The document provides an abstract of cost for the construction of Ward 7 Office Building. It lists 22 items with quantities, unit rates, and amounts for civil works, sanitary and water supply works, and electrical works. The total cost is estimated to be NPR 9,793,717.11 which includes the subtotals for civil works (NPR 8,149,468.08), sanitary and water supply works (NPR 63041.91), electrical works (NPR 72718.30), 13% VAT (NPR 1,077,079.68), 4% contingency (NPR 331,409.13), and a provisional sum for labor insurance of NPR 100,000
The document provides an abstract of cost for the construction of Ward 7 Office Building. It lists 22 items with quantities, unit rates, and amounts for civil works, sanitary and water supply works, and electrical works. The total cost is estimated to be NPR 9,793,717.11 which includes the subtotals for civil works (NPR 8,149,468.08), sanitary and water supply works (NPR 63041.91), electrical works (NPR 72718.30), 13% VAT (NPR 1,077,079.68), 4% contingency (NPR 331,409.13), and a provisional sum for labor insurance of NPR 100,000
The document provides an abstract of cost for the construction of Ward 7 Office Building. It lists 22 items with quantities, unit rates, and amounts for civil works, sanitary and water supply works, and electrical works. The total cost is estimated to be NPR 9,793,717.11 which includes the subtotals for civil works (NPR 8,149,468.08), sanitary and water supply works (NPR 63041.91), electrical works (NPR 72718.30), 13% VAT (NPR 1,077,079.68), 4% contingency (NPR 331,409.13), and a provisional sum for labor insurance of NPR 100,000
Name of the Project: Construction of Ward No 7 Office Building
Location: Ward 7, Kailari Item No Particulars Quantity Unit Rate Amounts A Civil works 1.0 Site clearance 1.00 LS 15000.00 15000.00 Earthwork excavation in Foundation in 2.0 Ordinary Soil 133.23 Cu.m. 480.90 64068.28 Earthwork in filling by excavated earth or approved material with manual compaction in 15-15 cm layers with sprinkling of water and leveling of surface 3.0 122.23 Cu.m. 333.50 40762.31 Gravel packing/soiling for increasing bearing capacity with proper compaction as per engineer instruction 4.0 10.49 Cu.m. 8651.65 90759.01 Providing, mixing and laying PCC M20 grade (1:2:4) with aggregate, sand and cement for RCC work in column and beam above/ below GL complete as per specification and instruction net. 5.0 104.76 cu.m. 16170.21 1693999.65 Flat brick soling and compaction as per 6.0 drawing 172.64 sq.m. 1670.46 288388.21 Providing mixing and laying P.C.C. 7.0 (1:3:6) flooring works at ground floor. 20.34 cu.m. 12616.40 256617.58 Supply and cutting ,bending of Tor Steel Reinforcement bars or equvalent confirming to IS code 456-1978 & straightning, cutting,bending and placement with proper centering for Columns ,Beams and Slabs as per drawing specification and instruction net. 8.0 16.29 mt. 125810.79 2049958.76 Providing fitting & fixing of standard form work by shuttering and good planks including all necessary props, bracings,wedges and nails etc. and removal of formwork at approved time for all type of RCC works etc in cover slab complete as per specification and instruction net. 9.0 239.04 Sq.m. 805.06 192441.54 Providing fitting & fixing of standard form work by shuttering and good planks including all necessary props, bracings,wedges and nails etc. and removal of formwork at approved time for all type of RCC works in column and beams complete as per specification and instruction net.
10.0 347.57 sq.m. 1180.13 410177.78
Supply & fixing of 100 x 75mm size
having good finishing sal wood door and Window frame (Chaukosh) in the wall of building three nos of M/S holdfast eachside of vertical frame fastenning in to the wall providing 1:2:4 PCC work complete as per drawing 11.0 specification and instruction complete 1.39 cu.m. 294859.17 409854.25 Supply & fixing of Panneled door shutter providing 38 mm thick 100 x 75mm size sal wood with good finishing as per drawing specification and instruction complete 12.0 44.65 sq.m. 14597.98 651799.81 3x20mm size M.S. grill with almunium paints as per design and instruction all 13.0 complete. 7.62 sq.m. 2168.90 16527.02
First class Brick work in foundation
and superstructure at ground floor in cement sand mortar (1:4) with Chimney Kiln made bricks in perfect line, level and finishing (one brick thickness 230 14.0 mm or more) 92.04 Cu.m 14141.79 1301610.35
38 mm thick Screeding on the PCC
Providing 1:2:4 cement sand aggregate chips of good quality for the floor finishing as per specification and 15.0 drawing all complete nett 167.59 sq.m. 685.20 114832.67
Providing, mixing and laying 3mm.thick
net cement punning in 1:1 cement mortar on perfect line, level and curing all complete as per drawing, 16.0 specification and instruction nett. 39.41 sq.m. 270.36 10654.89 12.5mm thick plastering by 1:4 cement sand mortar in walls inside/outside providing the necessary scaffolding as per drawing specification and instruction nett 17.0 600.06 sq.m. 367.14 220306.03 12.5mm thick plastering by 1:3 cement sand mortar( with supply of materials) in ceiling of the rooms inside/outside providing the necessary scaffolding as per drawing specification and instruction nett 18.0 163.420 sq.m. 436.020 71254.39 Two coats water proof cement paint on the plastered surface inside/outside of wall and ceiling as per drawing specification and instruction nett 19.0 724.07 sq.m. 126.84 91841.04 2 coats of ready made enamel paint of approved colour over 1 coats of primer Painting over porperly sanded wooden 20.0 surface all complete 105.34 sq.m. 320.95 33808.22
Making and fitting fixing of stainless
steel pipe railling with 38mm.dia.stainless steel pipe handrail 2 row 25mm.dia.stainless steel pipe in between handrail and floor and 38mm.dia.stainless stell pipe for vertical post @ 2m. c/c including 21.0 welding 16.80 sq.m. 3061.29 51429.67
Supplying and laying of glazed or non
glazed tiles in cement sand mortar (1:4) ratio with approved colour on wall 22.0 and floor all complete. 21.80 sq.m. 3365.90 73376.62 Sub- Total A 8149468.08 B Sanitary and water supply 1.0 Sanitary, water Supply & Installation 1.1 White glazed earthenware Indian pattern W C 580mm Orissa Pan complete set 2.00 Set. 3496.05 6992.10 1.2 White glazed Oval wash basin 55X40cm all complete set. 1.00 Set. 6900.92 6900.92 1.3 C.P. Bibcock 15mm dia heavy type 3.00 Nos. 1029.43 3088.29 1.4 1 H.P. Electrical Motor Water Pump (Indian) 1.00 Nos. 16800.00 16800.00 2.0 Water Supply 2.1 25 mm dia CPVC Pipe SDR 13.5 CTS, 22.5 kg/cm2 includes fixing/laying with necessary fittings all complete. 40.0 R.m 438.89 17555.60 2.2 Providing and fixing in position vertical / horizontal cylindrical PVC 1000 litres water tank of Hill Take or equivalent brand make with required support including hosting and fixing with necessary connection all complete with testing and ready for operation as per
1.00 Nos 10603.0 10603.00
3.0 Miscellaneous a 12" x 18" bathroom mirror 1.00 Nos 1102.00 1102.00 Sub-Total B 63041.91 C Electrical Works 1.0 48" Ceiling Fan Set. 6.00 4905.55 29433.30 40 watt electric bulb of NS or ISI 2.0 standard Set. 6.00 22.00 132.00
Total of A+B+C 8,285,228.30 13%VAT 1,077,079.68 4% Contingency 331,409.13 Provisional Sum (Labour insurance) 100,000.00 Grand Total 9,793,717.11 Remarks