*A ----- Terminated Contract: Construction of COA-CAR Training Center and Dormitory - Phase 1
*B ----- Letter from the COA-CAR to the Contractor regarding the Notice of Termination
*C ----- Conduct of Inventory at the Project - Construction of COA - CAR Training Center and
Dormitory Phase I, Easter Road, Baguio City
B ----- Invitation of Zoom Meeting to Royalink re: Continuation of Training Center after
Pandemic
B1 ----- Letter of Royal Link not to pursue the Termination of the Contract: Construction of COA-
CAR Training Center and Dormitory - Phase 1
C ----- Memo of Atty. Saldo for RD. Eden re: Termination of Contract w/ RoyaLink
D ----- Memo for RD: Comments and Recommendation of the Project Team to Continue the
Termination of Project w/ Chronology of Events and Attachments
K ----- Letter of RD to Engr. Malig, Head, CPES-IU, Acting Director of Bureau of Quality and
Safety
N ----- Request for CPES from DPWH CPES Report From the TSO, COA.C.D
Q ----- Memo of Dir. Canlas to Director Malig for the Request of Accredited Personnel to
Conduct CPES by RD. Eden Rafanan
S ----- Letter of RD. Eden to Dir. Canlas Requesting CPES Accredited Personnel to Conduct
Performance Evaluation System