Rodeo 2.1 - Project Master Schedule
Rodeo 2.1 - Project Master Schedule
Rodeo 2.1 - Project Master Schedule
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
22 M9-Approval of Waste Gas Treatment-DBR1 day Fri 25/06/21 Fri 25/06/21 96
23 M10-Submission of Civil Tender Documents1 day Thu 17/06/21 Thu 17/06/21 100
24 M11-Submission of Mechanical Tender 1 day Mon 28/06/21 Mon 129
Documents 28/06/21
25 M12-Submission of Electrical Tender 1 day Fri 25/06/21 Fri 25/06/21 146
Documents
26 M13-Submission of I&C Tender Documents1 day Thu 24/06/21 Thu 24/06/21 155
27 M14- Submission of Chemical Distribution 1 day Thu 08/07/21 Thu 08/07/21 164
Sytem Tender Documents
28 M15- Submission of Gas Distribution 1 day Thu 08/07/21 Thu 08/07/21 172
System Tender Documents
29 M16-Submission of DI Water & ETP 1 day Thu 08/07/21 Thu 08/07/21 184
Tender Documents
30 M17 Submission of Waste Gas Treatment 1 day Thu 08/07/21 Thu 08/07/21 192
Tender Documents
31 M18- Appointment of Civil Contractors 1 day Thu 24/06/21 Thu 24/06/21 101
32 M19-Appointment of Mechanical Contractors 1 day Mon 05/07/21 Mon 05/07/21130
33 M20- Appointment of Electrical Contractors1 day Fri 02/07/21 Fri 02/07/21 147
34 M21- Appointment of I&C Contractors 1 day Thu 01/07/21 Thu 01/07/21 156
35 M22- Appointment of Chemical 1 day Thu 15/07/21 Thu 15/07/21 165
Distribution System Contractor
36 M23- Appointment of Gas Distribution 1 day Thu 15/07/21 Thu 15/07/21 173
System Contractors
Task Inactive Milestone Deadline
Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only
Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
37 M24-Appointment of DI Water & ETP 1 day Thu 15/07/21 Thu 15/07/21 185
Contractors
38 M25- Appointment of Waste Gas 1 day Thu 15/07/21 Thu 15/07/21 193
Treatment Contractors
39 M26- Release of Civil GFC Drawings 1 day Fri 06/08/21 Fri 06/08/21 215
40 M27- Release of Mechanical VDR 1 day Thu 22/07/21 Thu 22/07/21 134
41 M28- Release of Electrical VDR 1 day Wed 21/07/21 Wed 21/07/21151
42 M29 -Release of l&C VDR 1 day Tue 20/07/21 Tue 20/07/21 160
43 M30- Release of Chemical Distribution 1 day Tue 03/08/21 Tue 03/08/21 169
System VDR
44 M31- Release of Gas Distribution System VDR 1 day Wed 08/09/21 Wed 08/09/21181
45 M32- Release of DI Water & ETP VDR 1 day Tue 03/08/21 Tue 03/08/21 189
46 M33- Release of Waste Gas Treatment VDR1 day Tue 03/08/21 Tue 03/08/21 197
47 M34- Process Equipment Move-In 1 day Mon 21/02/22 Mon 21/02/22246SS
48 Concept 23 days Mon 24/05/21 Thu 24/06/21
49 Master Plan 13 days Mon 24/05/21 Thu 10/06/21
53 DBR for Civil (Utilities & Ancillary Buildings)
8 days Fri 04/06/21 Tue 15/06/21
58 DBR for Mechanical 7 days Fri 04/06/21 Mon 14/06/21
66 DBR for Electrical 7 days Fri 04/06/21 Mon 14/06/21
72 DBR for I&C 7 days Fri 04/06/21 Mon 14/06/21
77 Chemical Storage & Distribution System 15 days Fri 04/06/21 Thu 24/06/21
82 Bulk & Specialty Gas Storage and Distribution15 days Fri 04/06/21 Thu 24/06/21
Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
87 DI Water & ETP 15 days Fri 04/06/21 Thu 24/06/21
92 Waste Gas Treatment (Scrubbers) 15 days Fri 04/06/21 Thu 24/06/21
97 Tender 198 days Thu 01/04/21 Mon 03/01/22
98 Civil & Structural (Utilities & Ancillary) 12 days Tue 08/06/21 Wed 23/06/21
102 Mechanical 29 days Fri 11/06/21 Wed 21/07/21
135 Electrical 26 days Tue 15/06/21 Tue 20/07/21
152 I&C 25 days Tue 15/06/21 Mon 19/07/21
161 Specialty Utilities 53 days Fri 25/06/21 Tue 07/09/21
198 Process Equipment 198 days Thu 01/04/21 Mon 03/01/22
213 Civil & Structural GFC Drawings (Utility & Ancillary)
37 days Wed 16/06/21 Thu 05/08/21
214 Preparation and submission of Civil GFC 35 days Wed 16/06/21 Tue 03/08/21 57
Drawings for various Utility and Ancillary
requirements
215 Design workshop review and approval by 2 days Wed 04/08/21 Thu 05/08/21 214
client / Process consultant - Civil &
Structural GFC Drawings
216 Construction/Installation (Based on 220 days Mon 31/05/21 Fri 01/04/22
Indospace Vallam)
217 Main Building 100 days Mon 31/05/21 Sun 17/10/21
228 Facility/Utilities Services 115 days Wed 22/09/21 Tue 01/03/22
245 Process Equipment/Meterology Tools 30 days Fri 18/02/22 Fri 01/04/22
249 Manpower 20 days Tue 01/02/22 Mon 28/02/22
Page 4
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
250 50 Operators Onboarding 0 days Tue 01/02/22 Tue 01/02/22
251 Onboarding of total of 350 Operators 20 days Tue 01/02/22 Mon 28/02/22250
Page 5
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
01/04
01/04
23/05
31/05
Page 6
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Page 7
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Page 8
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Page 9
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
01/02
Page 10