PLANNED PROCUREMENT PROGRESS UPTO 30-04-2021-REPORT

PROGRESS UPTO Actual MPR MPR MPR


Activities Type Starting Finish Activity Status
30-4-2021 Status Item WEIGHT % ACTIVITY %

1 Reinforcement P.O 6/14/2020 6/30/2020 30/04/2021 Completed


2 backfill material P.O 6/14/2020 6/24/2020 30/04/2021 Completed
3 constrction Material (CHB WALL) P.O 6/14/2020 6/24/2020 30/04/2021 Completed
4 Sevage system P.O 6/14/2020 4/8/2020 30/04/2021 Completed
5 sanitary material and equipment P.O 6/14/2020 4/8/2020 30/04/2021 Completed
6 kitchen equipment and accessories P.O 6/14/2020 9/26/2020 30/04/2021 Completed
7 roofing material P.O 6/14/2020 9/26/2020 30/04/2021 Completed
8 roof drain system material P.O 6/14/2020 8/22/2020 30/04/2021 Completed
9 plumbing and fixtures P.O 6/14/2020 12/7/2020 30/04/2021 Completed
10 joint sealing material P.O 6/14/2020 8/22/2020 30/04/2021 Completed
11 wall and floor finishing material P.O 6/14/2020 8/22/2020 30/04/2021 Completed
12 preparation of purchase order P.O 7/13/2020 7/23/2020 30/04/2021 Completed 2.1.6 0.07 0.07
13 false floor P.O 5/8/2020 1/26/2021 30/04/2021 Completed
14 suspendedceiling P.O 5/8/2020 1/26/2021 30/04/2021 Completed
15 ceramic tiles P.O 5/8/2020 12/22/2020 30/04/2021 Completed
16 windowsand doors P.O 5/8/2020 12/22/2020 30/04/2021 Completed
17 steel ladders P.O 5/8/2020 1/26/2021 30/04/2021 Completed
18 wash room equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
19 launch room equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
20 store and photocopy room equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
21 locker room equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
22 training room equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
23 supervisor room equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
24 office rooms equipment and material P.O 5/8/2020 2/3/2021 30/04/2021 Completed
25 preparation of purchase order P.O 7/7/2020 7/18/2020 30/04/2021 Completed 2.1.7 0.07 0.07
26 main distribution panel MDP-1 P.O 7/30/2020 1/2/2021 30/04/2021 Completed 3.1.3.1 0.02 0.02
27 distribution panel DP-1 P.O 7/30/2020 1/2/2021 30/04/2021 Completed 3.1.3.2 0.02 0.02
28 Lghting panel LP-1 P.O 7/30/2020 1/2/2021 30/04/2021 Completed 3.1.3.3 0.02 0.02
29 Dry type transformer P.O 7/30/2020 2/24/2021 30/04/2021 Completed 3.1.3.4 0.02 0.02
30 power cables P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.3.5 0.02 0.02
31 recepticles lighting fixtures andswitches P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.3.6 0.02 0.02
32 conduuits andcable glands P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.3.7 0.02 0.02
33 junction boxes P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.3.8 0.01 0.01
34 grounding material P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.3.9 0.01 0.01
35 miscelleneous consumable electrical material P.O 7/30/2020 1/20/2021 30/04/2021 Completed
36 preparation of purchase order P.O 7/7/2020 7/18/2020 30/04/2021 Completed 2.1.8 0.07 0.07
37 Fiber optic cables P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.4.1 0.08 0.08
38 telephone and computer network cables and accessories P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.4.2 0.08 0.08
39 fire alarm system devices P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.4.3 0.08 0.08
40 fire alarm control panel P.O 7/30/2020 1/20/2021 30/04/2021 Completed 3.1.4.4 0.08 0.08
41 multipair signal cable P.O 7/30/2020 2/3/2021 30/04/2021 Completed 3.1.4.5 0.08 0.08
42 preparation of purchase order P.O 7/13/2020 7/23/2020 30/04/2021 Completed 2.1.9 0.07 0.07
43 central air conditioning units P.O 5/8/2020 2/3/2021 30/04/2021 Completed 3.1.1.1 0.2 0.2
44 air conditioning split units P.O 5/8/2020 2/3/2021 30/04/2021 Completed 3.1.1.2 0.05 0.05
45 air conditioning ducts P.O 5/8/2020 2/3/2021 30/04/2021 Completed 3.1.1.3 0.05 0.05
46 air conditioning accessories (diffuser,grill,damper,fans etc..) P.O 5/8/2020 2/3/2021 30/04/2021 Completed 3.1.1.4 0.05 0.05
47 Purchase order for F&G Detectors P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.14 0.04 0.04
48 Purchase order for ESD Valves P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.15 0.04 0.04
49 Purchase order for logic solver and ESD cabinet P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.16 0.04 0.04
50 Purchase order for pressure transmitters P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.17 0.04 0.04
51 purchase order for cables P.O 16/08/2020 18/08/2020 30/04/2021 Completed 2.2.2.22 0.04 0.04
52 purchase order for cable trays and conduits P.O 16/08/2020 18/08/2020 30/04/2021 Completed 2.2.2.23 0.04 0.04
53 purchase order for junction boxes and cable glands P.O 05/09/2020 07/09/2020 30/04/2021 Completed 2.2.2.24 0.04 0.04
54 purchase order for piping material P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.6 0.04 0.04
55 purchase order for valves larger than 2 inch P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.7 0.04 0.04
56 purchase order for smaller than 2 inch P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.8 0.04 0.04
57 purchase order for insulation and fire proofing P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.9 0.04 0.04
58 purchase order for pressure safety valves P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.10 0.04 0.04
59 purchase order for paint P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.11 0.04 0.04
60 PURCHASE order for contro valves P.O 20/08/2020 27/08/2020 30/04/2021 Completed 2.2.6.9 0.05 0.05
61 PurchaSE order for blowdown valves P.O 22/09/2020 29/09/2020 30/04/2021 Completed 2.2.6.10 0.05 0.05
62 Purchase order for PLC/DCS P.O 22/09/2020 29/09/2020 30/04/2021 Completed 2.2.6.11 0.05 0.05
63 PURCHASE ORDER for field instruments P.O 19/10/2020 03/11/2020 30/04/2021 Completed 2.2.6.19 0.05 0.05
64 purchase order for cables P.O 19/10/2020 26/10/2020 30/04/2021 Completed 2.2.6.20 0.05 0.05
65 purchase order for cable trays and conduits P.O 19/10/2020 26/10/2020 30/04/2021 Completed 2.2.6.21 0.05 0.05
66 purchase order for junction boxesand cable glnds P.O 21/11/2020 28/11/2020 30/04/2021 Completed 2.2.6.22 0.05 0.05
67 purchase order for FM200 System P.O 15/08/2020 19/08/2020 30/04/2021 Completed 2.2.4.7 0.03 0.03
68 Purchase Order for Compressors and Dryers P.O 28/10/2020 08/11/2020 30/04/2021 Completed 2.2.8.12 0.02 0.02
69 Purchase Order for piping and valves P.O 28/10/2020 08/11/2020 30/04/2021 Completed 2.2.8.13 0.02 0.02
70 Purchase Order for Pressure Regulating Valves P.O 25/11/2020 06/12/2020 30/04/2021 Completed 2.2.8.14 0.02 0.02
71 Purchase Order for Moisture Analysers P.O 25/11/2020 06/12/2020 30/04/2021 Completed 2.2.8.15 0.02 0.02
72 Purchase Order for Telephone System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.9 0.02 0.02
73 Purchase Order for Intercom System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.10 0.02 0.02
74 Purchase Order for CCTV System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.11 0.02 0.02
75 Purchase Order for Communication Cables P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.12 0.02 0.02
76 Purchase Order for Fire Alarm System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.13 0.02 0.02
77 Purchase Order for Power Supply Cables P.O 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.15 0.02 0.02
78 Purchase Order for Power Transformers P.O 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.16 0.02 0.02
79 Purchase Order for LV Switchgear and MCC's P.O 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.17 0.02 0.02
80 Purchase Order for Cable Trays & Conduits P.O 01/03/2020 05/03/2020 30/04/2021 Completed 2.2.5.18 0.02 0.02
81 Purchase Order for Junction Boxes and Cable Glands P.O 01/03/2020 05/03/2020 30/04/2021 Completed 2.2.5.19 0.02 0.02
82 Purchase Order for UPS P.O 15/10/2020 20/10/2020 30/04/2021 Completed 2.2.5.20 0.01 0.01
83 Purchase Order for Grounding P.O 26/10/2020 10/11/2020 30/04/2021 Completed 2.2.5.23 0.01 0.01
84 Purchase Order for Lighting P.O 26/10/2020 10/11/2020 30/04/2021 Completed 2.2.5.24 0.01 0.01
85 F&G Detectors for ESD System P.O 14/10/2020 18/04/2021 30/04/2021 Completed 3.2.3.3.1 2.4 2.4
86 ESD VALVES P.O 14/10/2020 01/08/2021 30/04/2021 Not Completed 3.2.1.5.1 5.23
87 logic solver and ESD Cabinets P.O 14/10/2020 23/05/2021 30/04/2021 Not Completed 3.2.3.2 6.08
88 pressure transmitters P.O 14/10/2020 25/03/2021 30/04/2021 Completed 3.2.3.3.2 0.2 0.2
89 cables P.O 05/09/2020 14/02/2021 30/04/2021 Completed 3.2.3.4.1 0.39 0.39
90 cable tray and conduits P.O 05/09/2020 14/02/2021 30/04/2021 Completed 3.2.3.5.1 0.13 0.13
91 junction box and cables glands P.O 24/09/2020 29/03/2021 30/04/2021 Completed 3.2.3.5.3 0.21 0.21
92 tie-in and welding P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.2 0.14 0.14
93 valves larger than 2 inch P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.7 1.54 1.54
94 valves sma;;er than 2inch P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.6 0.7 0.7
95 insulation and fire proofing P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.9 0.28 0.28
96 pressure safety valves P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.4 0.84 0.84
97 painting and wrapping P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.5 0.33 0.33
98 CONROL Valves P.O 22/09/2020 02/08/2021 30/04/2021 Not Completed 3.2.1.3 4.28
99 blowdown valves P.O 17/10/2020 03/08/2021 30/04/2021 Not Completed 3.2.1.5.2 2.6
100 PLC/DCS P.O 17/10/2020 25/05/2021 30/04/2021 Not Completed 3.2.3.1 6.42
101 Field instrurmtns P.O 21/11/2020 25/05/2021 30/04/2021 Not Completed 3.2.3.3.3 15.31
102 cables P.O 21/11/2020 02/05/2021 30/04/2021 Not Completed 3.2.3.4.2 1.04
103 cable tray and conduits P.O 21/11/2020 02/05/2021 30/04/2021 Not Completed 3.2.3.5.2 0.26
104 junction boxes and cable glands P.O 15/12/2020 19/06/2021 30/04/2021 Not Completed 3.2.3.5.4 0.41
105 Bulk material P.O 31+12-2020 31/05/2021 30/04/2021 Not Completed 3.2.3.7 0.34
106 Compressors&Dryers P.O 25/11/2020 22/06/2021 30/04/2021 Not Completed 3.2.7.1 1.63
107 Piping and Valves P.O 25/11/2020 18/05/2021 30/04/2021 Not Completed 3.2.7.2 0.16
108 Pressure Regulating Valves P.O 23/12/2020 24/08/2021 30/04/2021 Not Completed 3.2.7.3 0.16
109 moisture analyzer P.O 23/12/2020 20/07/2021 30/04/2021 Not Completed 3.2.3.6 0.34
110 Telephone System P.O 01/08/2020 21/01/2021 30/04/2021 Completed 3.2.4.1 0.33 0.33
111 Intercom System P.O 01/08/2020 21/01/2021 30/04/2021 Completed 3.2.4.2 0.55 0.55
112 CCTV System P.O 01/08/2020 02/02/2021 30/04/2021 Completed 3.2.4.4 1.17 1.17
113 Fire Alarm system P.O 01/08/2020 02/02/2021 30/04/2021 Completed 3.2.4.3 1.2 1.2
114 communication cables P.O 01/08/2020 10/01/2021 30/04/2021 Completed 3.2.3.4.3 0.26 0.26
115 13.8 KV Cable Connection & Installation P.O 15/10/2020 27/03/2021 30/04/2021 Completed 3.2.2.1 0.93 0.93
116 power cables P.O 15/10/2020 27/03/2021 30/04/2021 Completed 3.2.2.4 0.68 0.68
117 Power Transformers P.O 15/10/2020 16/06/2021 30/04/2021 Not Completed 3.2.2.3 1.27
118 LV swithgear and MCCs P.O 15/10/2020 24/05/2021 30/04/2021 Not Completed 3.2.2.2 3.46
119 Bus bar ducts P.O 15/10/2020 24/05/2021 30/04/2021 Not Completed 3.2.2.9 0.68
120 cable tray and conduits P.O 15/10/2020 27/03/2021 30/04/2021 Completed 3.2.2.5.1 0.2 0.2
121 junction boxes and cable glands P.O 15/10/2020 07/04/2021 30/04/2021 Completed 3.2.2.5.2 0.23 0.23
122 UPS P.O 17/11/2020 03/06/2021 30/04/2021 Not Completed 3.2.2.6 0.34
123 grounding material P.O 28/11/2020 27/04/2021 30/04/2021 Completed 3.2.2.7 0.17 0.17
124 lighting material P.O 28/11/2020 27/04/2021 30/04/2021 Completed 3.2.2.8 0.51 0.51
TOTAL 15.79
PLANNED PROCUREMENT PROGRESS UPTO 31-05-2021-REPORT
Activities Type Starting Finish PROGRESS UPTO Activity Status Actual MPR MPR MPR
31-5-2021 Status Item WEIGHT % ACTIVITY %
1 Reinforcement P.O 6/14/2020 6/30/2020 31/05/2021 Completed
2 backfill material P.O 6/14/2020 6/24/2020 31/05/2021 Completed
3 constrction Material (CHB WALL) P.O 6/14/2020 6/24/2020 31/05/2021 Completed
4 Sevage system P.O 6/14/2020 4/8/2020 31/05/2021 Completed
5 sanitary material and equipment P.O 6/14/2020 4/8/2020 31/05/2021 Completed
6 kitchen equipment and accessories P.O 6/14/2020 9/26/2020 31/05/2021 Completed
7 roofing material P.O 6/14/2020 9/26/2020 31/05/2021 Completed
8 roof drain system material P.O 6/14/2020 8/22/2020 31/05/2021 Completed
9 plumbing and fixtures P.O 6/14/2020 12/7/2020 31/05/2021 Completed
10 joint sealing material P.O 6/14/2020 8/22/2020 31/05/2021 Completed
11 wall and floor finishing material P.O 6/14/2020 8/22/2020 31/05/2021 Completed
12 preparation of purchase order P.O 7/13/2020 7/23/2020 31/05/2021 Completed 2.1.6 0.07 0.07
13 false floor P.O 5/8/2020 1/26/2021 31/05/2021 Completed
14 suspendedceiling P.O 5/8/2020 1/26/2021 31/05/2021 Completed
15 ceramic tiles P.O 5/8/2020 12/22/2020 31/05/2021 Completed
16 windowsand doors P.O 5/8/2020 12/22/2020 31/05/2021 Completed
17 steel ladders P.O 5/8/2020 1/26/2021 31/05/2021 Completed
18 wash room equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
19 launch room equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
20 store and photocopy room equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
21 locker room equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
22 training room equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
23 supervisor room equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
24 office rooms equipment and material P.O 5/8/2020 2/3/2021 31/05/2021 Completed
25 preparation of purchase order P.O 7/7/2020 7/18/2020 31/05/2021 Completed 2.1.7 0.07 0.07
26 main distribution panel MDP-1 P.O 7/30/2020 1/2/2021 31/05/2021 Completed 3.1.3.1 0.02 0.02
27 distribution panel DP-1 P.O 7/30/2020 1/2/2021 31/05/2021 Completed 3.1.3.2 0.02 0.02
28 Lghting panel LP-1 P.O 7/30/2020 1/2/2021 31/05/2021 Completed 3.1.3.3 0.02 0.02
29 Dry type transformer P.O 7/30/2020 2/24/2021 31/05/2021 Completed 3.1.3.4 0.02 0.02
30 power cables P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.3.5 0.02 0.02
31 recepticles lighting fixtures andswitches P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.3.6 0.02 0.02
32 conduuits andcable glands P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.3.7 0.02 0.02
33 junction boxes P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.3.8 0.01 0.01
34 grounding material P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.3.9 0.01 0.01
35 miscelleneous consumable electrical material P.O 7/30/2020 1/20/2021 31/05/2021 Completed
36 preparation of purchase order P.O 7/7/2020 7/18/2020 31/05/2021 Completed 2.1.8 0.07 0.07
37 Fiber optic cables P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.4.1 0.08 0.08
38 telephone and computer network cables and accessories P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.4.2 0.08 0.08
39 fire alarm system devices P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.4.3 0.08 0.08
40 fire alarm control panel P.O 7/30/2020 1/20/2021 31/05/2021 Completed 3.1.4.4 0.08 0.08
41 multipair signal cable P.O 7/30/2020 2/3/2021 31/05/2021 Completed 3.1.4.5 0.08 0.08
42 preparation of purchase order P.O 7/13/2020 7/23/2020 31/05/2021 Completed 2.1.9 0.07 0.07
43 central air conditioning units P.O 5/8/2020 2/3/2021 31/05/2021 Completed 3.1.1.1 0.2 0.2
44 air conditioning split units P.O 5/8/2020 2/3/2021 31/05/2021 Completed 3.1.1.2 0.05 0.05
45 air conditioning ducts P.O 5/8/2020 2/3/2021 31/05/2021 Completed 3.1.1.3 0.05 0.05
46 air conditioning accessories (diffuser,grill,damper,fans etc..) P.O 5/8/2020 2/3/2021 31/05/2021 Completed 3.1.1.4 0.05 0.05
47 Purchase order for F&G Detectors P.O 12/09/2020 27/09/2020 31/05/2021 Completed 2.2.2.14 0.04 0.04
48 Purchase order for ESD Valves P.O 12/09/2020 27/09/2020 31/05/2021 Completed 2.2.2.15 0.04 0.04
49 Purchase order for logic solver and ESD cabinet P.O 12/09/2020 27/09/2020 31/05/2021 Completed 2.2.2.16 0.04 0.04
50 Purchase order for pressure transmitters P.O 12/09/2020 27/09/2020 31/05/2021 Completed 2.2.2.17 0.04 0.04
51 purchase order for cables P.O 16/08/2020 18/08/2020 31/05/2021 Completed 2.2.2.22 0.04 0.04
52 purchase order for cable trays and conduits P.O 16/08/2020 18/08/2020 31/05/2021 Completed 2.2.2.23 0.04 0.04
53 purchase order for junction boxes and cable glands P.O 05/09/2020 07/09/2020 31/05/2021 Completed 2.2.2.24 0.04 0.04
54 purchase order for piping material P.O 22/10/2020 29/10/2020 31/05/2021 Completed 2.2.3.6 0.04 0.04
55 purchase order for valves larger than 2 inch P.O 22/10/2020 29/10/2020 31/05/2021 Completed 2.2.3.7 0.04 0.04
56 purchase order for smaller than 2 inch P.O 22/10/2020 29/10/2020 31/05/2021 Completed 2.2.3.8 0.04 0.04
57 purchase order for insulation and fire proofing P.O 22/10/2020 29/10/2020 31/05/2021 Completed 2.2.3.9 0.04 0.04
58 purchase order for pressure safety valves P.O 22/10/2020 29/10/2020 31/05/2021 Completed 2.2.3.10 0.04 0.04
59 purchase order for paint P.O 22/10/2020 29/10/2020 31/05/2021 Completed 2.2.3.11 0.04 0.04
60 PURCHASE order for contro valves P.O 20/08/2020 27/08/2020 31/05/2021 Completed 2.2.6.9 0.05 0.05
61 PurchaSE order for blowdown valves P.O 22/09/2020 29/09/2020 31/05/2021 Completed 2.2.6.10 0.05 0.05
62 Purchase order for PLC/DCS P.O 22/09/2020 29/09/2020 31/05/2021 Completed 2.2.6.11 0.05 0.05
63 PURCHASE ORDER for field instruments P.O 19/10/2020 03/11/2020 31/05/2021 Completed 2.2.6.19 0.05 0.05
64 purchase order for cables P.O 19/10/2020 26/10/2020 31/05/2021 Completed 2.2.6.20 0.05 0.05
65 purchase order for cable trays and conduits P.O 19/10/2020 26/10/2020
31/05/2021 Completed 2.2.6.21 0.05 0.05
66 purchase order for junction boxesand cable glands P.O 21/11/2020 28/11/2020 31/05/2021 Completed 2.2.6.22 0.05 0.05
67 purchase order for FM200 System P.O 15/08/2020 19/08/2020 31/05/2021 Completed 2.2.4.7 0.03 0.03
68 Purchase Order for Compressors and Dryers P.O 28/10/2020 08/11/2020 31/05/2021 Completed 2.2.8.12 0.02 0.02
69 Purchase Order for piping and valves P.O 28/10/2020 08/11/2020 31/05/2021 Completed 2.2.8.13 0.02 0.02
70 Purchase Order for Pressure Regulating Valves P.O 25/11/2020 06/12/2020 31/05/2021 Completed 2.2.8.14 0.02 0.02
71 Purchase Order for Moisture Analysers P.O 25/11/2020 06/12/2020 31/05/2021 Completed 2.2.8.15 0.02 0.02
72 Purchase Order for Telephone System P.O 09/07/2020 14/07/2020 31/05/2021 Completed 2.2.7.9 0.02 0.02
73 Purchase Order for Intercom System P.O 09/07/2020 14/07/2020 31/05/2021 Completed 2.2.7.10 0.02 0.02
74 Purchase Order for CCTV System P.O 09/07/2020 14/07/2020 31/05/2021 Completed 2.2.7.11 0.02 0.02
75 Purchase Order for Communication Cables P.O 09/07/2020 14/07/2020 31/05/2021 Completed 2.2.7.12 0.02 0.02
76 Purchase Order for Fire Alarm System P.O 09/07/2020 14/07/2020 31/05/2021 Completed 2.2.7.13 0.02 0.02
77 Purchase Order for Power Supply Cables P.O 23/09/2020 28/09/2020 31/05/2021 Completed 2.2.5.15 0.02 0.02
78 Purchase Order for Power Transformers P.O 23/09/2020 28/09/2020 31/05/2021 Completed 2.2.5.16 0.02 0.02
79 Purchase Order for LV Switchgear and MCC's P.O 23/09/2020 28/09/2020 31/05/2021 Completed 2.2.5.17 0.02 0.02
80 Purchase Order for Cable Trays & Conduits P.O 01/03/2020 05/03/2020 31/05/2021 Completed 2.2.5.18 0.02 0.02
81 Purchase Order for Junction Boxes and Cable Glands P.O 01/03/2020 05/03/2020 31/05/2021 Completed 2.2.5.19 0.02 0.02
82 Purchase Order for UPS P.O 15/10/2020 20/10/2020 31/05/2021 Completed 2.2.5.20 0.01 0.01
83 Purchase Order for Grounding P.O 26/10/2020 10/11/2020 31/05/2021 Completed 2.2.5.23 0.01 0.01
84 Purchase Order for Lighting P.O 26/10/2020 10/11/2020 31/05/2021 Completed 2.2.5.24 0.01 0.01
85 F&G Detectors for ESD System P.O 14/10/2020 18/04/2021 31/05/2021 Completed 3.2.3.3.1 2.4 2.4
86 ESD VALVES P.O 14/10/2020 01/08/2021 31/05/2021 Not Completed 3.2.1.5.1 5.23
87 logic solver and ESD Cabinets P.O 14/10/2020 23/05/2021 31/05/2021 Completed 3.2.3.2 6.08 6.08
88 pressure transmitters P.O 14/10/2020 25/03/2021 31/05/2021 Completed 3.2.3.3.2 0.2 0.2
89 cables P.O 05/09/2020 14/02/2021 31/05/2021 Completed 3.2.3.4.1 0.39 0.39
90 cable tray and conduits P.O 05/09/2020 14/02/2021 31/05/2021 Completed 3.2.3.5.1 0.13 0.13
91 junction box and cables glands P.O 24/09/2020 29/03/2021 31/05/2021 Completed 3.2.3.5.3 0.21 0.21
92 tie-in and welding P.O 16/11/2020 27/04/2021 31/05/2021 Completed 3.2.1.2 0.14 0.14
93 valves larger than 2 inch P.O 16/11/2020 27/04/2021 31/05/2021 Completed 3.2.1.7 1.54 1.54
94 valves sma;;er than 2inch P.O 16/11/2020 27/04/2021 31/05/2021 Completed 3.2.1.6 0.7 0.7
95 insulation and fire proofing P.O 16/11/2020 27/04/2021 31/05/2021 Completed 3.2.1.9 0.28 0.28
96 pressure safety valves P.O 16/11/2020 27/04/2021 31/05/2021 Completed 3.2.1.4 0.84 0.84
97 painting and wrapping P.O 16/11/2020 27/04/2021 31/05/2021 Completed 3.2.5 0.33 0.33
98 CONROL Valves P.O 22/09/2020 02/08/2021 31/05/2021 Not Completed 3.2.1.3 4.28
99 blowdown valves P.O 17/10/2020 03/08/2021 31/05/2021 Not Completed 3.2.1.5.2 2.6
100 PLC/DCS P.O 17/10/2020 25/05/2021 31/05/2021 Completed 3.2.3.1 6.42 6.42
101 Field instrurmtns P.O 21/11/2020 25/05/2021 31/05/2021 Completed 3.2.3.3.3 15.31 15.31
102 cables P.O 21/11/2020 02/05/2021 31/05/2021 Completed 3.2.3.4.2 1.04 1.04
103 cable tray and conduits P.O 21/11/2020 02/05/2021 31/05/2021 Completed 3.2.3.5.2 0.26 0.26
104 junction boxes and cable glands P.O 15/12/2020 19/06/2021 31/05/2021 Not Completed 3.2.3.5.4 0.41
105 Bulk material P.O 31+12-2020 31/05/2021 31/05/2021 Completed 3.2.3.7 0.34 0.34
106 Compressors&Dryers P.O 25/11/2020 22/06/2021 31/05/2021 Not Completed 3.2.7.1 1.63
107 Piping and Valves P.O 25/11/2020 18/05/2021 31/05/2021 Completed 3.2.7.2 0.16 0.16
108 Pressure Regulating Valves P.O 23/12/2020 24/08/2021 31/05/2021 Not Completed 3.2.7.3 0.16
109 moisture analyzer P.O 23/12/2020 20/07/2021 31/05/2021 Not Completed 3.2.3.6 0.34
110 Telephone System P.O 01/08/2020 21/01/2021 31/05/2021 Completed 3.2.4.1 0.33 0.33
111 Intercom System P.O 01/08/2020 21/01/2021 31/05/2021 Completed 3.2.4.2 0.55 0.55
112 CCTV System P.O 01/08/2020 02/02/2021 31/05/2021 Completed 3.2.4.4 1.17 1.17
113 Fire Alarm system P.O 01/08/2020 02/02/2021 31/05/2021 Completed 3.2.4.3 1.2 1.2
114 communication cables P.O 01/08/2020 10/01/2021 31/05/2021 Completed 3.2.3.4.3 0.26 0.26
115 13.8 KV Cable Connection & Installation P.O 15/10/2020 27/03/2021 31/05/2021 Completed 3.2.2.1 0.93 0.93
116 power cables P.O 15/10/2020 27/03/2021 31/05/2021 Completed 3.2.2.4 0.68 0.68
117 Power Transformers P.O 15/10/2020 16/06/2021 31/05/2021 Not Completed 3.2.2.3 1.27
118 LV swithgear and MCCs P.O 15/10/2020 24/05/2021 31/05/2021 Completed 3.2.2.2 3.46 3.46
119 Bus bar ducts P.O 15/10/2020 24/05/2021 31/05/2021 Completed 3.2.2.9 0.68 0.68
120 cable tray and conduits P.O 15/10/2020 27/03/2021 31/05/2021 Completed 3.2.2.5.1 0.2 0.2
121 junction boxes and cable glands P.O 15/10/2020 07/04/2021 31/05/2021 Completed 3.2.2.5.2 0.23 0.23
122 UPS P.O 17/11/2020 03/06/2021 31/05/2021 Not Completed 3.2.2.6 0.34
123 grounding material P.O 28/11/2020 27/04/2021 31/05/2021 Completed 3.2.2.7 0.17 0.17
124 lighting material P.O 28/11/2020 27/04/2021 31/05/2021 Completed 3.2.2.8 0.51 0.51
TOTAL 49.54