The weekly progress report summarizes the 65.02% completed construction of a residential home. Key tasks completed include 90% of site clearing and excavation, 95% of scaffolding installation, and 90% of floor leveling. Foundation work is 90% complete, including installation of stone foundations, footings, and columns. Wall framing and plastering is 80-90% finished. However, tiling, stonework, doors, and windows are all less than 30% installed. The report provides status updates on 18 line items with volume, unit, budget weight, achievement, and earned value.
The weekly progress report summarizes the 65.02% completed construction of a residential home. Key tasks completed include 90% of site clearing and excavation, 95% of scaffolding installation, and 90% of floor leveling. Foundation work is 90% complete, including installation of stone foundations, footings, and columns. Wall framing and plastering is 80-90% finished. However, tiling, stonework, doors, and windows are all less than 30% installed. The report provides status updates on 18 line items with volume, unit, budget weight, achievement, and earned value.
The weekly progress report summarizes the 65.02% completed construction of a residential home. Key tasks completed include 90% of site clearing and excavation, 95% of scaffolding installation, and 90% of floor leveling. Foundation work is 90% complete, including installation of stone foundations, footings, and columns. Wall framing and plastering is 80-90% finished. However, tiling, stonework, doors, and windows are all less than 30% installed. The report provides status updates on 18 line items with volume, unit, budget weight, achievement, and earned value.
Lokasi : Kompleks TNI AL Kodamar Tanggal : 23 Mei 2021 Progress : 65,02 %
NO ITEM PEKERJAAN VOLUME SATUAN BOBOT PRESTASI BOBOT PRESTASI
A PEKERJAAN PERSIAPAN & TANAH 1 Pembersihan lokasi & bongkar bangunan eksisting 456.00 M2 0.57 90% 0.52 2 Gudang & camp pekerja 40.00 M2 1.01 100% 1.01 3 Pantek sumur bor untuk air kerja 1.00 Ls 0.88 0.00 4 Sewa skafolding 4.00 Bulan 0.15 0.00 5 Listrik kerja 4.00 Bulan 0.25 75% 0.19 6 Bouwplank T 1 M 214.20 M 0.81 95% 0.77 7 Galian tanah pondasi 2 M M3 0.00 0.00 8 Galian tanah pondasi 1,5 M 137.09 M3 1.36 95% 1.29 9 Galian Tanah Septick Tank 4.00 M3 0.05 0.00 10 Pemadatan tanah pondasi 47.03 M2 0.34 0.00 11 Urugan dalam bangunan T 50 cm 91.50 M2 2.01 90% 1.81 12 Urugan sirtu bawah lantai T 5 cm 9.15 M2 0.42 90% 0.38 13 Pemadatan lantai bangunan 183.00 M2 0.16 90% 0.14 14 Urugan taman T 50 cm 70.50 M3 1.55 0.00 17 Buang puing bongkaran 5.00 RIT 0.22 0.00