Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

Iraq Brach

Revision History
Rev A IFA 25/11/18 Rev A
Rev A Received Comments on 24/02/2019
Rev B Revised and Comments incorporated on 26/02/2019
Rev C Comments incorporated. IFA 29/06/2019 Rev C
Rev 0 Issued For Use Rev 0 on 14th August 2019

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 2 of 15
Issue Date: 14-08-2019
Iraq Brach

TABLE OF CONTENTS

1. PURPOSE -------------------------------------------------------------------------------------------------------------------------------------- 4

2. SCOPE OF WORK--------------------------------------------------------------------------------------------------------------------------- 4

3. DEFINITIONS --------------------------------------------------------------------------------------------------------------------------------- 4

4. REFERENCE DOCUMENTS -------------------------------------------------------------------------------------------------------------- 4

5. DUTIES AND RESPONSIBILITIES------------------------------------------------------------------------------------------------------ 5

6. METHODOLOGY----------------------------------------------------------------------------------------------------------------------------- 7

7. HSE REQUIREMENTS -------------------------------------------------------------------------------------------------------------------- 13

8. QUALITY CONTROL REQUIREMENTS ---------------------------------------------------------------------------------------------- 14

9. EQUIPMENT AND TOOLS --------------------------------------------------------------------------------------------------------------- 14

10. DOCUMENTATION ------------------------------------------------------------------------------------------------------------------------- 15

11. ATTACHMENTS----------------------------------------------------------------------------------------------------------------------------- 15

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 3 of 15
Issue Date: 14-08-2019
Iraq Brach

1. PURPOSE
Purpose of this method statement is to establish a detailed method, resources, equipment, quality control
and HSE measures to be planed, prepared and implemented to ensure that the cleaning, water filling,
hydrostatic testing, dewatering and drying of piping systems are performed according the project
specifications within DS6 Major Tie ins Facilities at WQI, Iraq.

2. SCOPE OF WORK
This method statement is made to enumerate the general requirements for inspection, flushing, testing,
dewatering/draining, and drying of piping at the DS6 Major Tie-Ins Facilities at WQI, Iraq. In the event of that
is not fully addressed, SUBCONTRACTOR will perform the Work in accordance with the applicable codes
and best recognized practices in the onshore oil and gas industry. All activities will be performed in strict
compliance with the requirements of the project HSE Method Statements and safe working practices.

3. DEFINITIONS
COMPANY ExxonMobil Iraq Limited (EMIL) - The entity issuing the contract for
the work or their authorized agent
CONTRACTOR SAIPEM S.p.A. Iraq Branch - The entity contracted to perform the
work for the COMPANY
SUBCONTRACTOR Calethon Construction Group
CONTRACT DOCUMENTS The documents that form the CONTRACT issued by the COMPANY
SUBCONTRACT DOCUMENTS The documents that form the subcontract issued by the
CONTRACTOR
WORK Activities to be performed
DS6 Degassing Station 6
WPS Welding Procedure Specification
ITP Inspection and Test Plan
QC Quality Control
MOAP Maximum Allowable Operating Pressure
IFC Issued For Construction
P&ID Piping & Instrument Diagram
HSE Health Safety and Environment

4. REFERENCE DOCUMENTS
• IQWQ-FT-LSPDS-00-031902 Upstream Piping Fabrication, Erection, Inspection, Testing and Cleaning
• IQWQ-FT-LSPDS-00-032002 Upstream piping classification line classes atmospheric and 125
• IQWQ-FT-LSPDS-00-032003 Upstream piping classification line class 150
• IQWQ-FT-LSPDS-00-032004 Upstream piping classification line class 300

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 4 of 15
Issue Date: 14-08-2019
Iraq Brach

• IQWQ-FT-LSPDS-00-032005 Upstream piping classification line class 600


• IQWQ-FT-LSPDS-00-290119 Fasteners for pressure retaining services
• IQWQ-FT-LSPDS-00-030604 Vents, drains, flushing and cleaning
• IQWQ-FT-LSSTD-00-0007 Pipe standard details
• IQWQ-FT-LSPDS-00-0004 Pipe welding data sheets
• IQWQ-SA-KPCEP-D6-0003 Hydro Testing Plan
• ASME 31.3 Process piping
• IQWQ-EI-QSCAS-00-0001 Project Quality Assurance General Requirements
• IQWQ-SA-QPQAC-D6-0001 Project Quality Plan
• IQWQ-SA-QPQAC-D6-0003 Quality Management Requirements for Construction CONTRACTOR
• IQWQ-SA-QPQAC-D6-0004 Quality Control Requirements for Construction SUBCONTRACTOR
• IQWQ-SA-KSMTH-D6-0026 Method Statement For Suspended Scaffold
• OSHA 1910.28 Safety Requirements For Scaffolding
• IQWQ-FT-SPSAF-00-0001 Health, Safety & Environment Plan
• IQWQ-SA-SPSAF-D6-0011 HSE Manual For Construction
• IQWQ-FT-SPSAF-00-0004 Emergency Preparedness and Response Plan
• IQWQ-EI-SSPDS-00-0002 Project Safety Specification for Safety
• CA-16-041-WQ0301-0103 Emergency Response Plan
• CA-16-041-WQ0301-0106 Medical Evacuation Plan
All other specifications mentioned and incorporated into the above referenced documents.

5. DUTIES AND RESPONSIBILITIES


5.1 Construction Manager
 Construction Manager ensures the time, cost, quality, safety and environmental protection
requirements during the construction and erection activities in take place and met:
o Cross checking the procedures defined for site activities are applied.
o Ensuring the achievement of the mechanical completion objective.
 Construction Manager shall ensure the activity is executed in a safe and controlled manner and
ensure that:
o All JSA s mitigation measures shall be implemented before work commences.
o Ensure all Supervisors staffs are familiar with their works, trained and fully aware with
safety requirements for the activities. Planning, direct and monitor the project team.
o Ensure the required resources (manpower, equipment and materials) are on site with
correct quantity and condition.
o Adequate provision of fire and medical equipment.
o Firefighting equipment is located in correct location.

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 5 of 15
Issue Date: 14-08-2019
Iraq Brach

o Planning and co-ordinate of all manpower and equipment, materials supply, and SUB-
CONTRACTOR services, towards the proper completion of the work on schedule with
approved drawings, specifications and quality limitations.
o Ensure the effective undertaking and completion of all scope identification, planning,
preparation, prefabrication, construction and installation in harmony to the associated
testing requirements.
o Coordinates the parties involved in the construction and testing activities.
o Provide the required resources to execute the pressure test activities.

5.2 Hydro test Engineer/Discipline Superintendent


Hydrotest Engineer / Discipline Superintendent will check and give guideline and ensure the work
progress proceed respecting the safety, health and environmental protection requirements. Hydrotest
Engineer / Discipline Superintendent should give unconditional support to the HSE department to
obtain the correct execution of work permit procedure, issuing of JSA and to ensure all safety
measures specified in method statement. Support to HSE department to prepare daily observations,
near miss / accident reports.
• Shall be full in charge of all activities related to pressure operations.
• Ensure that pressure gauges, pressure recorder, temperature recorder, pressure relief valve etc.
shall have valid calibration certificates.
• Responsible for all the calculations and documentation.
• Ensure pressure relief valve fitted to the system to be tested, set at 5% above for hydrotesting and
10 % above for Pneumatic testing, specified test pressure.
• Ensure trained supervisor and proper communication available at site during testing.
• Liaison with COMPANY or his representative(s), and with the HSE Dept. on matters regarding
health, safety and environmental protection.
• Ensure that all construction activities are stopped within the radius of 30 Mts of the testing.
• Display warning signs in English and Arabic (“Danger – High Pressure Test On-Going”) in all entry
points and ensure that no unauthorized persons are within the radius of 30 Mts of the testing.
• Ensure that all personnel are engaged in the job, knows the proper communication and emergency
procedure.
• Ensure that the testing supervisor is properly communicated for operation of all test equipment /
instrumentations.
• Ensure necessary clearance from safety and quality department for the system identified for test.
• Provides means of safeguarding the safety of personnel and equipment working in close vicinity of
the test section.

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 6 of 15
Issue Date: 14-08-2019
Iraq Brach

• Will conduct the toolbox talk and advice the personnel concerned, radius of effected area, escape
route, emergency procedure, and hazards associated with hose / pipe work / fitting failure under
pressure.
• Shall responsible to comply with all requirements detailed in the permit work.

5.3 QA/QC Engineer/Inspector


• Shall be responsible for:
 Conduct inspection activities;
 Check qualification of workforce;
 Implement the requirements of the project quality plan;
 Prepare and verify inspection reports;
 Verify compliance to project quality requirements;
 Identify non-conformities;
 Verify corrective actions.

5.4 HSE Officer


• Shall be responsible for:
 Managing the implementation of all safety requirements during handling operations.

6. METHODOLOGY
6.1 General
Before Hydro testing of any piping system, it shall be inspected for the following:
• Piping has been erected as per latest approved drawings.
• All supports have been installed correctly and test preparation has been carried out.
SUBCONTRACTOR shall submit the hydro test plan/Test pack with the following documents, prior to
start of the Hydro test for approval from client.
• Marked up P&ID with Test Packs/Hydro test loop
• Isometric drawing latest approved
• Piping check list for testing
• Piping punch list
• Line list approved for construction.
• Weld history sheet
• Piping support installation report
• List of valves include piping test
• Calibration certificate of instruments
• Test Pack Content
• Cover Sheet
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 7 of 15
Issue Date: 14-08-2019
Iraq Brach

• Pipe work pre-test Check List


• Pressure Test Safety Instruction Sheet
• Test Pack Isometric Index
• Pre-Test Piping Punch List, PIP-102 Piping correct for system Mechanical Completion
• Flange tightening Report
• PIP-111, P02 Q Piping Installation / Pre- Flushing Hydro Check
• P04 Q Piping system Flushing record
• P05 Q Bolt Tensioning / Torque
• P06 Q Piping Restoration Report
• P07 Q Pipe Cleaning, PIP-107, Piping system Cleaning - Blowing – Flushing Record
• PIP-104, F75201 Q Pressure Test Report
• PIP-107 Piping System Drying and Inerting
• Piping Test Equipment Calibration Record
• Pressure Safety Valve Inspection / Calibration
All the above documents shall be submitted by SUBCONTRACTOR to CONTRACTOR for testing
clearance.

6.2 Flushing by air blowing


• Flushing of all lines shall be done before pressure testing.
• Pipe must be clean to remove any foreign material/debris that may have been left behind
during the construction period. Otherwise, debris from un‐cleaned piping system can lead to
contamination, clogging pipe or control valves, malfunctioning of equipment, or damage of
rotating equipment.
• These methods utilized the kinetic energy of a fluid to dislodge foreign material such as sand,
rust and weld slag.
• Air blowing, using air from a utility air supply or a temporary compressor, can be carried out in
the following ways: In the air ‐ accumulation method, a column, drum or vessel associated
with the pipe is filled with compressed air. Then, the pipe at the downstream end is blown out
by opening the valve. In the direct ‐ blowing method, the pipe to be air ‐ blown is connected to
the air supply source using a temporary pipe or hose. In large diameter pipe (8 inch or more),
where it is difficult to get sufficient velocities for air blowing, the "cardboard‐blasting" method is
applied. First, one end of the pipe is covered by a thin polymer film/cardboard. The pressure is
slowly raised by connecting air through a hose or temporary connection. When the
film/cardboard burst, the shock waves carries the dirt along with it. The blowing or blasting
procedure is repeated until foreign particles are no longer visible in the discharge. If
necessary, the thickness of the film/cardboard can be gradually increased so that higher
pressure can be used.
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 8 of 15
Issue Date: 14-08-2019
Iraq Brach

• In line instruments like control valves, orifice plates, rotameters, safety valves and other
instruments like thermo‐wells which may interfere with flushing instruments shall not be
included in flushing circuit.
• From all permanent strainers the screen/mesh shall be removed before flushing.
Screen/meshes shall be reinstalled after flushing but before testing.
• Precaution shall be taken to prevent entry of foreign matter into equipment, electric motors,
instruments, electrical installations etc. in vicinity of lines being flushed.
• During flushing all flange joint used shall be provided with temporary gaskets.
• After flushing is completed, the required/applicable valves, piping specials etc. shall be
reinstalled with permanent gaskets. However, flanges of equipment nozzles and other places
where isolation is required during testing, only temporary gaskets shall be provided.

6.3 Extent of Testing


• With the exclusion of instrumentation, piping systems fabricated or assembled in the field shall
be tested.
• To facilitate the testing of piping systems, vessels and other equipment may be included in the
system with the approval of client if the test pressure specified is equal to or less than that for
the vessels and other equipment.
• Pumps, compressors and other rotary equipment shall not be subjected to field test pressure.
• Lines which are directly open to atmosphere such as vents, drains, safety valves discharge
need not be tested but all joints be visually inspected, wherever necessary such line shall be
tested by continuous flow of fluid to eliminate the possibility of blockage.
• Seats of all valves shall not be subjected to a pressure in excess of the maximum cold
working pressure of the valve. Test pressure applied to valves shall not be greater than the
manufacturers recommendations nor less than that required by the applicable code. Wherever
allowable seat pressure is less than test pressure, test shall be made through an open valve.
• Instruments in the system to be tested shall be excluded from the test by isolation or
removals, unless approved otherwise by Client.
• Orifice plates shall not be installed unless testing is complete. Control valve should not be
included in the test system. Where bypasses are provided test shall be performed through the
bypass and/ or necessary spool shall be used in place of control valve.
• Pressure gauges which are part of finished system but cannot withstand test pressure shall
not be installed until the system has been tested.
• Testing shall be carried out with permanent gaskets installed unless specified otherwise.
Testing shall not be carried against closed valves.
• Wherever in line any void is existing due to any reason for absence of control valves, check
valves etc. it shall be fitted with temporary spools.
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 9 of 15
Issue Date: 14-08-2019
Iraq Brach

• Weld joints preferred to be painted after hydrostatic testing.


• All joints welded, screwed or flanged shall be cleaned by wire brush to free it from rust and
any other foreign matter.
• Open ends of piping system where blanks cannot be used, shall be blinded off by using blind
flange of same rating.
• Pressure gauges used in testing shall be installed as close as possible to the lowest point in
the piping system to be tested to avoid overstressing of any of the lower portion of the system.
For longer /vertical lines two pressure gauges shall be installed.

6.4 Testing Medium


• In general, all pressure test shall be hydrostatic using water, which is clean and free of slit.
Potable water shall be used for the hydrostatic testing. The water test report shall be
submitted to ensure for its non‐aggressiveness and suitability for using as the test medium.
• For carbon steel pipe systems, potable water with a maximum chloride content of 250 ppm is
preferred. See IQWQ-FT-RSPDS-00-181001 for hydrotesting with non-potable water
• For stainless steel pipe systems, draining procedures, and drying procedures, water quality
shall be in accordance with the section on Hydrostatic Test and Wash Water Quality of IQWQ-
FT-RSPDS-00-181001.
• The test fluids shall be specified in the line list.

6.5 Test Pressure


• Hydrostatic test pressure shall be as indicated and yellow highlighted in the piping isometrics
line list according to attached mark‐up P&ID. For typical Hydrotest pressures, a distance of
minimum 15 Mts shall be considered safe. Refer to Section 7 – HSE Requirements for the
calculation of the exclusion zone distance.

6.6 Pressure Instruments & Equipment


• All Pressure Gauges shall be calibrated. Pressure gauges if required shall be calibrated at site
using Dead weight tester having a valid calibration certificate not older than one year.
• The hydrotest pressure shall be monitored with a bourdon tube pressure gauge that has been
calibrated with a dead weight tester within the last 30days. Maximum scale range of the
pressure gauge should be minimum 1.5 times or 150% of the test pressure. One pressure
gauge should be fixed at the lowest point and the other one should be fixed at the highest
point of the piping system to be tested.
• All pressure & temperature gauges used should have suitable range and valid calibration
certificate.
• Pressure pump shall be of sufficient capacity to enable pressurization within a suitable time

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 10 of 15
Issue Date: 14-08-2019
Iraq Brach

and good Pressure control at all time.


• Pressure and temperature recorder instruments shall be used during pressure hold.

6.7 Testing Method


• All vent points shall be kept open.
• Water shall be introduced in the system from low point to avoid air pocket formation. Vents at
high point shall be left open and not closed until water flows out. All air shall be removed
before pressurizing.
• Close the vent points prior to pressurizing the piping system.
• Pressure shall be applied after the system/line is ready for pressurization.
• The pump shall be attended constantly during the pressurization by an authorized person.
• Pressure shall be applied by means of suitable pump which shall be isolated from the system
as soon as the test pressure is reached and stabilized in the system.
• The rate of pressure increases in approaching the test shall not exceed 5 bar per minute.
• Care shall be taken to avoid increase in the pressure due to temperature variation during the
test.
• After the required test pressure has been attained, all welds, flange joints shall be frequently
inspected. If any leak occurs in the system, it shall be rectified.
• Leakage, if any, noticed during testing shall be rectified immediately and retesting of the
system/line shall be done after rectified.
• Pressure pump shall be disconnected from the system/piping loop during holding period.
• If pressure will rise from specify limit due to temperature, then bleed out the water to maintain
the test pressure.
• Test pressure shall be maintained for a period of minimum two hours. Test duration is Min 2
Hrs.
• During the holding period, pressure & temperature shall be checked every 15 minutes
intervals and it shall be recorded on "Hydrostatic Testing Report for Piping".

6.8 Depressurization
• After the acceptance of a successful test, the system shall be immediately depressurized and
vented in a gradual and safe manner. The pressure shall be reduced at a rate such that no
vibrations develop.
• SUBCONTRACTOR shall ensure that the depressurizing carried out safely and completely.

6.9 Dewatering/Draining
• The system shall be dewatered from the lowest available drain point and branch connections if
available.
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 11 of 15
Issue Date: 14-08-2019
Iraq Brach

• Proper barricading and warning sign boards shall be providing near this activity(s) area for the
safety to avoid any type of incidents and accidents.
• Dewatering of the system shall be carried out after the test/Depressurizing. The water used for
hydrostatic testing shall be collected in the storage tank for further use or for disposal at a
designated area.
• The water from tested piping will be collected first in storage tank from the lowest point by
using diesel driven pump/other suitable that acceptable to Client with connecting hose
assembly. The storage tank and pump assembly will be placed safely at allocated area.
• Then the collected water will be transferred from storage tank to water tanker by using diesel
driven pump with hose assembly to dispose the water in designated area.
• After hydrostatic testing of the system is complete and approved, all lines and equipment shall
be completely drained of the test fluid. Piping systems vents shall be opened while draining to
avoid vacuum. Special attention shall be given to points where water may be trapped, such as
in valve bodies or low points.
• An air compressor designed to deliver high volume dry air shall be connected to the system
high point(s). Air shall be blown continuously until all water has been drain out and the Client
accepts this activity(s).

6.10 Drying
• The drying of the tested piping/system will be carried out after the complete
dewatering/draining activities.
• The drying shall be performed by using air compressor with connecting hose assembly that
safely placed at the allocated area.
• Proper barricading and warning sign boards shall be providing near this activity(s) area to
avoid any type of incidents and accidents.
• Only the allocated personnel shall be allowed in this area during these activities.
• An air compressor designed to deliver high volume dry air shall be connected to the tested
piping/system high point(s). Air shall be blown continuously until piping/system shall be
completely dry.
• Open all the Vent and drain points one by one provided in the piping/system while running the
air compressor to ensure there will not be any water trapped inside.
• The drying activity will be continued until the complete satisfaction and acceptance of Client.
• After the acceptance of drying activity(s), the air-drying report shall be signed by
Calethon/Client for the record and further references.

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 12 of 15
Issue Date: 14-08-2019
Iraq Brach

7. HSE REQUIREMENTS
• The approved procedure of Health, Safety and Environment shall be followed during the execution.
• An exclusion zone distance of minimum 15 mts (refer to Table 1) shall be considered safe for
hydrotesting. To establish and confirm the distance for higher pressures methods, the following
formula shall be used:

Table 1. Distance from systems to pressure control points and limited access boundaries

• Only authorized personnel as defined/identified shall be allowed within the test area.
• Warning signs in English & shall be placed in prominent about above ground piping and test area to
warn any personnel and public.
• All flexible hoses & fittings shall be checked prior to connecting.
• Proper Personal Protective Equipment (PPE) should be used.
• No stage of activity shall progress without the specific clearance of the Activity in charge.
• Proper lightning arrangement shall be done at site. All electrical circuits, wiring, circuit board etc. shall
be checked for electrical hazard.
• Proper housekeeping shall be maintained throughout the hydrostatic testing operation.
• All activities at heights will be provided with suitable working platform. Properly erected ladders and
scaffoldings shall be used, and safety harness shall be used and secured, where required.
• Scaffolds shall be built by competent people by certified 3rd party.
• All erection, dismantling and modification of scaffolding system shall be as per approved Method
Statement IQWQ-SA-KSMTH-D6-0026 following the Safety Requirements OSHA 1910.28.
• All scaffolding shall be used per safety “Tag” System.
• When working at height, do not allow simultaneous works at same area but different height. Barricade
the area below the work is being carry out.
• All tools/materials will be string tied to prevent accidental dropped object. Use appropriate tool tethers,
such as Tool Belts, Wristbands, Tool Buckets, Tool Holster, etc. in all locations where personnel are
DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0
METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 13 of 15
Issue Date: 14-08-2019
Iraq Brach

employed to perform work at height or where they may be exposed to a dropped object by working
below other personnel, tools, equipment and platforms.
• SUBCONTRACTOR Safety Manager shall keep updated the Emergency Response Plan CA-16-041-
WQ0301-0103 and Medical Evacuation Plan CA-16-041-WQ0301-0106 and instruct to the HSE
supervisors to ensure the availability of First Aid kits, escape route signs, emergency call numbers,
emergency assembly point, etc. as well as preparing schedules of exercises and drills periodically.

8. QUALITY CONTROL REQUIREMENTS

• All necessary inspections shall be carried out as per ITP approved by CONTRACTOR / COMPANY.
• Prior to start any inspection activity, the Quality Inspector shall raise the IN, sending a written Inspection
Notification to CONTRACTOR 24 Hrs. in advance. The IN must be approved by CONTRACTOR /
COMPANY in order to proceed for the inspection.
• Quality shall be maintained by ensuring the systematic implementation of this procedure and the
necessary quality records shall be generated as per appended formats of the QCP.
• The test equipment shall be calibrated and certified by third party. The certificates and records shall be
kept available during the inspection.
• Supervisor or Foremen shall conduct all the tests and shall be witnessed by CONTRACTOR /
COMPANY. SUBCONTRACTOR Quality Inspector shall be present during the tubing test and recording
the values in the Inspection Forms.

9. EQUIPMENT AND TOOLS


Following are the minimum tools and equipment required to perform the activities:
 Water Tanker
 Test Manifolds
 Test Pumps
 Dewatering Pumps
 Air compressor
 Diesel Generator
 Tower Light
 Boom Truck
 Torque Wrench
 Hand tools
Other alternative tools or equipment as required and previously approved by CONTRACTOR/COMPANY.

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 14 of 15
Issue Date: 14-08-2019
Iraq Brach

10. DOCUMENTATION
On completion of hydrostatic testing of piping, SUBCONTRACTOR shall furnish all the Test Reports duly
signed by SUBCONTRACTOR, CONTRACTOR and COMPANY, immediately upon completion of successful
hydrostatic test of piping.
a) Drawing (Mark‐up P&ID)
b) Calibration/Test Certificate
c) Line List (Pressure indicated / highlighted by yellow)
d) ITP Forms in line with CONTRACTOR document IQWQ-SA-QPITP-D6-9631

11. ATTACHMENTS
 Risk Assessment CA-16-041-WQ0301-F-0215 - Hydrostatic Activity

DOC No: IQWQ-SA-KSMTH-D6-0008 Rev 0


METHOD STATEMENT FOR HYDROSTATIC TESTING, DEWATERING/DRAINING AND DRYING OF PIPING

Page 15 of 15
Issue Date: 14-08-2019

You might also like