Primavera P6 Project Management Reference Manual - Part5
Primavera P6 Project Management Reference Manual - Part5
Primavera P6 Project Management Reference Manual - Part5
Mark the Link Actual and Actual This Period Units and Cost checkbox
if you intend to store past period actuals using the Store Period
Performance feature. If this option is not selected, you cannot store
period performance or edit past period actuals.
You may want to create your OBS to match each EPS node and project
set up in the EPS. You can initially match OBS names to the EPS node
and project names. For example, for the Corporate (Corporate IT) node,
name the OBS element, Corporate IT Manager.
For more information Assign users, by their login names, to the OBS elements to grant access
about setting up security,
see the Administrator’s
to the corresponding EPS nodes or projects. The type of access granted
Guide. to a user is determined by the project security profile assigned to the
user. Security profiles are set up on the Security Profiles dialog box
(choose Admin, Security Profiles) and then assigned to users on the
Users dialog box (choose Admin, Users).
The OBS can mirror the EPS at the node and project level, or include
additional OBS levels to accommodate your management organization.
For example, you may want to specify team leaders as the responsible
managers for the WBS levels of a project, and the project manager
above the team leaders in the OBS as the responsible manager of the
project. In this way, you can delineate appropriate access and security
measures at various levels of the EPS while maintaining an OBS that
accurately reflects your organization chart.
For more information You can also produce reports based on your OBS; several standard OBS
about producing OBS and
reports are included with the sample projects.
other standard reports, see
“Customizing Reports” on
page 473.
Viewing an OBS
You can view an OBS in two ways: as a chart or a table. Choose
Enterprise, OBS, to open the Organizational Breakdown Structure
dialog box.
View the OBS chart Click the Display Options bar, then choose
Chart View. To change the information included in the chart and the way
it is displayed, click the Display Options bar and choose Chart Box
Template, Customize.
View the OBS table Click the Display Options bar, then choose
Table View.
Setting Up an OBS
Use the Organizational Breakdown Structure dialog box to create, view,
and edit the global OBS. You can also use this dialog box to view a list
of users who can access an OBS element’s global and project
information, and to see how people are assigned across the enterprise of
projects.
For more information Create an OBS A root OBS node is automatically assigned to the
about establishing EPS
root EPS node so that a default OBS element can be assigned to each
nodes, see “Setting Up the
Enterprise Project project you add to the EPS root. When you use the Enterprise Project
Structure” on page 67. Structure dialog box to set up the EPS nodes that make up the
foundation of the EPS, you can use the existing root EPS as the default
for each node, or you can set up the OBS before you build the EPS. You
can then assign actual responsible managers when you create EPS
nodes. Once your basic OBS is in place, you can include additional OBS
elements to provide access to specific EPS nodes, projects, and WBS
elements, to users not included with the original enterprise OBS node.
For details on establishing View users associated with OBS elements Click the Users tab
users and profiles, see the
Administrator’s Guide.
in the Organizational Breakdown Structure dialog box to view the users
and corresponding security profiles associated with an OBS element.
You can also assign users from this tab, if you have appropriate access
rights.
Resources Overview
You can develop a resource plan that integrates resources, costs, and the
schedule so you can effectively control your projects. Begin by defining
a list of all the resources necessary to complete the projects included in
your enterprise project structure (EPS). For each resource, set
availability limits, unit prices, and a calendar to define its standard
worktime and nonworktime. Define shifts and apply one or more of the
shifts to the resources to whom they apply. Group the resources by
broad categories so you can easily find a specific resource when
assigning resources to a project.
Resources are different than expenses. While some resources are time-
based and generally extend across multiple activities and projects,
expenses are one-time expenditures for nonreusable items required by
activities.
Roles If you are in the planning stage of your project or want to see
how certain resource assignments will affect the schedule, you can
assign roles as temporary placeholders for resource assignments. Roles
are project personnel job titles or skills. They represent a type of
resource with a certain level of proficiency—rather than a specific
individual. Roles can also be assigned to specific resources to further
identify that resource’s skills.
For information about Primary resources An activity’s primary resource is typically the
assigning resources to
activities, see “Working
resource who is responsible for coordinating an activity’s work. The
with Activities” on primary resource updates the activity’s start date, finish date, and
page 211. expected end date. In addition, if an activity has any material resources,
the primary resource may be responsible for reporting the material
resource’s hours/units.
Primary resources are also responsible for editing the physical percent
complete when weighted steps are linked to activity percent complete
for the corresponding activities in a selected project.
The module uses your calendar assignments for activity scheduling, The minimum amount of
tracking, and resource leveling; you can select a global calendar or a time a resource is available
resource calendar for the resource. to work on an activity
Default Units/Time
You can enter the default units/time value as a numeric value followed
by a forward slash (/) and the appropriate time duration, depending on
your user preference setting for time units, or as a percentage for labor
and nonlabor resources. For example, if the selected resource is one
person, a reasonable value may be eight hours (units) per day (duration).
In this case, the Default Units/Time would be 8.00h/d, or eight hours of
work per day. If you are entering a percentage, you would enter 100%
indicating that the resource is available to work full-time. Similarly, if
the selected resource is a department with five people, the Max Units/
Time may be 40.00h/d, or 500%. This means that five people can
perform 40 hours of work per day, rather than one person performing 8
hours of work per day. The module uses this value in conjunction with
the calendar assignment to calculate resource allocation/distribution
during scheduling and leveling.
Units and prices Use the Units & Prices tab to specify available
quantities (limits) for the resource. Setting limits helps you quickly
identify areas of resource overload in Resource Usage Profiles using
different colors to represent limits and overallocated units in histograms.
The module automatically adjusts the resource’s costs for its assigned
activities to reflect price changes for different timeperiods.
Select the resource’s shift calendar and type the applicable Double-click the cell, then type
shift number for which you are setting limits, if the shift the resource’s price followed by
calendar has more than one shift. See the Defining Resource a forward slash (/) and the unit
Shifts section for information about defining shifts. associated with the price.
You can set varying limits The number of units available during each workperiod
and prices over time by (hour, day, week, or month) of the specified timeframe;
specifying the effective start you can enter a percentage, or a numeric value followed
date for each change. by a forward slash (/) and the appropriate time duration,
depending on your user preference setting for time units.
10AUG01 0h/h
10SEP01 1h/h
Notes Use the Notes tab to enter comments about the resource. You
can use HTML editing features, which include formatting text, inserting
pictures, copying and pasting information from other document files
(while retaining formatting), and adding hyperlinks.
For more information Timesheets Use the Timesheets tab to specify the selected resource’s
about configuring
resources for use with the
timesheet login name and whether the resource uses timesheets to
Timesheets module, see record hours for assigned activities. You must first set up login names in
the Administrator’s Guide. the Users dialog box. Choose Admin, Users, then click the General tab.
Click to access the Users dialog Click the Browse button to select
box, where you can specify a the resource’s timesheet
different login name and password. approval manager.