Rodeo 2.1 - Project Master Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021

Mode Mar Apr


1 Proposed Rodeo-2.1 Solar Cell Line Project 262 days Thu 01/04/21 Fri 01/04/22
2 Commercial Production Start Date 0 days Fri 01/04/22 Fri 01/04/22 248
3 Project Kick-Off Date 0 days Thu 01/04/21 Thu 01/04/21 01/04
4 LOI/PO to OE 0 edays Sun 23/05/21 Sun 23/05/21
5 Kick off Meeting with OE 1 day Mon 24/05/21 Mon 24/05/214
6 Statuatory Approvals - CTE 30 days Fri 06/08/21 Thu 16/09/21 215
7 3rd Part Audit from PESO for Gas 15 days Mon 17/01/22 Fri 04/02/22 234
Distribution system
8 CTO 30 days Mon 07/02/22 Fri 18/03/22 7
9 Site Finalization & Agreement Date 0 edays Mon 31/05/21 Mon 31/05/21
10 TTRO - Water Source from official bodies 180 edays Fri 18/06/21 Wed 15/12/219FS+15 days
11 Power Demand from CEIG 180 edays Fri 18/06/21 Wed 15/12/219FS+15 days
12 PCB Approval for Treated Water Discharge 180 edays Fri 18/06/21 Wed 15/12/219FS+15 days
13 Project Milestones 182 days Fri 11/06/21 Mon 21/02/22
14 M1- Finalisation & Master Plan Sign off 1 day Fri 11/06/21 Fri 11/06/21 52
15 M2-Approval of Civil DBR 1 day Wed 16/06/21 Wed 16/06/2157
16 M3-Approval of Mechanical DBR 1 day Tue 15/06/21 Tue 15/06/21 65
17 M4-Approval of Electrical DBR 1 day Tue 15/06/21 Tue 15/06/21 71
18 M5-Approval of I&C DBR 1 day Tue 15/06/21 Tue 15/06/21 76
19 M6- Approval of CDS DBR 1 day Fri 25/06/21 Fri 25/06/21 81
20 M7- Approval of Gas Distribution System -DBR
1 day Fri 25/06/21 Fri 25/06/21 86
21 M8-Approval of DI Water & ETP-DBR 1 day Fri 25/06/21 Fri 25/06/21 91

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
22 M9-Approval of Waste Gas Treatment-DBR1 day Fri 25/06/21 Fri 25/06/21 96
23 M10-Submission of Civil Tender Documents1 day Thu 17/06/21 Thu 17/06/21 100
24 M11-Submission of Mechanical Tender 1 day Mon 28/06/21 Mon 129
Documents 28/06/21
25 M12-Submission of Electrical Tender 1 day Fri 25/06/21 Fri 25/06/21 146
Documents
26 M13-Submission of I&C Tender Documents1 day Thu 24/06/21 Thu 24/06/21 155
27 M14- Submission of Chemical Distribution 1 day Thu 08/07/21 Thu 08/07/21 164
Sytem Tender Documents
28 M15- Submission of Gas Distribution 1 day Thu 08/07/21 Thu 08/07/21 172
System Tender Documents
29 M16-Submission of DI Water & ETP 1 day Thu 08/07/21 Thu 08/07/21 184
Tender Documents
30 M17 Submission of Waste Gas Treatment 1 day Thu 08/07/21 Thu 08/07/21 192
Tender Documents
31 M18- Appointment of Civil Contractors 1 day Thu 24/06/21 Thu 24/06/21 101
32 M19-Appointment of Mechanical Contractors 1 day Mon 05/07/21 Mon 05/07/21130
33 M20- Appointment of Electrical Contractors1 day Fri 02/07/21 Fri 02/07/21 147
34 M21- Appointment of I&C Contractors 1 day Thu 01/07/21 Thu 01/07/21 156
35 M22- Appointment of Chemical 1 day Thu 15/07/21 Thu 15/07/21 165
Distribution System Contractor
36 M23- Appointment of Gas Distribution 1 day Thu 15/07/21 Thu 15/07/21 173
System Contractors
Task Inactive Milestone Deadline
Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
37 M24-Appointment of DI Water & ETP 1 day Thu 15/07/21 Thu 15/07/21 185
Contractors
38 M25- Appointment of Waste Gas 1 day Thu 15/07/21 Thu 15/07/21 193
Treatment Contractors
39 M26- Release of Civil GFC Drawings 1 day Fri 06/08/21 Fri 06/08/21 215
40 M27- Release of Mechanical VDR 1 day Thu 22/07/21 Thu 22/07/21 134
41 M28- Release of Electrical VDR 1 day Wed 21/07/21 Wed 21/07/21151
42 M29 -Release of l&C VDR 1 day Tue 20/07/21 Tue 20/07/21 160
43 M30- Release of Chemical Distribution 1 day Tue 03/08/21 Tue 03/08/21 169
System VDR
44 M31- Release of Gas Distribution System VDR 1 day Wed 08/09/21 Wed 08/09/21181
45 M32- Release of DI Water & ETP VDR 1 day Tue 03/08/21 Tue 03/08/21 189
46 M33- Release of Waste Gas Treatment VDR1 day Tue 03/08/21 Tue 03/08/21 197
47 M34- Process Equipment Move-In 1 day Mon 21/02/22 Mon 21/02/22246SS
48 Concept 23 days Mon 24/05/21 Thu 24/06/21
49 Master Plan 13 days Mon 24/05/21 Thu 10/06/21
53 DBR for Civil (Utilities & Ancillary Buildings)
8 days Fri 04/06/21 Tue 15/06/21
58 DBR for Mechanical 7 days Fri 04/06/21 Mon 14/06/21
66 DBR for Electrical 7 days Fri 04/06/21 Mon 14/06/21
72 DBR for I&C 7 days Fri 04/06/21 Mon 14/06/21
77 Chemical Storage & Distribution System 15 days Fri 04/06/21 Thu 24/06/21
82 Bulk & Specialty Gas Storage and Distribution15 days Fri 04/06/21 Thu 24/06/21

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
87 DI Water & ETP 15 days Fri 04/06/21 Thu 24/06/21
92 Waste Gas Treatment (Scrubbers) 15 days Fri 04/06/21 Thu 24/06/21
97 Tender 198 days Thu 01/04/21 Mon 03/01/22
98 Civil & Structural (Utilities & Ancillary) 12 days Tue 08/06/21 Wed 23/06/21
102 Mechanical 29 days Fri 11/06/21 Wed 21/07/21
135 Electrical 26 days Tue 15/06/21 Tue 20/07/21
152 I&C 25 days Tue 15/06/21 Mon 19/07/21
161 Specialty Utilities 53 days Fri 25/06/21 Tue 07/09/21
198 Process Equipment 198 days Thu 01/04/21 Mon 03/01/22
213 Civil & Structural GFC Drawings (Utility & Ancillary)
37 days Wed 16/06/21 Thu 05/08/21
214 Preparation and submission of Civil GFC 35 days Wed 16/06/21 Tue 03/08/21 57
Drawings for various Utility and Ancillary
requirements
215 Design workshop review and approval by 2 days Wed 04/08/21 Thu 05/08/21 214
client / Process consultant - Civil &
Structural GFC Drawings
216 Construction/Installation (Based on 220 days Mon 31/05/21 Fri 01/04/22
Indospace Vallam)
217 Main Building 100 days Mon 31/05/21 Sun 17/10/21
228 Facility/Utilities Services 115 days Wed 22/09/21 Tue 01/03/22
245 Process Equipment/Meterology Tools 30 days Fri 18/02/22 Fri 01/04/22
249 Manpower 20 days Tue 01/02/22 Mon 28/02/22

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 4
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 2, 2021
Mode Mar Apr
250 50 Operators Onboarding 0 days Tue 01/02/22 Tue 01/02/22
251 Onboarding of total of 350 Operators 20 days Tue 01/02/22 Mon 28/02/22250

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 5
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

01/04
01/04
23/05

31/05

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 6
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 7
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 8
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 9
Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
01/02

Task Inactive Milestone Deadline


Split Inactive Summary Critical
Milestone Manual Task Critical Split
Project: msproj11 Summary Duration-only Late
Date: Tue 25/05/21
Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slack
Inactive Task Finish-only

Page 10