Riyadh Metro Project Package 3 Comments Resolution Sheet: M3-GEG-MST-EAR00-ELS-000002
Riyadh Metro Project Package 3 Comments Resolution Sheet: M3-GEG-MST-EAR00-ELS-000002
Transmittal Title Method Statement for Concrete Screed Installation, Line 4, Elevated Stations Document Type Method Statement
Date Received 05.12.2017 09.12.2019 Lead Reviewer ILIAS CHRONOPOULOS ILIAS CHRONOPOULOS
No. Section/ Page/ Drawing No. PMCM Comments Doc. Rev. By Contractor Response By Review Code Status
First cycle response : There is no approval status provided for MAR, please provide the status of First cycle response : M3-CJV-MAR-ECI00-S30-000251 _ AB_Code A and
3 Section 6, 6.1: MATERIALS each materials. AA AB MMH MMH M3-CJV-MAR-ECI00-S30-000252 _ AA_Code B (included in section 6.1) A
Second cycle response : NOTED Second cycle response :
First cycle response : The method of statement submitted for all elevated station in line 4 First cycle response : Concrete screed placement procedure was elaborated in section 7.2 &
4 therefore you have to provide each methodology on respective structures on how you will cast
Section 7: WORK METHODOLOGY the screed and be specify also on how you will protect other structures during the concreting.
AA AB MMH MMH 7.3 and protection was included in section 7.1.1.9 A
Second cycle response :
Second cycle response : NOTED
First cycle response : The ITP provide still not approved please provide the signed copies of ITP. First cycle response : M3-CJV-ITP-EAR00-GEN-000003_AA_Cdoe A (Signed Copy attached)
5 Section 11: ITP Second cycle response : NOTED AA AB MMH MMH Second cycle response : A
First cycle response : No need to attached the entire project specification on this method of
statement it is general information to all, the reference number is enough to include to make First cycle response : Noted and complied as per comment
6 Section 11: PROJECT SPECIFICATIONS the method statement as brief as possible.
AA AB MMH MMH
Second cycle response :
A
Second cycle response : NOTED
Disclaimer : Permission to proceed shall not constitute acceptance or approval of design details, calculations, analyses, test methods or materials developed or selected by the Contractor and shall not relieve the Contractor from full compliance with Contractual
Obligations. Status
Page 1 of 5 CRS_Rev. 2
No. Section/ Page/ Drawing No. PMCM Comments Doc. Rev. By Contractor Response By Review Code Status
The contractor is liable to obtain from the Engineer and the Client, approval of all the proposed designs, materials, as well as the subcontractors and suppliers he proposes to use on the Project. The result of this review does not allow the contractor to proceed without
getting all of the requisite approvals. This is a mandatory contractual requirement. For clarity FAST has the obligation before any construction proceeds to:- Get the approval of the design from the Engineer.- Get the approval of the proposed material from the Engineer.- Closed
Get the approval of the supplier from the Engineer.- Get the approval of the Sub Contractor from the Engineer. The contractor is only authorized to proceed when he has completed all of the above steps.
Agree to Close
Open
Page 2 of 5 CRS_Rev. 2
Requestor Name Sender Entity Overall Status Code Medium Code
CLOSED Original Red
OPEN Source File Orange
Hard Copy Green
CD/DVD
Other
Status
A
B
C
D
E
Over All Code
A - Reviewed - Work may proceed.
B - Reviewed with comments - Revise and resubmit. Work may proceed subject to incorporation of comments.
C - Objection - Revise and resubmit. Work may not proceed
D - Rejected
E - Review not Required - Work may proceed