Company: Palmer's & Associates Company Ltd.

Project: Construct a Primary School


Author: APalmer
Account: Enter Account Code for Project
Date: Dec 19,2019

Dec 30,2019 91+ Mar 30,2020 Mar 30,2020 62+ May 31,2020 May 31,2020 122+ Sep 30,2020 Sep 30,2020 91+ Dec 30,2020 Dec 31,2020 183+ Jul 02,2021 Jul 02,2021 91+ Oct 01,2021 Oct 01,2021 62+ Dec 02,2021 Dec 02,2021 62+ Feb 02,2022 Feb 02,2022 62+ Apr 05,2022
Planning, Designing, Foundation Final Layout Excavation Laying of Electrical Compacting the ground Pouring of concrete to Installation of footings Slabbing and Flooring Painting
Procurement and Labor wiring and Reinforcement Steel required level and
installaion and Fra Paving
Dec 30,2019 0+ Mar 30,2020 Mar 30,2020 0+ May 31,2020 Jun 01,2020 1+ Oct 01,2020 Oct 01,2020 1+ Dec 31,2020 Dec 31,2020 0+ Jul 02,2021 Jul 02,2021 0+ Oct 01,2021 Oct 01,2021 0+ Dec 02,2021 Dec 02,2021 0+ Feb 02,2022 Feb 02,2022 0+ Apr 05,2022

May 31,2020 152+ Oct 30,2020 Oct 30,2020 62+ Dec 31,2020 Oct 01,2021 91+ Dec 31,2021 Dec 31,2021 31+ Jan 31,2022
Foundation Works and Plumbing Framing, Roofing and Electrical and Fixtures
Construction Winsows Installation installations

May 31,2020 0+ Oct 30,2020 Oct 30,2020 0+ Dec 31,2020 Oct 03,2021 2+ Jan 02,2022 Jan 02,2022 2+ Feb 02,2022

Early Start Duration EarlyFinish


Task Name or Description

Late Start Float Late Finish

Page: 1 of 1 "Day" runs from 8:00 am until 7:59 am on following day. Produced by an unpaid evaluation copy of PlanBee (http://www.guysoftware.com/planbee.htm)
+ against a duration indicates elapsed days rather than working days.