Professional Documents
Culture Documents
Toaz - Info Method Statement For Hydrostatic Testing PR
Toaz - Info Method Statement For Hydrostatic Testing PR
Revision History
Rev A IFA 25/11/18 Rev A
Rev A Received Comments on 24/02/2019
Rev B Revised and Comments incorporated on 26/02/2019
Rev C Comments incorporated. IFA 29/06/2019 Rev C
Rev 0 Issued For Use Rev 0 on 14th August 2019
Page 2 of 15
Issue Date: 14-08-2019
Iraq Brach
TABLE OF CONTENTS
1. PURPOSE -------------------------------------------------------------------------------------------------------------------------------------- 4
2. SCOPE OF WORK--------------------------------------------------------------------------------------------------------------------------- 4
3. DEFINITIONS --------------------------------------------------------------------------------------------------------------------------------- 4
6. METHODOLOGY----------------------------------------------------------------------------------------------------------------------------- 7
11. ATTACHMENTS----------------------------------------------------------------------------------------------------------------------------- 15
Page 3 of 15
Issue Date: 14-08-2019
Iraq Brach
1. PURPOSE
Purpose of this method statement is to establish a detailed method, resources, equipment, quality control
and HSE measures to be planed, prepared and implemented to ensure that the cleaning, water filling,
hydrostatic testing, dewatering and drying of piping systems are performed according the project
specifications within DS6 Major Tie ins Facilities at WQI, Iraq.
2. SCOPE OF WORK
This method statement is made to enumerate the general requirements for inspection, flushing, testing,
dewatering/draining, and drying of piping at the DS6 Major Tie-Ins Facilities at WQI, Iraq. In the event of that
is not fully addressed, SUBCONTRACTOR will perform the Work in accordance with the applicable codes
and best recognized practices in the onshore oil and gas industry. All activities will be performed in strict
compliance with the requirements of the project HSE Method Statements and safe working practices.
3. DEFINITIONS
COMPANY ExxonMobil Iraq Limited (EMIL) - The entity issuing the contract for
the work or their authorized agent
CONTRACTOR SAIPEM S.p.A. Iraq Branch - The entity contracted to perform the
work for the COMPANY
SUBCONTRACTOR Calethon Construction Group
CONTRACT DOCUMENTS The documents that form the CONTRACT issued by the COMPANY
SUBCONTRACT DOCUMENTS The documents that form the subcontract issued by the
CONTRACTOR
WORK Activities to be performed
DS6 Degassing Station 6
WPS Welding Procedure Specification
ITP Inspection and Test Plan
QC Quality Control
MOAP Maximum Allowable Operating Pressure
IFC Issued For Construction
P&ID Piping & Instrument Diagram
HSE Health Safety and Environment
4. REFERENCE DOCUMENTS
• IQWQ-FT-LSPDS-00-031902 Upstream Piping Fabrication, Erection, Inspection, Testing and Cleaning
• IQWQ-FT-LSPDS-00-032002 Upstream piping classification line classes atmospheric and 125
• IQWQ-FT-LSPDS-00-032003 Upstream piping classification line class 150
• IQWQ-FT-LSPDS-00-032004 Upstream piping classification line class 300
Page 4 of 15
Issue Date: 14-08-2019
Iraq Brach
Page 5 of 15
Issue Date: 14-08-2019
Iraq Brach
o Planning and co-ordinate of all manpower and equipment, materials supply, and SUB-
CONTRACTOR services, towards the proper completion of the work on schedule with
approved drawings, specifications and quality limitations.
o Ensure the effective undertaking and completion of all scope identification, planning,
preparation, prefabrication, construction and installation in harmony to the associated
testing requirements.
o Coordinates the parties involved in the construction and testing activities.
o Provide the required resources to execute the pressure test activities.
Page 6 of 15
Issue Date: 14-08-2019
Iraq Brach
• Will conduct the toolbox talk and advice the personnel concerned, radius of effected area, escape
route, emergency procedure, and hazards associated with hose / pipe work / fitting failure under
pressure.
• Shall responsible to comply with all requirements detailed in the permit work.
6. METHODOLOGY
6.1 General
Before Hydro testing of any piping system, it shall be inspected for the following:
• Piping has been erected as per latest approved drawings.
• All supports have been installed correctly and test preparation has been carried out.
SUBCONTRACTOR shall submit the hydro test plan/Test pack with the following documents, prior to
start of the Hydro test for approval from client.
• Marked up P&ID with Test Packs/Hydro test loop
• Isometric drawing latest approved
• Piping check list for testing
• Piping punch list
• Line list approved for construction.
• Weld history sheet
• Piping support installation report
• List of valves include piping test
• Calibration certificate of instruments
• Test Pack Content
• Cover Sheet
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING
Page 7 of 15
Issue Date: 14-08-2019
Iraq Brach
Page 8 of 15
Issue Date: 14-08-2019
Iraq Brach
• In line instruments like control valves, orifice plates, rotameters, safety valves and other
instruments like thermo‐wells which may interfere with flushing instruments shall not be
included in flushing circuit.
• From all permanent strainers the screen/mesh shall be removed before flushing.
Screen/meshes shall be reinstalled after flushing but before testing.
• Precaution shall be taken to prevent entry of foreign matter into equipment, electric motors,
instruments, electrical installations etc. in vicinity of lines being flushed.
• During flushing all flange joint used shall be provided with temporary gaskets.
• After flushing is completed, the required/applicable valves, piping specials etc. shall be
reinstalled with permanent gaskets. However, flanges of equipment nozzles and other places
where isolation is required during testing, only temporary gaskets shall be provided.
Page 9 of 15
Issue Date: 14-08-2019
Iraq Brach
Page 10 of 15
Issue Date: 14-08-2019
Iraq Brach
6.8 Depressurization
• After the acceptance of a successful test, the system shall be immediately depressurized and
vented in a gradual and safe manner. The pressure shall be reduced at a rate such that no
vibrations develop.
• SUBCONTRACTOR shall ensure that the depressurizing carried out safely and completely.
6.9 Dewatering/Draining
• The system shall be dewatered from the lowest available drain point and branch connections if
available.
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING
Page 11 of 15
Issue Date: 14-08-2019
Iraq Brach
• Proper barricading and warning sign boards shall be providing near this activity(s) area for the
safety to avoid any type of incidents and accidents.
• Dewatering of the system shall be carried out after the test/Depressurizing. The water used for
hydrostatic testing shall be collected in the storage tank for further use or for disposal at a
designated area.
• The water from tested piping will be collected first in storage tank from the lowest point by
using diesel driven pump/other suitable that acceptable to Client with connecting hose
assembly. The storage tank and pump assembly will be placed safely at allocated area.
• Then the collected water will be transferred from storage tank to water tanker by using diesel
driven pump with hose assembly to dispose the water in designated area.
• After hydrostatic testing of the system is complete and approved, all lines and equipment shall
be completely drained of the test fluid. Piping systems vents shall be opened while draining to
avoid vacuum. Special attention shall be given to points where water may be trapped, such as
in valve bodies or low points.
• An air compressor designed to deliver high volume dry air shall be connected to the system
high point(s). Air shall be blown continuously until all water has been drain out and the Client
accepts this activity(s).
6.10 Drying
• The drying of the tested piping/system will be carried out after the complete
dewatering/draining activities.
• The drying shall be performed by using air compressor with connecting hose assembly that
safely placed at the allocated area.
• Proper barricading and warning sign boards shall be providing near this activity(s) area to
avoid any type of incidents and accidents.
• Only the allocated personnel shall be allowed in this area during these activities.
• An air compressor designed to deliver high volume dry air shall be connected to the tested
piping/system high point(s). Air shall be blown continuously until piping/system shall be
completely dry.
• Open all the Vent and drain points one by one provided in the piping/system while running the
air compressor to ensure there will not be any water trapped inside.
• The drying activity will be continued until the complete satisfaction and acceptance of Client.
• After the acceptance of drying activity(s), the air-drying report shall be signed by
Calethon/Client for the record and further references.
Page 12 of 15
Issue Date: 14-08-2019
Iraq Brach
7. HSE REQUIREMENTS
• The approved procedure of Health, Safety and Environment shall be followed during the execution.
• An exclusion zone distance of minimum 15 mts (refer to Table 1) shall be considered safe for
hydrotesting. To establish and confirm the distance for higher pressures methods, the following
formula shall be used:
Table 1. Distance from systems to pressure control points and limited access boundaries
• Only authorized personnel as defined/identified shall be allowed within the test area.
• Warning signs in English & shall be placed in prominent about above ground piping and test area to
warn any personnel and public.
• All flexible hoses & fittings shall be checked prior to connecting.
• Proper Personal Protective Equipment (PPE) should be used.
• No stage of activity shall progress without the specific clearance of the Activity in charge.
• Proper lightning arrangement shall be done at site. All electrical circuits, wiring, circuit board etc. shall
be checked for electrical hazard.
• Proper housekeeping shall be maintained throughout the hydrostatic testing operation.
• All activities at heights will be provided with suitable working platform. Properly erected ladders and
scaffoldings shall be used, and safety harness shall be used and secured, where required.
• Scaffolds shall be built by competent people by certified 3rd party.
• All erection, dismantling and modification of scaffolding system shall be as per approved Method
Statement IQWQ-SA-KSMTH-D6-0026 following the Safety Requirements OSHA 1910.28.
• All scaffolding shall be used per safety “Tag” System.
• When working at height, do not allow simultaneous works at same area but different height. Barricade
the area below the work is being carry out.
• All tools/materials will be string tied to prevent accidental dropped object. Use appropriate tool tethers,
such as Tool Belts, Wristbands, Tool Buckets, Tool Holster, etc. in all locations where personnel are
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING
Page 13 of 15
Issue Date: 14-08-2019
Iraq Brach
employed to perform work at height or where they may be exposed to a dropped object by working
below other personnel, tools, equipment and platforms.
• SUBCONTRACTOR Safety Manager shall keep updated the Emergency Response Plan CA-16-041-
WQ0301-0103 and Medical Evacuation Plan CA-16-041-WQ0301-0106 and instruct to the HSE
supervisors to ensure the availability of First Aid kits, escape route signs, emergency call numbers,
emergency assembly point, etc. as well as preparing schedules of exercises and drills periodically.
• All necessary inspections shall be carried out as per ITP approved by CONTRACTOR / COMPANY.
• Prior to start any inspection activity, the Quality Inspector shall raise the IN, sending a written Inspection
Notification to CONTRACTOR 24 Hrs. in advance. The IN must be approved by CONTRACTOR /
COMPANY in order to proceed for the inspection.
• Quality shall be maintained by ensuring the systematic implementation of this procedure and the
necessary quality records shall be generated as per appended formats of the QCP.
• The test equipment shall be calibrated and certified by third party. The certificates and records shall be
kept available during the inspection.
• Supervisor or Foremen shall conduct all the tests and shall be witnessed by CONTRACTOR /
COMPANY. SUBCONTRACTOR Quality Inspector shall be present during the tubing test and recording
the values in the Inspection Forms.
Page 14 of 15
Issue Date: 14-08-2019
Iraq Brach
10. DOCUMENTATION
On completion of hydrostatic testing of piping, SUBCONTRACTOR shall furnish all the Test Reports duly
signed by SUBCONTRACTOR, CONTRACTOR and COMPANY, immediately upon completion of successful
hydrostatic test of piping.
a) Drawing (Mark‐up P&ID)
b) Calibration/Test Certificate
c) Line List (Pressure indicated / highlighted by yellow)
d) ITP Forms in line with CONTRACTOR document IQWQ-SA-QPITP-D6-9631
11. ATTACHMENTS
Risk Assessment CA-16-041-WQ0301-F-0215 - Hydrostatic Activity
Page 15 of 15
Issue Date: 14-08-2019