50 000
However, since these space requirements are quite different, it may be most economical to lease
only the amount needed each month on a month- by-month basis. On the other hand, the
additional cost for leasing space for additional months is much less than for the first month, so it
may be less expensive to lease the maximum amount needed for the entire 5 months. Another
option is the intermediate approach of changing the total amount of space leased (by adding a new
lease and/or having an old lease expire). The space requirement and the leasing costs for the
various leasing periods are as follows:
If 1st contract rents 30 000 square feet from month 1 to 3, and 2nd contract rents 20 000 square feet from 3
to 5. The available square feet at month 3 is 30 000 + 20 000 =50 000.
Index
t index of time t = 1···T
j index of leasing period j = 1···J
Parameters
st: be the minimum required space at time t
cj: be the cost per square foot leased for the contract covering j periods
Decision variables
Xtj be the binary variable, Xtj = 1 if the contract covering j periods starts at time t otherwise; Xtj = 0
Rtj be the area rented by the contract covering j periods starting at time t, if Xtj = 0 then Rtj = 0
GOOD LUCKS!