Professional Documents
Culture Documents
Atoha PMPPRO S2 - Integration
Atoha PMPPRO S2 - Integration
Session 2
4.1 Develop Project Charter [I] The process of developing a document that
formally authorizes the existence of a project and provides the project
manager with the authority to apply organizational resources to project
activities.
4.2 Develop Project Management Plan [P] The process of defining,
preparing, and coordinating all plan components and consolidating them
into an integrated project management plan.
4.3 Direct and Manage Project Work [E] The process of leading and
performing the work defined in the project management plan and
implementing approved changes to achieve the project’s objectives.
4.4 Manage Project Knowledge [E] The process of using existing knowledge
Chapter 4
and creating new knowledge to achieve the project’s objectives and
contribute to organizational learning.
4.5 Monitor and Control Project Work [M&C] The process of tracking,
reviewing, and reporting overall progress to meet the performance
PROJECT INTEGRATION MANAGEMENT objectives defined in the project management plan.
includes the processes and activities to identify, define, 4.6 Perform Integrated Change Control [M&C] The process of reviewing all
combine, unify, and coordinate the various processes and change requests; approving changes and managing changes to deliverables,
project management activities within the Project OPAs, project documents, and the project management plan; and
communicating the decisions.
Management Process Groups.
4.7 Close Project or Phase [C] The process of finalizing all activities for the
project, phase, or contract
2
PROJECT MANAGEMENT PROCESS GROUPS
Project Management Process Groups
Knowledge Areas
Initiating Planning Executing Monitoring and Controlling Closing
4. Integration 4.1 Develop Project 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work 4.7 Close Project
4.2 Develop Project Management Plan
Management Charter 4.4 Manage Project Knowledge 4.6 Perform Integrated Change Control or Phase
5.1 Plan Scope Management
5. Scope Management 5.2 Collect Requirements 5.5 Validate Scope
5.3 Define Scope 5.6 Control Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6. Schedule Management
6.3 Sequence Activities 6.6 Control Schedule
6.4 Estimate Activity Durations
6.5 Develop Schedule
7.1 Plan Cost Management
7. Cost Management 7.2 Estimate Costs 7.4 Control Costs
7.3 Determine Budget
8. Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9.3 Acquire Resources
9.1 Plan Resource Management
9. Resource Management 9.4 Develop Team 9.6 Control Resources
9.2 Estimate Activity Resources
9.5 Manage Team
10. Communications
10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications
Management
11.1 Plan Risk Management
11.2 Identify Risks
11. Risk Management 11.3 Perform Qualitative Risk Analysis 11.6 Implement Risk Responses 11.7 Monitor Risks
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12. Procurement
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
Management
13. Stakeholder
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement 3
Management
PROJECT INTEGRATION
MANAGEMENT
Includes the processes and activities to identify, define,
combine, unify, and coordinate the various processes and
project management activities within the Project
Management Process Groups. In the project management
context, integration includes characteristics of unification,
consolidation, communication, and interrelationship. These
actions should be applied from the start of the project
4
through completion.
PROJECT INTEGRATION Projects and project management are integrative by nature.
The links among the processes in the Project Management
MANAGEMENT (cont.) Process Groups are often iterative.
6
4.0 PROJECT SELECTION
i A project manager is not typically involved in project selection.
The reasons a project is selected and the value it is expected to bring to an organization indicate its significance to
the company.
The project manager needs to know if the project was selected because it will establish a new area of business, if it
is being implemented to meet regulatory or compliance requirements, or if it was chosen because it was the least
expensive or most feasible solution to a problem. The reasons a project was selected can impact which constraints
are most flexible, and knowing this information will influence how the project manager plans and manages the
project. A project manager must keep the reasons the project was selected in mind throughout the project to
ensure the objectives are achieved.
Question: Is the present value of $300,000 to be received three years from now, with an expected interest rate of
10 percent, more or less than $300,000?
Answer: Less. You can put an amount of money less than $300,000 in the bank and in three years have $300,000.
To perform the calculation: $300,000/(1 + 0.1)^3= $300,000/1.331 = $225,394.
Question. An organization has two projects from which to choose. Project A will take three years to complete and
has an NPV of $45,000. Project B will take six years to complete and has an NPV of $85,000. Which one is a better
investment?
Answer. Project B. The number of years is not relevant, as that would have been taken into account in the
calculation of the NPV.
Question. An organization has two projects from which to choose: Project A with an IRR of 21 percent and Project
B with an IRR of 15 percent. Which one is a better option?
Answer. Project A
Question. There are two projects from which to choose: Project A with a payback period of six months and Project
B with a payback period of 18 months. Which one should the organization select?
Answer. Project A
In some cases, the best choice might be a project that has a longer payback period but various other advantages!
Question. An organization has a project with an initial budget of $ 1,000,000. The project is half complete, and it
has spent $2,000,000. Should the organization consider the fact that it is already $1,000,000 over budget when
determining whether to continue with the project?
Answer. No. The money spent is gone.
17
4.1 DEVELOP PROJECT CHARTER
The process of developing a document that formally authorizes the
? existence of a project and provides the project manager with the
authority to apply organizational resources to project activities.
- They are NOT project documents; Use the business need and the cost benefit analysis to justify and establish boundaries for the
project.
Benefits management plan describes how and when the benefits of the project will be delivered
describes the mechanisms that should be in place to measure those benefits
key elements of the benefits: Target benefits, Strategic alignment, Timeframe for realizing benefits,
Benefits owner, Metrics, Assumptions, Risks,…
makes use of the data in the business case and needs assessment.
Development and maintenance of the project benefits management plan begins early in the project
life cycle and is an iterative activity.
2 contracts, memorandums of understanding (MOUs), service level agreements (SLA), letters of agreement, letters of intent,
Agreements (*) verbal agreements, email, or other written agreements. (a contract is for an external customer)
Are used to define initial intentions for a project The business case is created as a result of one or more of the following:
• Market demand (e.g., an automobile manufacturer authorizing a project to build more fuel-efficient cars in response to
Maybe NOT have before start a project
gasoline shortages),
• Organizational need (e.g., due to high overhead costs, a company may combine staff functions and streamline processes
to reduce costs),
3
• Customer request (e.g., an electric utility authorizing a project to build a new substation to serve a new industrial park),
Enterprise environmental factors • Technological advance (e.g., an airline authorizing a new project to develop electronic tickets instead of paper tickets
based on technological advances),
• Legal requirement (e.g., a paint manufacturer authorizing a project to establish guidelines for handling toxic materials),
4
Organizational process assets • Ecological impacts (e.g., a company authorizing a project to lessen its environmental impact), or
• Social need (e.g., a nongovernmental organization in a developing country authorizing a project to provide potable water
systems, latrines, and sanitation education to communities suffering from high rates of cholera).
gather data and solutions or ideas … when developing the project charter.
Focus groups (*) SME/Prequalified stakeholder Bring people … to learn about the perceived project risk, success
criteria,…
Interviews obtain high-level requirements, assumptions or constraints, approval criteria, from stakeholders by
talking directly. (1:1, 1:N, N:1)
3
Interpersonal And Team Skills Conflict management bring stakeholders into alignment on the objectives, success criteria, high-level requirements, project
description, summary milestones, and other elements of the charter.
Facilitation (*) All contributions are considered, that conclusions or results have full buy-in according to the decision
process established for the project.
Meeting Management preparing the agenda, ensuring that a representative for each key stakeholder group is invited, and
preparing and sending the follow-up minutes and actions.
4 are held with key stakeholders to identify the project objectives, success criteria, key deliverables, high-level
Meetings requirements, summary milestones, and other summary information.
ensures a common understanding by the stakeholders of the key deliverables, milestones, and the roles and
responsibilities of everyone involved in the project
2 High-level strategic and operational assumptions and constraints are normally identified in the business case
Assumption Log BEFORE the project is initiated and will flow into the project charter
is used to record all assumptions and constraints throughout
Lower-level activity and task assumptions are generated throughout the project such as defining technical
the project life cycle
specifications, estimates, the schedule, risks,…
24
4.2 DEVELOP PROJECT MANAGEMENT PLAN
The process of defining, preparing, and coordinating all plan
? components and consolidating them into an integrated project
management plan.
document issued by the project initiator or sponsor The type and amount of information in the project charter varies depending on the complexity of the project and
the information known at the time of its creation.
formally authorizes the existence of a project
2
OUTPUTS FROM OTHER PROCESSES (*) are integrated to create the project management plan.
- In first round, there is almost nothing in the outputs of other processes. Project management plan will include
Outputs from many of the other processes described in development approach, life cycle, and how you will plan for each knowledge areas
chapter 5 through chapter 13 - Later, there are all detailed information that are integrated to create the project management plan.
Subsidiary plans and baselines that are an output from other
planning processes (changes to these documents may
necessitate updates to the project management plan)
3
Enterprise environmental factors
4
Organizational process assets
as appropriate for the activity being performed comprises two parts: idea generation and analysis.
gather data and solutions or ideas … when developing the project charter.
2
Data Gathering Checklists standardized checklists available based in their own experience or use checklists from the industry. A
checklist may guide the project manager to develop the plan or may help to verify that all the
required information is included in the project management plan.
Focus groups (*) Bring people … to learn about the perceived project risk, success criteria,… SME/prequalified
(more conversational way than a 1:1 interview)
Interviews obtain high-level requirements, assumptions or constraints, approval criteria, from stakeholders by
talking directly.
3
Interpersonal And Team Skills Conflict management bring diverse stakeholders into alignment on all aspects of the project management plan.
Facilitation (*) ensures that there is effective participation, that participants achieve a mutual understanding, that
all contributions are considered, and that conclusions or results have full buy-in according to the
decision process established for the project
Meeting Management is necessary to ensure that the numerous meetings that are necessary to develop, unify, and agree
on the project management plan are well run.
4 are used to discuss the project approach, determine how work will be executed to accomplish the project
Meetings objectives, and establish the way the project will be monitored and controlled.
The project kick-off meeting is usually associated with the end of planning and the start of executing
Kickoff Meeting
Before the Develop Project Management Plan process can be completed and project executing can begin, a kickoff meeting should
be held. This is a meeting of the key parties involved in the project (customers, sellers, the project team, senior management,
functional management, and the sponsor). The purpose of this meeting is to announce the start of the project, to ensure everyone is
familiar with its details - including the project objectives and stakeholders roles and responsibilities and to ensure a commitment to
the project from everyone. In other words, the meeting is held to make sure everyone is on the same page. In addition to
introducing those involved in the project, the meeting may review such items as project milestones, project risks, the
communications management plan, and the meeting schedule.
32
4.3 DIRECT AND MANAGE PROJECT WORK
The process of leading and performing the work defined in the project
? management plan and implementing approved changes to achieve
the project’s objectives.
The project manager, along with the project management team, directs the performance of the planned project
activities and manages the various technical and organizational interfaces that exist in the project.
Available resources are allocated, their efficient use is managed, and changes in project plans stemming from analyzing
work performance data and information are carried out.
document that describes how the project will be Project management plan is one of the PRIMARY
executed, monitored and controlled, and closed documents used to manage the project.
2
Project Documents (*) Change log contains the status of all change requests
Lessons learned register Lessons learned are used to improve the performance and to avoid repeating mistakes.
The register helps identify where to set rules or guidelines so the team’s actions are aligned.
Project communications include performance reports, deliverable status, and other information generated.
Project schedule includes the list of work activities, their durations, resources, planned start-finish dates.
Requirements traceability Links product requirements to the deliverables that satisfy them and helps to focus on the final
matrix outcomes.
Risk register provides information on threats and opportunities that may impact project execution.
Risk report provides information on sources of overall project risk along with summary information on identified
individual project risks.
3
Approved Change Requests (*) an output of the Perform Integrated Change Control process and include reviewed and approved by the PM/CCB
4 may be a corrective action, a preventive action, or a defect repair.
Enterprise environmental factors
are scheduled and implemented by the project team, can impact any area of the project / project management plan
5
Organizational process assets can also modify the formally controlled project management plan components or project documents
judgment provided based upon expertise • Technical knowledge on the industry and focus area of the project,
(application area, Knowledge Area, discipline, industry,…) • Cost and budget management,
• Legal and procurement,
as appropriate for the activity being performed • Legislation and regulations, and
• Organizational governance.
3 are used to discuss and address pertinent topics of the project when directing and managing project work.
Meetings
Each attendee should have a defined role to ensure appropriate participation
Types of meetings: kick-off, technical, sprint or iteration planning, Scrum daily standups, steering group, problem
solving, progress update, and retrospective meetings
are typically the outcomes of the project and can include components of the project management plan
2
Work Performance Data (*) are raw observations & measurements identified during activities being performed to carry out the project work
Data are often viewed as the lowest level of detail from which information is derived by other processes.
Data is gathered through work execution and passed to the controlling processes for further analysis.
3
Issue Log is created for the first time as an output of this process, although issues may happen at any time during the project.
Negative impact happened is updated as a result of the monitoring and control activities throughout the project’s life cycle.
may modify project policies/procedures/cost/budget/schedule/quality, product scope/results. Other change requests cover
the needed preventive/corrective actions to forestall negative impact later in the project.
are processed for review and disposition through the Perform Integrated Change Control process
can be initiated from inside or outside the project and they can be optional/legally/contractually mandated
5
Project Management Plan Updates a change request > organization’s change control process > Any change to the project management plan (result)
6
Project Documents Updates Project documents that may be updated as a result of carrying out this process
7
Organizational process assets Updates Any organizational process asset can be updated as a result of this process
38
4.4 MANAGE PROJECT KNOWLEDGE
The process of using existing knowledge and creating new knowledge
? to achieve the project’s objectives and contribute to organizational
learning.
Knowledge management:
• is concerned with managing both tacit and explicit knowledge for two purposes: reusing existing knowledge and creating new
knowledge. The key activities that underpin both purposes are knowledge sharing and knowledge integration.
• is about making sure the skills, experience, and expertise of the project team and other stakeholders are used before, during, and
after the project.
• is creating an atmosphere of trust so that people are motivated to share their knowledge. (Even the best knowledge management
tools & techniques will NOT work if people are NOT motivated to share what they know or to pay attention to what others know)
In practice, knowledge is shared using a mixture of knowledge management tools and techniques (interactions
between people) and information management tools and techniques (in which people codify part of their explicit
knowledge by documenting it so it can be shared).
Misconception that managing knowledge involves just documenting it so it can be shared / just obtaining lessons
learned at the end of the project, in order to use it in the future projects. ONLY codified explicit knowledge can be
shared in this way, but it lacks context and is open to different interpretations, so even though it can easily be shared, it
is NOT always understood or applied in the right way. Tacit knowledge has context built in but is very difficult to codify.
4.4 MANAGE PROJECT KNOWLEDGE 40
4.4 MANAGE PROJECT KNOWLEDGE - INPUTS
1 integrates and consolidates all of the subsidiary
Project Management Plan (*) management plans and baselines,… to manage the
project.
document that describes how the project will be Project management plan is one of the primary
executed, monitored and controlled, and closed documents used to manage the project.
2
Project Documents (*) Lessons learned register information on effective practices in knowledge management
Project team assignments information on type of competencies & experience available & knowledge may be missing.
Resource breakdown structure information on composition of team > what knowledge is available & is missing.
Stakeholder register details about identified stakeholders > what knowledge they may have.
3
Deliverables (*)
Is any unique and verifiable product, result, or capability to
perform a service
4
Enterprise environmental factors
5
Organizational process assets
2
Knowledge Management (*) Knowledge management tools and techniques connect people so they can work together to create new knowledge, share
tacit knowledge, and integrate the knowledge of diverse team members.
Tools and techniques: networking, Communities of practice,
Meetings, forums, events, workshops, fairs, training,… can be applied face-to-face (most effective) or virtually (can be used to maintain the relationship), or both.
3
Information Management (*) Information management tools and techniques are used to create and connect people to information. They are effective for
sharing simple, unambiguous, codified explicit knowledge.
Tools and techniques: Methods for codifying explicit
knowledge, Lessons learned register, Library services, Interaction and support also helps find relevant information (Asking easier and quicker than identify search terms)
Information gathering, PIMS.
should be connected to project processes and process owners
4
Interpersonal And Team Skills
Active listening, Facilitation, Leadership,
Networking, Political awareness
include components the situation: is used as an input and updated as an output in many processes throughout the project
• the category and description
• the impact, recommendations, and At the end of a project or phase, the information is transferred to an organizational process asset called
proposed actions associated a lessons learned repository
• challenges, problems, realized risks
and opportunities
44
4.5 MONITOR AND CONTROL PROJECT WORK
The process of tracking, reviewing, and reporting overall progress to
? meet the performance objectives defined in the project management
plan.
document that describes how the project will be Project management plan is one of the primary
executed, monitored and controlled, and closed documents used to manage the project.
2
Project Documents (*) Assumption log Basis of estimates Cost forecasts Issue log
Schedule forecasts Milestone list Quality reports Risk register Risk report
3
Work Performance Information (*) Specific work performance metrics for scope, schedule, budget, and quality are defined at the start of the project
as part of the project management plan.
is Work Performance Data after compared with
the project management plan components, is combined, recorded, and distributed in a physical or electronic form in order to create awareness and generate decisions or
project documents,… actions.
4
Agreements (*) A procurement agreement includes terms and conditions, and may incorporate other items that the buyer specifies regarding
what the seller is to perform or provide
5 If the project is outsourcing part of the work, the project manager needs to oversee the contractor’s work to make certain that
Enterprise environmental factors all agreements meet the specific needs of project while adhering to organizational procurement policies
6
Organizational process assets
2
Data Analysis (*) Alternatives analysis Root cause analysis Trend analysis
3
Decision Making (*) Voting Autocratic decision making Multicriteria decision
making decisions based on
analysis
unanimity (100%), majority one individual takes the uses a decision matrix to provide
(>50%), or plurality (max responsibility for making the a systematic analytical approach
group) decision for the entire group.
4
Meetings face-to-face formal
Virtual informal
are representation of work performance may include status reports, progress reports, earned value graphs & information, trend lines & forecasts, reserve burndown
information intended to generate decisions, charts, defect histograms, contract performance information, and risk summaries.
actions, or awareness.
4
Project Documents Updates Issue log Lessons learned register Risk register
that may be updated as a result of carrying out this Cost forecasts Schedule forecasts
process
resulting from this process are resulting from this process are
recorded using cost recorded using schedule
management processes management processes
50
4.6 PERFORM INTEGRATED CHANGE CONTROL
The process of reviewing all change requests; approving changes and
? managing changes to deliverables, organizational process assets,
project documents, and the project management plan; and
communicating the decisions.
2
Project Documents Basis of estimates Requirements traceability matrix Risk report
are representation of work performance schedule and cost data Burnup/down charts
information intended to generate decisions,
actions, or awareness.
4
Change Requests (*) Corrective action Preventive action Defect repair Updates
Many processes produce change requests Changes may or may not impact the project baselines — sometimes only the performance against the baseline is
as an output affected
Change requests that have an impact on the project baselines include: Cost of implementing the change,
modifications in the scheduled dates, resource requirements, and risks
should be approved by the CCB (if it exists) and by the customer/sponsor, unless they are part of the CCB.
5
Enterprise environmental factors
6
Organizational process assets
judgment provided based upon expertise • Technical knowledge of the industry and focus area of the project,
(application area, Knowledge Area, discipline, industry,…) • Legislation and regulations,
• Legal and procurement,
as appropriate for the activity being performed • Configuration management, and
• Risk management.
2
Change Control Tools Tools should support the following configuration management activities
is focused on identifying, documenting, and Identify configuration item Record & report Perform configuration item
approving/rejecting changes to the project documents, configuration item status verification & audit
deliverables, or baselines.
Tools should support the following change management activities
Tools are also used to manage the change requests and the resulting decisions
made for communications to assist the change control board (CCB) members
3
Data Analysis Alternatives analysis Cost-benefit analysis
is used to assess the requested changes and decide which are helps to determine if the requested change is worth its
accepted/rejected/need to be modified to be finally accepted associated cost.
4
Decision Making Change control meetings are held with a change control board (CCB) and reviewing the change requests and
approving/rejecting/deferring change requests.
5
Meetings CCB decisions are documented and communicated to the stakeholders for information and follow-up actions
2
Project Management Plan Updates Changes to baselines are ONLY made from the last baseline forward. Past performance is NOT changed.
This protects the integrity of the baselines and the historical data of past performance.
Any formally controlled project document may be
changed as a result of this process
3
Project Documents Updates Change log
57
4.7 CLOSE PROJECT OR PHASE
The process of finalizing all activities for the project, phase, or
?
contract
3
Project Documents Assumption log Change log Issue log Milestone list Requirements documentation
4
Accepted Deliverables may include approved product specifications, delivery receipts, and work performance documents. Partial or
interim deliverables may also be included for phased or cancelled projects. This is from Validate Scope process.
5
Business Documents
6
Agreements
7
Procument Documentation To close the contract, all procurement documentation is collected, indexed, and filed
contract schedule, scope, quality, and cost performance along with all contract change documentation, payment
records, and inspection results are cataloged.
can be used for lessons learned information and as a basis for evaluating contractors for future contracts
8
Organizational process assets
2
Data Analysis Document analysis Assessing available documentation > identifying lessons learned and knowledge sharing for future
projects and organizational assets improvement.
Regression analysis analyzes the interrelationships between different project variables that contributed to the project
outcomes > improve performance on future projects.
Trend analysis validate the models used > implement adjustments for future projects.
Variance analysis improve the metrics of the organization by comparing what was initially planned and the end result.
3
Meetings • To confirm that the deliverables have been accepted,
• to validate that the exit criteria have been met,
• to formalize the completion of the contracts,
• to evaluate the satisfaction of the stakeholders,
• to gather lessons learned,
• to transfer knowledge and information from the project, and
• to celebrate success.
Attendees may include project team members and other stakeholders involved in or affected by the project.
face-to-face formal
Virtual informal
that may be updated as a result of carrying out this final lessons learned register (especially) may include information on benefits management, accuracy of the
process business case, project and development life cycles, risk and issue management, stakeholder engagement,…
2
Final Product/Service/Result Transition A product, service, or result, once delivered by the project, may be handed over to a different group/ organization
that will operate, maintain, and support it throughout its life cycle.
3
Final Report • Scope objectives, the criteria used to evaluate the scope, and evidence that the completion criteria were met.
• Quality objectives, the criteria used to evaluate the project and product quality, the verification and actual
provides a summary of the project performance milestone delivery dates, and reasons for variances.
• Cost objectives, including the acceptable cost range, actual costs, and reasons for any variances.
• Schedule objectives including whether results achieved the benefits that the project was undertaken to address.
• If the benefits are NOT met at the close of the project, indicate the degree to which they were achieved and
estimate for future benefits realization.
• If the business needs are NOT met at the close of the project, indicate the degree to which they were achieved
and estimate for when the business needs will be met in the future.
4
Organizational Process Asset Updates Project documents Operational and Project or phase Lessons learned
support documents closure documents repository
cs@atoha.com