Professional Documents
Culture Documents
Projects-ESIA Aek Sibundong Energy
Projects-ESIA Aek Sibundong Energy
Assessment Report
Mini Hydro Power Plant 2x4 MW
Sigulok, North Sumatera, Indonesia
1508
2018
Mini-Hydro Power Plant Project 2X4 MW
For
Approved by,
Nigel Landon
President Director
15 August 2018
Distribution
Internal Confidential Public
This report has been prepared by PT ESC Environment Indonesia with all reasonable
skill, care and diligence within the terms of the Contract with the Client, incorporating
our General Terms and Conditions of Business and taking account of the resources
devoted to it by agreement with the Client. We disclaim any responsibility to the Client
and others in respect or any matters outside the scope of the above. This report is
confidential to the Client and we accept no responsibility of whatsoever nature to any
third parties to whom this report, or any part thereof, is made known.
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
TABLE OF CONTENTS
PAGE
LIST OF FIGURES
LIST OF TABLES
ABBREVIATIONS
AF Associated Facilities
ASE PT. Aek Sibundong Energi
AQ Air Quality
Badan Meteorologi, Klimatologi dan Geofisika/ Meteorology Climatology and
BMKG
Geophysics Council
CR Critical
RUPTL Rencana Usaha Penyediaan Tenaga Listrik/ Electricity Supply Development Plan
EXECUTIVE SUMMARY
Project Overview
PT. Aek Sibundong Energi (hereafter ‘ASE’ or the Client) is a subsidiary of PT. Paesa Pasindo
Engineering (‘PPE’) formed in 2014 whose principal projects involve the development of Mini Hydro
Power Plants (‘MHPP’ or the Project). As for the composition of ASE shareholders is 99% PPE and 1%
of Panal Banjarnahor. This Independent Power Producer company is established under Deed Number
03, in the presence of Notary Bonar Sihombing, SH. This deed has gained approval from the Ministry
of Justice and Human Rights, Republic of Indonesia Number: AHU – 14891.AH.01.01 Year 2014.
As a national mini hydro project developer, PT Aek Sibundong Energi is planning to develop a Mini
Hydro Power Plant on Aek Sibundong River, in Sigulok Village, North Sumatera, Indonesia. It is
expected that the Aek Sibundong MHPP project in Aek Sibundong River will generate 2X4 MW
electric capacity by implementing a run-of-river system with an offtake from a regulating weir which
will not require a dam or any water impoundment.
The Project has reached the end of the development phase, and most of the Project licensing has been
secured, and a PPA term sheet with PLN has also been signed (September 2017). The Project will soon
enter the financing phase, for which one of the key activities is to complete the ESIA (Environmental
Social and Impact Assessment) document. The Project UKL/UPL for Sigulok Site was conducted in
2016 and the Project already has the Environmental Permit which was approved in 2017.
The Project has gained approval through the Republic of Indonesia legal process to assess
environmental and social impacts and risks of the construction and operation phase of the project in
the form of the Environmental Management Effort (UKL) and Environmental Monitoring Effort
(UPL). This ESIA has been prepared to reflect the requirements of the International Finance
Corporation (IFC) Performance Standards and Guidelines, and the Equator Principles. PT Aek
Sibundong Energi has implemented compliance with these guidelines to meet industry best practices.
The Project is located in the Sigulok Village, Sijamapolang Sub-district, Humbang Hasundutan
Regency. The Sigulok village is about 30 km to the south from Dolok Sanggul, the closest city from
the Project site. The Project is located on the Aek Sibundong River, within a V-shape valley with 25 to
30 m width. The river flows from the northeast to the southwest through other land use are (Area
Penggunaan Lain) in the upstream part, then in the midstream part to end of the Project site it passes
through production forest area.
According to the project Environmental Permit (number 21 of 2017) issued by the investment
coordinating body, the site area of the Mini Hydro Power Plant Project is approximately 25.08 Ha.
However, according to the UKL/UPL, the site area is 26.08 ha with the details are 20.87 ha is
Permanent Production Forest Area (Kawasan Hutan Produksi Tetap) and other utilization area (Area
Penggunaan Lain/APL) and 5.21 ha is land belong to PT. Toba Pulp Lestari. ASE has obtained Izin
Pinjam Pakai Kawasan Hutan (IUPPKH) Number 522/2350.
This ESIA represents and assesses the construction and operation phases of the MHPP project
including the associated facilities (AF) of the project. The construction and operation phase of the
MHPP project and AF development will require activities which may result in significant
environmental, social or health impacts relating to:
• Construction workforce employment;
• Transport and mobilization of equipment and material;
• Land clearance;
• Construction of power house, weir and supporting facilities; and
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Approach
ASE have adopted a risk based approach to defining potential environmental and social impacts, in
order to provide rigour to the definition of mitigation processes and evaluation of their effectiveness.
This ESIA is structured around industry best practice approach of defining the existing
environmental values, identifying the potential environmental impacts from project activities, and
then applying a mitigation strategy that will eliminate or reduce potential impacts, with management
plans to monitor and measure the outcomes. In order to define the significance of potential impacts a
risk framework has been established, which can then be used to evaluate the residual risk once a
mitigation strategy is applied.
The outcome of a risk based approach is a rating of environmental and social risks on ascending scale
of negligible-minor-moderate-major-critical – this rating is based upon a combination of the severity
of the potential impact, and the likelihood that it will occur. The specific parameters used to evaluate
the degree of risk are presented in this ESIA and their outcomes will be represented in this Executive
Summary.
Project Description
In broad terms, this ESIA explores the potential impacts and mitigation strategies of two major
activities including the construction and operation of Aek Sibundong MHPP project. The activities of
pre-construction phase including the public consultation and land acquisition were already
conducted by ASE. Those are not addressed in this ESIA study.
The construction activities will consist of major civil works and construction involving a new access
road development, Mini-hydro Power Plant and associated facilities development. Details of the
construction activities include: recruitment and mobilization of construction workforce; mobilization
of materials and heavy equipment; land preparation; and the construction of main infrastructure of
Aek Sibundong MHPP and the associated facilities. During the peak of the construction works,
approximately 150 people will be employed.
Activities in the operation phase will comprise recruitment of workforce, the operation and
maintenance of Aek Sibundong MHPP. Approximately 12 people will be hired for the operation of
the Aek Sibundong MHPP project.
minor pollution load due to the domestic discharge from the nearby settlements and agricultural
activity around the Aek Sibundong River.
Noise Level
The direct noise level measurements at both sampling points within the community settlement and
project area during the baseline studies indicate that there were no levels which exceeded the
threshold limit values of both national and international standards, which are 55 dB A for Residential
Areas, and 70 dB A for Industrial Areas (MoE Decree No.48/1996) and the Guidelines for Community
Noise (Day-time), WHO (1990) except for one noise level recorded in the community settlement at
15:00. The noise level at this time was recorded slightly above the threshold limit value at 64.3 dB A.
During the baseline sampling, noise levels measured ranged from 35.8 dB A to 64.3 dB A.
The lowest noise level from the result of baseline sampling were observed at 04:00 in the morning as
there are no activities conducted at this time. While the highest noise level was observed at 15:00 at
the community settlement area and at 10:00 at the project location.
The site survey indicated that the primary sources of noise around the Project Area and the Project
Area of Influence are from motor vehicles and audible noises of the Aek Sibundong river. Moreover,
the project site is located nearby to community housing with typical rural and/or agricultural noise
levels.
Terrestrial Biodiversity
The Project location is located in natural habitat. Several modified habitats were discovered in
and around the project locationincluding; plantation forest, dry-land agriculture, paddy field
and shrub. Natural habitat is primarily riverine forest ecosystem.
A Terrestrial flora survey was conducted within the project footprint area. The survey
covered plots that were distributed along the river area from the power house up to the weir
location. 43 species of flora were recorded during the survey. Casuarina sumatrana (local:
Anturmangan) and Quercus javanensis are dominant species that were recorded. This species
was found to be abundant in the surrounding river area. Other species that were recorded
include Exbucklandia populnea (local: Hapas-hapas) and Quercus javanesis. E. populnea which
were wide spread across the study area.
For bird groups, the survey recorded 45 species from 22 families. Dominant families that were
recorded within the study area include Timaliidae and Sylviidae (each 6 species), followed by
Apodidae, Pycnonotidae, and Nectariniidae (each 4 species). Both Timaliidae and Sylviidae
generally inhabit forest, shrubs and bushland. Both are insectivore bird families, their main
food source includes caterpillars and other small insects.
There are 6 bird species protected by the Indonesian government based on Law no. 5 of 1990
and Government Regulation no. 7 of 1999 concerning preservation of plant and animal
species. Based on the IUCN Red list, there are two species of birds that are categorized as
Near Threatened (NT), namely the Ixos virescens (Sunda Bulbul) and Stachyris nigricollis
(Temminck’s Sunbird).
For mammals, there were not many results during the field survey. Wild boar (Sus scrofa) was
the most common species found in the forest and agricultural areaa. The net survey method
only record one bat species; Chironax melanocephalus.
Two species of fish were recorded during the baseline survey, namely Semah (Tor soro), and
Seluang (Rasbora sp). Semah is the dominant species found in the main river, and Seluang was
only found in the small creeks. A total of 14 individuals of Semah were captured in main river
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
during the survey. Typical habitat for Semah is upstream river in forested areas with a rocky
river bottom and fast currents. Seluang (Rasbora bankanensis) were also found to be abundant
and dominant in the smaller creeks. The typical habitat for this species is river and swamp in
forested areas. They live in rivers with weak flow and calm currents.
Aquatic Biota
The diversity indices of phytoplankton, zooplankton and benthos at all sampling locations are
indicative of unpolluted waters as the diversity indices are greater than two. The equitability indices
and dominance indices indicates that there is no dominant species in the water. Aquatic biodiversity
shows that the surface water quality, both in upstream, mid-stream, and downstream of the Project
Area, are still in good condition.
Traffic Sampling
The traffic counting data shows that motorcycles were the most common mode of transportation,
with 4,681 vehicles recorded in peak hours on two days, representing one day of peak hours in the
weekend and one of day peak hours in the weekday. Motorcycles were followed by light vehicles
such as cars with 2,212 vehicles (30%), then light trucks with 234 (3%). 4 units (of non-motorized
vehicles such as bicycles and gerobak (carts) were recorded in the study area (0.05%).
The traffic counting data shows that motorcycles were the most common mode of transportation in
Sigulok Village, with 15 vehicles recorded in the peak hours on two days, representing one day of
peak hours in the weekend and one of day peak hours in the weekday. Motorcycles were followed by
light vehicles such as cars with 4 vehicles (21%). There are no other types of vehicle recorded during
the traffic survey in Sigulok Village.
Indigenous People
IFC Performance Standards 7 recognises indigenous people as social groups with identities (language,
culture, etc.) that are distinct from the mainstream population. They are often among the most
marginalized and vulnerable segments of the population. Based on household survey and Key
Informant Interview results, no indigenous people were found in the impacted area. From the
economic, cultural, and social perspective, Batak ethnic is not distinct from other ethnic groups. They
are already a part of the broader society, and are not isolated from other ethnic groups. Moreover,
vulnerable groups are those who are more likely to experience poverty and social exclusion than the
general population. These groups constitute ethnic minorities, migrants, disabled people, homeless,
drug addicts, isolated elderly people and children. They face higher risks of low education,
unemployment and underemployment. Thorugh this definition, Batak ethnic is not classified as
vulnerable groups.
Cultural Heritage
IFC Performance Standard 8 defines that cultural heritage refers to: (i) tangible forms of cultural
heritage, such as tangible moveable or immovable objects, property, sites, structures, or groups of
structures, having archaeological (prehistoric), paleontological, historical, cultural, artistic, and
religious values; (ii) unique natural features or tangible objects that embody cultural values, such as
sacred groves, rocks, lakes, and waterfalls; and (iii) certain instances of intangible forms of culture
that are proposed to be used for commercial purposes, such as cultural knowledge, innovations, and
practices of communities embodying traditional lifestyles. Based on household survey and Key
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Informant Interview results, no cultural heritage were found in the impacted area.
Cumulative Impact
ESC identified one cumulative impact due to project operation activity. The overall cumulative
impact from existing activities within the Project Area of Influence is considered moderate for water
quality. The cumulative environmental impact would be associated with the sediment flushing
activitiy of Aek Sibundong MHPP operation. The Aek Sibundong MHPP project contributes a
negligible to minor-moderate impact after mitigation.
Mitigation Significance
No Potential Impact Activity Phase
Before After
1 Air Quality
Air quality impact due to Construction Phase Moderate Minor
the vehicle and machinery
emission source
Air quality impact due to Construction Phase Moderate Minor
dust generation
2 Noise
Noise impact due to Construction Phase Moderate Minor
construction activities
Noise impact due to turbine Operation Phase Minor Negligible
operation
3 Water Quality
Water quality impact due Construction Phase Major Minor-Moderate
to land clearance activities
Water quality impact due Construction Phase Minor Negligible
to potential soil erosion
Water quality impact due Construction Phase Major Minor
to construction of weir
Water quality impact due Operation Phase Negligible Negligible
to sediment increase
Water quality impact due Construction and Minor Negligible
to domestic wastewater Operation Phase
discharge
4 Soil/Land Contamination
Land contamination due to Construction Phase Minor Negligible
chemical and petroleum Operation Phase
products
Land contamination due to Construction Phase Minor Negligible
leakage from machinery or
vehicle
Land contamination due to Construction Phase Minor Negligible
materials stored onsite and Operation Phase
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Mitigation Significance
No Potential Impact Activity Phase
Before After
solid waste generation
5 Hydrology
Water balance alteration Construction phase Minor Negligible
Potential flooding due to Construction Phase Minor-Moderate Negligible
land clearing and
construction activities
Water course impact due to Construction phase Minor Negligible
weir construction
Water flow impact Operation Phase Minor Negligible-Minor
6 Biodiversity Resources
Impact on Habitat Construction Phase Moderate Minor
Impact on Fauna during Construction Phase Moderate Minor
Construction Phase
Impact on Fauna during Operation Phase Minor-Moderate Negligible-Minor
Operation Phase
Impact on Migratory Fish Operation Phase Addressed in Section 6.5.4
Impact on Aquatic Construction Phase Addressed in Section 6.3
Biodiversity
7 Socio Economic and Culture
Impact on Community Construction Phase Major Minor
Livelihoods
8 Community Health Safety and Security
Emission from vehicle and Construction Phase Moderate Minor
equipment
Dust generation Construction Phase Moderate Minor
Noise Construction and Addressed in Section 6.2
Operation Phase
Traffic and road safety Construction Phase Major Negligible-Minor
Sediment flush Operation Phase Addressed in Section 6.5.4
Infrastructure safety Operation Phase Major Minor-Moderate
9 Occupational Health Safety and Security
OHS Issues during Construction Phase Major Minor
construction
OHS issues during Operation Phase Minor-Moderate Negligible-Minor
operation
1. INTRODUCTION
General
The Indonesian National Electricity Forecast (Rencana Ketenagalistrikan Nasional) as published by
the Indonesia Ministry of Energy and Mineral Resources (MoER) predicts an electricity demand
increasing by about 10% annually in line with an Indonesian population growth rate of around 5 to
6 % per year. National electricity installment totaled 36 Gigawatt (GW) in 2010; to fulfill community
needs and to support economic development, the government is targeting to increase the installed
capacity to 115 GW in 2025 through an energy mix of oil (25%), gas (20%), coal (30%), and
renewable energy (RN) (25%), for a total of 600 GW in 2050 as shown in Figure 1.
The Government of Indonesia (GoI) energy policy also includes increasing electricity generation by
35 GW in a fast-track program. At the same time the GoI is committed to reduce 26 % of greenhouse
gas emission (GHG) by prioritizing the use of renewable energy as outlined in Presidential Decree
(Perpes) No 61 of 2001 on National Action Plan for Reduction of Greenhouse Gas Emission through
Electricity Generation from Renewable Energy Sources. This commitment to reduce GHG emission
is also reflected in COP21 UNFCCC (21st Conference of Parties United Nations Framework
Convention on Climate Change) in Paris in 2015, when the GoI announced its commitment to
reduce the GHG emission by 29 % in 2030 by its own efforts or by 41 % in 2030 with International
support.
Indonesia has high potential for renewable resources including mini/micro-hydro, biomass, solar,
and wind power. The government of Indonesia is committed to the contribution of renewable
energy for the national primary energy mix program of 2025 according to the Presidential
Regulation No. 5 Year 2006 regarding the National Energy Policy (Perpres No. 5 Tahun 2006
tentang Kebijakan Energi Nasional). The government expects mini hydro power could be
developed to approximately 2,846 MW by 2025 by implementing several programs to support mini-
hydro development include integration of mini hydro power development into community
1
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
economic activities, optimisation of the irrigation channels for mini hydro power, encouraging the
national mini hydro industry and expanding the various type of partnerships and effective funding.
The total hydro power potential output, including mini/micro-hydro, in Indonesia is estimated at
75,000 MW. The government expects mini-hydro power could be developed to approx. 2,846 MW
by 2025 by implementing several programmes to support mini-hydro development including the
integration of mini-hydro power development into community economic activities, optimisation of
the irrigation channels for mini-hydro power, encouraging the national mini-hydro industry and
expanding the various type of partnerships & effective funding. In 2014, the national installed
capacity of mini -hydro power plants in Indonesia was 139.87 MW (Electrification Statistic, 2014).
As a national mini hydro project developer, PT Aek Sibundong Energi is planning to develop a
Mini Hydro Power Plant on Aek Sibundong River, in Sigulok Village, North Sumatera, Indonesia.
It is expected that the Aek Sibundong MHPP project in Aek Sibundong River will generate 2X4 MW
electric capacity by implementing a run-of-river system with an offtake from a regulating weir
which will not require a dam or any water impoundment.
The Project has gained approval through the Republic of Indonesia legal process to assess
environmental and social impacts and risks of the construction and operation phase of the project
in the form of the Environmental Management Effort (UKL) and Environmental Monitoring Effort
(UPL). This ESIA has been prepared to reflect the requirements of the International Finance
Corporation (IFC) Performance Standards and Guidelines, and the Equator Principles. PT Aek
Sibundong Energi has implemented compliance with these guidelines to meet industry best
practices.
This ESIA represents and assesses the construction and operation phases of MHPP project
including the associated facilities (AF) of the project.
Project Location
The Project is located in the Sigulok Village, Sijamapolang Sub-district, Humbang Hasundutan
Regency. The Sigulok village is about 30 km to the south from Dolok Sanggul, the closest city from
the Project site. The project administrative boundaries of Aek Sibundong MHPP are as follows.
North side: Bordered by Batu Ngajar Village, District of Sijamapolang
East: Bordered by Simarigung Village, Dolok Sanggul District.
South: Bordered by Manalu Dolok Village, District Parmonangan.
West side: Bordered by Sibuntuon Village, District Sijamapolang.
The Project is located on the Aek Sibundong River, within a V-shape valley with 25 to 30 m width.
The river flows from the northeast to the southwest through other land use are (Area Penggunaan
Lain) in the upstream part, then in the midstream part to end of the Project site it passes through
production forest area.
According to the project Environmental Permit (number 21 of 2017) issued by the investment
coordinating body, the site area of the Mini Hydro Power Plant Project is approximately 25.08 Ha.
However, according to the UKL/UPL, the site area is 26.08 ha with the details are 20.87 ha is
Permanent Production Forest Area (Kawasan Hutan Produksi Tetap) and other utilization area (Area
Penggunaan Lain/APL) and 5.21 ha is land belong to PT. Toba Pulp Lestari. ASE has obtained Izin
Pinjam Pakai Kawasan Hutan (IUPPKH) Number 522/2350.
The location, however, can be easily accessed from Silangit airport with a total travel time around
two hours by car. The MHPP project location is shown in Figure 2 below.
2
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Project Outline
The pre-construction, construction and operation phase of the MHPP project and associated
facilities development will require activities that may result in significant environmental, social or
health impacts related to:
Land acquisition;
Construction workforce employment;
Transport and mobilization of equipment and material;
Land clearance;
3
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
PT. Aek Sibundong Energi (hereafter ‘ASE’ or the Client) is a subsidiary of PT. Paesa Pasindo
Engineering (‘PPE’) formed in 2014 whose principal projects involve the development of Mini
Hydro Power Plants (‘MHPP’ or the Project). This Mini Hydro Power Generation business was
initially managed by PT. Paesa Pasindo Engineering (PPE). PPE is a private company engaged in
general contractor business. Along with the development and facilitation of the field then the
Management decided to create a separate business entities that concentrate fully manage this
Power Plant, so that stand PT. Aek Sibundong Energi. As for the composition of ASE shareholders
is 99% PPE and 1 % of Panal Banjarnahor. This Independent Power Producer company is
established under Deed Number 03, in the presence of Notary Bonar Sihombing, SH. This deed has
gained approval from the Ministry of Justice and Human Rights, Republic of Indonesia Number:
AHU – 14891.AH.01.01 Year 2014 ASE carries on activities as the manager of natural resources for
electricity, business in the field of power support services and power plant development services.
Aek Sibundong MHPP is located in Humbang Hasundutan District, North Sumatra Province.
Utilizes Aek Sibundong River water stream which produces 8 MW of electricity.
4
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Currently the Sigulok Mini-hydro Power Plant Project already has an Indonesian compliant EIA
(locally known as UKL-UPL - environmental management and monitoring effort) in 2016 and has
been approved by the Humbang Hasundutan Regency Local Environemntal Agency, prepared by a
local consultant. No IFC PS compliant Environmental and Social Impact Assessment (ESIA) studies
have been conducted for this Project to-date. The current project status at the Mini-hydro Power
Plant Projects is summarized in Table 1 below based on the document provided by ASE.
Location Permit (Izin Lokasi) Obtained Humbang Hasundutan Regent Decree No.
71 Year 2016 dated 14 April 2015
Izin Usaha Penyediaan Tenaga Obtained The decision of the head of the investment
Listrik Sementara (IUPTLS) coordinating body No. 3/1/IUPTL-
S/PMDN/2018
5
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESIA Objectives
The pre-construction, construction and operation phase of the Aek Sibundong MHPP and
associated facilities are significant project components that have the potential to cause
environmental and social impacts. The main objectives of the ESIA are to assess the environmental,
social, and health & safety risks of each phase of the project. Furthermore, the ESIA identifies
measures to avoid, minimise, mitigate, and monitor these risks.
The broad goal of this effort is to confirm compliance of all phases of the projects with various
environmental and social guidelines and standards. These include:
IFC Equator Principles and Performance Standards;
Applicable local/national laws and regulations;
Relevant World Bank Group environmental and social guidelines; and
Other international benchmarks and standards.
The Scope of Work for this ESIA study is designed to meet the following specific objectives:
Characterise the proposed Project’s environmental, social, health and safety aspects and
impacts, develop relevant and realistic mitigation measures, and compile a robust
Environmental and Social Management Plan;
Carry out an evaluation based on a comprehensive review of existing environmental and
social information and documentation;
Assess the Project's compliance with requirements under the Equator Principles (July 2006),
including relevant IFC Performance Standards (2012) and World Bank Group
Environmental, Health and Safety Guidelines (EHS Guidelines); and
Advise the Project Proponents on compliance with any other relevant environmental
policies and guidelines.
This document has been prepared to be read as a stand-alone document (i.e. it does not need to be
read in conjunction with the UKL-UPL approved by the Republic of Indonesia). It has been
structured and prepared with reference to the IFC Performance Standards and Guidelines,
specifically the following:
IFC Performance Standard 1 – Assessment and Management of Social and Environmental
Risks and Impacts;
IFC Guidance Note One – Social and Environmental Assessment and Management Systems;
and
IFC Guidance Note One, Annex A – Social and Environmental Impact Assessment (SEIA)
Report.
The baseline data gathering and impact assessments which form the basis of this report have been
undertaken with regard to IFC Performance Standards two through to six (and accompanying
guidance notes) and related IFC guidelines:
IFC Performance Standard 2 – Labour and Working Conditions;
IFC Performance Standard 3 – Resource Efficiency and Pollution Prevention;
IFC Performance Standard 4 – Community Health, Safety and Security;
IFC Performance Standard 5 - Land Acquisition and Involuntary Resettlement;
6
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESIA Structure
This ESIA has been arranged in one volume, organized in the following sections:
Section 1 – Introduction
Section 2 – Policy, Legal and Administrative Framework
Section 3 – Project Description
Section 4 – The Environmental and, Social Impacts Assessment Process
Section 5 – Environmental and Social Baseline
Section 6 – Potential Environmental & Social Impacts Identification and Mitigation
Section 7 – Cumulative Impact Assessment
Section 8 – Public Consultation and Information Disclosures
Section 9 – Environmental and Social Management Plan (ESMP)
Section 10 - References
7
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Indonesian Regulations
Indonesian Laws and Regulations will act as regulatory framework that contains of applicable
Indonesian Regulations such as National Regulations, Provincial Regulations, Regency Regulations
and other local regulations. These regulations will govern the environmental and social practices of
the Project including environmental assessment of the Project, environmental regulations, social
and land use regulations and international treaties and agreements to which Indonesia is a
signatory.
Indonesia is divided into five administrative layers (Figure 3). At the top level is the nation, which
consists of 34 provinces. Each province is headed by a governor. The various provinces (otherwise
known as Level 1 regions) are further subdivided into kabupaten or regencies (Level 2 regions,
headed by the district administrators), which are further subdivided into districts, subdistrict and
villages. Within the provinces, there are also municipalities or city governments, which have the
same status as regencies. These metropolitan regencies are referred to as Kota (or townships), not
Kabupaten. Each township is headed by a mayor.
Sijamapolang Subdistrict
Sigulok Village
8
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
9
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
10
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
11
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The IFC Policy categorizes projects depending on their potential to cause social and environmental
risks and impacts, and the level of assessment required to review these potential impacts. Under
this system, works assessed in this document are deemed to be a Category B project, defined as "a
project that has medium risk which mean the Projects with potential limited adverse environmental
and social risks and/or impacts that are few in number, generally site-specific, largely reversible
and readily addressed through mitigation measures".
There are seven Performance Standards (PS) under the IFC Policy that are applicable to the project.
The risks and impact identification process has been based on recent environmental and social
baseline data at an appropriate level of detail and considers issues related to applicable PS’s. Those
standards are:
PS1 Assessment and Management of Environmental and Social Risk and Impacts;
PS2 Labour and Working Conditions;
PS3 Resource Efficiency and Pollution Prevention;
PS4 Community Health, Safety and Security;
PS5 Land Acquisition and Involuntary Resettlement;
PS6 Biodiversity Conservation and Sustainable Management of Living Natural Resource;
PS 7 Indigenous People; and
PS8 Cultural Heritage.
It should be noted that IFC PS 7 was not applied in this ESIA study, as no impact to indigenous
people was established during the environmental and social risk and impact identification process
as described further in the section 5 and section 6 of this report.
The key process elements of an ESIA generally consist of: (i) initial screening of the project and
scoping of the assessment process; (ii) examination of alternatives; (iii) stakeholder identification
(focusing on those directly affected) and gathering of environmental and social baseline data;
(iv) impact identification, prediction, and analysis; (v) generation of mitigation or management
measures and actions; (vi) significance of impacts and evaluation of residual impacts; and (vii)
documentation of the assessment process (i.e., ESIA report).
The breadth, depth and type of analysis should be proportionate to the nature and scale of the
proposed project’s potential impacts as identified during the course of the assessment process.
The ESIA must conform to the requirements of the host country’s environmental assessment
laws and regulations, including the relevant disclosure of information and public consultation
requirements, and should be developed following principles of good international industry
practice.
The environmental elements that need to be included in this ESIA are determined in the IFC
General EHS Guidelines and IFC EHS Guidelines for Electric Power Transmission and Distribution.
The screening and scoping process will consider these guidelines in the context of the proposed
development, the geography and prevailing environmental conditions to determine the extent and
level of detail required to provide appropriate baseline information for the ESIA.
12
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
3. PROJECT DESCRIPTION
13
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The electrical system in Doloksanggul and its surroundings is supplied from Hose Substation 20 kV
located behind PLN Rayon Doloksanggul office. Whereas Hose Substation is interconnected with
several Mini Hydro Power Plant and 150 kV Substation, located in Humbang Hasundutan, Tobasa
and North Tapanuli Regency. MHPP and 150 kV Substation interconnected with Hose Substation
PLN Rayon Doloksanggul.
According to Feasibility Study, the majority consumption of electricity in PLN Rayon Doloksanggul
is consumed by household (60%), commercial (18%), industry (14%), and public (8%). The
electricity needs in the Doloksanggul and surrounding areas in general is for household usage, only
a small portion used for commercial and industrial purposes. Therefore, the peak load the
electricity is started between the hours of 17-22 at night. Load conditions at peak load times at night
only reach about ± 5 MW, then with a total existing power plant capacity of 14 MW, at PLN Rayon
Doloksanggul already has an excess supply. The excess supply is sent to another rayon such as PLN
Rayon Siborongborong, Tarutung and Tele.
From a potential water study conducted on Aek Sibundong in Doloksanggul District, it was
obtained that the river has discharge of 111.41 m3/sec, with a net fall of 82.50 m. It means that Aek
Sibundong MHPP has the potential to generate 8018 kW of electricity.
14
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
part of the plan for MHPP development in the Humbang Hasundutan Regency. In a more detailed
manner, the majority of the Aek Sibundong MHPP area located in Kecamatan Sijamapolang can be
classified as dry agriculture land. There are also some minor designations as well, such as Low
Density Residential Zone, Livestock Farming Zone, Techno Park Zone, Tourism Zone, and Inland
Aquaculture Zone.
As shown by the above zoning classification planning issued by the Regional Government with the
exception of the coastal buffer zone, none of these zones in the Aek Sibundong MHPP area are
classified as restricted zones. Since the mini hydro power plant development and operation does
not change/prevent the existing land uses and can co-exist with its existing neighbours, it is
believed that the development of the Aek Sibundong MHPP project in the area does not contradict
the current spatial plan, and will not cause significant land use conflict with the existing land use
zones. Additionally, it is believed that the existence of the Aek Sibundong MHPP project will
benefit its surrounding area, by providing a clean and dependable power generated from clean and
renewable energy, as well as adding a new tourist attraction and educational tool for students and
public that can demonstrate the technology for clean energy. Moreover, the Aek Sibundong MHPP
has gained Recommendation for Space Utilization from BAPPEDA No.
050/691/BAPPEDA/V/2015. Overlay of project area location with Local Spatial Plan is presented
in the following Figure 5 and Figure 6.
15
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Figure 5 Project Conformance to the Local Spatial Plan (Pattern Map) according to BAPPEDA
16
16
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Figure 6 Project Conformance to the Local Spatial Plan (Structural Map) according to BAPPEDA
17
17
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
18
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
• The Construction Phase – Construction phase of the project has not been started at the
time of ESIA study. The construction phase is estimated to be completed within 20
(twenty) months. The work includes detailed engineering work, procurement and
construction.
• The Commissioning Phase – After Construction is finished, commissioning to check the
condition of the Project prior to the Commercial Operation Date is expected to take up to
3 (three) months.
• The Operation Phase – Subsequent to commissioning, commercial operations of the mini-
hydro plant are expected to begin after the commissioning phase completed. The
commercial operation period will be for 20 years.
Pre-Construction Phase
Pre-Construction stage is the initial stage and is the most decisive stage whether the project is
continued in the construction stage or not, otherwise it is almost all activities from other stages
include data or documents performed at this stage. Pre-construction stages include the Feasibility
Study phase including UKL/UPL study activities with an estimated time of 4 months, Detail Detail
Engineering (DED) with an estimated time of 3 months and auction process with an estimated time
of 3 months.
Preliminary survey and study which will be conducted by technical consultant team cover major
aspects as follows.
1. Topography
The detail situation measurement method is done by using cross method combined with
radial method, with interval cross 10-15 m.This method is selected because it is faster and
the results can also represent the morphological shape of the measured area. Measurement
of topographic detail is done by capturing high point information and description of
special information such as road, river channel, building, titiko drill and other objects
within the survey area, the tool used is Total Station.
2. Hydrology
Hydrology data required are including characteristic of watershed, rainfall precipitations,
temperature, evaporation and infiltration, stream flow, runoff coefficient, stream sediment
(type of sediment, size of grains, load intensity). Hydrology data is required to discover
hydrology characteristic of Aek Sibundong Watershed (DAS Aek Sibundong), particularly
at the upstream area of the weir location plan of Aek Sibundong MHPP, so that the stream
flow plan can be calculated.
3. Geology and Soil Mechanics
Geology and soil mechanics study are including qualitative data collection which both from
primary and secondary sources of research, ie:
a. possible surface soil movement, such as surface rocks and soil that move when it
rains, water and sludge movement;
b. possible underground soil movement, such as earthquake and landslides;
c. type of rocks, soil and sand;
d. soil bearing capacity at structural building location of Aek Sibundong MHPP.
19
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
e. Soil boring will also be conducted in order to investigate the soil mechanics
condition and subsequently determine the suitable type of foundation.
4. Electricity Study
Electrivity study was collected through primary and secondary data collection. The method
includes conducting survey of the electricity condition of Doloksanggul city and its
surrounding. From the secondary data collection against load conditions current and future
electrivity condition, the data was used to predict the need for electricity in the service area
of PLN Rayon Doloksanggul and Humbang Hasundutan District and surrounding areas.
Technical feasibility study has been conducted to assure that the project is technically feasible,
through the comprehensive study of flow reliability (Q), head loss, and geological condition of
project location. While the financial feasibility study reviews the rate of profit from investments, by
assessing the applicable financial instruments, such as Pay Back Period NPV, IRR, PBP, PI and ROI.
The Feasibility Study of Aek Sibundong Energy's Power Plant Development is intended for
conducting research and assessment on the feasibility of AEK MHPP project development. If the
result of the project analysis is technically feasible, economic-financial and environmental, then the
plan of Aek Sibundong Energi MHPP project will be continued till Detail Engineering Design and
implementation of the construction so it is expected to operate and produce optimally and can be
accounted for. The summary of project location is presented in the following table 7.
No Description Remarks
Project Name Aek Sibundong Mini-Hydro Power Plant
1 Scheme Run of River - Medium Head
Project Site
2 Sigulok Village
Location
3 River Aek Sibundong
Location
4
Administrative
Village Sigulok
Sub-district Sijamapolang
District Humbang Hasundutan
Provincial North Sumatera
Geographical
5
location
Weir 20 08'51.70"N; 98 46'10.90" E
Powerhouse 20 8' 37.4" N; 980 45' 08.1"E
Source: PT Aek Sibundong Energi Feasibility Study 2013
The environmental feasibility study is conducted with reference to Minister of Environment
Regulation No. 5 of 2012, regarding Business Plans / activities requiring Mandatory Environmental
Impact Assessments (Amdal), which is for power plant with capacity of ≥ 50 MW. The capacity of
Aek Sibundong MHPP is about 10 MW – 12 MW, therefore it is not required to develop Amdal
study. However, the project is obligate to develop Environmental Management and Monitoring
Effort Plan (UKL-UPL document) as the prerequisite to obtain the Environmental Permit issued by
Environmental Agency of Humbang Hasundutan Regency. This study has objectives to assess the
potential impacts and manage them so the adverse impacts will be minimized and the positive
impacts will be optimized.
20
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
3.4.3 Permitting
Prior to physical activities, project proponent is obligue to prepare several legal permits related to
the project plan. ASE has completed most of legal permits required for Aek Sibundong MHPP
development plan, as listed in section 1.5.2. Legal Matters. Environmental permit as prerequisite
permit prior to construction activities has also been obtained in 2017 through completion of UKL-
UPL study. According to the information from desk research, all permits and licenses are still valid
to support ASE company activities. The ESC team can conclude that ASE is fulfilling their legal
obligations in conducting company activities. Generally, there are no significant issues identified in
relation with legal requirements of ASE.
3.4.4 Socialization
The socialization has been and will be conducted by the company together with the Humbang
Hasundutan Regency and Sigulok Village government as well as the local community. Socialization
is important to provide information and gather a better understanding on the project development,
gather an inputs of the construction of Aek Sibundong MHPP. The company gives explanations to
the community about the positive and negative impacts of hydropower development so that the
local people understand about this activity. Things that are important given understanding to the
community such as; 1. Recruitment of manpower, 2. Land acquisition / plant compensation, 3.
Hydropower operation system.
Land acquisition will be conducted in conjunction with the National Board of Directors (BPN).
Activities begin with a survey location along with BPN staff with a document map boundaries of
land to be released, then do socialization and data collection land ownership. After price
negotiations are approved by both parties (landowners and buyer of land), then the payment and
disposal of land rights can be done. This land acquisition activity is estimated to take 3 months,
assuming there are no significant social problems.
ASE has documentation in regard to land acquisition including certificate of ownership, attendance
list, minute of meeting and proof of payment. The land acquisition process was conducted in 2017.
Based on the land acquisition document, it was noted that ASE has conducted socialization to the
local land owner through the Sigulok Village Government. According to the document received,
negotiation was conducted in transparent manner. In addition, ASE maintains good documentation
in regard to the land acquisition.
The land acquisition process is based on willing buyer and seller transaction, with transparency
through community disclosure and consultation. Based on interview with local land owner, there
was no significant issues identified as the local land owner is supporting the Aek Sibundong MHPP
Project and willing to sell their land to ASE. There was no conflict occurred between the land owner
and project owner as observed by ESC during site visit. The compensation of land and crops is
conducted in fair and transparent manner.
According to the land acquisition document reviewed, it was noted that ASE has conducted
socialization through Village Government, survey of area of the land, price negotiation and
payment of compensation. According to interview with ASE, Head of Sigulok Village and local
land owner, it was noted that the land acquisition process is following applicable Indonesia
Regulations comprising Presidential Regulation No. 40/2014 (Perpres 40/2014) on Land
Acquisition for Development Activities in the Public Interest.
21
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
According to the ASE and Head of Sigulok Village, the land acquisition process for the Aek
Sibundong MHPP is undertaken as follows:
Establish the preliminary Layout based on the design in the Feasibility Study;
Conduct the public consultation which involves the socialization of affected communities
regarding the layout and the discussion of expected price (including land price and
agricultural crop price);
Collaborate with the village head and community leaders to identify the land ownership
and crosscheck with the Land Title Registrar to identify any discrepancies between the on-
field status and legal status;
Finalize the final layout of the land acquisition footprint based on the final Feasibility Study
Design for staking;
Measurement of land ownership status by ASE involving BPN based on the legal
documents;
Land verification with TPT and notary or Land Title Registrar (Pejabat Pembuat Akta
Tanah/PPAT) to check the validity of the ownership of the land based on the legal
documents available;
Land Payment after the grievances have been settled and the legal documents have been
verified, executed by Sale and Purchase Agreement (Akta Jual Beli/AJB) and Letter
Assignment of Right (Sertifikat Pemindahan Hak/SPH);
Finalize the certificate ownership from the land owners to ASE as Building Rights
Certificate/Hak Guna Bangunan (HGB).
All of the land in the project area is identified as private land. In particular, ASE seeks to ensure
there is a willing buyer and seller transaction framework, with transparency through community
disclosure and consultation. The ESIA studies will not cover further requirements on PS5 Land
Acquisition and Involuntary Resettlements as the impact to the community livelihoods is
considered limited or not significant. Nonetheless, the approach to land management and
resettlement does have the potential for social impacts that need to be managed.
Construction Phase
Executor construction must be detrmined and appointed to be able to conduct construction
activities, other factors that need to be fulfilled are licensing requirements such as IMB, Water Use
Permit need to be obtained. In terms of funding, stages of the process until the financial clossing
has to be done in order to facilitate the funding process during construction activities. The
construction stage is the whole process in order to prepare civil buildings construction, from the
preparation stage to the preparation of facilities for the installation process of Mechanical Electrical
equipment. The total time required for the construction phase of civil buildings construction is
estimated for 20 month, with some activities inside it can be implemented in parallel.
According to the UKL/UPL document, number of workforce at the construction stage requires
skilled and non-skilled labor which is predicted as many as ± 150 people. Outline the needs of labor
at this stage of construction is generally temporary workers which come from the region around
and from outside this area. It is expected that the education level of workers will be varied from
elementary school (SD), junior high school (SMP), senior high school (SMA), diploma (D3) and
22
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
As the initial stage of the implementation of Aek Sibundong MHPP development activities, it will
mobilise equipment and building materials or heavy equipment such as bulldozers, exacavator,
dump truck, pipe, stone, sand, cement, solid iron, wood, zinc etc. These heavy equipment and
transportation equipment are used for construction of roads, building, and clearing of site land
development of Aek Sibundong MHPP. Mobilization of materials and heavy equipment will be
conducted at the beginning of construction phase. According to Feasibility Study, the equipment
for construction is stated as follows:
Metal work equipment required include welding machine, crane, plate cutting machine,
drilling machine and so on. While the function and usefulness of the above equipment
among others for penstock manufacture and installation, saddle peir, crane line installation
and cutting steel reinforcement as well as forming/bending in accordance with the
drawing of the plan;
Work structure equipment include concrete mixer with a capacity of 0.5 m3, water tankers
to supply water needs, dump trucks for transporting materials, scaffolding and scaffolding
for concrete/concrete work, concrete mixer vibrator / concrete vibrator and others;
The ground work equipment consists of dump trucks, bulldozers, wheel loaders, motor
graders, vibrators roller, excavator/back-hoe, hand stamper;
Excavation works require the operation of equipment include excavators for extracting and
decocating excavation profiles, wheel loader, dump truck for the loading process of
minerals and further process transport to bank spoil location and bulldozer for flattening;
Heap work requires the operation of equipment such as dump trucks for transporting
materials, excavator/bulldozer and wheel loader for loading, vibratory roller for
compaction, hand stamper for compaction on a small scale or for material compaction,
reuse and effect of compaction due to the tool is not allowed to interfere the structure of the
building underneath or in the vicinity, water tankers for watering / wetting the material if
the required water content for compaction does not meet the existing requirements;
Access road works require the following equipment bulldozer, macadam roller for basic
soil preparation, macadam roller, motor grader, tire roller and water sprinkler truck for the
upper layers of foundation and the bottom foundation, and tire roller, asphalt ketle, asphalt
sprayer for surface coating;
Demolition work (if any) requires equipment such as leg hammer, dump truck; and
Equipment for architectural work in the form of carpentry equipment and auxiliary
equipment and others, such as ladders, drilling machines, gurinda and others.
The construction phase will commence with land clearing and preparation activities, which involve
vegetation clearance, excavation/filling to required levels, and incorporation of appropriate sand,
gravel and aggregates for appropriate compaction and structural stability.
Any remaining vegetation will be cleared from the site and topsoil will be removed and stored.
Cleared vegetation, where viable, will be mulched and retained with the topsoil and kept for
growth medium for landscaping or remediation activities.
23
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Measures will be taken during the construction phase to reduce or eliminate soil and sediment
erosion. These will include:
Site level and drainage control;
Appropriate treatment of slopes and batters for cut and fill;
Careful management of spoil heaps, including provision of cover during major rain events;
Silt fences in addition to the drainage control to prevent silt run off into the river.
Watering for exposed surfaces during dry periods; and
Revegetation of exposed areas not covered by civil works as soon as possible.
All construction and preparations in proximity to sensitive receptors in the community will take
construction impacts into consideration. This includes minimizing noise impacts, measures to
contain drainage erosion, and watering of exposed surfaces during dry periods to minimize dust
drift. In detail, the land preparation will cover several activities as follows.
a. Clearing, grubbing and stripping the top soils, are including land clearing from vegetations,
surface rocks, and stripping of soft soil surfaces, and temporary road access construction
towards the dumping site of cleaned materials. Specifically for top soils, it will be located
on the outskirts of the location and subsequently will be utilized for landscaping.
b. Normalization of river as the site for weir construction. This work will scrapes the river
bank at the left and right side to meet the civil engineering criteria.
c. Temporary stream flow diversion (if required), it will be considered as alternative practice
to expedite the construction of water structure, so in the sudden floading situation, the
construction of water structure will be safe from the brunt of the hard objects carried by the
stream.
d. Cut and fill works which will be conducted according to land condition. Cutting will be
done if the land is higher from the planned elevation, and filling will be done to the land
with lower elevation with soils which meet the criteria for land filling. If the excavated soils
in the project site meet the criteria, it will be kept to be utilized as land filling. If it doesn’t
meet the criteria, the excavated soils will be discarded out of the site.
e. Slope stabilizaton works is required if the planned location has a significant height
variation. Slope stabilization types will depend on the variation of heights, type of soils and
the slope angle.
Access road serves as the connection road from the primary/ provincial roads towards the weir
and power house location plan. The entrance to be built is planned for 1500 m from Sigulok Village
road, 3.5 wide and with 1 m roadside, where from Sigulok Village to Weir Location is 1.5 km away
and to to the power house is 1 km away, the road is also utilized for roadway inspection and access
road to the headpond. The road is started from the Sigulok Village border.
Entrance roads to powerhouses are required during construction to transport materials / building
materials, construction equipment, generating equipment parts and after a trial period for
operation and maintenance traffic.
The cross section of the access road is planned according to the classification and traffic
24
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
requirements to the MHPP location. The required lane for the entrance is approximately 3.5 km
with the detail as follows.
Aek Sibundong MHPP main facilities consist of weir, diversion weir and intake, settling basin,
forebay, waterway, penstock, power house and tailrace.
a. Aek Sibundong MHPP is a run off river power plant with location of weir is adjacent to
intake. Design criteria of the weir for Aek Sibundong MHPP is described as follows.
25
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
c. Settling basin is designed to contain the sediment load such as sand or sludge. Settling
basin generally consists of flushing channel and flushing gate. Flushing channel is used to
channel the sediment load and overflow water from diversion weir towards the river. The
flushing gate is generally smaller than intake gate since this gate is seldom be used. Design
criteria for settling basin is as follows.
26
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Following the construction of main facilities, mechanical and electrical works will be conducted for
Aek Sibundong MHPP. The design criteria for mechanical and electrical works will be selected with
consideration of gross head, dependable flow rate, and penstock design. The following Table 16
describes the design criteria of mechanical and electrical components of Aek Sibundong MHPP in
detail.
Table 16 Design Criteria of the Mechanical and Electrical Components of Aek Sibundong MHPP
Design Parameter
Head 82.5 m
Installed capacity 2 x 4009 kW
Annual total energy 50.95 GWh
production
Own utilization (1%) and 0.9 GWh
distribution losses (1%)
Energy that ca ne sold per year 50.95 GWh
Turbine Specifications
Type of turbine Turbin Francis
Horizontal
Q rated 5,705 m3/s
Capacity 2 x 4009 kW
Numer of turbines 2 Units
Generator rotational speed 600 Rpm
Runner turbin diameter 0.9 m
Suction head -0.38 m
Runner weight 574.66 kg
Turbine weight 14,516.07 kg
Turbine power 4220 kW
Generator
Type of generator 3Ø
27
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
28
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
B (IEC 60076)
Colling system ONAN (IEC 60076)
Vector group Dnd11
Grounding system Solid grounded
Impedantion 4 %
20 kV Switchgear
Rated voltage 24 kV
Nominal System Voltage 20 kV
Rated lightining impulse 50 kV
withstand voltage
Short time withstand voltage 50 kV
Rated frequency 50 Hz
Rated current 1000 A
Short time withstand current 25 kA
(kA/1 s)
Bus bar continous rating 1000 A
Bus bar momentary rating 100 kA
Control bus nominal volatge 220 Vac
Parts of the engine and generator units are equipped with control and safety systems. The control
system can work electrically or mechanically. All control and safety equipments and their auxiliary
equipment are placed inside the panel. To facilitate monitoring, the control system is equipped with
an indicator and alarm system. The way the safety equipment works is divided into two categories:
If there is electrical or mechanical disturbance at the time the plant operates then the alarm
will sound and if in a certain time there is no improvement then the plant will shut down
automatically.
If at the time of operation there is an abnormal situation then the alarm will sound.
The control and safety system of the mechanical apparatus comprises controlling and monitoring of
temperature, pressure, power flow, son quantity, speed drop, load limit and operational valves
where the control and monitoring of the instrument can be done manually or electrically from the
local as well as remote.
Electrical control and security consists of control and monitoring of current, voltage, power,
watthour, power factor, frequency, operation of the breaker, synchronization process and interlock
system. The start / stop operation can be done from the local / remote panel either manually or
automatically. The shut down operating system Aek Sibundong MHPP consists of three modes:
Normal shut down
Quick shut down
Emergency shut down
Electrical control / safety safeguards are among others used in safety releases used in generators,
transformers and other system safeguards.
29
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Following the finalization of construction phase, a number of workforce will be demobilized from
the site. Workforce with sufficient qualification will be considered to be employed during the
operational phase of Aek Sibundong MHPP. Work termination will follow the applicable
regulation in Indonesia.
As well, demobilization of construction material and equipments will be conducted subsequent to
the end of construction phase. In practice, demobilization of heavy material and equipments will be
done gradually to minimize the potential impacts ie dust generation and increasing noise.
The transmission line will be connected to Dolok Sanggul Substation (Gardu Induk Dolok Sanggul)
20 kV. There will be no land acquisition for the transmission line development. The transmission
line of Aek Sibundong MHPP is as follows:
Table 17 Aek Sibundong Point Connection Plan
No Description Remarks
30
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
No Description Remarks
31
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
No Description Remarks
Resistance to voltage Wet: 65 kV; Impuls: 110 kV
Mechanical strength 7000 DAN
Minimum propagation 295 mm
distance
6 Conductor
Disposal current 5 kA
Working voltage 20 kV
Maximum voltage 24 kV
32
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
No Description Remarks
Class 0.2
5 KWh comparison meter
C. Generator Transformer
1 Capacity 2 unit x 5,000 kVA
Phase 3
Volatge 6.3 / 20 kV
Cooling ONAN
Frequency 50 Hz
Operation Phase
After commissioning (Trial Phase) and does not have any further problems that can hamper the
smoothness of the operation. Then, the operation of the MHPP in principle utilizing the height
difference and the amount of water discharge per second available on the flow of the Aek
Sibundong river. This water flow will rotate the axis turbine so as to produce mechanical energy.
This energy is next moving the generator and generating electricity.
33
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Expected
No Workforce Position Quantity Gender Origin
Qualification
Associate Degree
5 Finance 1 F Local
(D3)
Financial Associate Degree
6 1 M Local
Administration (D3)
General Associate Degree
7 1 M Local
Administration (D3)
Elementary –
8 Technician 1 M Local
Vocational School
Elementary –
9 Operator 2 M Local
Vocational School
Office Boy/Cleaning
10 1 High School M Local
Service
Total 12
The operation of Aek Sibundong MHPP will utilize Aek Sibundong River stream with total energy
up to 8 MW. Following the electric generation in power house, water will be channelled back to
Aek Sibundong River.
During operational phase, the maintenance activities for Aek Sibundong MHPP units and
associated facilities will include:
1. Instalation maintenance, will be conducted periodically to ensure the performance of
turbine, generator, controlling tools, etc;
2. Over haul activities for turbine, generator and othe electrical components periodically;
3. Removal of sand from settling basin periodically.
During operational phase, Aek Sibundong MHPP will be operated to produce electricity which will
be distributed to the PLN through Dolok Sanggul Substation. In the distribution of electricity
produced by Aek Sibundong MHPP, the operator will oversee the meter measuring current,
voltage, MVA, MVAR, and Cos φ so that the limitations of transmission line delivery capacity are
not exceeded. Implementation of electricity distribution will be in accordance with applicable SOP.
Project Alternatives
ASE has explored Project alternatives, in particular related to MHPP location and technology.
34
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
3.8.1 No Project
The no project scenario is that the MHPP is not built. In the event that the MHPP is not built there
will be no negative impacts in terms of those that might be typical of MHPP (surface water quality,
sedimentation, etc.). The Humbang Hasundutan Regency, on which territory the MHPP is
supposed to be built, and the host communities will in this scenario feel negative impact because
they do not receive the financial and other rewards associated with the construction of the MHPP
as a major private investment in this otherwise economically challenged area.
From a national perspective, there will be a negative impact in that North Sumatera will be more
reliant on fossil thermal power generation to meet increasing energy demand and also Indonesia
will not be developing renewable energy sources in line with its international obligations. Without
the Project, 10 MW of electricity for the North Sumatera electric grid has to be obtained from
another source, the most likely source being mini hydro power plant. Mini Hydro Power Plant
would not create significant carbon emissions.
The Project location is guided by water flow rate and topography observed at the area which
control how much energy a potential MHPP could produce. While limited few alternative sites in
North Sumatera with similar MHPP potential exist, but they don’t offer significant economic or
environmental advantages. Site selection is further limited given that similar projects are in
planning in the larger Project area.
Early in the planning process, ASE considered alternative scenarios associated with the MHPP at
the proposed site. These considered the following:
Location of power house;
Total head loss; and
Penstock and waterway route.
Through some comprehensive studies, ASE has come to a final plan for location of power house,
total head loss and penstock and waterway route which are described in detail in the Feasibility
Study. This ESIA refers to the final project plan as described in the UKL-UPL and Feasibility study.
The Project site has no particular advantages for any technology other than climatic conditions. A
power plant using conventional fossil fuel including diesel would very likely be sited elsewhere.
The Sijamapolang Subdistrict would not be impacted by any of the environmental and social
impacts associated with the Project, but the region would forego all of the economic benefits.
Practically, there are only one route that could be used for the delivery of major plant items to the
site. This transportation route will require the Project to upgrade parts of the local road to meet the
size and weight requirements for the delivery vehicles. It should be noted that zero community
displacement is expected within the transportation route. It is hoped that this upgrade will help
support the development of the Sigulok Village.
35
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Overview
This ESIA has been prepared for the specific project of Aek Sibundong MHPP and associated
facilities including the access road. The ESIA process has been undertaken in accordance with IFC
Guidelines. The following sections describe in more detail how this general ESIA framework has
been applied to the Aek Sibundong MHPP Project.
Screening
Screening represents a preliminary assessment of the likely environmental, social and health
impacts resulting from a project to determine if a full ESIA is required. Under IFC Policy on
Environmental and Social Sustainability, the screening process will typically categorise projects into
one of three groups:
CATEGORY A
Business activities with potential significant adverse environmental or social risks and/or
impacts that are diverse, irreversible, or unprecedented
CATEGORY B
Business activities with potential limited adverse environmental or social risks and/or
impacts that are few in number, generally site-specific, largely reversible, and readily
addressed through mitigation measures.
CATEGORY C
Business activities with minimal or no adverse environmental or social risks and/or
impacts.
Mini Hydro Power Plant projects in general fall under Category B since the project is a
relatively small scale renewable energy project with limited adverse environmental and social
impacts.
Scoping
Scoping determines the extent to which a project will interact with environmental or social
elements. Through this exercise, the priorities and extent of baseline studies and assessments are
36
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
determined. IFC Guidelines require that this stage is the start of interaction with local communities,
to determine the key issues that need to be addressed, to ensure that impacts to the community and
any sensitive receptors will be defined as part of the ESIA process. It is important to understand the
values that the local community places upon environmental resources that may be impacted by the
project.
Under Indonesian regulations, an UKL-UPL has been prepared for the Aek Sibundong MHPP
Project. The scoping exercise for this ESIA largely comprised a review and updating of an initial
UKL-UPL (National-level EIA) for the project that was prepared for submission under Indonesian
Legislation. This scoping exercise comprised:
Review of the project description to understand the nature and components of the
structures and activities of the proposed project;
Discussions with OTE engineering team to further understand the nature and scale of the
proposed works;
Baseline data collection and analysis of data obtained, including the social aspect;
Extension of study area which not only covers the Aek Sibundong MHPP but also the
Associated Facilities such as new proposed access road and transmission line development
area;
Conducting an impact assessment and evaluation of potential impacts using robust criteria
(sensitivity, magnitude and significance);
Review and update of mitigation measures to produce an Environmental and Social
Mitigation and Management Plan; and
Consideration of potential significant cumulative impacts.
37
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
38
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Table 21 below provides a description of the terminologies used throughout this document to
define and describe impacts.
Term Definition
Impact Magnitude
Magnitude Estimate of the size of the impact (e.g. the size of the area damaged or
impacted, the percentage (%) of a resource that is lost or affected etc.)
Impact Nature
Negative Impact An impact that is considered to represent an adverse change from the
baseline, or introduces a new undesirable factor
Impact Duration
Short-Term Impacts that are predicted to last for a limited period (e.g. during
construction) but will cease on completion of the activity, or as a result of
mitigation/reinstatement measures and natural recovery
Long-Term Impacts that will continue over an extended period (e.g. operational noise)
but cease when the Project stops operating. These will include impacts that
may be intermittent or repeated rather than continuous if they occur over
an extended time period.
Permanent Impacts that occur once on development of the Project and cause a
permanent change in the affected receptor or resource (e.g. the destruction
of a cultural artefact of loss of a sensitive habitat) that endures substantially
beyond the Project lifetime
Impact Extent
Local Impacts are on a local scale (e.g. restricted to the vicinity of the plant,
restricted to within the Project footprint)
39
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Term Definition
Regional Impacts are on a broader scale (effects extend well beyond the immediate
vicinity of the facilities and affect the Pasaman Barat District)
International Impacts are on a global scale (e.g. could extend beyond national
boundaries/ affect existence of species)
The ESIA not only describes the direct impacts of the project itself, but also the way in which the
project will interact with other influences that may derive a social or environmental impact. Thus
there are a number of different types of impact that need to be considered as described in Table 22
below.
Direct Impact Impacts that result from a direct interaction between a planned
project activity and the receiving environment (e.g. between
occupation of a plot of land and the habitats which are lost)
Secondary Impact Impact that follow on from the primary interactions between the
project and its environment as a result of subsequent interactions
within the environment (e.g. loss of part of a habitat affects the
viability of a species population over a wider area)
Indirect Impact Impact that result from other activities that are encouraged to
happen as a consequence of the Project (e.g. presence of project
promotes service industries in the region)
Cumulative Impact Impacts that act together with other impacts to affect the same
environmental resource or receptor
Residual Impact Impacts that remain after mitigation measures have been designed
into the intended activity
In evaluating the significance or importance of impacts, several factors are taken into consideration.
These include an assessment of the project component and its effect on the existing environment as
a baseline and the potentially affected sensitive receptors. The impact is then assessed based on its
potential severity and magnitude. The steps involved in evaluating the significance of impacts are
summarized in the Figure 8 below and key steps described in more detail in the following sections
40
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
All activities associated with the proposed project are identified and potential impacts resulting
from these activities listed.
The criteria used to assess the sensitivity of the receiving environment include:
• Abundance:
Rarity: does the impacted receptor comprise a rare environmental resource (such as
an endangered species or habitat);
Size or extent: What is the size or extent of a resource that would be affected by a
particular impact?
41
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
• Adaptability:
Resilience: what is the ability of the particular environmental or social element to
withstand the change? (for instance social/health impacts may have different
outcomes of a very old or very young members of the community);
Ability to recover: what is the potential to recover from the impact, how complete
will recovery be and how long will it take?;
• State:
Degree of disturbance: is the state of the environmental or social element in its
natural condition, or has it been disturbed by other activities in the past?;
Uniqueness: is the particular environmental condition unique, or is it fairly
commonplace?, What is the potential to replicate the situation by way of offset or
compensation?;
Establishment: how well-established is this particular environmental/social
condition, is its future tenuous or is it likely to persist?
• Value:
Implicit value: how important is it to retain particular environmental/social
condition, in the context of its interrelationship with the broader environment?
Would the loss of this particular environmental/social condition lead to further
breakdown of the existing environment?
Recognised value: has the environmental condition been recognised in some formal
sense, such as a declaration of a conservation area?
42
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
In evaluating the significance or importance of impacts, several factors are taken into consideration.
These include an assessment of the project component and its effect on the existing environment as
a baseline and the potentially affected sensitive receptors. The impact is then assessed based on its
potential severity and magnitude.
The ESIA process comprises several steps, namely to identify and predict potential impacts arising
from project activities, evaluate impacts, design measures to mitigate or avoid adverse impacts, and
assess the significance of any residual impacts.
Severity of impacts depends on the nature and sensitivity of the impact receptor, and the extent,
magnitude, and duration of potential impacts. The matrix to determine the severity of each impact
by comparing impact magnitude against the sensitivity of the receptor is provided in the Table 23
below.
Sensitivity of Receptor
Change
The significance of potential impacts is assessed based on their estimated severity and likelihood of
occurrence. The likelihood of occurrence is estimated based upon experience and/or evidence that
such an outcome has previously occurred. Potential impacts are thus determined to be Negligible,
Minor, Moderate, Major or Critical as shown in the Table 24 below.
43
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Likelihood of Occurrence
e e -Minor
Significance is assessed after taking into account planned measures to manage and mitigate the
risks and impacts. Impacts assessed to have Negligible or Minor significance require no additional
management of mitigation measures. Moderate and Major impacts are considered ‘significant’.
Moderate impacts should be mitigated where practical and to the extent that is cost-effective. Major
impacts must be mitigated such that residual impacts are reduced to at least Moderate levels.
Critical impacts are evaluated as unacceptable impacts that are not amenable to mitigation and thus
project alternatives must be found that avoid such impacts.
For unplanned events or extreme situations, the likelihood that the particular event, impact or
outcome will occur can be ascribed a qualitative probability, as per the categories defined in the
Table 25 below.
Table 25 Likelihood Category
Likelihood Definition
Extremely The event is very unlikely to occur under normal operating conditions
Unlikely but may occur in exceptional circumstances (i.e., the event is generally
never heard of in industry).
Unlikely The event is unlikely but may occur at some time during normal
operating conditions (i.e., the event is heard of in industry).
Low Likelihood The event is likely to occur at some time during normal operating
conditions (i.e., incident has occurred in the company before)
Medium The event is very likely to occur during normal operating conditions, (i.e.,
Likelihood the event occurs several times per year in the company).
High Likelihood/ The event will occur during normal operating conditions (is inevitable),
Inevitable (i.e., the event happens several times per year at a location).
44
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Likelihood is estimated on the basis of experience and available evidence that such an outcome has
occurred in other similar projects. Impacts resulting from routine or planned events (normal
operations) are classified as having a high likelihood of occurrence.
For the purposes of ascribing significance to the impacts in Aek Sibundong MHPP environmental
impact assessments, the terminology that has been adopted is described in the Table 26 below.
Significance Definition
An impact that is considered to represent an improvement on the
Positive Impact
baseline or introduces a new desirable factor
Negligible Impact Magnitude of change is comparable to natural variation
Minor Impact Detectable but is not significant
Significant, amenable to mitigation, should be mitigated where
Moderate Impact
practicable
Major Impact Significant; amenable to mitigation; must be mitigated
Intolerable; not amenable to mitigation; alternatives must be
Critical Impact
identified – Project Stopper
It must be noted that critical impacts are not acceptable for planned operations, and can only be
tolerated in the instance of unplanned or incidental events, and only then when the likelihood of
occurrence has been reduced through project planning to least low or unlikely. For unplanned
events or impacts to which probability of occurrence may be ascribed, severity of the impact needs
to be considered in conjunction with the likelihood of its occurrence as described in the Table 27
below.
Impact Likelihood
High
Extremely Low Medium
Unlikely Likelihood/
Unlikely Likelihood Likelihood
Inevitable
Negligible -
Low Negligible Negligible Negligible Minor
Minor
Minor-
Medium Negligible Minor Minor Moderate
moderate
Minor-
Impact Severity
Minor- Moderate -
Critical Major Major Critical
moderate Major
45
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
46
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Impact Likelihood
High
Likelihood/
Low Medium
Extremely Unlikely Unlikely Inevitable
Likelihood Likelihood
(Planned
Event)
Impact Severity/ Magnitude
Mitigation
The ESIA process is intended to identify impacts and benefits associated with project activities and
ways of dealing with them during the planning and design stage of the project. The ultimate goal of
the issue process is to reduce the negative impacts and enhance the benefits or positive impact of
any intended activity. Planned mitigation measures will be described, and additional measures or
controls will be recommended where impacts are still considered to be unacceptable.
47
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Many mitigation or control measures will require a degree of management to ensure their success
in reducing potential impacts to the residual level that is expected through the ESIA process. Most
of these residual outcomes are likely to require a degree of monitoring through project
implementation to ensure that the mitigation management process is effective. It is these
management and monitoring efforts that report to the environmental and social management plan
(ESMP) as part of the ESIA.
In deciding appropriate mitigation strategies there is a hierarchy of response as indicated in Figure
9 below.
There are also the possibilities of unplanned events, including extreme and unusual environmental
conditions that may lead to the possibility of major or even critical impacts. It is incumbent on the
project proponent to reduce the probability of such events to as low as reasonably practical. Even
where steps have been undertaken to reduce risks, a necessary part of the mitigation process to
define a response should the event occur. There is again a hierarchy of response to such occurrences:
Control: this is a response to deal with potential negative impacts at the time and
an emergency situation may be occurring, it can include such things as bushfire
fighting capacity, or even stop work plans for extreme weather events;
Recovery: in the event that the emergency situation has occurred it is important to
identify how project proponents will respond to the potentially negative impacts
such recovery plans could include response plans for containing spills, or
compensation packages were affected parties.
48
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
implementation of the project to avoid, reduce, or compensate for adverse social and environmental
impacts. It typically includes the responsible parties within the organization and the timelines for
their implementation. It will include reference to a number of more detailed management plans and
procedures to be followed within the organization, such as environmental monitoring programs,
community safety and security policies, community consultation plans, maintenance procedures
and schedules. It should also describe desired outcomes as measurable events and parameters
(including performance indicators, targets, or acceptance criteria) that can be tracked over defined
time periods, and indicates resources that will be committed for implementation of the plan. It
should also indicate responses that will need to be undertaken, in the event that performance
criteria are not being met. For instance, it should recommend immediate remedial action if an
element of pollution abatement infrastructure seems to be failing. Where measures and actions are
identified as being necessary for the project to comply with applicable laws and regulations these
should be included in the ESMP.
The development of the ESMP is an iterative process as part of the ESIA process public disclosure
of the findings of the environmental and social analysis is an important step, and often the ESMP
will be refined on the basis of community feedback. Also, as the project progresses, it is often the
case that procedures are modified and optimized in response to changing circumstances, or simply
that a better way of doing things becomes more obvious than it was at the planning stage of the
project. Thus the ESMP, and its underlying monitoring and management procedures are a living set
of documents which reflect the current status of the environmental and social management
approach and plans.
49
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Environmental Baseline
5.1.1 Climate
The analysis on climate component including rain intensity, extreme rain, temperature, air
humidity, sun light duration, wind speed and direction, and sunlight intensity was obtained from
Pinangsori Weather Station, Sibolga, for the period of 2005 to 2014. Pinangsori Weather Station is
the closest weather station to the Projet, where the long-term weather data is available.
Sibolga monthly rain intensities for the last 10 years are shown in Table 30. The lowest average rain
intensity occurred in January for 113 mm in 2012 and the highest (1174 mm) occurred in July 2007
with a standard deviation of 191 mm.
Table 30 Average Monthly Rain Intensity (mm) in Sibolga for the Last 10 years (2005-2014)
Year Jan Feb Mar Apr May Jun Jul Ags Sep Oct Nov Dec
2005 219 192 274 173 117 178 327 768 310 1.056 610 491
2006 462 427 371 477 192 186 221 365 498 597 439 533
2007 407 390 340 273 297 249 1.174 226 513 945 546 292
2008 298 427 685 354 413 424 363 412 496 350 811 331
2009 385 241 511 342 220 209 254 476 526 407 466 313
2010 298 427 685 354 413 424 363 412 496 350 811 331
2011 301 269 418 492 206 152 231 463 452 576 962 768
2012 113 480 322 450 286 178 476 361 461 282 660 684
2013 211 192 220 375 218 128 134 424 286 637 603 273
2014 339 39 240 360 276 293 264 286 423 386 620 397
AVG 303 308 406 365 263 242 263 419 446 453 652 441
Figure 10 shows that in August and October 2005, July and October 2007, November –December
2011, extreme rain events were occurred.
50
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
MHPP SIGULOK
51
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Schmidt and Ferguson (1951) classified climate type in Indonesia which is defined by dividing
average dry months (D) by average wet months (W) during specific observation years; Q = D/W.
Dry months are identified where the monthly precipitation is less than 60mm, while wet months
are defined when the monthly precipitation is over 100mm.
Over the period data was collected, the average dry and wet months in the project area are 0 and
120 respectively. The Q value is 0, so that the climate is categorized as Very Wet (Zone A)
according to rainfall data 2005 - 2014.
Extreme rain is an element of weather that needs to be taken into account since it will directly or
indirectly affect human’s activities. Figure 12 shows that extreme rain event frequency for each
extreme rain limit (≥50mm/24 hour, ≥100 mm/24 hour, and ≥150 mm/24 hour) decreased
gradually for the last 10 years.
52
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
That the average temperature ranges between 25.4 - 27.7 0C in Table 32.
Table 32 Monthly Air Temperature (0C) in Sibolga for the Last 10 years (2005-2014)
Year Jan Feb Mar Apr Mei Jun Jul Ags Sep Oct Nov Dec
2005 26.4 26.9 26.8 27.1 26.9 26.3 26.0 25.8 26.3 25.7 25.6 25.7
2006 25.8 26.3 26.6 26.6 26.8 26.4 25.9 26.1 25.4 25.6 26.0 25.9
2007 26.0 26.2 26.4 26.8 27.2 26.7 26.0 25.9 25.8 25.5 25.6 25.8
2008 26.2 26.4 25.7 26.4 26.5 25.8 25.6 26.0 25.7 25.9 25.9 25.7
2009 26.1 26.0 26.2 26.8 26.9 26.5 26.0 25.7 27.7 26.1 25.9 26.3
2010 26.3 26.3 26.7 27.2 27.4 26.8 26.3 26.2 25.9 25.9 25.5 25.9
2011 25.9 26.1 26.2 26.4 27.1 27.0 26.3 26.0 24.8 26.1 26.2 26.1
2012 26.5 25.9 26.6 26.6 27.2 26.3 25.7 26.0 26.2 26.2 26.0 26.0
2013 26.9 26.1 26.8 26.6 27.2 26.8 26.3 26.1 26.1 26.1 25.9 26.4
2014 26.6 26.9 27.0 26.8 26.9 26.8 26.4 25.9 26.1 26.1 25.9 26.0
AVG 26.3 26.3 26.5 26.7 27.0 26.5 26.1 26.0 26.0 25.9 25.9 26.0
Figure 13 shows that in the last 10 years (2005-2015), air temperature ranges between 25.8°C - 27°
with a standard deviation of 0.5°C. The lowest mean air temperature occurred in November (25.8°C)
and the highest was in May (25.8°C).
53
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Table 33 Monthly Air Humidity (%) in Sibolga for the last 10 years (2005-2014)
Year Jan Feb Mar Apr May Jun Jul Ags Sep Oct Nov Dec
2005 86 87 86 86 85 85 85 86 85 87 87 86
2006 84 86 84 86 86 84 81 82 86 86 86 87
2007 84 80 82 83 82 83 83 82 84 86 83 83
2008 84 80 83 83 83 84 83 80 84 84 84 86
2009 82 82 85 84 82 82 74 85 84 85 86 84
2010 84 84 84 85 83 83 84 84 86 84 87 84
2011 83 79 72 81 83 79 80 83 89 83 82 84
2012 82 86 82 84 81 82 85 85 85 86 88 88
2013 82 83 80 84 82 80 81 83 82 84 88 83
2014 83 84 86 87 87 85 88 87 84 86 87 88
AVG 83 83 82 84 83 83 82 84 85 85 86 85
Figure 14 shows that the lowest average air humidity (82%) occurred in March while the highest
(86%) occurred in November with a standard deviation of 2.5%. An extreme air humidity occurred
in July 2009 and March 2011, which were 74% and 72%, respectively. This means that the water
vapor content in the air is relatively smaller compared to its average; it also means that the air
humidity is low.
54
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Total sun light duration is a duration of sun light in a month. Table 34 and Figure 15 shows total
sun light duration in the last 10 years. The lowest (November) was 89 hours and the highest (May)
was 164 hours, with a standard deviation of 36 hours. There is an increased trend of sun light
duration within 10 years observation.
Table 34 Monthly Duration in Sibolga (hour) for the last 10 years (2005-2014)
Year Jan Feb Mar Apr May Jun Jul Ags Sep Oct Nov Dec
2005 148 127 42 135 113 169 140 147 124 109 65 130
2006 116 134 134 110 122 150 163 138 17 53 18 106
2007 115 168 122 101 172 n/a 147 130 66 91 84 102
2008 134 108 101 131 139 122 129 110 82 115 85 99
2009 138 112 139 140 187 172 149 131 122 106 111 151
2010 160 149 150 127 286 104 124 171 114 138 97 118
2011 124 159 152 131 147 169 192 113 125 132 122 112
2012 146 117 121 115 155 124 161 139 94 107 119 136
2013 155 115 194 117 189 249 142 162 181 128 82 103
2014 174 151 141 143 127 178 167 140 126 123 111 108
AVG 141 134 130 125 164 144 151 138 105 110 89 117
Extreme events occurred in September to November 2006 with the total duration of 17, 53 and 18
hours, respectively. It means that intense clouds blocked sun lights during that period. This
situation occurred in March 2005 in which sun light duration was only 42 hours. The opposite
situation occurred in May 2010 and June 2013 in which sun light duration was 286 and 249 hours,
respectively. It means that less clouds blocked sun lights during that period.
55
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
During 2005-2014, wind in Sibolga is dominated with western (W) wind with the percentage of 6%
and from northwest (NW) for 4% and from east (E), southeast (SE), and south (S) for 1%,
respectively. The dominated wind flowing to the west has a speed of 4-7 knots. Meanwhile, the
average wind speed for 2005-2014 was 0.92 knots.
The most wind speed frequency distribution mostly occurred in the interval of 4-7 knots speed
(6.6%), followed by 7-11 knots speed (6%). Calm wind was accounted for 87%. Maximum wind
with the speed of 11-17 knots flown from west (W) and northwest (NW) directions.
The dominant wind with the highest speed (7-11 knots) flown from west (W). The wind speed
frequency distribution is shown in Table 35.
Table 35 Wind Speed Distribution Frequency in Sibolga for the last 10 years, periode 2005-2014
All Years
(2005- Directions / Wind 1-4 4-7 7 - 11 11 - 17 17 - 21 >= 22 Total (%)
2014) Classes (Knots)
1 N 0.0 0.2 0.2 0.0 0.0 0.0 0
2 NE 0.0 0.1 0.1 0.0 0.0 0.0 0
3 E 0.0 0.2 0.1 0.0 0.0 0.0 0
4 SE 0.1 0.4 0.3 0.0 0.0 0.0 1
5 S 0.1 0.5 0.2 0.0 0.0 0.0 1
6 SW 0.0 0.5 0.4 0.0 0.0 0.0 1
7 W 0.1 2.8 3.0 0.2 0.0 0.0 6
8 NW 0.1 2.0 1.8 0.2 0.0 0.0 4
Sub-Total 0.3 6.6 6.0 0.4 0.1 0.0 13
Calms 87
Missing/Incomplete 0
Total 100
Wind dominance flown from west to northwest direction (Figure 16) is because Sibolga is located in
the western coast of North Sumatera adjacent to Indian Ocean. Meanwhile, the location of Sibolga
in bay area had caused the uniqueness of wind pattern, as described in the section of daily wind
variation.
56
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Daily wind variation is a wind circulation within 24 hours or one day. Figure 17 shows that there is
a significant wind speed, between 0.5 knots to 3.5 knots, in 03 UTC to 12 UTC or 10 AM to 7 PM. It
is indicated that wind starts in the mid-morning to dusk. Meanwhile, calm wind blows at night (7
PM) to morning (7 AM).
Figure 17 shows that in the morning (07-10 AM), the wind blows calmly and it is dominated by
wind blowing from the south east direction (SE) with a dominant speed of 4 – 7 knots. In the
afternoon, the dominant wind changes to the west to northwest with an increasing speed to
maximum (3.6 knots) in 1 PM. Afterwards, the wind speed decreases gradually until evening (7 PM)
and is dominated by wind blowing from northwest direction.
57
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Figure 17 Diurnal Variation Windrose of Average Wind Speed, Hour 07.00 PM-04.00 AM
58
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The difference of heat capacity in land and ocean, or the difference in storing heat between land
and ocean. Land heats faster compared to ocean, land is hotter in the morning than ocean, land air
pressure is lower compared to the ocean. In the peak time during the day, the gradient of the
pressure difference between land and ocean reach its maximum value, so the wind will blow from
ocean (that has a higher air pressure) to the land (that has low air pressure). At night, land releases
heat faster than ocean, land cools faster so the air pressure in land will be higher than in the ocean.
This situation will continue until morning comes so the wind will blow from land to ocean.
3.5
100%
3
80%
Calm Wind
2.5
2 60%
1.5
40%
1 Avg. Wind Speed
20%
0.5
0 0%
00 UTC (07 03 UTC (10 06 UTC (13 09 UTC (16 12 UTC (19 15 UTC (22 18 UTC (01 21 UTC (04
WIB) WIB) WIB) WIB) WIB) WIB) WIB) WIB)
January to February, Asian winter wind or west monsoon was active, but the effect of west
monsoon still could not overthrow the dominance effect of Indian Ocean in the western part of
Sibolga. Therefore, dominance wind is blown from west (W). March is when the transition of west
monsoon begun by a weakened west monsoon wind. Start from April, the dominance of Indian
Ocean strengthened. In May, the dominance of Indian Ocean much strengthened and the average
wind speed is increased compared to previous months. Wind speed in June reached its peak,
which was 1.17 knots. The changes occurred in August that the dominant wind came from
southeast (SE). From September to December, the wind dominance back again from west (W) and
the wind speed decreased gradually to 0.75 knots.
59
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
60
60
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Ambient air quality sampling was conducted to determine the current air quality baseline
condition in the vicinity of the Project Area location and within the Project Area of Influence.
The sampling locations were selected based on consideration of nearby sensitive receptors
within the Project Area to represent the background concentrations of the most sensitive
conditions within the Project Area and Project Area of Influence.
The air quality sampling was conducted for 24 hours. Air quality sampling results were
determined against standards set out in Government Regulation (GR) No. 41 Year
1999regarding Air Pollution Control and International Standards of Guidelines of Air Quality:
Global Update (WHO, 2006); Guidelines for Air Quality (WHO, 1999) and National Ambient
Air Quality Standard (US EPA, 2012). Results of ambient air quality sampling are
summarized in Table 36 below.
Result Threshold
No. Parameter Limit Value Unit
AQ1 AQ2
(TLV)
I Physical
II Chemical
Note:
AQ1: Sampling location at settlement with coordinate of 2˚ 08' 33.2" N and 98 ˚ 45'30.1" E
AQ2: Sampling location at the project location (power house area) with coordinate 2˚ 08'
34.2"N and 98 ˚ 45'18.4" E
61
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The ambient air quality measurement results show that there were no parameters which
exceeded the threshold limits. All parameters measured are present in the atmosphere at low
concentrations, indicating the existing condition of ambient air quality is considered to be
quite good. Generally, the condition of ambient air quality in the nearby settlement area (AQ1)
is cleaner than the condition of air quality nearby the Project Area (AQ2) which was indicated
by lower pollutant concentrations.
The Project Area is mostly located within an agricultural area and open land which has good
ambient air quality. The potential sources of air pollution that were been observed during the
site visit mainly derive from community vehicle emissions. Other sources that might impact
air quality are solid waste burning and land clearing. According to the local community,
farmers clear the land to open the new land or to prepare the land for crops by using cutting
methods. There were no burning methods implemented in the agriculture practice conducted
by the local community.
62
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
of internal combustion engines, which might occur from poorly maintained engines. CO
levels measured at all sampling points were below the laboratory detection limit of 30,000
µg/Nm3 for 1 hour sampling period as stated in GR No. 41 Year 1999 and 40,000 μg/Nm3 as
stated in National Ambient Air Quality Standard, USEPA (2012) for 1 hour sampling period.
Hydrocarbons
Hydrocarbons are released into the air naturally and from partial combustion of fossil fuels,
industrial and biological processes. Hydrocarbons have been identified to be toxic and
carcinogenic to humans. The level of toxicity may depend on the hydrocarbon type and its
exposure. Hydrocarbons are present in the atmosphere as trace gases with methane (CH 4) as
the predominant component.
The sampling recorded hydrocarbon levels at the settlement area within the vicinity of the
Project Area of Influence at <13 μg/Nm3 while the sample collected at the Project Area show
result of <13 μg/Nm3.
Analytical results from the sampling show that hydrocarbons concentrations were
significantly below the threshold limit stated in GR No. 41 Year 1999 of 30,000 μg/Nm 3 for 3
hour sampling period. Currently there are no recognizable standards for total hydrocarbon
level in ambient air especially for a 1-hour period and most international standards focus on
specific types of hydrocarbons such as Poly Aromatic Hydrocarbon (PAH).
Ozone (O3)
Ozone is present in the upper atmosphere (Stratosphere) and lower atmosphere
(Troposphere). Ozone in Stratosphere is beneficial to prevent cancer skin from ultraviolet
radiation. However, Tropospheric Ozone is known as atmospheric pollutant which can be
harmful to human respiratory system. Ozone in troposphere is not emitted directly from
vehicle engines, but it is formed by the reaction of sunlight on air containing hydrocarbons
and nitrogen oxides.
The analytical results during the sampling show that there were no Ozone concentrations
which exceeded the threshold limit stated in GR No. 41 Year 1999, of 235 µg/Nm3 for average
1 hour sampling period. The concentration of Ozone at both sampling points was below the
threshold limit value of 48 µg/Nm3 and 49 µg/Nm3 at community settlement and project area,
respectively.
Baseline data from sampling result shows that the Ozone concentrations were well below the
maximum Ozone concentration allowed in the Guidelines of Air Quality: Global Update
(WHO, 2006), of 100 µg/Nm3.
Lead (Pb)
Lead (Pb) is a metal that can be found naturally in the environment and in manufacture
industries. At high exposures, lead is poisonous to animals and humans. It can damage the
nervous systems and causing brain disorders. Lead is a neurotoxin that accumulates both in
soft tissues and the bones. Lead exposure also affects the oxygen carrying capacity of the
blood. The main sources of lead emissions are from fuels in motor vehicles and industrial
sources.
During the sampling, no lead levels exceeded the GR No. 41 Year 1999 for 24 hours sampling
period which is 2 µg/Nm3. Lead levels measured at both sampling locations were below the
63
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
laboratory limit of detection, or < 0.1 µg/Nm3 for both of sampling points.
Noise sampling was conducted to determine the background noise conditions around the
planned Mini-Hydro Power Plant project locations as well as within the settlement area. The
construction and operation of the Mini-Hydro Power Plant has the potential to increase the
surrounding noise level. Noise level measurements was conducted on March 2018. The
sampling points were determined based on the most sensitive receptor sites in the settlement
areas within the Project Area and Project Area of Influence with the potential to be impacted
due to the construction and operation of the Mini-Hydro Power Plant project. Noise sampling
locations were the same as the location of air quality sampling.
Result Threshold
No. Parameter Limit Value Unit
N1 N2
(TLV)
64
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Result Threshold
No. Parameter Limit Value Unit
N1 N2
(TLV)
Note:
N1: Sampling location at settlement with coordinate of 2˚ 08' 33.2" N and 98 ˚ 45'30.1" E
N2: Sampling location at the project location (power house area) with coordinate 2˚ 08' 34.2"N
and 98 ˚ 45'18.4" E
: Above threshold limit value
The direct noise level measurements at both sampling points in the community settlement
and project area during the baseline studies indicate that there were no levels which exceeded
the threshold limit values of both national and international standards, which are 55 dB A for
Residential Area (MoE Decree No.48/1996), 70 dB A for Industrial Area (MoE Decree
No.48/1996) and the Guidelines for Community Noise (Day-time), WHO (1990) except for
one noise level recorded in the community settlement at 15:00. The noise level at this time
was recorded slightly above the threshold limit value which is 64.3 dB A. During the baseline
sampling, noise levels measured were ranged from 35.8 dB A to 64.3 dB A.
The lowest noise level from the result of baseline sampling were observed at 04:00 in the
morning as there are no activities conducted at this time. While the highest noise level was
observed at 15:00 at the community settlement area and at 10:00 at the project location.
The site survey indicated that the primary sources of noise around the Project Area and the
Project Area of Influence are from motor vehicles and audible sounds of the Aek Sibundong
river stream. Moreover, the project site is located nearby from community housing with
typical rural or agricultural noise environment.
65
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
In general, the land use surrounding Aek Sibundong MHPP is forest, shrubs, and open field.
The number of settlements is considered low or not densely populated area. The map of land
use surrounding Aek Sibundong MHPP is presented in Figure 20 below.
66
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Most of the landscape in Aek Sibundong MHPP and Aek Sibundong Catchment Area are
covered by natural vegetation, shrubs, agricultural areas and production forest owned by PT.
Toba Pulp Lestari. The land cover within the Project Area of Aek Sibundong MHPP is
presented in Figure 21 below. According to the UKL/UPL, the site area is 26.08 ha with the
details are 20.87 ha is Permanent Production Forest Area (Kawasan Hutan Produksi Tetap) and
other utilization area (Area Penggunaan Lain/APL) and 5.21 ha is land belong to PT. Toba
Pulp Lestari. However, Aek Sibundong MHPP project is located in Other Use Area (Area
Penggunaan Lain) outside of the protected forest area.
Figure 21 Land Cover with the Project Area of Aek Sibundong MHPP
67
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The area at an altitude below 500 m above sea level is only about 12% covering part of Pakkat
and Tarabintang subdistricts, 500-1000 m above about 36% covering Tarabintang District,
Baktiraja, part of Pakkat and Parlilitan Subdistricts, altitude between 1000-1500 m asml about
48% covering Doloksanggul District, Pollung, Lintongnihuta, Paranginan, Onanganjang,
Sijamapolang, part of Pakkat and Parlilitan subdistricts, altitude above 1500 m above sea
level about 3% covers the area of Mount Dolok Potos. As such, the Aek Sibundong Mini
Hydro Power Plant is located at altitude between 1000 – 1500 m asml. The topography map of
Aek Sibundong MHPP can be seen in the Figure 22 below.
68
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
According to Feasibility Study, the landscape of the investigation area or project location is at
a hilly location with a steep slope incline with a high height of about 100 m more. The Aek
Sibundong River that divides the morphology is a permanent river with a relatively steep
river gradient with a V-shaped valley. The location of the weir is planned after the confluence
of two rivers, ie at relatively straight streams and relatively flat gradients. The valley at this
location is also still V-shaped with a slope of the left and right slopes including steep with a
slope angle of about 45º - 55º. Left and right bank cliffs are relatively stable and there is no
avalanches or fractures that can become avalanche.
Furthermore, the waterway is on the left slope with the slope varying between 30º - 45º. Some
69
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
of the tributaries that lead to the Aek Sibundong river cross this location with deep valleys.
Throughout the location of the waterway is generally located in a relatively stable area but
there are locations with a fairly wide and deep landslides. The location of the tranquilizer
plan lies on a slope area with a not too steep slope of about 30º and there is no indication of
avalanche symptoms. The penstock plan aims at the height of the slopes varying from steep
to steep. Steep areas are generally close to the river. At this location there is also no indication
of ground motion. The location of the central building is in a relatively fairly steep area close
to the river flow. There is no indication of fractures leading to avalanches and this location is
generally already grounded by rocks so that this location is stable. The topographical survey
result of the Mini Hydro Power Plant is presented in the Table 39 below.
Coordinate Elevation
Benchmark
No. Location
Name Z (m)
X (m) Y (m)
70
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.7.2 Geology
Based on the regional geological map of Sidikalang sheet published by the Center for
Research and Development of Geology (1983). The location of the Aek Sibundong MHPP
plan is in the Toba Tuffs formation which consists of tufa riodasit which is non welded.
According to regional geological maps the entire site is based on rocks from the formation of
tufa toba but mostly especially in the area of waterway, head pond, and penstock is
constituted by a mild sandy soil with loose to medium dense. The regional geology map is
shown in Table 40.
Legend:
Moreover, the Aek Sibundong MHPP is in Tuba Tuffs as seen in Figure 23 below.
71
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The weir area is based on welded tuff basement. This outcrop looks good on the Aek
Sibundong river and its tributaries. Tuff rocks show a dirty white gray color, massive,
somewhat weathered, slightly muscular with irregular directions, medium strength. At the
weir location, this rock outcrop is very clearly visible on the cliff and the river bed. The
location of the weir can be said to be safe against stability or piping, local scanning, and also
leaks through the left and right cliffs. Left and right cliffs are also stable against avalanches.
The same rocks are also present in the central building plan site where these rocks underlie
cliffs and rivers. The weathered soil in the form of sand lanauan plaster cover most of the
weir area. Soil conditions generally have low density and tend to be loose. This weathering
72
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
soil underlies the plan of waterway, head pond and penstock. Furthermore, the subsurface
geology of the project components are presented below:
Weir
The weir foundation is based on massive tuff rocks with strength including CL-CM
class with RQD about 80%. The filtration coefficient of 10 -5 cm/s. There are no
indications of weak structures in rocks or caesarean structures. Left and right cliffs
are also not covered by colluvium deposits (changes) of avalanches.
Waterway
Based on the core drilling results are known to the depth of 20 m is based on the
material of lanauan sand clay with very low density (very loose) to low (loose). Such
condition is known from the result of standard penetration test which shows the
value of Nspt ranged from 1 to 8. The result of water passing test is known that the
filtration order is 10-4 to 10-5 cm/s. Based on the test wells also known that to a depth
of 3 meters is based on the sand lanauan slab with low density. there is no indication
of materials of the avalanche material results along the waterwayl plan.
Head Pond
Based on drilling results it is known that tuffed rocks are from a depth of 12.20 m to a
depth of 20 m more. On top of the tuff rocks there is a weathering ground in the form
of sand of lanauan lempungan. the conditions of silica sand generally show a low
density (loose) with Nspt values ranging from 5-7. While tuff rocks show a slightly
weathered conditions with medium strength (CL-CM class). The test results show a
filtration order of 10-4 to 10-5 cm/s which is semi-impermeable.
Penstock
Based on the core drilling results known that tuff rocks are depth of 11 meters while
the weathering soil in the form of sand lanauan plaster above rocks. Tuff rocks are
generally slightly weathered with medium strength (CL-CM class) there are some
sturdy with a value of RQD 78%, while the weathering soil shows loose to medium
(medium) with Nspt values ranging from 3 to 10. Water graduation test results
shows a 10-5 cm / s filtration order including waterproof. The results of the
investigation test with the test paritudes found no indication of weak or fault lines
and also no koluvial deposits (material of avalanches).
Power House
At the location of the power house conducted core drilling investigation to a depth of
20 m. From drilling results note that tuff is from 17 m depth to 20 m more. Rocks are
generally slightly weathered and weathered strongly at the top, with medium
strength (CL-CM class) with rock quality at 60% to 85% (medium quality-good). The
results of the water graduation test show a 10 -5 cm/s filtration order which includes
waterproof.
73
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.7.3 Soil
Generally, as in the islands of Sumatra, in general the type of soil consists of Podsolik Red
Yellow land which is made up of various parent materials. Land in the mountains (as in
Humbang Hasundutan District) has the spreading which is very complicated, but generally
still consists of various forms of Yellow Podsolics soil associated with Latosol and Litosol.
Area rocky limestone covered by Podsolic soil, Chocolate and Renzina soil, Andosol and
Podsolic soils of Gray Chocolate are found on volcanic rocks. The soil classification of Aek
Sibundong MHPP can be seen in Figure 24 below.
74
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Furthemrore, according to Feasibility Study, examples of soil originating from the core drill
and pit test along waterway and access road can be summarized as follows:
Specific gravity :2.6
Water content : 21% - 58%
Dry density content : 0.9 – 1.4 t/m3
Pore number : 0.8 – 1.6
Porosity : 0.4 – 0.6
Saturation degree : 65 – 98%
Cc : 0.2 – 0.5
Wopt : 14 – 18%
Dry density maximum : 1.5 – 1.6 t/m3
According to Feasibility Study, in the weir, the left and right banks is not covered with
colluvium deposits of avalanches. Colluvium is typically composed of a heterogeneous range
of rock types and sediments ranging from silt to rock fragments of various sizes. While in the
waterway, the foundation is based on lanauan sand clay. Furthermore, it was identified in the
head pond that the foundation is based on lanauan sand clay. This condition is the same as in
the penstock area, it was observed that the soil type is lanauan sand clay. Moreover, in the
power house area it was investigated that the condition of rocks are generally slightly
weathered and weathered strongly at the top.
75
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.8.1 Drought
Drought is a natural disaster event occurs due to lack of water supply and rain deficit of the
environment. This natural disaster event will give adverse impact to the environment and
society in term of economic, environment, and health. The impact might include lack of water
and food supply to support the life of people who live within and nearby the drought area.
The drought hazard in Aek Sibundong area can be scaled from 0 – 1 and is particularly
indicated to be in the low to medium based on BNPB.
76
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.8.2 Flood
Based on Badan Naional Penanggulangan Bencana (BNPB) it was indicated that Ketaun Tengah
MHPP area is in a non flood hazard area from the highest value of 0.8330433 where the
world’s highest level of flood area in Global Flood Hazard Frequency and Distribution is
indicated as 25 to 100 years flood period. Thus, Aek Sibundong MHPP is located in a non
flood hazard zone.
Figure 26 Map of Flood Hazard in the Surrounding of Aek Sibundong MHPP Area
77
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.8.3 Landslide
Landslides such as rockfalls, deep failure of slopes, and shallow debris flows can cause huge
economic loss and damage to the property in regard to the infrastructure of Aek Sibundong
Mini Hydro Power Plant. According to BNPB it was indicated that the MHPP area is located
in a medium hazard Zone. Hence, Aek Sibundong MHPP has medium landslide hazard.
Figure 27 Map of Landslide Hazard in the Surrounding of Aek Sibundong MHPP Area
78
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.8.4 Seismic
The seismic coefficient can be calculated based on the Indonesian seismic zone map issued by
the Water Engineering Projects Planning Section of Directorate General Irrigation, the
Ministry of Public Works in 1999/2000. The seismic coefficient of Aek Sibundong MHPP is
0.22 on a 100 year return period. According to United States Geological Survey (USGS), the
Aek Sibundong MHPP has medium to high earthquake potential.
79
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5.1.9 Hydrology
The water resources owned by Humbang Hasundutan Regency come from lakes, rivers and
swamps. Humbang Hasundutan regency is located on a plateau with several headwaters
(DAS) flowing into several neighboring districts. Watersheds located in Humbang
Hasundutan Regency include Aek Simonggo Watershed, Aek Sibundong Watershed, Aek
Silang Watershed and other watersheds. While the source of water coming from the lake that
is from Lake Toba in District Baktiraja.
Singkil (Renun) /
1 52,66 127.981,491
Aek Simonggo
Batang Toru /
2 12,36 12.506,425
Aek Doras
Tapus Lumut /
4 34,89 71.735,004
Aek Sibundong
The project area of Aek Sibundong MHPP is located in the Aek Sibundong Watershed with
area of 71.735,004 km2. The MHPP is located in Aek Sibundong Watershed which is currently
covered by trees and bush/shrub areas, as well as agricultural crops of paddy, corn, and pulp
plantation. The agricultural crops within this area were noted to be productive and very well
groomed.
According to Feasibility Study, the calculation of flood discharge at the Aek Sibundong River
is based on the observed instantaneous discharge data from the Aek sibundong River which
was then converted for the location of Aek Sibundong MHPP area. Table 42 shows the
observed flood discharge from 1991 to 2010 which utilized for the flood discharge calculation
of Aek Sibundong River.
80
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
81
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The results of laboratory analysis of surface water quality in the baseline studies are
summarised in Table 44 below. A discussion of the results of these laboratory and field
measurements is provided in the following sections. The UKL-UPL Study didn’t analyse all
parameters as stated in GR No. 82 Year 2001 on Water Quality Management and Water
Pollution Control. As the result of UKL-UPL Study was not adequate to support the baseline
of the project location, the results of this baseline studies are considered to be more
representative for the Study. Samples were collected from three locations representing the
baseline condition within the Project Area and its vicinity; consisting of SW1 in the proposed
weir area which represents the condition of water quality upstream of the Aek Sibundong
MHPP Project Area of Influence, SW2 in the middle stream of Aek Sibundong River and SW3
in the proposed power house area which represents the condition of water quality
downstream of the Aek Sibundong MHPP area.
Results Threshold
No. Parameter Limit Value Unit
SW1 SW2 SW3
(TLV)
I Physical
II Chemical
2. Biochemical 5 5 6 3 mg/L
Oxygen Demand
(BOD5)
82
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Results Threshold
No. Parameter Limit Value Unit
SW1 SW2 SW3
(TLV)
Dissolved Metal
83
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Results Threshold
No. Parameter Limit Value Unit
SW1 SW2 SW3
(TLV)
III Microbiology
Note:
SW1: Upstream with coordinate 2˚ 08' 53.3" N and 98 ˚ 46'12.8" E
SW2: Middle stream with coordinate 2˚ 08' 47.1" N and 98 ˚ 45'33.3" E
SW3: Downstream with coordinate 2˚ 8 ' 41.6" N and 98 ˚ 45 ' 08.1" E
: Above threshold limit value
The following sections describe the baseline water quality in the Project Area from the result
of baseline sampling.
Temperature
Temperature is an important factor in determining water quality; temperature can influence
several other parameters and can alter the physical, chemical, and biological properties of
water, including density, pH, metabolic rate and photosynthesis, salinity, conductivity, etc. In
the dry season sampling, temperature was measured onsite and the direct readings at two
sampling locations ranged from 20.7° C at SW 1, 20.8° C at SW2 and 21.1° C at SW 3. Both
national and international standard state that the standard of temperature for surface waters
is within three standard deviations from the ambient temperature (temperature on surface
water should be within ±3ºC from the ambient air temperature).
84
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
TDS measured at three sampling locations ranged from 20.1 mg/L at SW1, 23.4 mg/L at SW2,
and 23 mg/L at SW3. The TDS concentrations were all significantly below the threshold limit
stated in National GR No. 82 Year 2001 for Surface Water Class of II of 1,000 mg/L. This
indicates that current baseline conditions for TDS are very good.
pH
Water with pH levels above 9 and below 4 is deadly to some aquatic organisms especially
fish. Anthropogenic activity which can influence pH in surface water includes the discharge
of industrial pollutants directly into water. Measurement results at three sampling locations
during the baseline sampling ranged from 7.54 at SW1, 7.52 at SW2 and 7.48 at SW3, which
conformed to the threshold range stated in GR No. 82 Year 2001 for Surface Water Class II
which is 6 to 9 as well as USEPA 62-302.530 Surface Water Quality Class III which is 6 to 8.5.
Generally natural surface water should have pH in a range of 6.5 to 8.5 and pH of drinking
water should be in between 6.5 to 9.0.
85
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Nutrients
Common nutrients in water comprise Nitrogen, Ammonia and Phosphates. The presence of
these nutrients is very influential for the ecosystem equilibrium. Low levels of nutrients in
water can inhibit the growth of algae, while excess levels of nutrients in water can lead to the
excessive growth of algae which is known as eutrophication. Eutrophication results in rapid
decreases of dissolved oxygen. Anthropogenic nutrients sources in water bodies are derived
from various non-point (e.g. leached fertilizer and manure run off from agricultural land) or
point (e.g. sewage effluent) sources (De Meester, 2009).
Measurement results at the three sampling locations (SW1, SW2 and SW3) show that
phosphate concentrations were 0.174 mg/L at SW1, <0.003 mg/L at SW2 and 0.043 mg/L at
SW3, which are all well below the GR No. 82 Year 2001 value of 0.2 mg/L.
Nitrate concentrations at the three sampling locations were detected at 0.9 mg/L at SW1, 0.8
mg/L at SW2 and 0.9 mg/L at SW3 and below the laboratory limit of detection, all of which
were well below the threshold limit value of 10 mg/L.
Ammonia levels were recorded at <0.03 mg/L at SW1 and below the laboratory detection
limit of <0.03 mg/L at SW2 and <0.03 mg/L at SW3. The ammonia concentration at all
sampling location were below the threshold limit value of 0.02 mg/L from USEPA 62-302.530
Surface Water Quality Class III.
Nitrite concentrations at the three sampling location during the baseline sampling were
below the laboratory detection limit value of 0.006 mg/L at SW1, 0.004 mg/L at SW2 and
0.006 mg/L at SW3, lower than both the National and International Threshold standard of
0.06 mg/L and 10 mg/L respectively for Nitrite.
Metals
Metals are naturally occurring in surface water as vital micronutrients, but in excessive
concentrations, metals are toxic. Some metals in surface waters are derived primarily from
the natural weathering of soils and rocks, from volcanic eruptions, and from anthropogenic
sources such as mining, processing or use of metals and substances that contain metal
pollutants.
Metals measured consisted of Arsenic, Cobalt, Barium, Boron, Selenium, Cadmium,
Chromium (VI), Copper, Iron, Lead, Manganese, Mercury and Zinc. Analytical results for all
metals were below laboratory detection limits at three sampling locations. For Cadmium,
Chromium (VI), Copper and Mercury, compliance with the adopted international threshold
86
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
values could not be determined as the threshold limit was lower than the laboratory limit of
detection.
Based on site investigations, there were no significant metal releasing activities observed near
the Project Area. The concentration of metals in the water bodies is likely associated with
natural weathering of soil and rock in the Project area.
Chloride
Chloride can be easily found in nature due to its soluble characteristic. In appropriate
concentrations, Chloride is useful for water treatment, irrigation, and many chemical
industries. In excess concentration, Chloride causes the water to be saline. Naturally,
Chloride is also contained in the urine produced by humans and animals. Chloride levels
measured at three sampling locations were detected at 0.4 mg/L for SW1, 0.5 mg/L at SW2
and 0.2 mg/L for SW3. There is no threshold limit stated in either GR No. 82 Year 2001 for
Surface Water Class II or USEPA 62-302.530 Surface Water Quality Class III.
Cyanide
Cyanide is naturally produced by bacteria, fungi and algae. It is also found in vegetation,
bound to glucose which is called amygdalin. Cyanide in water is usually derived from
industrial wastewater discharges, such as from electroplating industry, gold and silver
mining, fertilizer industry, and steel and iron industry. Cyanide is also used for pesticides
and fumigants. Cyanide is extremely toxic to human health. Cyanide concentrations
measured at the three sampling locations during the baseline sampling were below the
laboratory detection limit of <0.001 mg/L at SW1, <0.001 mg/L at SW2 and <0.001 mg/L at
SW3. Compared to GR No. 82 Year 2001, Cyanide result were below the threshold limit of
0.02 mg/L. However, the USEPA 62-302.530 threshold limit of 0.0052 mg/L was below the
laboratory limit of detection.
Fluoride
Fluoride occurs naturally in the earth’s crust, and can be found in rocks, coal, and clay.
Fluoride is widely used in the industries of steel, glass, metal plating, aluminium, fertilisers
and pesticides. Fluoride in appropriate concentrations is useful for preventing dental cavities,
but in excessive levels it can lead to fluorosis in bone and teeth. Fluoride concentrations
during the baseline sampling were below the laboratory detection limit value of <0.09 mg/L
at SW1, <0.09 mg/L at SW2 and <0.09 mg/L at SW3. Fluoride concentrations were below the
threshold limit value of GR No. 82 Year 2001 Class II and USEPA 62-302.530 Class III which
are 1.5 mg/L and 10 mg/L respectively. Fluoride was not detected during the UKL-UPL
baseline study.
Sulphate
Sulphate is an anion that is naturally found in water, common sources of sulphate in waters
are oxidation of sulfite ores, the presence of shales, or industrial waste. Sulphate levels are a
common concern in clean water piping network systems as the presence of Sulphate can lead
to crust, odour, and corrosion within the pipes. At high levels, sulphate can give water a
bitter or astringent taste and can have laxative effects. Sulphate concentrations measured
during the dry and wet season at the two sampling locations were below the laboratory
87
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
detection limit of 5 mg/L at SW1, 4 mg/L at SW2 and 6 mg/L at SW3. There is no threshold
limit stated in either GR No. 82 Year 2001 for Surface Water Class II or USEPA 62-302.530
Surface Water Quality Class III.
Microbiology
Coliform bacteria are a type of microorganism commonly used as an indicator to determine
the contamination of pathogens in water. It is used as a general indicator of potential
contamination from pathogenic organisms which in polluted waters are usually much lower
in number and much harder to isolate than coliforms. Faecal coliform are facultative-
anaerobic bacteria which can be found in the faeces of humans and animals. Escherichia Coli
is a type of faecal coliform which is a pathogen and can cause diarrhoea or bloody diarrhoea,
abdominal cramps, nausea, and malaise in humans if consumed.
The measurement results show that the total coliform levels at SW2 (middle stream) was the
lowest with concentration detected at 4352/100mL in comparison to the concentration of
faecal coliform at SW1 (upstream) with the concentrations detected at 4674/100mL and at
SW3 (downstream) with the concentration detected at 5938/100mL. The highest total
coliform was detected in the downstream of Aek Sibundong River. Detection of microbes
(comprised of faecal coliform and total coliform) in the Aek Sibundong River were lower than
the threshold limit value of faecal coliform as stated in GR No. 82 Year 2001 Class II and
USEPA 62-302.530 Class III which are 1,000/100 mL and 500/100mL respectively and the
threshold limit value of 5,000/100 mL for total coliform as stated in GR No. 82 Year 2001
Class II.
It was observed that contamination of microbes was relatively higher at the downstream
location (SW3) compared to the upstream (SW1) and middle stream area (SW2). This may be
due to the relatively closer vicinity of SW3 sampling points to the settlements areas. High
concentrations of coliforms may be due to contamination from human/animal waste.
Organic Chemicals
Organic chemicals in freshwater are mostly derived from domestic sewage (raw or treated),
urban run-off, industrial effluents and agricultural wastes. Excess concentrations of organic
chemicals in water can cause the depletion of dissolved oxygen. It can also lead to increased
turbidity which reduces the light available for photosynthesis activity.
Organic chemicals at three sampling locations were measured in terms of oil & grease,
detergent as MBAS, and phenol. Oil & grease, detergent and phenol concentrations were
below the laboratory limit of detection at all sampling locations. These concentrations were
all below the threshold limit stated by the International Standard and National Standard.
Aquatic biodiversity sampling was conducted to determine the abundance and diversity of
plankton in water bodies, which can be used as an indicator of baseline condition of water
bodies. Aquatic biodiversity is commonly used as water pollution bio-indicator due to their
habitat requirements, mobility and a relatively long lifetime to inhabit water. Aquatic
biodiversity measured includes phytoplankton, zooplankton and benthos. The results of
aquatic biodiversity sampling are described in the following section.
88
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Phytoplankton
Seven classes of phytoplankton, consisting of Bacillarophyceae, Chlorophyceae,
Coscinodiscophyceae, Cyanophyceae, Euglenophyceae, Mediophyceae and Zygnematophyceae were
identified at three sampling locations during the baseline sampling. 25 taxas at AB1
(upstream), 15 taxas at AB2 (middle stream) and 20 taxas at AB3 (downstream) were
identified. In general, the compositions of phytoplankton species detected in each sampling
location were relatively similar. The results of identified phytoplankton are presented in
Table 45 below.
Phytoplankton
Bachillariophyceae
Chlorophyceae
Coscinodiscophyceae
89
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Phytoplankton
Cynophyceae
Euglenophyceae
Mediophyceae
Zygnematophyceae
Taxa (S) 25 15 20
Note:
AB1: Upstream with coordinate 2˚ 08' 53.3" N and 98 ˚ 46'12.8" E
AB2: Middle stream with coordinate 2˚ 08' 47.1" N and 98 ˚ 45'33.3" E
AB3: Downstream with coordinate 2˚ 8 ' 41.6" N and 98 ˚ 45 ' 08.1" E
The abundance levels of phytoplankton ranged from 1,025 Cell/L at AB1, 630 Cell/L at AB2
and 1,105 Cell/L at AB3. AB3 has the highest abundance level of phytoplankton than the
90
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
AB1 and AB2, which may indicate the cumulative impacts on the water pollution in the
downstream. The species with the highest abundance percentage at three sampling location
was Fragillaria sp., from Bacillariophyceae class, at 9.76%, 66.67% and 29.41% respectively.
The diversity indexes ranged from 2.548 at AB1, 1.380 at AB2 and 2.449 at AB3. Lee (1978)
stated that the biota diversity index of heavily polluted water is less than one (H < 1),
moderately polluted waters are between 1.0 and 1.5 (1.0 < H < 1.5), lightly polluted waters are
between 1.6 and 2.0 (1.6 < H < 2.0) and unpolluted waters are greater than two (H > 2). The
diversity indexes at AB1 and AB3 sampling locations indicate the water body is considered as
unpolluted water, which is also reflected in the surface water quality result. While AB2 is
considered moderately polluted waters.
The equitability indexes at all sampling locations ranged from 0.791 at AB1, 0.510 at AB2 and
0.817 at AB3. The dominance indexes at all sampling locations ranged from 0.1236 at AB1 to
0.1278 at AB2 and from 0.114 at AB1, 0.0460 at AB2 and 0.130 at AB3. Equitability indexes and
dominance indexes at all sampling locations indicate that there is no dominant species in the
water, which is shown by the value close to 1 for equitability index and close to 0 for
dominance index.
Zooplankton
Two classes of zooplankton, consisting of Crustacea and Ciliata, were identified at AB1 while
there were three classes, consisting of the same classes as AB1 with Rotatoria as additional
class, identified at AB2. Both locations had seven taxas that are further presented in Table 44.
Three classes of zooplankton, consisting of Crustacea, Ciliata and Rotatoria, and four species
were identified at AB1 while there were two classes, consisting of Crustacea and Ciliata, and
three species identified at AB2.
Zooplankton
Branchiopoda
Copepoda
Rotifera
91
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Zooplankton
Tubulinea
Taxa (S) 7 6 6
Note:
AB1: Upstream with coordinate 2˚ 08' 53.3" N and 98 ˚ 46'12.8" E
AB2: Middle stream with coordinate 2˚ 08' 47.1" N and 98 ˚ 45'33.3" E
AB3: Downstream with coordinate 2˚ 8 ' 41.6" N and 98 ˚ 45 ' 08.1" E
The abundance levels of zooplankton ranged from 55 ind/L at AB1, 45 ind/L at AB2 and 55
ind/L at AB3. The diversity indexes ranged from 1.768 at AB1, 1.677 at AB2 and 1.642 at AB3.
The diversity indexes at all sampling locations indicate that the water quality in sampling
locations was considered to be lightly polluted as the diversity indices were in the range of
1.6 < H < 2.0.
The equitability indexes at all sampling locations during the wet season ranged from 0.908 at
AB1, 0.936 at AB2 and 0.916 at AB3 implying that populations of zooplankton species are
evenly spread and there is no dominance as the equitability index values were close to 1. The
dominance indexes at all sampling locations ranged from 0.207 at AB1, 0.210 at AB2 and 0.223
at AB3 which is also consistent with equitability index indicating the absence of dominant
species as the index value is close to 0.
Benthos
Two classes of benthos, consisting of Insecta and Oligochaeta, were identified at three sampling
locations. Two taxas were identified in AB1 and AB2 while one taxa were identified in AB3.
The results of benthos analysis are presented in Table 47 below.
92
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Benthos
Branchiopoda
3. Philopotamus sp. - - 38 50 - -
Copepoda
Taxa (S) 2 2 1
Note:
AB1: Upstream with coordinate 2˚ 08' 53.3" N and 98 ˚ 46'12.8" E
AB2: Middle stream with coordinate 2˚ 08' 47.1" N and 98 ˚ 45'33.3" E
AB3: Downstream with coordinate 2˚ 8 ' 41.6" N and 98 ˚ 45 ' 08.1" E
The abundance level of benthos at all sampling locations ranged from 114 ind/m2 at AB1, 76
ind/m2 at AB2 and 38 ind/m2 at AB3. The results of plankton and benthos analysis
consistently show higher abundance levels in the upstream area than the downstream area.
The diversity indexes ranged from 0.918 at AB1, 1 at AB2 and 0 at AB3. The diversity indexes
at all sampling locations indicates that the water quality at the sampling locations was
considered moderately polluted water with diversity index between 1.0 and 1.5 (1.0 < H <
1.5).
The equitability indexes at all sampling locations ranged from 0.918 at AB1, 1 at AB2 and 0 at
AB3. The dominance indexes at both sampling locations ranged from 0.556 at AB1, 0.5 at AB2
and 1 at AB3. Both equitability index and dominance index show that there is no dominance
of species in the water.
93
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The main public transportations in the study area are motorcycle and motorcycle taxi (locally
known as becak motor) in Dolok Sanggul. There are no public transport that connects Dolok
Sanggul and Sigulok Village. The common transport from Dolok Sanggul to Sigulok Village
is motorcycle. Furthermore, the local transport in Sigulok Village is motorcyle. It was
observed that very limited four wheel vehicle presence in Sigulok Village. No significant
numbers of pedestrians and no dedicated walkways for pedestrians were observed in the
study area. Local community use undeveloped parts of the side road as footpaths. When
there is insufficient space to walk on side of the road, pedestrians walk on the road itself.
Aek Sibundong MHPP Project can be accessed from Jakarta via Silangit International Airport
then to Dolok Sanggul via road approximately 30 minutes drive. Administratively, Aek
Sibundong MHPP is included in the administrative area of Sigulok Village, Sijamapolang
SubDistrict, Humbang Hasundutan District. Sigulok Village is located 30 km direction south
of Doloksanggul Town which is the nearest town from the location of the MHPP.
The access road to powerhouse area is located in Sigulok Village. The distance between the
main road and power house area is approximately 500 m, passing through agricultural areas
with unsealed roads. From the main road, larger vehicles such as cars can only access the
main road (Jalan Desa) with an approximate with 2 m width to reach the entrance to the
power house. The remaining journey needs to be continued by foot.
The access road to the weir area is located in Sigulok Village, located approximately 2 km
from the power house access road. The distance between the main road and weir area is
approximately 2 km, the entrance is a village road within the community area, the 2 km
journey to the weir which can be accessed only by foot.
The brief description related to the journey to the project location is presented in the
following Table 48.
94
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The road conditions within the Project Area are summarized in the Table 49.
Description Photo
Location:
T-Junction at Jalan Letkol GA
Manulang, Dolok Sanggul
Approximate Coordinate:
2° 15'3"N
98°45'4"E
Width:
5m
Road Condition:
- Paved road
- No pedestrian walkway
- 2 ways, 2 lanes
- Undivided
95
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Description Photo
Location:
Road access to Siborboron
Approximate Coordinate:
2° 15'2"N
98°45'4"E
Width:
2m
Road Condition:
- Paved road
- No pedestrian walkway
- 2 ways, 2 lanes
- Undivided
Location:
Road access to Simarigung
Approximate Coordinate:
2° 15'2"N
98°45'4"E
Width:
2m
Road Condition:
- Paved road
- No pedestrian walkway
- 2 ways, 2 lanes
- Undivided
96
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Description Photo
Location:
Village Road near power house
access road (direction to Bonan
Dolok)
Approximate Coordinate:
2° 15'42"N
98°44'50"E
Width:
1.5 m
Road Condition:
- Unpaved road
- Surrounded by agriculture
land and open land
Location:
Village Road near power house
access road (direction to Tornauli)
Approximate Coordinate:
2° 8'28"N
98°45'21"E
Width:
1 .5 m
Road Condition:
- Unpaved road
- Surrounded by agriculture
land and open land
97
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Description Photo
Location:
Access road to Power House
Approximate Coordinate:
2° 8'28"N
98°45'20"E
Width:
50 cm
Road Condition:
- Unpaved road
- Surrounded by agriculture
land and open land
Location:
Access road to weir
Approximate Coordinate:
2° 8'32"N
98°45'45"E
Width:
50 cm
Road Condition:
- Unpaved road
- Surrounded by agriculture
land and open land
98
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Traffic counting was conducted at Jalan Letkol Manulang T-junction which connects three
road sections with 6 road direction which are Jalan Letkol Manulang to Simarigung,
Simarigung to Jalan Letkol Manulang, Siborboron to Jalan Letkol Manulang and Jalan Letkol
Manulang to Siborboron. The vehicle proportion in study area is shown in Figure 29 below.
2212
4681
Motorcycle Light Vehicle Medium Heavy Vehicle Light Bus Light Truck Unmotorised
15
Motorcycle Light Vehicle Medium Heavy Vehicle Light Bus Light Truck Unmotorised
99
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The traffic counting data shows that motorcycles were the most common mode of
transportation in Sigulok Village, with 15 vehicles recorded in the peak hours on two days,
representing one day of peak hours in the weekend and one of day peak hours in the
weekday. Motorcycles were followed by light vehicles such as cars with 4 vehicles (21%).
There are no other types of vehicle recorded during traffic survey in Sigulok Village.
Vehicle classification has three classes: motorcycle (MC), light vehicle (LV), and heavy vehicle
(HV). For capacity analysis purposes, these vehicle classifications were converted into
passenger car units (PCU) using passenger car equivalent factors. This converting factor
compares one type of vehicle with a passenger car in terms of their impact on traffic
behaviour. The vehicle classifications and PCU equivalent factor refer to MKJI code are
summarized in Table 50 below.
The total traffic volume was calculated by converting the traffic counting values into
pcu/hour as shown in Table 51. Traffic volume in Jalan Letkol Manulang T-Junction was
busier on weekend than the weekdays. Considering Jalan Letkol Manulang is the central
entrance to the Simarigung and Siborboron, with the the presence of PT Toba Pulp Lestari
plantation, the high traffic volume on weekday may be due to the amount of local community
who reach the central district on working days.
Siborboron to
Letkol 69.35 63.025 51.575 72.85 60.075 41.6
Manulang
100
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Siborboron
Letkol
Manulang to 37.575 57.075 63.8 42.95 57.025 53.05
Simarigung
Simarigung to
Letkol 42.3 49.75 48.15 45.825 49.375 45.425
Manulang
Tornauli to
0.5 0.375 0 0.25 0 0.25
Bonan Dolok
Bonan Dolok to
0.375 0.25 0.125 0.25 0.125 0.375
Tornauli
As described previously, there was one junction with three main roads in the survey area
with 6 directions; consisting of Jalan Letkol Manulang to Simarigung, Simarigung to Jalan
Letkol Manulang, Siborboron to Jalan Letkol Manulang and Jalan Letkol Manulang to
Siborboron. Moreover, the Jalan Desa in Sigulok Village has one main road with 2 directions
which are Bonan Dolok to Tornauli and Tornauli to Bonan Dolok. Further details of the road
capacity according to MKJI are described below.
101
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
in the entire area. Side friction of in this section is considered as low (L). According to the
MKJI calculation method, link capacity of Jalan Letkol Manulang to Siborboron Road is 1,345
PCU/hour. Divided into two directions, each direction has link capacity value of 672.5
pcu/hour.
Volume to capacity ratio (V/C Ratio) is a conventional level-of-service (LoS) measure for
roadways, comparing roadway demand (vehicle volumes) with road supply (carrying
capacity). This measure can alert transportation providers to areas where traffic mitigation
measures should be considered. The standard of LoS is summarized in Table 52 below.
102
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The V/C ratio is derived by dividing traffic volume (V) by capacity (C). An empty/free flow
road condition is represented by a V/C ratio = 0 and a V/C ratio = 1 represents an on-
capacity road condition. Calculation result shows that road conditions are classified as class
A LoS (≤ 0.60) during both weekday and weekend, which is considered as free flow traffic.
Despite the free flow condition of LoS in the study area, it is recommended to prevent any
traffic safety issue by developing traffic mitigation. The results of V/C ratio calculations are
summarised in Table 53.
Siborboron to
Letkol 0.05 0.05 0.04 0.05 0.04 0.03
Manulang
Letkol
Manulang to 0.06 0.05 0.04 0.05 0.05 0.03
Siborboron
Letkol
Manulang to 0.03 0.04 0.05 0.03 0.04 0.04
Simarigung
Simarigung to
Letkol 0.03 0.04 0.04 0.03 0.04 0.03
Manulang
Tornauli to
0 0 0 0 0 0
Bonan Dolok
Bonan Dolok to
0 0 0 0 0 0
Tornauli
The baseline biodiversity resources data was developed by using primary and secondary
data. The primary data collection on biodiversity resources has been conducted in March
2018. The biodiversity survey covers the Project Area, including associated facilities, and the
nearby vicinity. Secondary data was taken from Integrated Biodiversity Assessment Tool
(IBAT) and was developed by considering several known reliable information sources such
as the International Union for Conservation of Nature Extend of Occurrence (IUCN EOO)
maps, Important Bird Area (IBA), Key Biodiversity Area (KBA), UNESCO Site and Ramsar
Wetland as applicable to get a bigger picture of the biodiversity condition within the Project
Area and Project Area of Influence.
103
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
1
https://www.worldwildlife.org/ecoregions/im0158 accessed March 29, 2018
104
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Occurrence (EOO) maps for many of the worlds threatened species. EOO is maps that show
the potential geographical distribution of a species. A species is considered threatened if the
conservation status is classed as vulnerable (VU), endangered (EN) or Critically Endangered
(CR). For the purposes of critical habitat mapping using IFC PS6 guidelines, only EN and CR
are considered in the analysis of critical habitat. IFC PS6 conservation status categories of
IUCN are presented in Figure 31 below.
There are six threatened species identified in the EOO analysis potentially inhabiting the
Project Area; five species of mammals (Hylobate agilis, Manis javanica, Presbytis melalophos,
Pteromyscus pulverulentus, Symphalangus syndactylus) and one species of bird (Asarcornis
scutulata). The EOO Maps of Aek Sibundong MHPP Project Area is presented in Figure 32
below.
105
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
106
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW in
Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Figure 33 Location of the Nearest Key Biodiversity Area from the Project Area
It is confirmed that the project is not located in Key Biodiversity Area/Important Bird Area or
other biodiversity hotspots according to Ministry of Environment and Forestry. There are no
protected areas in the vicinity of the project location as confirmed through desk based study.
107
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Project location is located in natural habitat. Several modified habitat was discovered in
project location landscape, they are plantation forest, dry-land agriculture, paddy field and
shrub. Natural habitat that found is riverine forest ecosystem. The forest has very steep
elevation buffered the river area. Figure 34 is habitat type on project footprint landscape and
Figure 33 is habitat map on study area and surroundings.
108
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Natural Habitat
Natural habitats are areas composed of viable assemblages of plant and/or animal species of
largely native origin, and/or where human activity has not essentially modified an area’s
primary ecological functions and species composition (IFC PS 6, 2012).
Of the Project area footprint and surrounding area, the land cover within project surrounding
was classified as natural habitat. It comprised the river and riparian area. The total natural
habitat impacted by the Project footprint is considered to be very small scale compared to the
Project Area footprint with 200m buffer which is deemed to be a minor scale direct impact on
habitat and ecosystems.
Modified Habitat
Modified habitats are areas that may contain a large proportion of plant and/or animal
species of non-native origin, and/or where human activity has substantially modified an
area’s primary ecological functions and species composition. Modified habitats may include
areas managed for agriculture, forest plantations, reclaimed coastal zones, and reclaimed
wetlands (IFC PS 6, 2012). Modified habitat comprising agricultural land (paddy, corn, oil
palm, etc.) and housing occupied not significantly in Project Area footprint within 200m
buffer.
109
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Terrestrial Flora
Terrestrial flora survey was conducted on project footprint area. Survey developed the six
plots that distributed along river area from power house up to weir location. There is 43
species of flora was recorded during the survey. Casuarina sumatrana (local: Anturmangan)
and Quercus javanensis are dominant species was recorded. This species was found very
abundant in surrounding river area. Other species that recorded are Exbucklandia populnea
(local: Hapas-hapas) and Quercus javanesis. E. populnea has wide spread in study area. Table
54 is top five dominant trees species in study area. Shannon-wiener diversity index and
Richness index value is show the study area has high diversity of vegetation.
The important value index of the vegetation is presented in the Table 55 below.
110
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
111
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Important
Number of Number Density Relative Relative Diversity
No Scientific Name Local Name Frequency Value
Individual of Plot (ind/ha) Density Frequency Index (H')
Index
24 Hoting porbue 1 1 25 0.70 0.17 1.43 2.13 0.03
25 Hoting sangkar 1 1 25 0.70 0.17 1.43 2.13 0.03
26 Houwandolok 2 1 50 1.40 0.17 1.43 2.83 0.06
27 Jomak jomak 1 1 25 0.70 0.17 1.43 2.13 0.03
28 Maudang 2 1 50 1.40 0.17 1.43 2.83 0.06
29 Mayang 1 1 25 0.70 0.17 1.43 2.13 0.03
30 Meyang 3 3 75 2.10 0.50 4.29 6.38 0.08
31 Modang 1 1 25 0.70 0.17 1.43 2.13 0.03
32 Modang loreng 1 1 25 0.70 0.17 1.43 2.13 0.03
33 Motung 1 1 25 0.70 0.17 1.43 2.13 0.03
34 Pinasa pinasa 1 1 25 0.70 0.17 1.43 2.13 0.03
35 Pinus 2 1 50 1.40 0.17 1.43 2.83 0.06
36 Sikam 1 1 25 0.70 0.17 1.43 2.13 0.03
37 Sikem 1 1 25 0.70 0.17 1.43 2.13 0.03
38 Simarsuhulsuhul 2 2 50 1.40 0.33 2.86 4.26 0.06
39 Situlan 1 1 25 0.70 0.17 1.43 2.13 0.03
40 Schima Wallichi Sumartolu 7 5 175 4.90 0.83 7.14 12.04 0.15
41 Tinggiran 4 1 100 2.80 0.17 1.43 4.23 0.10
42 Tuba 1 1 25 0.70 0.17 1.43 2.13 0.03
43 Tulason 2 1 50 1.40 0.17 1.43 2.83 0.06
Total 43 143 3,575 100.00 11.67 100.00 200.00 3.02
Richness Index 3.60
Similarity Index 3.76
112
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Terrestrial Fauna
For bird group, survey recorded 45 species of 22 families. Dominant families that found in
study area are Timaliidae and Sylviidae (each 6 species) followed Apodidae, Pycnonotidae, and
Nectariniidae (each 4 species). Figure 36 is graph of species number each family were recorded
on baseline study. Both Timaliidae and Sylviidae generally inhabit forest, shrubs and bushes.
Both are insectivore bird families, the main feed is caterpillars and other small insects.
Sampling location selection is representative of project location and habitat type; they are
paddy field and shrub, forest, dry land agriculture and forest plantation. Figure 37 is graph of
species number and abundant on sampling location. Forest habitat is the area with highest
species and individual abundance finding. The most abundant number of species found is in
natural forests (Weir), this is due to the good condition of riverine forest. The structure and
composition of the plant is also still complete, there are still many trees with large diameter.
30
19 21 19
18
20
10
10
0
Paddy Field and Bush Natural Forest (power Natural Forest (weir) Plantation forest and
(power house) house) garden (weir)
113
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Diversity Index is index that shows relationship between number of species and number of
individual each species on habitat type. Natural forest has most diverse of bird species,
followed by paddy field and shrub and forest plantation. Forests provide more diverse food
composition and shelter than other habitat types. Plantation forests have the lowest diversity
due to the low diversity of vegetation. Evenness Index is reflects the distribution of the
number of individuals in each species. The Evenness index can be categorized as good
condition if the value is close to 1 which means there is no dominant species in the location,
and it is uneven if the value is nearing 0 which means that there is a certain species that
dominates the most in that location.
1.5
0.86 0.91
1 0.77 0.81
0.5
0
Paddy Field and Bush Natural Forest (power Natural Forest (weir) Plantation forest and
(power house) house) garden (weir)
H' E
There are 6 bird species protected by the Indonesian government based on Law no. 5 of 1990
and Government Regulation no. 7 of 1999 concerning preservation of plant and animal
species (Table 56). Based on the IUCN Redlist, there are two species of birds that are
categorized as Near Threatened (NT), namely the Ixos virescens (Sunda Bulbul) and Stachyris
nigricollis (Temminck’s Sunbird).
114
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
PP No 7
No Indonesia Name Scientific Name English Name IUCN CITES
Year 1999
singalensis Sunbird
6 Burung madu ekor Aethopyga Temminck’s LC - Protected
merah temmincki Sunbird
7 Burung madu sriganti Cinnyris jugularis LC - Protected
Olive-backed
Sunbird
Below is the result of primary data collection of the bird species observed within the project
area and surrounding.
115
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Location
No Familia Local Name Scientific Name English Name
1 2 3 4
13 Campephagidae Sepah dagu kelabu Pericrocotus solaris Grey-chinned Minivet - 4 6 -
14 Pycnonotidae Brinji gunung Ixos virescens Sunda Bulbul - 2 5 -
15 Pycnonotidae Cucak kutilang Pycnonotus aurigaster Sooty-headed Bulbul 8 - - 2
16 Pycnonotidae Merbah cerukcuk Pycnonotus goiavier Yellow-vented Bulbul 6 2 - 2
17 Pycnonotidae Merbah corok-corok Pycnonotus simplex Cream-vented Bulbul - 4 - -
18 Laniidae Bentet kelabu Lanius schach Long-tailed Shrike 2 - - 1
19 Turdidae Cingcoang cokelat Brachypteryx leucophrys Lesser Shortwing 1 4 1 -
20 Timaliidae Berencet kerdil Pnoepyga pusilla Pygmy Wren-Babbler - 1 1 -
21 Timaliidae Ciu besar Pteruthius flaviscapis White-browed Shrike- - - 1 -
Babbler
22 Timaliidae Ciung air coreng Macronous gularis Striped Tit-Babbler - - 2 -
23 Timaliidae Tepus dahi merah Stachyris rufifrons Rufous-fronted Babbler - - 6 -
24 Timaliidae Tepus emas Stachyris chrysaea Golden Babbler - - 1 -
25 Timaliidae Tepus kaban Stachyris nigricollis Black-throated Babbler - - 3 -
26 Sylviidae Cici padi Cisticola juncidis Zitting Cisticola 2 - - -
27 Sylviidae Cikrak bambu Abroscopus superciliaris Yellow-bellied Warbler - - 2 -
28 Sylviidae Cikrak kutub Phylloscopus borealis Arctic Warbler - - 4 -
29 Sylviidae Cinenen gunung Orthotomus cuculatus Mountain Tailorbird 2 - 4 2
30 Sylviidae Cinenen belukar Orthotomus atrogularis Dark-necked Tailorbird - 2 - 1
31 Sylviidae Perenjak gunung Prinia atrogularis Hill Prinia 1 1 - 2
32 Muscicapidae Niltava kumbang- Niltava grandis Large Niltava 1 1 - -
padi
33 Acanthizidae Remetuk laut Gerygone sulphurea Golden-bellied 2 - - -
Geryone
34 Rhipiduridae Kipasan gunung Rhipidura albicollis White-throated Fantail 1 - 3 -
35 Paridae Gelatik batu kelabu Parus major Great Tit - 6 2 -
36 Dicaeidae Cabai gunung Dicaeum sanguinolentum Blood-breasted 2 4 5 -
Flowerpecker
37 Nectariniidae Burung madu Anthreptes singalensis Ruby-cheeked Sunbird - - 2 -
belukar
38 Nectariniidae Burung madu ekor Aethopyga temmincki Temminck’s Sunbird 2 - - -
merah
39 Nectariniidae Burung madu Cinnyris jugularis Olive-backed Sunbird 1 - - -
sriganti
40 Nectariniidae Pijantung kecil Arachnothera longirostra Little Spiderhunter - 2 1 -
41 Zosteropidae Kacamata gunung Zosterops montanus Mountain White-eye - 6 - -
42 Ploceidae Burung gereja erasia Passer montanus Eurasian Tree Sparrow - - - 4
43 Dicruridae Srigunting bukit Dicrurus remifer Lesser Racquet-tailed - - 1 -
Drongo
44 Dicruridae Srigunting kelabu Dicrurus leucophaeus Ashy Drongo - 3 1 -
45 Corvidae Tangkar uli sumatera Dendrocitta occipitalis Sumatran Treepie 2 - - -
116
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
For mammals group, there are no many findings during field survey. Wild boar (Sus scrofa) is
most common species that found in forest and agriculture area. The net method only record a
bat species namely Chironax melanocephalus.
Survey conducted during rainy season. The river has a large flow with fast currents. Average
of river width is around 5 to 10 meters with fast current conditions. Data collection method is
using net.
117
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Two species were recorded during the baseline survey, namely Semah (Tor soro), and Seluang
(Rasbora sp). Semah is dominant species on main river and Seluang only found on the creeks.
Total individual of Semah that captured in main river is around 14 individual. Habitat of
Semah is upstream river in forest area with rocky in river bottom with fast current. Seluang
(Rasbora bankanensis) also found abundant and dominant in the river creek. The habitat of this
species is river and swamp in forested area. They live in river with weak flow and calm
current. The distribution in Malaya, Borneo and Sumatra.
The Project Area footprint and the applied 200 m buffer area comprise of modified habitat
and natural habitat. The nearest key biodiversity areas are Danau Toba KBA and Batang Toru
KBA, which are located approximately 30 km from the Project Area. Due to the highly
fragmented landscape of the Project Area and surroundings, which comprise the mixing of
Natural Habitat and Modified Habitat such as the paddy field and agricultural land, it can be
confirmed that the Project Area footprint will not disturb any area of the Danau Toba KBA as
well as Batang Toru KBA. However, it is expected that some mobile species such as mammals
and birds may utilize the Project Area through the Natural Habitat corridor, even if it is
dominated by degraded habitats and subject to human disturbance. The characteristics of the
Project Area footprint and surrounding can be summarized as shown in Table 58.
118
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Land Use Status (Spatial Plan) Plantation forest, Paddy field, open field
Terrestrial Biodiversity
Species Protection
- CITES None
Migratory and/or
None
congregatory species
Aquatic Biodiversity
Species Protection
- CITES None
Migratory and/or
None
congregatory species
Ecosystem of Concern
Wetland None
Dryland Yes
Coastal None
Significant Landscape
119
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
It should be noted that impact on biodiversity is expected to be minor due to the small scale
area of the Project Area footprint which will be occupied of the total Project Area footprint
and 200 m buffer. Project Activities of construction and operation seem would not impede the
movement nor would have an effect on the behaviour, reproduction or abundance of the
several IUCN Endangered Species.
Based on the site observation, literature studies and the biodiversity surveys; it is considered
that the Aek Sibundong MHPP does not pose a significant threat to of endemic and/or
restricted range species, nor highly threatened and/or unique species or ecosystems, or to
evolutionary processes and ecosystems services identified within the Project Area footprint
and surrounding. Due to this consideration, it is confirmed that critical habitat was not
identified in the Project Area footprint.
120
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Social Baseline
A social study designed to fill the identified social data gaps using a combination of
quantitative and qualitative data collected through literature review, secondary data
collection, stakeholder mapping, household surveys, and key informant interview. A
comprehensive social baseline study for ESIA was conducted on March 2018 in Sigulok
Village, Sijamapolang Sub-district.
Humbang Hasundutan Regency is made of 10 sub-districts and 154 villages with total area of
2,517.66 km2. It was part of North Tapanuli Regency until 2003. The study area is located at
Sigulok Village in Sijamapolang Sub-district. The population within the study area in 2016 is
244 people.
Gender distribution within the study area shows that number of female is higher than
number of male, similar to sub-district and regency levels. Sigulok Village has a sex ratio of
89 males to 100 females, which equates to 115 males and 129 females. Sijamapolang Sub-
district and Humbang Hasundutan Regency has a sex ratio of 98 males to 100 females, which
equates to 2,673 males and 2,724 females in Sijamapolang Sub-district and 91,789 males and
93,126 females in Humbang Hasundutan Regency.
Population density in Sigulok Village is 10.17 people/km2 which is low compared to sub-
district level and regency level. The study is mostly agricultural area with limited number of
settlements. Further detail on population data is presented in Table 59.
121
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
70 - 74
60 - 64
50 - 54
40 - 44
30 - 34
20 - 24
10 - 14
0-4
500 400 300 200 100 0 100 200 300 400
Male Female
A total of 16 households were surveyed in Sigulok Village. Based on the age characteristics of
the participants, the survey generally represented all of the age groups capable of mature
responses and adequate experience and knowledge to provide valuable insights. Most
respondents were from the age group of 30 – 39 and 50 – 59, both at 31%, and then followed
by respondents from the age group of 40 – 49 at 25%. Age group older than 60 was also
covered in the social survey with the smaller portion of 6%. Detail of age group for household
survey respondents is presented in Figure 45 below.
6%
6%
31%
30 - 39
40 - 49
50 - 59
31%
60+
Unknown
25%
122
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The household survey covered 63% of female respondents and 38% of male respondents.
From the total respondents, 88% of respondents were married and a small portion of
respondents were widowed at 13%. Details of respondents’ marital status in the Study Area
are presented in Error! Reference source not found.. Detail of gender and marital status for
ousehold survey respondents is presented in Figure 46 and Error! Reference source not
found.7.
38%
Male
Female
63%
13%
Married
Widowed
88%
Household survey results show that the main livelihood in Sigulok Village is farming which
comprised 88% respondents respectively as shown in Figure 48. According to the Key
Informant Interview, men and women within the affected communities have equal access to
employment. The division of labour between men and women in domestic activities, public
economic activities and public social activities is not rigid as is practiced in other regions. In
domestic tasks, women have primary responsibility. Typically the following crops were
123
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
grown: paddy, corn, coffee, potato, etc. Several local people also tap kemenyan sap in the
forest area as side job. Some others hunt for wild boar, deer, etc. to be sold at Dolok Sanggul.
7%
Farmer
Civil Servant
93%
As presented in Table 60, according to the Humbang Hasundutan Regency in Figures 2017,
approximately 87.1% of the labour force in Humbang Hasundutan Regency is economically
active. The remaining 12.9% who were not economically active were attending school (4.86%),
housekeeping (3.98%) or undertaking other activities (3.17%). Of those economically active
individuals, 86.04% are working (employed) and 1.06% are seeking employment
(unemployed). Meanwhile, household survey results show that 93.75% of respondents were
in the labour force and 6.25% were not. The labour force participation rate in the project
impact areas is higher than both the district and national averages.
Source: 1Primary Data Collection, February 2018; 2Humbang Hasundutan Regency in Figures
2017; 3Indonesia Statistic 2017
124
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Statistics at the district level divide gender-disaggregated data of labour force based on sector
into several types including agriculture, manufacture, and services. As presented in Table 61,
the district labour force is dominated by the agriculture sector, which is also reflected by the
main livelihood data during household surveys.
Household survey results show that the educational attainment Sigulok Village varies from
not completing any formal schooling to completing a diploma/university degree. The
number of respondents who did not complete formal schooling is relatively high at 31.25%,
compared to the regency level at 7.24% and national level at 15.78%. The proportion of
respondents in Sigulok Village who had only received formal education up to the elementary
school level is at 6.25%. The data indicates that the educational attainment in Sigulok Village
is mostly middle school and high school at 25% and 25% respectively, similar to the national
level. Meanwhile the number of people who have received diploma/university is at 12.50%.
Statistic of educational attainment in the Study Area as well as regency and national level is
presented in Table 62.
The Impacted Communities generally have low education levels, in which about third of the
people did not complete formal schooling or only completed elementary school. The
education status of communities within the impacted area is generally in line with the
Indonesian national averages except for elementary school level and below.
Education affects an individual’s capacity to access potential employment opportunities and
pursue particular livelihood strategies. The project will likely generate both direct and
indirect employment opportunities at the local-level. While these opportunities will likely be
in the form of unskilled (rather than skilled) labour (e.g. construction, security, supporting
service roles), they will still have an impact on the local labour force and community.
Income of the Affected Community is most commonly derived from agriculture. According
125
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
to the household survey, the average income for households usually ranged between IDR
800,000 and IDR 1,500,000 per month. This household survey results reflect that the incomes
of most survey respondents are still below the minimum wage for North Sumatera in 2018
which is Rp 2,132,188. Food and education were the two main monthly household expenses
identified by respondents.
The quality and availability of housing and services are key determinants of poverty and can
influence the health status of a community. Within the impacted area, two types of housing
were identified, including:
Permanent houses – cement brick and wall, and usually separated from animal
rearing area; and
Semi-permanent houses – cement brick foundation and half of the wall building or
wood/bamboo foundation and wall.
The household survey showed that the majority of respondents in Sigulok Village live in
semi-permanent houses with a percentage of 93% (Figure 49). However the secondary data
from Sijamapolang Sub-district (Table 63) shows that the approximately half of housing type
in Sigulok Village is non-permanent house.
13%
Permanent
Semi Permanent
93%
According to the household survey data presented in Figure 50, the majority of participants
own their house (47%). The remaining respondents either inherited their home from family
(40%) or rent (13%).
126
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
40%
47%
Parents
Rent
Self Owned
13%
5.2.3.1 Religion
The majority of the community within the study area are Christian. This was confirmed by
the outcomes of household surveys and interviews, which indicated that 100% of
respondents are Christian. No statistical data was available regarding the religion of the
community. This number indicates the uniformity of community within the impacted area.
In Batak society, men are the leaders of family and acts as family representative during
traditional ceremony. However in Sigulok Village, women also actively take part in
community forums. Land and its resources belong to the family. Land can only be sold after
decision is made through family forum.
Stakeholders in the villahe include community leader, traditional leader, head of village,
youth group (Karang Taruna), family welfare development (Pembinaan Kesejahteraan
Keluarga or PKK), and farmer groups. Traditional leader also acts as religious leader as many
traditional ceremonies in Sigulok Village are part of religious ceremonies. During community
forums, the three components that must be present are head of villagem community leader,
and traditional leader. BPD (Badan Perwakilan Desa or Village Representative Council) is
also present as adviser.
Batak ethnic was the dominant ethnic group within Sigulok Village. 100% of household
survey respondents identified as Batak. During household survey, the field team also found
immigrants from other ethnic minority groups (Javanese) through marriage. The immigrants
follow their in-laws marga (last name). There are no ethnic minority in Sigulok Village.
The main language used for daily communication in Sigulok villages was Batak language,
but most respondents also understood Bahasa Indonesia.
127
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
IFC Performance Standards 7 recognises indigenous people as social groups with identities
(language, culture, etc.) that are distinct from the mainstream population. They are often
among the most marginalized and vulnerable segments of the population. Based on
household survey and Key Informant Interview results, no indigenous people were found in
the impacted area. From the economic, cultural, and social perspective, Batak ethnic is not
distinct from other ethnic groups. They are already a part of the broader society, and are not
isolated from other ethnic groups. Moreover, vulnerable groups are those who are more
likely to experience poverty and social exclusion than the general population. These groups
constitute ethnic minorities, migrants, disabled people, homeless, drug addicts, isolated
elderly people and children. They face higher risks of low education, unemployment and
underemployment. Thorugh this definition, Batak ethnic is not classified as vulnerable
groups.
IFC Performance Standard 8 defines that cultural heritage refers to: (i) tangible forms of
cultural heritage, such as tangible moveable or immovable objects, property, sites, structures,
or groups of structures, having archaeological (prehistoric), paleontological, historical,
cultural, artistic, and religious values; (ii) unique natural features or tangible objects that
embody cultural values, such as sacred groves, rocks, lakes, and waterfalls; and (iii) certain
instances of intangible forms of culture that are proposed to be used for commercial purposes,
such as cultural knowledge, innovations, and practices of communities embodying
traditional lifestyles. Based on household survey and Key Informant Interview results, no
cultural heritage were found in the impacted area.
The community has access to sanitation facilities as shown in the household survey and Key
Informant Interview results that the majority of residents utilised private toilet with septic
tanks. There were no municipal wastewater sewerage systems available in the impacted area.
As for solid waste management, all household survey respondents manage the waste by
burning. Through interview it is also found out that several household conduct composting.
6%
94%
128
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The household survey and Key Informant Interview results show that the community sources
clean water for daily use from mountain spring piped to houses. The quantity and quality of
clean water remains constant throughout the year. Water from Aek Hinalang (a small river
that flows near to the village) is utilised for animal husbandry and irrigation. Aek Sibundong
is not utilised for clean water source. Aek Sibundong is only utilised by few community
members for recreation (fishing).
Data from the household survey demonstrates that use of health facilities was relatively low
with all respondents rarely visit medical facility (Puskesmas). The main reasons community
members visit a medical facility is due to fever and cold. While fever was noted as the most
common reason for community to visit any medical facility, fevers are often an initial
symptom of another type of illness. No infectious disease and permanent disease has
occurred in Sigulok Village according to household survey and Key Informant Interviews.
As all population of Sigulok Village is Christian, the only available worship facilitiy is church.
There are two churches in the village, HKBP and GPDI. This is in line with the secondary
data from Sijamapolang Sub-district in Figures 2017.
Secondary data from the district level showed that there is only one medical facility in
Sigulok Village which is Puskesmas (community health center) with one midwife and no
doctor. If the community need further medical service, they will be referred to Puskesmas in
Sijamapolang Sub-district.
The educational facility available in Sigulok Village is one public elementary school (SD) and
one early childhood education program (PAUD). At sub-district level, educational facilities
available varied from kindergarten to high school as shown in Table 64.
It also demonstrated that the availability of university within the sub-district and district was
still low. Thus, residents who want to pursue a higher education level, such as university,
usually migrate to other cities. No secondary data was available regarding education facilities
in Sigulok Village
129
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
According to the household survey, Sigulok Village is covered by PLN for electricity survey.
Secondary data from Sijamapolang sub-district in Figures 2017 indicated that there are 47
customers for electricity from PLN. Types of electricity consumer in West Pasaman consist of
household and public facility.
The perception of impacted community on change in local economy is presented in Figure 52.
Approximately 33% of respondents within the impacted villages perceived that the Aek
Sibundong MHPP project will bring positive impacts on local economic development as this
project will create more business opportunities for the local community. Another 13%
expected live quality improvement from the project. Providing electrical power is expected
not just to increase the domestic or public electricity for lighting, but also potential for
widening the development in other sectors for better community welfare. Economic
development opportunities from the project construction are expected, with more job
opportunities being just one example.
33% of respondents assume that this project will not bring any significant change to the local
economy. Due to a lack of knowledge about the project, 20% of respondents don’t know
whether this project will bring positive or negative impact to the local economy. However,
there are no respondent assume that this project will bring negative impact to the local
economy from higher competition with outsiders (non-local) for work opportunities.
0% Local economy
development (+)
20%
33% Life quality improvement
(+)
No significant impact
33% (neutral)
13%
Do not know (neutral)
130
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The perception of impacted community on local work oppotunity is presented in Figure 53.
All respondents think that the project will create more job opportunities for locals, both in
direct and indirect forms. Direct employment will most likely be available during the
construction phase which will provide opportunities for unskilled labour. Moreover, the
project is also expected to create indirect employment within the villages from income
generating activities, such as food production, food stalls, and workshops.
Generally, the field study found that the project was positively perceived by the community
as they expect the project will prioritize local workforce. However the community leaders are
also aware that the work opportunity may only be available during construction phase as
they refer to similar MHPP nearby that does not need a lot of employees during operational
phase.
0%
0% 0%
More work opportunity
for local (+)
More work opportunity
for national scale (+)
Less work opportunity for
100% local (-)
Do not know (neutral)
131
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
0%
Environmental quality
7% 14%
degradation (-)
Local environmental
quality improvement (+)
No significant impact
79% (neutral)
Do not know (neutral)
132
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
0% 0%
Community health
27% degradation (-)
Community health
improvement (+)
73% No significant impact
(neutral)
Do not know (neutral)
0% 0%
Negative impact in
social sensitivity (-)
40%
Increase diversity (+)
60%
No significant impact
(neutral)
Do not know (neutral)
133
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
roads to the village will be improved and can be utilised even after the construction ends. No
respondents have negative perception on the project in regards to local infrastructure.
0% 0%
Increase in local
7% infrastructure load (-)
Local infrastructure
improvement (+)
No significant impact
93%
(neutral)
Do not know (neutral)
134
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Table 65 Summary of Environmental and Social Impacts for Aek Sibundong MHPP
Mitigation Significance
No Potential Impact Activity Phase
Before After
1 Air Quality
Air quality impact due to Construction Phase Moderate Minor
the vehicle and machinery
emission source
Air quality impact due to Construction Phase Moderate Minor
dust generation
2 Noise
Noise impact due to Construction Phase Moderate Minor
construction activities
Noise impact due to turbine Operation Phase Minor Negligible
operation
3 Water Quality
135
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Mitigation Significance
No Potential Impact Activity Phase
Before After
Water quality impact due Construction Phase Major Minor-
to land clearance activities Moderate
Water quality impact due Construction Phase Minor Negligible
to potential soil erosion
Water quality impact due Construction Phase Major Minor
to construction of weir
Water quality impact due Operation Phase Negligible Negligible
to sediment increase
Water quality impact due Construction and Minor Negligible
to domestic wastewater Operation Phase
discharge
4 Soil/Land Contamination
Land contamination due to Construction Phase Minor Negligible
chemical and petroleum Operation Phase
products
Land contamination due to Construction Phase Minor Negligible
leakage from machinery or
vehicle
Land contamination due to Construction Phase Minor Negligible
materials stored onsite and Operation Phase
solid waste generation
5 Hydrology
Water balance alteration Construction phase Minor Negligible
Potential flooding due to Construction Phase Minor- Negligible
land clearing and Moderate
construction activities
Water course impact due to Construction phase Minor Negligible
weir construction
Water flow impact Operation Phase Minor Negligible-
Minor
6 Biodiversity Resources
Impact on Habitat Construction Phase Moderate Minor
Impact on Fauna during Construction Phase Moderate Minor
Construction Phase
Impact on Fauna during Operation Phase Minor- Negligible-
Operation Phase Moderate Minor
Impact on Migratory Fish Operation Phase Addressed in Section 6.5.4
Impact on Aquatic Construction Phase Addressed in Section 6.3
Biodiversity
7 Socio Economic and Culture
Impact on Community Construction Phase Major Minor
Livelihoods
8 Community Health Safety and Security
Emission from vehicle and Construction Phase Moderate Minor
equipment
Dust generation Construction Phase Moderate Minor
Noise Construction and Addressed in Section 6.2
Operation Phase
Traffic and road safety Construction Phase Major Negligible-
Minor
Sediment flush Operation Phase Addressed in Section 6.5.4
Infrastructure safety Operation Phase Major Minor-
136
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Mitigation Significance
No Potential Impact Activity Phase
Before After
Moderate
9 Occupational Health Safety and Security
OHS Issues during Construction Phase Major Minor
construction
OHS issues during Operation Phase Minor- Negligible-
operation Moderate Minor
Air Quality
6.1.1 Air Quality Impact due to Vehicle and Machinery Emission Source
Operation of equipment and machinery vehicles will produce emissions, which could
impact on the ambient air quality.
The baseline ambient air quality presented on Section 5 shows in the larger part of
the proposed project area is that of a typical rural area with agricultural activities,
characterised by good air quality.
Construction Phase
The most significant sources of gaseous emissions are expected to be from operation of
vehicles and equipment. Powered equipment will be required during construction work,
causing fuel combustion emissions during Aek Sibundong MHPP and associated
facilities constructions activities. Powered equipment use will include:
Use of heavy equipment including generators and vehicles such as excavators,
bulldozer, vibro roller, dump truck, pick-up vehicle, concrete mixer, water tank
vehicle and crane; and
Up to 150 workers will commute by passenger vehicles to the site during peak
construction.
The gaseous emissions caused by the project based on the above listed equipment,
are expected to include CO2, NO2, SO2, and hydrocarbons including volatile organic
compounds since most of the construction equipment and machinery will be powered
by diesel engines.
Significant receptors in as far as any changes in ambient air quality are concerned will be
the construction worker, communities living nearby the construction area and access
road, and small number of the local farmers doing work in their agricultural land nearby.
It is also important to note that, gaseous emissions are not restricted to the emission
sources; they can spread to a wider area as determined by the direction of wind.
Emissions associated with Aek Sibundong MHPP are not expected to noticeably alter air
quality or cause concentrations that exceed the national environment air quality standard
and the lack of other significant cumulative impacts from vehicles.
Impact magnitude is considered to be MEDIUM as the impact will occur from the
vehicles and machinery that will be utilized during the construction work. Sensitivity of
ambient air quality as a receptor is considered to be LOW-MEDIUM given the baseline
air quality in the nearby Project Area were still considered to be in a good condition and
137
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
considering the impact will be temporary, localised and reversible meanwhile emission
will directly impacting the the 150 construction worker. Those gases emissions of CO,
NOx, SOx, hydrocarbons, lead and other related combustion pollutants have the
potential to harm human health. Therefore the severity of impact is considered to be
MEDIUM. The likelihood of emission from vehicle and machinery due to the
construction activities development is INEVITABLE. The potential significance of the
impact is MODERATE.
ESMP Issue: AQ1 – Emission from Vehicle and Machinery during Construction Phase
Potential Impact Significance: MODERATE
Mitigation:
Exhaust emissions from vehicles operating within the site, including trucks,
excavators, diesel generators or other equipment, will be controlled by the
contractor by ensuring that emissions are minimized through regular
servicing of machinery to meet the relevant emission standards;
Ensure that the engines of all vehicles and machinery on site are not left
running unnecessarily;
Equipment to be used in the project to comply with recognized performance
design standards;
All emission-producing equipment will be operated only when necessary and
unnecessary idling of equipment will be avoided; and
A grievance mechanism will be put in place to address air quality grievances
from local stakeholders.
Mitigated Significance: MINOR
Operation Phase
During the operations phase, emissions will be restricted to light vehicles transporting
operation and maintenance crew to and from site. These emissions are considered
insignificant and have therefore not been assessed further.
Dust will be generated during construction activities and it may have several negative
impacts as follows:
Affect respiratory health of workers and potentially local community members.
Temporarily hinder visibility for workers and local communities;
Cover vegetation surfaces including crops in the surroundings, in so doing
slowing down the rate of photosynthesis and affecting the quality of forage for
animals;
Relevant baseline information presented at Section 5 indicates that the proposed project
138
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
area can be described as generally rural with interfaces of natural vegetation, cultivated
lands and lands under fallow. The dust concentration in the ambient air shows the level
of total suspended particulates in the ambient air did not exceed the national threshold
standard of 230 µg/Nm3 according to the Government Regulation No. 41 Year 1999 and
were lower than the international threshold standard of 120 µg/Nm3 according to the
Guidelines for Air Quality, Global Update, WHO 2006.
Construction Phase
Construction activities will result in dust generation as a result of vegetation
clearance at the proposed project site for establishment of the different infrastructure
components. Dust will also be generated during the transportation of required
construction materials from the different source points to the construction sites. Due to
this condition, the impact magnitude of dust generation during the Construction
activities is considered to be MEDIUM given the activities of construction will occur
temporarily during the construction work so that the impact will be temporary, localised
and reversible.
Sensitivity of ambient air quality as a receptor is considered to be low given the baseline
air quality in the nearby Project Area were still considered to be in a good condition and
considering the impact will be temporary, localised and reversible. However, dust will
directly impact the the construction worker and small number of the local farmers doing
work in their agricultural land nearby. Dust generation may also impact the communities
along the roads that will be used to access to the proposed project site from Dolok
Sanggul to Sigulok Village. An issue also raised by the community was that due to the
construction activities dust contaminants in the air along the road particularly caused by
the transportation activities will be increased in the dry season. Due to this condition, the
sensitivity of ambient air quality as the receptor is considered to be LOW-MEDIUM.
Therefore the impact severity is considered to be MEDIUM. The likelihood of dust
generation during the construction activities is INEVITABLE. The potential significance
of the impact is MODERATE.
139
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
and monitored daily during the construction phase. In addition, they will be
located away from public and residential areas;
A speed limit of 40 km/h for light vehicles and 30 km/h for heavy vehicles
will be maintained on routes used to access the construction site especially
during the dry season and during windy conditions;
Minimize the amount of excavated material on site;
Vehicle washing facilities provided to minimise the quantity of material
deposited on public roads;
Restrict heights from which materials are dropped, as far as practicable, to
minimize the fugitive dust arising from unloading/loading;
Consideration of the location of stockpiles for temporary storage areas with
respect to the location of sensitive receptors and prevailing wind;
ASE environmental team to have responsibility to monitor conditions and
adjust the frequency of watering;
Sealing /re-vegetation of completed earthworks as soon as reasonably
practicable after completion; and
A grievance mechanism will be put in place to address grievances from local
communities.
Mitigated Significance: MINOR
Operation Phase
The likely dust generation during the operations phase will be insignificant since during
this phase, emissions will be restricted to light vehicles transporting the operation
and maintenance crew to and from site. This impact has therefore not been assessed
further.
Noise
Noise will be generated from project activities and could become a nuisance to the local
stakeholders within the vicinity of the project site.
Relevant baseline information is presented in Section 5. According to baseline
information, the average noise levels at the selected sensitive receptors were within noise
threshold standard of 55 dB for residential areas according to the national standard
Ministry of Environment Decree No. 48 Year 1996 and the international standard
Guidelines for Community Noise (WHO, 1999), except for one noise level recorded in the
community settlement at 15:00. The noise level at this time was recorded slightly above
the threshold limit value at 64.3 dB A. The primary sources of noise around the Project
Area and the Project Area of Influence are from motor vehicles and audible sounds of the
Aek Sibundong river stream.
The major sources of noise during the construction of the Aek Sibundong MHPP
will be mainly from vehicles, operation of construction equipment, and noise generated
by the construction workforce. According to baseline information, the average noise
140
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
levels at the proposed project area were below the noise threshold standard of 55 dB for
residential areas according to the national standard Ministry of Environment Decree No.
48 Year 1996 and the international standard Guidelines for Community Noise (WHO,
1999), except for one recorded time at 15:00 in the community settlement.
In the worst case condition of construction activities, assuming one excavator and one
generator operated in the same time during the day time (8 am to 5 pm) at the
construction period, then it can be estimated the noise generation at the Aek Sibundong
MHPP project area during construction phase will be approximately higher than the
National standard of the noise level in the industrial area in accordance to the both of
National and International Standard of 70 dBA. This noise level generation will directly
impacted about 150 construction workers and the local famers which conducted work in
their agricultural land area.
The impact magnitude of noise during the construction phase is considered to be
MEDIUM by considering the as the impact will occur during the construction work
which designates the impact as temporary, localised and reversible. Sensitive receptors
identified in the site vicinity include residents located at the Sigulok Village and farmers
working near construction site may consider the noise from construction as annoyance.
Given this condition, the sensitivity of receptor is considered to be LOW-MEDIUM as
these receptors would be exposed to intermittent noise during daylight hours. Therefore
the severity of impact is MEDIUM. The likelihood of noise level increase during the
construction work is INEVITABLE. The potential significance of the impact is
MODERATE.
141
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Noise emissions during the operations phase will be generated by the installed
machinery at the powerhouse particularly the turbine noise also operation and
maintenance of vehicles onsite. However, the power house will be insulated and access
to these structures will be restricted thus preventing exposure of the community
members to the noise emitted. In addition turbine noise may impact the 12 personnel of
operational workers.
Impact magnitude of noise increase during the operation phase is considered to be LOW
even the turbine noise will be continuously generated but the area of hydro-power
turbine will be isolated. The sensitivity of receptor is considered to be LOW-MEDIUM
by concerning the impact on the operation workers; while the impact on the other
sensitive receptors including settlement area and agricultural area were insignificant due
to the considerable distance. Therefore the impact severity is LOW. The likelihood of
noise level increase during the operation or turbine is INEVITABLE. The potential
significance of the impact is MINOR.
142
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Water Quality
The Aek Sibundong MHPP project will utilize Aek Sibundong River. Based on analysis of
hydrology, geology, and optimization studies of Aek Sibundong MHPP, data used as
design parameters, is summarised in Table 66.
The baseline information presented in the section 5 of this report shows that there were a
contamination of surface water at the Aek Sibundong River including the contamination
of physical elements (TSS concentration) and microbiological element (Total Coliform).
Table 67 below summarized the water quality parameters which exceed the National and
International Threshold Standard.
The Aek Sibundong River and its tributaries were not utilized by the communities for
potable purposes. Most of the communities were using spring water distributed to
143
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The topography of the project footprint is hilly area with steep slope incline. The project
footprint will traverse the plantation forest and Aek Sibundong River. Land preparation
for construction will involve removing trees, bushes, roots and stones which will result in
exposing soil which has the potential to erode during rain storms.
Surface runoff occurs when rainfall intensity exceeds the infiltration rate or when the soil
has been saturated. This condition will be common in the rainy season and frequent
during storm events in the dry season. Surface runoff can cause erosion of surface soils
and transport of vegetation debris into streams resulting in increased turbidity and the
build-up of gross pollutant materials.
Land preparation can have a significant impact on downstream water quality of the Aek
Sibundong River. High concentrations of sediment in the river can cause siltation,
reducing the storage capacity of rivers and streams and potentially even changing their
course.
The intensity of sediment influx to rivers depends on the intensity and duration of
surface runoff. The potential for sediment influx is expected to be higher during the
rainy season.
The two main indicators of declining water quality due to erosion are Total Dissolved
Solids (TDS); and Total Suspended Solids (TSS). Government Regulation No. 82 Year
2001 regarding water quality management and water pollution control for class II water
courses defines the TDS and TSS thresholds as 1000 mg/L and 50 mg/L, respectively. As
stated in the previous section, the TSS concentration in one of the surface water sample at
Aek Sibundong River was detected at 80 mg/L, higher than the national threshold
standard of 50 mg/L.
Land preparation works have the potential to increase turbidity in the Aek Sibundong
River due to the activities of land preparation of the new access road, Aek Sibundong
MHPP and associated facilities development. Several mitigation measures should be
applied by considering the condition of existing TSS at the Aek Sibundong River which
was observed has a concentration level higher than the threshold standard.
Mitigation measures that should be conducted not only to protect the water quality but
also to protect the aquatic life including microorganism such as plankton and benthos
also fish life. High turbidity can reduce light penetration which is required by
phytoplankton during photosynthesis which has the potential to impact the oxygen
balance in the impacted Aek Sibundong River.
The substantial impact for aquatic biota and fish life are anticipated to occur from the
upstream of Aek Sibundong River until the downstream within the Project Area of
Influence.
If the turbidity rate in the surface increases due to increased sediment flux from land
clearing activities, this contamination will be an impact of MEDIUM magnitude because
the river habitat will also be impacted; however, the condition is considered reversible as
it only occurs during construction phase. The receptor sensitivity is HIGH due to the
144
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
existing TSS contamination in the surface water, aquatic biota that will be impacted.
Therefore the severity of the potential impact is HIGH. The likelihood of increased
turbidity rate due to land clearing is MEDIUM. The potential raw significance of the
impact is MAJOR.
ESMP Issue: WQ1 – Water Quality Impact due to Land Clearance Activities –
Construction Phase
Potential Impact Significance: MAJOR
Mitigation:
Install soil erosion control structures at all construction sites;
Install and regularly empty, sediment traps in surface drains, along roads and
construction areas;
Proper design for storm water drainage facilities and maintenance during the
construction phase are critical so it can be implemented and useful for the
monitoring purposes;
Construction during heavy rains should be avoided as much as is possible as
water logged soils are easily eroded;
Disposal of cut top soil should be undertaken outside fragile ecosystems
(fragile ecosystems including the area nearby the Aek Sibundong River
riparian zone and nearby the paddy field area) and water sources
downstream; and
Following completion of construction works, top soil removed and stockpiled
should be used in restoration; vegetation native to the area will be re-
established to ensure stabilisation of project area and its surroundings.
Mitigated Significance: MINOR-MODERATE
Construction Phase
Cut and fill associated with construction of waterway, main Aek Sibundong MHPP foot
print area and the associated facilities have the potential to increase the probability of
landslides which can in turn lead to erosion impacts. The project area was located in
medium hazard zone in accordance to BNPB, and therefore has medium landslide
hazard.
The magnitude of this impact of degradation due to landslides and erosion is considered
to be LOW given the existing erosion condition and considering the area that will be
utilized for the project compared to the total catchment the project activities are relatively
small scale. The sensitivity of these receptors is MEDIUM given the condition on the
water quality contamination caused by soil erosion was not observed within the project
area of influence but the area has medium landslide hazard. Other consideration
comprise: receptors such as the communities primarily utilized the Aek Sibundong River
were not utilized for the potable purposes; the most sensitive receptor may comprise the
aquatic biota life such as micro-organism and the fish life at the Aek Sibundong River.
145
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: WQ2 – Water Quality Impact due to Soil Erosion – Construction Phase
Potential Impact Significance: MINOR
Mitigation:
Stabilization of project footprint by planting crops or masonry stabilization;
Consider a retaining systems;
Build terraces for steep slopes; and
Monitoring of potentially impacted river section area;
There will be controlled clearance of vegetation and this will be limited to
only sections that are required for the access and installation of the project
infrastructure;
An efficient drainage system will be incorporated in the project design
to ensure that storm water especially along the access roads to the
powerhouse and water way and along the headrace canal is efficiently and
effectively controlled; and
Where possible, construction activities will not take place during heavy rains.
Mitigated Significance: NEGLIGIBLE
Operation Phase
During the operation of Aek Sibundong MHPP, all the waste collected from the headrace
system at the time of cleaning will be disposed of appropriately at designated waste
disposal sites. In the other case, there will be accumulated sediment in the sedimentation
tank. This sediment naturally is a sediment load in the Aek Sibundong River which
trapped in the sediment tank during the operation of Aek Sibundong MHPP.
The magnitude of impact on water quality is considered to be NO CHANGE since this
sediment is natural sediment load which were exist in the Aek Sibundong River. The
sensitivity of water quality as the receptor is considered to be MEDIUM as the existing
water quality at Aek Sibundong River were already contaminated by TSS at the
downstream of Aek Sibundong River which has concentration exceedance than the
National Threshold Standard of 50 mg/L. This is also considered about the sensitivity of
aquatic biota as a secondary receptor which will have higher sediment load period
occasionally compares to the natural systems. Therefore the severity of the potential
impact is SLIGHT. The likelihood of increased potential sediment to surface water due
to the operation phase of Aek Sibundong MHPP is MEDIUM likelihood. The potential
significance of the impact is NEGLIGIBLE. However, there were several mitigations
measure that should be conducted to minimize the impact of the sediment load during
the operation phase of Aek Sibundong MHPP.
146
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
\
ESMP Issue: WQ6 – Surface water quality degradation due to Sediment Load of Aek
Sibundong MHPP – Operation Phase
Potential Impact Significance: NEGLIGIBLE
Mitigation:
It is recommended that during flushing of the sedimentation tank, sediments
will be flushed back into the river where they came from;
Monitor the condition in the downstream area during the flushing occurred to
prevent the impact on the local farmer and/or fisherman who unintentionally
visit the area where the sediment load discharged; and
Install the warning sign for not enter the discharging area.
Mitigated Significance: NEGLIGIBLE
During the construction of the weir, channel deepening and widening is likely to result
into increased turbidity and change the colour of the Aek Sibundong River. In addition,
the materials used in the establishment of the weir such as cement may result in
increased concentration of ions such as calcium, silicon, aluminium, iron and sulfates to
levels above the recommended national limits for (untreated) domestic water available
for water consumers.
Mitigation should be conducted not only to protect the water quality from high turbidity
and contamination but also protect the aquatic life including microorganism such as
plankton and benthos also fish life.
The magnitude of impact to water quality due to the weir construction is considered to
be MEDIUM considering the high turbidity due to channel deepening and the widening
also utilization of construction materials during the weir construction meanwhile the
impact will not be permanent and irreversible. The sensitivity of water quality as a
receptor of impact is considered to be HIGH by considering the existing condition of the
Aek Sibundong River which observed the contamination of TSS in the surface water. The
other sensitive receptors which will be impacted include the aquatic life in the Aek
Sibundong River including microorganism such as plankton and benthos also fish.
Therefore the severity of impact is considered to be HIGH. The likelihood of increased
turbidity rate and materials contaminations due to weir development is HIGH
LIKELIHOOD/INEVITABLE. The potential significance of the impact is MAJOR.
ESMP Issue: WQ3 – Water Quality Impact due to Weir Development – Construction
Phase
Potential Impact Significance: MAJOR
Mitigation:
Consider phasing plan to minimize the period of exposure for river cleared
areas;
Frequent monitoring of potentially impacted rivers and channels to include
147
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
6.3.4 Water Quality Impact due to Sediment Increase from Aek Sibundong MHPP
During the operation of Aek Sibundong MHPP, all the waste collected from the headrace
system at the time of cleaning will be disposed of appropriately at designated waste
disposal sites. In the other case, there will be accumulated sediment in the sedimentation
tank. This sediment naturally is a sediment load in the Aek Sibundong River which
trapped in the sediment tank during the operation of Aek Sibundong MHPP.
The magnitude of impact on water quality is considered to be NO CHANGE since this
sediment is natural sediment load which were exist in the Aek Sibundong River. The
sensitivity of water quality as the receptor is considered to be MEDIUM as the existing
water quality at Aek Sibundong River were already contaminated by TSS which has
concentration exceedance than the National Threshold Standard of 50 mg/L. This is also
considered about the sensitivity of aquatic biota as a secondary receptor which will have
higher sediment load period occasionally compares to the natural systems. Therefore the
severity of the potential impact is SLIGHT. The likelihood of increased potential
sediment to surface water due to the operation phase of Aek Sibundong MHPP is
MEDIUM LIKELIHOOD. The potential significance of the impact is NEGLIGIBLE.
However, there were several mitigation measures that should be conducted to minimize
the impact of the sediment load during the operation phase of Aek Sibundong MHPP.
ESMP Issue: WQ4 – Surface water quality degradation due to Sediment Load of Aek
Sibundong MHPP – Operation Phase
Potential Impact Significance: NEGLIGIBLE
Mitigation:
It is recommended that during flushing of the sedimentation tank, sediments
will be flushed back into the river where they came from;
Monitor the condition in the downstream area during the flushing occurred to
prevent the impact on the local farmer and/or fisherman who unintentionally
visit the area where the sediment load discharged; and
Install the warning sign for not enter the discharging area.
Mitigated Significance: NEGLIGIBLE
148
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The analysis of the potential project impacts discussed in this section is related to the
possibility that during the implementation of project activities, domestic wastewater
generated may be poorly handled and disposed of. The baseline information stated that
there were good sanitation facilities at the communities nearby the Project Area.
However, baseline water quality data in the Section 5 shows concentration of Total
Coliform at one sampling point is higher than the National Threshold Standard as Stated
in the Government Regulation No. 82 Year 2001 Appendix II which indicates a domestic
contamination in the surface water nearby the Project Area.
Domestic sewage is not characterized as hazardous and toxic (B3) liquid waste, it can
contain high nutrient (N & P), suspended solids and pathogen (e.g., faecal coliform)
concentrations, and other organic contents (such as oil and grease). These pollutants can
cause impacts to receiving water bodies, including depletion of dissolved oxygen;
eutrophication, aesthetic problems due to it unsightly appearance as well as odour;
turbidity as a result of presence of suspended solids, and public health (disease-
transmission due to the presence of pathogens).
During the construction phase, approximately 150 workers will be hired. While during
the operation phase there will be fewer workers for the operation works (approximately
12 operation workers). However, if not managed properly, the domestic wastewater may
become a significant issue.
The construction and operation areas will be served by toilets which will be equipped
with a portable septic tank. Portable toilets would be cleaned daily and discharge taken
to the portable septic tank. Sludge from septic tank would be removed as required and
transported to appropriate sewage treatment facilities for disposal. Meanwhile the grey
water from the activity of bathing and washing will directly discharging to the drainage
systems and flows to the Aek Sibundong River. Grey water may potentially have high
nutrient loading due to the utilization of detergents.
Under the scenario above, potential impact from the domestic wastewater would be
limited to the leakage of portable toilets/seepage from the septic tank and the potential
of nutrients contamination from grey water discharge, therefore the impact will be
localized and considered to be MEDIUM. Toilets and septic tanks would be sited away
from sensitive surface water resources as far as practicable, thus the sensitivity of water
quality as a receptor is considered to be LOW-MEDIUM. Then the impact severity is
MEDIUM. The likelihood of leakage/seepage is considered LOW. The overall impact
significance is considered as MINOR.
149
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Soil/Land Contamination
According to the IFC EHS Guidelines, land is considered to be contaminated when it
contains hazardous materials or oil concentrations above background or naturally
occurring levels. Contaminated lands may involve surficial soils or subsurface soils that,
through leaching and transport, may affect groundwater, surface water and adjacent site.
Contaminated land may contain pollutants that have an adverse effect on human health
and environment. It becomes a problem in an agricultural land, or when the
contaminated land is close to residential areas and water bodies. Contaminated land is
not necessarily site specific; when hazardous waste infiltrates into groundwater, it can be
transported offsite.
There is potential for land contamination by chemical and petroleum products from:
Equipment maintenance activities (spill of lubricant),
Fuel storage areas (spill of diesel oil and gasoline),
Refuelling stations (spill of diesel oil and gasoline); and
Vehicle/equipment wash down areas (spill of lubricant).
The impact magnitude is considered to be LOW although there would be significant
change in soil chemistry from any spillage, the scale of operations associated with the
project indicated that any potential incidents would be small in scale. Considering that
agriculture is the main activity in the Project Area, the sensitivity of receptor is MEDIUM,
thus the severity of impact is considered to be MEDIUM. The likelihood of chemical and
petroleum product spill is LOW LIKELIHOOD. Therefore, the significance of impact is
MINOR. However, there are several mitigation measures that should be conducted to
minimize the impact of the land contamination of chemical and petroleum products
during the construction phase of Aek Sibundong MHPP.
ESMP Issue: LC1 – Land Contamination due to Chemical and Petroleum Products
Potential Impact Significance: MINOR
Mitigation:
Any accidental spills will be managed in accordance with spill response
procedures;
Storage of petroleum and chemical products in a designated storage receptacle
150
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: LC2 – Land Contamination due to Leakage from machinery or Vehicle
Potential Impact Significance: MINOR
Mitigation:
Any accidental spills will be managed in accordance with spill response
procedures.
Mitigated Significance: NEGLIGIBLE
6.4.3 Soil/Land Contamination from Materials Stored Onsite and Solid Waste Generation
Waste generation during the construction phase that has the potential to cause land
contamination includes the use of solid or powdered chemical, metal scrap, plastic from
waste storage facilities also the domestic waste from food waste. The operational waste
may not have a significant impact on the solid waste generation due to the relatively
small number of workers during the operation activities also the typical activities during
the operation may have negligible waste generation. Storm-water run-off may be
contaminated by the solid waste and materials stored onsite without cover. Poor
handling and storage of waste can cause percolation of spills into soil. Chemical and
petroleum products can percolate into shallow groundwater, but it is expected that the
impact would be highly localized and the contamination would degrade and be diluted
over time.
The impact magnitude is considered to be LOW as any incident is likely to be small scale
and localized. Considering that agriculture is the main activity in the project area, the
sensitivity of receptor is MEDIUM. Therefore the severity of impact is considered to be
151
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
MEDIUM. The likelihood of an event in the Mini-hydro Power Plant Project is LOW
LIKELIHOOD. Therefore the significance of impact is MINOR.
ESMP Issue: LC3 – Land Contamination due to the Materials Stored Onsite and Solid
Waste Generation
Potential Impact Significance: MINOR
Mitigation:
All waste materials shall be segregated into hazardous and non-hazardous and
stored in adequate containers on impermeable bases or within engineered
containment areas prior to removal from site for proper disposal at established
waste management facilities; and
ASE shall propose an allocation area for waste segregation and storage,
opportunities for reuse of inert waste, and schedules for removing waste from
the site for proper disposal at established waste management facilities.
Mitigated Significance: NEGLIGIBLE
Hydrology
The project area of Aek Sibundong MHPP is located at Aek Sibundong Watershed with
total catchment area is 71,735.004 km2. The land cover of the proposed project footprint
was mostly comprised of vegetation cover such as bush/shrub areas and agricultural
crops. In the terms of the surface water utilization; the Aek Sibundong River is not used
by the local community.
Civil structures such as weirs and drains should include measures in the design to
conserve water flow from upstream to downstream. The objective of this section is to
assess the potential impact of the project on water conservation and propose design and
engineering solutions as mitigation.
Construction of the Aek Sibundong MHPP, including the main facilities and the
associated facilities, has the potential to alter the natural flow of water resources. The
majority of land uses affected by the construction activities were mostly the plantation
forest and agriculture.
The main buildings of Aek Sibundong MHPP such as the settling basin, waterway and
power house will be built on a foundation of concrete. Water demand for these
construction activities will be obtained from the groundwater. This is not expected to
have an impact on the river water volume. The construction of the main facilities and
associated facilities of the Aek Sibundong MHPP development areas will involve
significant amounts of cut and fill.
The impact magnitude of water balance alteration is considered to be LOW as the
impacted forest field areas were relatively small scale and considering the impact will
only be temporary, reversible and localised during the first sequence of the construction
phase. There are paddy fields in the project area. However, the irrigation water is
sourced from another river. As such, there will be no water shortage for irrigation, which
gives LOW sensitivity. The severity of the impact is LOW. If not properly designed, the
likelihood of Aek Sibundong MHPP Project to obstruct water flow is considered as LOW
152
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: H1 – Water Balance Alteration due to the Cut and Fill Activity of the
development of Aek Sibundong MHPP and Associated Facilities
Potential Impact Significance: MINOR
Mitigation:
Cut and fill should not impact paddy fields or other agricultural land outside
the project footprint;
Storage area of the cutting materials should consider surface hydrology;
Frequent monitoring and review of surface hydraulics;
Civil design will necessarily include a number of hydraulic designs, in
particular drains and culverts to ensure continuous hydraulic flows. Where the
project footprint intersects a paddy field, culverts should be included in the
design to maintain adequate flows; and
Grievance mechanism to ensure that affected parties can report abnormalities
in stream water.
Mitigated Significance: NEGLIGIBLE
6.5.2 Potential Flooding due to the Land Clearing and Construction Activities
There will be low potential of flooding in the Aek Sibundong MHPP project area. Based
on Badan Nasional Penanggulangan Bencana, it is indicated that Aek Sibundong MHPP
area is located in non flood hazard area. Based on this assessment the project area and
surrounding are not located in flood prone areas.
Soil infiltration capacity is determined by soil type, initial soil moisture content and
vegetation/ground cover. During a rain event, infiltration continues until soil reaches its
saturation point. Then, the excess water will flow into the river as surface runoff. Land
preparation activities including soil compaction and utilization of bitumen structure for
road construction, concrete pavement at the Aek Sibundong MHPP (mainly at the
settling basin, power house, water way and MHPP facilities and disposal area) and the
compaction and clearance at the transmission line area will increase surface runoff to
adjacent areas.
The Aek Sibundong MHPP main facilities and associated facilities area development will
have the greatest impacted area during land clearing. However, the total impacted area
will not be significant as such it can be stated that it is a very small scale and considering
the characteristic of impact which is reversible and localized, thus the overall magnitude
of the potential impact is LOW. An increase in surface runoff has many indirect impacts
such as erosion, increased turbidity, downstream aquatic ecology deterioration (loss of
biota and less of biota production) and flooding. But, considering that the project area
footprint and surrounding were not considered to be flood prone areas then the
sensitivity of receptor is LOW. Therefore, the severity of the impact is LOW. It is very
likely (MEDIUM) that surface runoff will increase because of land clearing; therefore the
unmitigated significance of the impact is MINOR-MODERATE.
153
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: H2 – Potential Flooding due to the Land Clearing and Construction
Activities
Potential Impact Significance: MINOR-MODERATE
Mitigation:
Design drainage systems particularly to serve road corridors and the main Aek
Sibundong MHPP facilities;
Avoid vegetation clearance outside of the project footprint; and
Re-vegetate after construction work is completed.
Mitigated Significance: NEGLIGIBLE
Existing flows are likely to require diversion around the civil works. In particular,
construction of weir may require the Aek Sibundong River to be temporarily diverted.
The impact magnitude is considered to be LOW by assuming that the river will be
diverted prior the weir construction starting and the impact is considered as temporary
and reversible. The downstream aquatic biota that live in the river are assessed to have
LOW-MEDIUM sensitivity. Therefore, the severity of impact is considered to be LOW.
The likelihood of this impact is considered to be INEVITABLE. The unmitigated
significance of the impact is MINOR.
During the operations phase, river water will be diverted by a weir through an opening
in the river side (the ‘intake’) into a channel to the headrace for use in the generation of
power. This will result in a fluctuation in the volume of water left to continue flowing
normally through the existing watercourse particularly for the section between the intake
weir and powerhouse.
Abstraction of water from the Aek Sibundong River for power generation will therefore
reduce the amount of water available especially during the minimum river flows in the
dry season. This has the potential to impact on the aquatic biodiversity although Aek
Sibundong River does not have rich aquatic biodiversity condition.
154
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Impact magnitude of water flow during the operation of Aek Sibundong MHPP
operation is considered to be MEDIUM if not well mitigated by implementing the
ecological flow. Due to the lo impact to the Aek Sibundong River thus the receptor
sensitivity is considered to be LOW. Therefore, the severity of the potential impact is
LOW. Therefore, the potential significance of the impact is MINOR.
ESMP Issue: H4 – Water Flow Changes due to Operation of Aek Sibundong MHPP
Potential Impact Significance: MINOR
Mitigation:
Maintain at all times, especially during critical low flow periods, ecological
flow in the river section between the intake works and point of return of flow
to the main Aek Sibundong River for purposes of aquatic biodiversity
sustainability;
Manage operations to avoid rapid fluctuations in downstream flow by
conducting periodic monitoring of water flow between the weir and
powerhouse and downstream of the powerhouse.
Mitigated Significance: NEGLIGIBLE-MINOR
Biodiversity Resources
The Project Area is considered as a mixing of natural (river, riparian and forest/bush)
and modified habitat (agricultural land, paddy field, housing). This project has the
potential to impact habitats and vegetation within the project area footprint in several
ways:
Vegetation communities will be directly impacted by the land preparation for
access road, main Aek Sibundong MHPP development area and associated
facilities.
Indirect impacts to habitats and vegetation adjacent to works areas can include
deposition of dust generated by increased traffic/construction activities, spillage
of chemicals, improper wastewater discharge and dumping of solid waste.
During the ESIA biodiversity survey; any IUCN endangered and critically
endangered flora species were not found within the Project Area footprint and
surrounding.
The impact magnitude is considered LOW given the total area that will be cleared within
the project area footprint is considered as a small scale area. Potential receptors of these
impacts are considered of MEDIUM sensitivity. Therefore the severity of impact is
considered to be MEDIUM. Impact likelihood is inevitable, so the overall impact
significance is considered MODERATE.
ESMP Issue: BR1 – Loss of Habitat and Vegetation during the Construction Activities
155
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Implement the Flora Removal and Clearance Plan during the civil works at the
construction phase; and
Following the construction phase, the affected areas will be restored and only
indigenous vegetation replanted. Intentional restoration using exotic plant
species will be avoided.
Mitigated Significance: MINOR
As stated in the above section, the Project Area mostly comprise of plantation area. These
land uses indicate that the majority of the land area is disturbed and much of the natural
vegetation is displaced.
The Government Regulation No. 7 Year 1999 stated that any flora and fauna shall become
protected under several criteria as follows:
Has a small population
Has high decrease of individual in nature
Considered to have an endemic distribution
For those species which are stated as protected, conservation should be applied. The
conservation of flora and fauna could be conducted in situ and ex situ. The in situ
conservation were include the identification of species, inventorization, monitoring,
habitat and population development, species rescue, also the analysis, research and
development of species. While the ex situ conservation measures could include
preservation, breeding, analysis, research and development of species, fauna
rehabilitation and species rescue.
Construction phase activities have the potential to impact wildlife within the project area
in several ways:
Construction of new access roads, Aek Sibundong MHPP and associated
156
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
facilities will inhibit movement of wildlife and fragment habitats in the Project
Area.
Direct impacts to wildlife may also occur inside the construction boundaries if
wildlife enter into the construction site and pose risks to individuals within and
across the site boundary. Mitigation to appropriately handle wildlife entry into
construction sites will reduce risks to both animals and the construction crews.
Sources of indirect impacts on fauna also include noise from the construction
activities, general increased in human activity, evening light pollution, which
have the potential to stress or disorientate wildlife in the project area. Mitigation
activities that reduce noise and evening pollution will minimize these impacts.
However, it should be noted that impact on the biodiversity might in a minor
scale due to the small scale area of the Project Area footprint. Project Activities of
construction and operation seem would not impede the movement nor would
have an effect on the behaviour, reproduction or abundance of the several IUCN
Endangered Species.
Overall, the sensitivity of receptors is MEDIUM, given some species of conservation
interest are known/possibly to occur within/close to proposed works areas. The
magnitude of the impact is considered LOW, therefore the severity of impact is
considered to be MEDIUM. The likelihood of habitat loss is HIGH
LIKELIHOOD/INEVITABLE, and overall impact significance is considered
MODERATE.
157
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
clearing;
To minimise death of fauna, vegetation clearance should always be
undertaken first, as this scares away most of the fauna, as opposed to direct
use of graders to clear routes for access road construction, or direct dumping
of construction materials and excavated soils;
Training of construction crews on the appropriate response to wildlife
encounters that may occur in the project area;
Instruction to construction crews to refrain from harassing wildlife; and
Proper disposal of construction and worker waste.
Mitigated Significance: MINOR
Compared to the construction phase above, activities during the operations phase will be
of a low magnitude i.e. the operations phase essentially will involve running and
maintenance of the hydropower project. Several consideration of impacts on fauna were
as follows:
Consideration of terrestrial fauna within the project footprint may be killed as a
result of drowning in the open headrace channel.
The continuous turbine noise may affect the animal’s psychology and behaviour
particularly if they are moving nearby the powerhouse area.
The height of the electricity transmission pole and the electricity carried by the
transmission line can pose potentially fatal risk to birds through collisions and
electrocutions. Avian collisions with power lines can occur in large numbers if
located within daily flyways or migration corridors, or if groups are traveling at
night or during low light conditions (e.g. dense fog). In addition, bird collisions
with power lines may result in power outages and fires.
Overall, the sensitivity of receptors is HIGH, given some species of conservation interest
are known to occur within/close to proposed works areas. The magnitude of the impact
is considered LOW, therefore the severity of impact is considered to be MEDIUM. The
likelihood of habitat loss during operation is MEDIUM, and overall impact significance
is considered MINOR-MODERATE.
158
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
safety;
Fencing/hoarding around works areas to prevent animal entry and minimize
light/disturbance impacts;
Training for crews, during operation of the turbine, on the appropriate
response to wildlife encounters that may occur on the Aek Sibundong MHPP
site;
Training for power house occupants on the appropriate response to wildlife
encounters that may occur and instruction to occupants to refrain from
harassing wildlife; and
Installing visibility enhancement objects such as marker balls, bird deterrents,
or diverters to minimize avian collisions and electrocutions in the transmission
line.
Mitigated Significance: NEGLIGIBLE-MINOR
The analysis of the impact discussed in this section is based on the fact that during
the implementation of the proposed Aek Sibundong MHPP activities, an intake weir will
be constructed across the river. Construction of the weir across the river will create a
barrier effect of the river. It will not only impact the river water flow, but also will
impede fish migration upstream of the weir. The implementation of mitigation measures
to address potential water flow impacts would also serve to protect the migratory fish
communities. These measures are fully described in Sections 6.5.4 (Water Flow Impact
due to Operation of Aek Sibundong MHPP), and therefore no specific additional
measures are required for the migratory fish communities.
As described in Section 6.3 (Water Quality), numerous activities associated with the
project have the potential to impact surface water resources. These impacts would also
affect aquatic communities. The implementation of mitigation measures to address
potential water impacts would also serve to protect aquatic communities. These
measures are fully described in Sections 6.3, and therefore no specific additional
measures are required for aquatic communities.
Ecosystem services that are considered to be affected by the project are provision of
fisheries, water resources, wildlife habitat, and disaster mitigation. Table 68 below
presents a summary of the predicted impacts to ecosystem services due to the Aek
Sibundong MHPP project which consideres project components which affect these
ecosystem services as well as the magnitude of these impacts.
159
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Affected
Project Impact Evaluation of Ecosystem
Project Activity Project Impacts Existing Conditions Ecosystem
Component Services
Services
Land Land clearing and Soil erosion The habitat in the Water Tree logging impacts may
preparation alteration project area is already resource significantly cause increased TSS
Increased TSS and
degraded due to its replenishment and turbidity. TSS content can
turbidity in water
status as a Production as a cause eutrophication and
bodies
Forest as well as intense watershed. potential fish mortality due to
Noise disturbance land clearing for lack of nutrients in the ecosystem.
Wildlife
Terrestrial habitat agriculture, etc. This may significantly lower
Disaster fisheries’ yield during
degradation from tree TSS content in water in
mitigation construction period.
logging the downstream is
from landslide
above the threshold Tree logging may cause
limit value. insignificant impact to water
resource replenishment, wildlife
disturbance, and disaster
mitigation due to the already
degraded state of the area.
Construction MHPP and Potential oil leakage TSS content in water in Water Impact on fisheries degradation
facilities from mobilization the downstream is resource may be significant if pollution
construction above the threshold replenishment from construction equipment and
Potential DO
limit value. as a materials as well as domestic
Equipment and depletion and
watershed. wastewater is not handled
materials eutrophication of
carefully.
mobilization aquatic ecosystem Wildlife
from domestic Noise disturbance may cause
wastewater discharge insignificant impact to wildlife
disturbance as wildlife may
Noise disturbance
migrate to the proximate
160
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Affected
Project Impact Evaluation of Ecosystem
Project Activity Project Impacts Existing Conditions Ecosystem
Component Services
Services
from construction Protected Area to avoid
disturbance.
MHPP MHPP operation River water flow TSS content in water in Water Impact on fisheries degradation
operation decrease from MHPP the downstream is resource may be significant if pollution
operation above the threshold replenishment from mobilization and domestic
limit value. as a wastewater is not handled
Potential TSS increase
watershed. carefully.
in the river bodies
from trapped Wildlife Impact on fisheries degradation
sedimentation before from decreased river flow may
water enters the also be significant as it can cause
MHPP. supersaturation of the water. One
of the components that can be
Noise disturbance
supersaturated is TSS due to its
from MHPP
potential to become trapped
operation.
behind the dam before water
Potential DO enters the MHPP. This will cause
depletion and changes to physical and chemical
eutrophication of components of the aquatic
aquatic ecosystem ecosystem, thus subsequently
from domestic affecting the aquatic biota as well.
wastewater discharge
Noise disturbance may cause
Potential oil leakage insignificant impact to wildlife
from vehicle disturbance as wildlife may
mobilization migrate to the proximate
Protected Area to avoid
disturbance.
161
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Social Economics
162
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
The gaseous emissions are expected to be emitted from operation of vehicles and
equipment include CO2, NO2, SO2, and hydrocarbons including volatile organic
compounds since most of the construction equipment and machinery will be powered
by diesel engines.
Significant receptors in as far as any changes in ambient air quality are concerned will be
the local farmers doing work in their agricultural land nearby the proposed project area.
It is also important to note that, gaseous emissions are not restricted to the emission
sources; they can spread to a wider area as determined by the direction of wind.
The impact magnitude of exposure to dust is MEDIUM as the operations are relatively
small in scale and not immediately adjacent to local communities; and the sensitivity of
the receptors is HIGH. However, the likelihood that vehicle and equipment emission will
significantly impact local communities is considered to be LOW. The impact significance
is considered to be MODERATE. Several mitigation measures, presented in Section 6.1.1,
can minimize vehicle and equipment emission. In addition, mitigation measures that
reduce impacts to the local community can especially help to minimize overall impacts.
ESMP Issue: PHS1 – Vehicle and Equipment Emission and Impact to the Local
Community
Potential Impact Significance: MODERATE
Mitigation:
Involve the community in emergency planning, to lead to more effective
responses to monitoring system warnings.
Mitigated Significance: MINOR
Mobilization of materials and equipment during the construction phase may potentially
emit dust, also known as TSP (Total Suspended Particulate). Dust can arise from vehicle
movement on unpaved roads, which will be the state of the majority of the project’s new
roadways. Several new roadway segments are adjacent to residential and agricultural
areas, where the local community typically conducts daily activities. These people may
potentially be exposed to TSP. All of the equipment mobilization activities will comply
with a Standard Operating Procedure (SOP) developed by the project, and will involve
arrangements with local authorities along the route as required.
The impact magnitude of exposure to dust is MEDIUM as the operations are relatively
small in scale and not immediately adjacent to local communities; and the sensitivity of
the receptors is HIGH. However, the likelihood that dust exposure will significantly
impact local communities is considered to be LOW. The impact significance is considered
to be MODERATE. Several mitigation measures, presented in Section 6.1.2, can
minimize dust generation. In addition, mitigation measures that reduce impacts to the
163
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: PHS2 – Dust generation and Impact to the Local Community
Potential Impact Significance: MODERATE
Mitigation:
Minimize dust generation by managing haulage vehicles through a Traffic
Management Plan;
Monitor dust generation in the impact area and have response plans in place
to address exceedance; and
Pay attention to community feedback via the grievance mechanism.
Mitigated Significance: MINOR
Temporary noise disturbance may affect local communities throughout the construction
phase. The project area is rural, where noise levels are, on average, below 60 dBA.
Settlements located on major transport routes, will face increased noise levels, and noise
from construction and increased transport may exceed acceptable standards. The
construction noise may also impact small number farmers working at their
agricultural/plantation land.
Meanwhile, the operation noise may come from the continuous turbine noise. However,
the impact may be minimized for who are in close proximity to the power house area
such as communities who work at their plantation land.
Noise mitigation has already been addressed in Section 6.2. Noise mitigation measures
include installing acoustic barriers, minimizing loud project components during the day,
and creating a grievance mechanism for the community to report excessive noise.
One of the key public safety issues for local communities is the increased traffic
associated with the project. Many of the project components are in close proximity to
villages and agricultural land that are utilized by the local community.
Although the current traffic level on the road network within the project area is low with
the value of traffic volume to capacity of class A LoS (V/C < 0.60) considered as a free
flow traffic, the additional traffic will be noticeable to the local community members
and is likely to interfere with their regular movements as the utilization of the village
road for the mobilization of materials and equipment during the construction phase.
Furthermore, increased traffic and transportation of heavy loads may damage the
existing roads leaving them in a worse state.
The impact magnitude of construction activities to traffic increase is considered to be
MEDIUM. It also has MEDIUM sensitivity of receptor as it the volume to capacity of the
existing road was not an issue. Therefore the severity of the potential impact is HIGH.
The likelihood of traffic increase due to the construction phase on Aek Sibundong MHPP
164
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
During the operation of Aek Sibundong MHPP, all the waste collected from the headrace
system at the time of cleaning will be disposed of appropriately at designated waste
disposal sites. In the other case, there will be accumulated sediment in the sedimentation
tank. There are physical hazards associated with the activities of routine sediment
flushing. A significant amount of water and sediment will be discharging back to the Aek
Sibundong River. Impacts on community safety may become a concern particularly for
the communities in the downstream area of the Aek Sibundong MHPP during the
sediment flush activities. Several mitigation measures to minimize impact on
communities due to sediment flush activities were already addressed in the section 6.5.4
of this report it include:
Monitor the condition in the downstream area during the flushing occurred to
prevent the impact on the local farmer and/or fisherman who unintentionally
visit the area where the sediment load discharged; and
Install the signage advising of no entrance to the discharging area.
165
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
There are physical hazards associated with the Aek Sibundong MHPP infrastructure and
associated facilities that communities may be exposed to. Aek Sibundong MHPP
infrastructure can pose a risk to those who trespass, since trespassers will not be aware of
the site activities and not be wearing protective gear.
The impact magnitude of infrastructure risks on public safety is HIGH as the project
components pose a new and unknown risk to the community. The sensitivity of the
receptors is also HIGH. Therefore the severity of impact is CRITICAL. The likelihood
these issues may significantly impact local communities is considered to be MEDIUM.
Before mitigation, the impact significance is considered MAJOR.
During the construction phase, issues related to the occupational health and safety may
include the exposure to dust generation, vehicle gas emission, noise level and physical
hazards from vehicle movements. Issues can also come from the use of heavy equipment
and other construction-related areas. In addition, consideration should be given to
potential fires caused by equipment sparks, welding, or cigarettes.
Further health and safety issues may arise from temporary noise disturbances during the
construction activities particularly from the vehicle movements and construction noise.
The impact magnitude due to occupational health and safety is MEDIUM as the
construction of the Aek Sibundong MHPP and the associated facilities are relatively
small in scale; however, the sensitivity of receptors is HIGH because the workers are in
the immediate vicinity of the project activities. Therefore the impact severity is
considered to be HIGH. The likelihood that construction activities significantly impact
166
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: OHS1 – Occupational health and safety issues due to the construction
activities of Aek Sibundong MHPP– Construction Phase
Potential Impact Significance: MAJOR
Mitigation:
Prepare an Occupational Health & Safety Plan (OHS) in accordance to the
Government Regulation No. 50 Year 2012 regarding the Occupational health
and Safety. Measures included in the OHS Plan should include, but not be
limited to the following:
Provide occupational health and safety orientation training to all employees
for awareness of basic hazards, site-specific hazards, safe working practices,
and emergency procedures;
Ensure access for workers to drinking water;
Conduct daily safety assessment meetings to identify potential safety issues
(e.g., site access, construction, work practices, security, transportation of heavy
equipment, traffic management, emergency procedures, evacuation, wildlife
encounters, and fire control and management) and the measures to mitigate
them;
Provide fire suppression equipment in all vehicles and heavy equipment; and
Require use of Personal Protective Equipment (PPE), including shoes, self-
contained breathing apparatuses such as masks and earplugs.
Mitigated Significance: MINOR
During the operation phase, issues related to the occupational health and safety may be
reduced compared to the construction activities. It may include noise level exposure from
the turbine and physical hazards from vehicle movements also the operation and
maintenance of turbines. In addition, consideration should be given to potential fires
caused by equipment sparks, welding, or cigarettes.
The impact magnitude due to occupational health and safety is LOW as the operation
activities of the Aek Sibundong MHPP are relatively small compares to the construction
phase; however, the sensitivity of receptors is HIGH because the workers are in the
immediate vicinity of the project activities. Therefore the impact severity is considered to
be MEDIUM. The likelihood that operation activities significantly impact occupational
health and safety is considered to be MEDIUM LIKELIHOOD. The impact significance
before mitigation is therefore MINOR-MODERATE. Any mitigations which already put
in the previous section 6.1 until 6.9 will not be presented in this mitigation measures.
167
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
ESMP Issue: OHS2 – Occupational health and safety issues due to the operation
activities of Aek Sibundong MHPP– Operation Phase
Potential Impact Significance: MINOR-MODERATE
Mitigation:
Prepare an Occupational Health & Safety Plan (OHS) in accordance to the
Government Regulation No. 50 Year 2012 regarding the Occupational health
and Safety. Measures included in the OHS Plan should include, but not be
limited to the following:
Provide occupational health and safety orientation training to all employees
for awareness of basic hazards, site-specific hazards, safe working practices,
and emergency procedures;
Ensure access for workers to drinking water;
Conduct daily safety assessment meetings to identify potential safety issues
(e.g. work practices, security, emergency procedures, evacuation, wildlife
encounters, and fire control and management) and the measures to mitigate
them;
Provide fire suppression equipment; and
Require use of Personal Protective Equipment (PPE), including shoes, self-
contained breathing apparatuses such as masks and earplugs.
Mitigated Significance: NEGLIGIBLE-MINOR
168
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Table 69 Summary of Cumulative Impacts within the Project Area of Influence of Aek
Sibundong MHPP
Water Quality
Based on baseline survey, it was identified that the concentration of TSS in the
downstream of Aek Sibundong River is recorded above the threshold limit value. The
TSS concentration at the downstream in the SW3 was recorded above the threshold limit
value with concentration of 80 mg/L. The TSS concentrations measured at other two
sampling locations ranged from below the limit of detection of 49.5 mg/L at SW1 to 49
mg/L at SW2. The measurement results show that the TSS concentrations at two of the
sampling locations were well below the threshold limit stated in GR No. 82 Year 2001 for
Surface Water Class of II which is 50 mg/L.
The cumulative impact to the Aek Sibundong River will be from operation activity of
169
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Aek Sibundong MHPP specifically from flushing activities of sediment. The flushing of
sediment will cause increasing TSS concentration in the downstream of Aek Sibundong
River. High concentration of TSS will give impact to TSS refers to sediment, silt, sand,
plankton, algae or other organic materials found drifting or floating in the water column.
Excessive suspended solids in water can have negative impacts for human health and
aquatic ecosystems. High concentrations of suspended solids can block sunlight and
reduce photosynthesis rates. It also increases flooding risks. In addition, high levels of
TSS will increase water temperatures and decrease dissolved oxygen levels.
Due to these considerations, the cumulative impact of water quality is currently
considered to be Moderate.
Conclusion
ESC identified one cumulative impact due to project operation activity. The overall
cumulative impact from existing activities within the Project Area of Influence is
considered moderate for water quality. The cumulative environmental impact would be
associated with the sediment flushing activitiy of Aek Sibundong MHPP operation. The
Aek Sibundong MHPP project contributes a negligible to minor-moderate impact after
mitigation.
170
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Stakeholder Identification
Aek Sibundong MHPP has identified stakeholders associated with the Project that could
directly or indirectly, positively and negatively, affect or influence the Project were
identified. The primary categories of stakeholders identified for the Project included:
Government (regional, district, village level) including Bupati, BPN, related
agency
Traditional authorities (communities leader and religious leader), and
Local communities (households affected people).
ASE has consulted with the community including the households being and will be
compensated. The consultation process has frequently made use of image and verbal
presentation to share information with communities. The Head of Village have played
171
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
integral role in communicating with the communities and Aek MHPP has maintained a
close engagement with them.
As of March 2015, ASE has made consultation with the households being and will be
compensated particularly for negotiation on the final purchase price. Land valuation
methods and the amount land owners was to receive were explained to land owners
particularly if people had concerns regarding the Project or the compensation price. The
contact numbers of the team and construction site were also provided in case they need
to be contacted after these meetings; these meetings were usually carried out over several
visits to ensure everybody was contacted and informed; depending on the concerns of
the land owners, an additional trip to the site was conducted for revising the determined
values of the assets and investigating both requests and objections of the titleholders; all
the valuation results and outcomes of disclosure meetings were considered in an internal
meeting measures were taken to ensure that all land owners were treated in the same
manner and their land valuation was consistent and equitable; the final offers on
compensation for the lands to be sold were calculated and disclosed to the land owners
through face-to-face interviews;
They basically agreed to lease their land however; they requested negotiation about the
price. ASE has established communication with local government and the meeting with
Regence has been held to gain support from the governments for price and ongoing
consultation and disclosure activities and accelerated the process. Table 70 shows the
public consultation meetings that have been held.
Based on Government Regulation No. 27 of 2012 every business and/or activity that does
not require AMDAL should conduct UKL/UPL. The Aek Sibundong MHPP has gained
approval from Local Environmental Agency Humbang Hasundutan Regency
Government. The company will continue to engage stakeholders related to the
implementation of UKL-UPL. The project not only include engagement regarding Project
approvals or the development but also during construction and operation of the Project
Table 71 captures, main Company-Government engagement activities.
172
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
173
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Grievance Mechanism
While the Project aims to resolve the majority of individual, group, and community
grievances by direct resolution at individual or group levels, a hierarchical grievance
resolution mechanism has been developed as follows:
1. Direct resolution at the individual or group level;
2. Community-level resolution through public meetings;
3. Resolution through a stakeholder group comprising Project representatives,
government representatives, religious and village leaders, and the complainants;
and
4. Recourse to legal counsel if the grievance cannot be resolved.
With regard to IFC’s requirements, this ESIA has been completed with a grievance
mechanism which can be use to receive and resolve the project-affected communities’
environmental and social concerns and complaints and based on the following principles:
proportionality, accessibility, transparency and culturally appropriateness.
To make these principles clearer, it can be said that;
Proportionality means scaling the mechanism to the project needs. In a project
with low potential adverse impacts, simple and direct mechanisms for problem
solving is preferred for addressing and resolving complaints such as public
meetings, telephone hotline, existing media, brochures, and a community liaison
officer;
Accessibility means establishing a mechanism which is clear, free of charge and
easy to access for all segments of the affected communities and other potential
stakeholders. The best way of achieving this is to localize the point of contact.
174
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Related to that, staff with the appropriate skills, training and familiarity with
community liaison work should be employed in the field. Accessibility enables to
build more constructive relationships with local communities. This will also help
intervene quickly in any dispute or social unrest and in an appropriate manner
because maintaining a regular presence of a familiar face in the field greatly
helps engendering trust and thus, constructive and closer relations;
Transparency means that members of the affected communities know who is
responsible for handling the complaints and communicating the outcomes of
corrective actions to be taken about the complaints; and
Culturally appropriateness means having cultural sensitiveness while designing
and executing the grievance mechanism.
The critical issue for responding to complaints is to ensure that all received complaints
are recorded; and responsive to complaints; and that corrective actions are mutually
acceptable. Thus, responses to complaints will be satisfactory for both parties, actions are
followed up, and the complainants will be informed about the outcomes of the corrective
actions. For the Project, on-site staff will be responsible for establishing close relationship
with local people, authorities and other interest groups, informing them about the Project
progress when needed, listening their concerns about the Project and recording them,
receiving demands and complaints, recording them regularly and sharing them with the
Project Team.
175
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
176
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
177
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Check and ensure that operation activities are undertaken following the
procedure manual;
Sampling and measurement for environmental and social parameters;
Checking records in relation to environmental and social parameters; and
Making a report and communicating it to the project owner.
The following Table 74 of ESMP outlines the overall composition of the environmental
and social monitoring program that will be carried out in relation to the Project. The table
also provides information related to frequency needed for each parameter and assigns
responsibilities for each monitoring activity.
178
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Table 74 Environmental and Social Management and Monitoring Plan for Aek Sibundong MHPP
A Construction Phase
1 Air quality degradation 1. Mobilization of 1. Install a monitoring station to monitor ambient air quality Contractor Construction Undertake periodic monitoring at Every 6 Contractor and
due to emission from Materials and that may include dust (Total Suspended Particles (TSP) – Phase the established monitoring sites and months during Independent
vehicle and machinery, Heavy PM2,5 and PM10) and other gaseous emissions such as near sensitive receptors in construction Consultant
and dust generation accordance with Indonesian Laws
Equipments Nitrogen Dioxide (NO2), Sulphur Dioxide (SO2), Carbon period
and Regulations and International
Monoxide (CO) and Hydro Carbon (HC) in compliance
2. Land Guideline that may include dust
with Indonesian regulation (Total Suspended Particles (TSP,
Preparation
PM2,5 and PM10) and other gaseous
3. Construction of 2. Spraying of water on unpaved access roads during dry ASE and Construction emissions such as Nitrogen Dioxide
MHPP and season using surface water or rain water harvesting, if Contractor Phase specific (NO2), Sulphur Dioxide (SO2),
Associated possible. Monitor the spray frequency and water usage when project Carbon Monoxide (CO) and Hydro
Carbon (HC)
Facilities traffic
4. Regular checks that all vehicle emissions meet with Contractor Construction
National Standard Phase
6. Install vehicles washing facilities on the project site to wash Contractor Construction
the vehicle before leaving the project site to minimise dust Phase
1. Install noise monitoring station to monitor noise level Construction Every 6 Contractor and
2 Increased Noise Level 1. Mobilization of Contractor Undertake periodic monitoring of months during Independent
resulting from construction activities in compliance with Phase
Materials and noise at the location at determined construction Consultant
Indonesian regulation and International Guideline noise level monitoring station
Heavy period
Equipments
Construction
2. Construction of 2. Restrict construction activities to within daylight hours. Contractor Note: Noise threshold standard of
Phase specific 55dB for residential areas according
MHPP and Night shift is allowable with approval from community
when project to the national standard Ministry of
Associated
traffic Environment Decree No. 48 Year
179
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Construction
4. Restrict off-road driving, acceleration and the use of horns. Contractor
Phase
Regulate vehicle speed limits on transportation routes will
be 40km/h for light vehicles and 30km/h for heavy
vehicles
4. Install a septic tank to treat the domestic wastewater and Contractor Construction
ensure that the organic waste is collected by third party Phase
5. Install soil erosion control structures and sediment traps, Contractor Construction Regular monitoring of potentially Every 6 Contractor and
and build terraces for steep slopes Phase impacted rivers and channels to months during Independent
include TDS and TSS near the construction Consultant
6. Restrict construction activities during heavy rain Contractor Construction sensitive receptors and regular period
Phase visual inspection of potential
sediment pathways to the river.
7. Where possible maintain riparian or buffer zones next to Contractor Construction
the river of 30 m that will not be cleared Phase
180
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
8. Undertake cut top soil disposal outside of fragile ecosystem Contractor Construction
(including riparian zone and water sources downstream) Phase
1. Frequent monitoring and review of surface hydraulics Contractor Construction Monitoring and review of surface Bi-weekly Contractor
4 Impact on Hydrology 1. Land
Phase hydraulics at the project site
Aspect, including: Water Preparation
Balance Alteration,
Potential Flooding, 2. Construction of 2. Restrict vegetation clearance outside project footprint Contractor Construction
Water Course Impact, Phase
MHPP and
Water Flow Impact Associated
3. Immediate revegetation after construction work is Contractor Construction
Facilities
completed Phase
6 Impact on Socio 1. Land 1. Give priority to local communities to work in the Project ASE and Construction Record the number of workforce Every month Contractor
Economy Aspect, ie Acquisition according to specification required Contractor Phase who are originated from Sigulok during
Changes in Community Village construction
Livelihoods 2. Recruitment of
period
workforce
2. Conduct socialization with the local community to inform ASE and Construction
job opportunities related to the project Contractor Phase
181
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Ongoing Contractor
10 Impact on Public Health, 1. Land 1. Install grievance box for the workers and local community ASE and Construction Maintain grievance log including
Safety and Security, Preparation Contractor Phase name, grievance/concerns, date and
including Traffic Issue supplementary information
2. Mobilization of 2. Recruit security team to guard the project area and open ASE and Construction
Materials and employment opportunity for local community Contractor Phase
Heavy
Equipments 3. Install fences and barricading to prevent any outsider from ASE and Construction
enter the project area Contractor Phase
3. Construction of
MHPP and Monitor and record vehicle and Daily Contractor
4. Implement Traffic Management Plan (Develop schedule for ASE and Construction
Associated material transport and operation of heavy equipment and Contractor Phase heavy equipment mobilisation in specific for
Facilities machineries, Develop vehicle routing and scheduling to the gate-in and out of the Project project
avoid traffic congestion, Install traffic signage in the Area traffic
vicinity of project area, Restrict acceleration and off-road
driving and regulate vehicle speed limits on transportation
routes will be 40km/h for light vehicles and 30km/h for
heavy vehicles)
6. Conduct inspection to ensure that no violation against OHS ASE and Construction
procedure and regulation Contractor Phase
1 Waste Generation 1. Land 1. Provide temporary waste storage for hazardous and non- ASE and Construction Maintain hazardous waste inventory Every month Contractor
Preparation hazardous waste separately, completed with required Contractor Phase with detail of hazardous waste based during
permit on the type. The inventory should construction
2. Construction of Contractor Construction include amount of waste produced period
2. Provide segregated waste bins with appropriate labelling
MHPP and system Phase per m3, treatment method, the
182
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Associated 3. Provide hazardous waste storage equipped with fire Contractor Construction producer, date produced and date of
Facilities extinguishers, bund wall, and proper labelling system Phase collection.
4. Contract a licensed third party to collect hazardous waste Contractor Construction
Phase
5. Monitor the hazardouse waste collection by a licensed third Contractor Construction
party and maintain a manifest of the hazardous waste Phase
collection to ensure chain of custody
2 Hazardous Materials 1. Land Contractor Construction
1. Provide a hazardous materials storage equipped with Maintain a hazardous material Every month Contractor
Generation Phase
Preparation portable fire extinguishers, MSDS, PPE, lock and proper inventory with details of quantity, during
labelling system user, characteristic, and type of construction
2. Construction of
Contractor Construction hazardous materials period
MHPP and 2. Provide MSDS for all hazardous materials stored in the
Phase
Associated project site for construction Maintain records of the hazardous
Facilities materials usage
3 Spill Prevention 1. Land 1. Install signs and announcement related with spill ASE and Construction Conduct inspection to monitor any Periodic check Contractor
Preparation prevention Contractor Phase spill onsite in the
hazardous
Contractor Construction material
2. Mobilization of 2. Provide spill kit at the hazardous materials storage and
Phase storage
Materials and pressure vessel tanks to store any liquid hazardous
Heavy materials
Equipments Contractor Construction
3. Install perimeter bund and provide secondary containment
Phase
3. Construction of for bulk liquid storage including tank, pressure vessel,
MHPP and drum, etc.
Associated Contractor Construction
4. Refuelling will be undertaken within or over the bunds to
Phase
Facilities minimize the risk of spills into the soil
Contractor Construction
5. Develop routine preventive maintenance to avoid any fuel
Phase
leakage or spill
B Operation Phase
Prior to
1 Increased Noise Level 1. Operation of 1. Implement building designs that minimize high noise ASE
commissioning Periodic monitoring to measure Every 6 ASE and
MHPP and exposure to workers in power house, ie: panel and noise level at the power house, and months during Independent
Associated operator room are designed to be closed and operational
183
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Facilities impermeable, separately from turbin generator area community settlements area phase Consultant
Commissioning
2. Install safety perimeter to restrict the access from local ASE
and Operational
community to the MHPP site to avoid direct exposure of
Phase
noise to the people
Operational
3. Provide PPE signage in areas of elevated noise if ASE
Phase
required
1. Install fencing/hoarding around works areas to prevent Prior to Conduct site inspection to monitor Every 6 ASE and
2 Impact on Biodiversity 1. Operation of ASE
animal entry and minimize light/disturbance impacts commissioning wildlife encounters that may occur months during Independent
Resources MHPP and
on the Aek Sibundong MHPP site operational Consultant
Associated
2. Install sign regarding prohibition of hunting activities in Operational phase
Facilities ASE Monitor discharge flow in the river
the Project Area, particularly for protected species Phase
2. Maintenance of section between the intake works
MHPP and 3. Train crews and power house occupants on the Operational and point of return of flow to the
ASE main Aek Sibundong River for
Associated appropriate response to wildlife encounters that may Phase
Facilities occur and instruction to occupants to refrain from purposes of aquatic biodiversity
harassing wildlife sustainability
1. Install a septic tank to manage domestic wastewater ASE Prior to Regular monitoring of potentially Every 6 ASE and
3 Decreased Water Quality 1. Operation of
produced by operational workers commissioning impacted rivers and channels i.e months during Independent
MHPP and operational Consultant
ASE Prior to solid waste, debris, etc
Associated 2. Contract a third party to collect domestic wastewater phase
from septic tank commissioning
Facilities
3. Install sand and sediment traps to reduce amount of sand ASE Prior to
and sediment entering water bodies commissioning
1. Monitor discharge flow in the river section between the Operational Monitor discharge flow in the river Every 6 ASE and
4 Impact on Hydrology 1. Operation of ASE
intake works and point of return of flow to the main Aek Phase section between the intake works months during Independent
Aspect, ie water flow MHPP and
Sibundong River for purposes of in stream water use and point of return of flow to the operational Consultant
impact, erosion Associated
main Aek Sibundong River for phase
Facilities
2. Monitoring of water flow between the weir and Operational purposes of in stream water use
ASE
powerhouse and downstream of the powerhouse Phase
184
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
1. Operation of 1. Install grievance box for the workers and local ASE Commissioning Maintain grievance log including Ongoing ASE
6 Impact on Public Health,
MHPP and community for operational phase and Operational name, grievance/concerns, date and
Safety and Security
Associated Phase supplementary information
Facilities ASE Commissioning
2. Install good security system at Aek Sibundong MHPP
(recruit security team to guard the project area, install and Operational
fences and barricading to prevent any outsider to enter Phase
the project area)
1. Restrict the employment of underage worker and forced Operational Prepare safety performance report of Every 3 ASE
7 Impact on Occupational 1. Operation of ASE
labour Phase the project. months during
Health and Safety MHPP and operational
(Labour and Working Associated ASE Prior to Maintain incident/accident report,
2. Develop Operation Manual for MHPP operation phase
Condition) Facilities commissioning internal/external audit report, etc.
2. Maintenance of 3. Train all employees regarding the Occupational, Safety ASE Prior to
MHPP and commissioning
and Health (OHS)
Associated
Facilities 4. Conduct safety briefing and induction for all workers in ASE Prior to
order to have basic safety knowledge prior working commissioning
onsite
1. Install segregated waste bins to be placed at appropriate ASE Operational Maintain hazardous waste Annual during ASE
1 Waste generation from 1. Operation of
locations with a proper labelling system Phase inventory and monitor hazardous operational
operation activities MHPP and
waste generation phase
Associated ASE Operational
2. Contract a licensed third party to collect and dispose
Facilities Phase
generated hazardous waste appropriately
2. Maintenance of
MHPP and
Associated
Facilities
185
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
10. REFERENCES
Convention on International Trade in Endangered Species of Wild Fauna and Flora (=CITES).
2012. Appendices I, II, and III. International Environment House, Geneva.
Feasibility Study Aek Sibundong Energi Mini Hydro Power Plant 2013
Humbang Hasundutan Regency in Figures 2017
Imanuddin, S. Persey, D. Priatna, L. D’Arcy and L. Sadikin. 2011. A Practical toolkits for
Identifying and monitoring biodiversity in oil palm landscape. The Zoological Society of
London – Biodiversity and oil palm project.
International Union for Conservation of Nature (=IUCN). 2015. The IUCN Red List of
Threatened Species. Version 2015.2. <www.iucnredlist.org>. Accessed on March 2016.
Indonesia Statistic 2017
Krebs, C.J. 1989. “ Ecological Methodology.” Harper & Row, New York.
Manual Kapasitas Jalan Indonesia. 1997. Direktorat Jenderal Bina Marga. Kementerian
Pekerjaan Umum.
Sijamapolang Sub-district in Figures 2017
UKL/UPL Aek Sibundong Mini Hydro Power Plant Development 2 x 4009 kW 2016
186
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
Key informant interviews were conducted in 1 impacted village with the list of respondents and
documentation as follows.
3. Ecosystem services
- The community uses water from mountain spring distributed using pipe for
daily use. The quality and quantity is good throughout the year.
- Local community use Aek Sibundong River for recreation (fishing) and
irrigation.
- Behind the village there is another river namely Aek Hinalang which is
used by community for animal husbandry.
- Land for farming is prepared by cutting down trees.
- Farming (coffee, corn, potato, etc.) and kemenyan tapping is often carried out
by the community in the forest area.
- There are no routine activities at the river.
187
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
5. Indigenous people
- The people who live in the area are Bataknese.
- Most common livelihood for people in Sigulok Village are farming (paddy,
corn, etc.) and hunting (wild boar, deer, etc.) to be sold at Dolok Sanggul.
- There are no cultural artifacts in Sigulok Village.
- Land ownership in the village is by family and decision on land is made
through family forum.
6. Cultural heritage
- No cultural heritage is found in Sigulok Village.
7. Perceptions of impacts
- The project is expected to increase work opportunity in Sigulok Village.
- Community is concerned with water contamination.
- The workforce from outside Sigulok Village may affect the community
health but not social sensitivity.
- The community expects that local infrastructure will improve (especially
roads).
3. Ecosystem services
- Community members source their water from mountain spring. Nobody
uses river water for daily use.
5. Indigenous people
- There is no house located within the project area.
- The project area and its surroundings are utilized for farming (paddy and
other crops) and hunting (wild boar, deer, etc.).
- The majority of livelihood in Sigulok Village is farmer (95%)
6. Cultural heritage
- There are 2 churches in Sigulok Village (GKPI and HKBP) but none are
located within project area.
- There is no traditional ceremony; all ceremonies are usually part of church
activity.
188
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
7. Perceptions of impacts
- The project is expected to provide work opportunity and road
improvement.
- Perception to the previous project (Aek Sibundong 1) is neutral.
- Community members are open to newcomers. Several surveys had been
conducted where the people stayed in community houses.
3. Ecosystem services
- Community utilizes water from mountain spring.
- Aek Sibundong is located relatively far from settlement area and is not
utilized by the community.
- Community often taps kemenyan sap from the forest.
5. Indigenous people
- There is no house located within the project area.
6. Cultural heritage
- There is no sacred site located within the project area.
- There is no ethnic minority in Sigulok Village.
7. Perceptions of impacts
- The project will not give large impact to the community as it will not need a
lot of workforce.
- The project will give minimum impact to the environment.
- Project proponent is expected to prioritize local workforce for construction.
189
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
3. Ecosystem services
- The community uses mountain spring water for daily use including
drinking. For irrigation, water from Aek Hinalang (a smaller river that will
converge with Aek Sibundong) is used.
- Around 5 people use Aek Sibundong for recreation (fishing).
- People clear the land for farming by cutting off trees. The wood is later used
for firewood.
- Water for animal husbandry is sourced from Aek Hinalang or mountain
spring.
5. Indigenous people
- No one lives at project area near Aek Sibundong.
- No one uses the water from Aek Sibundong as the water from other sources
is still sufficient.
- There are no cultural artifacts found in the project area.
- About 15 families own the land within the project boundary. The lands are
owned by families and none of them has certificate. Socialization has been
conducted 3 times since 2015 and all owners have agreed for Aek
Sibundong Energi to buy the land. Head of village acts as mediator.
6. Cultural heritage
- There is no cultural heritage or ethnic minority found in Sigulok Village.
7. Perceptions of impacts
- The project will not have significant impact to the local economy, but it is
expected that local community is prioritized for workforce.
- The project will have positive impact in work opportunity but only during
construction phase.
- Community has no concern about the project impact on environment as the
project is located far from settlement area. However some people are
concerned about the amount of fish at Aek Sibundong and vibration from
heavy equipments during construction.
- The community is not against workers from outside the village.
190
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
3. Ecosystem services
- People source the water for daily use from mountain spring.
5. Indigenous people
- Traditional custom is still strong in the community.
- Lands that are within the project boundary are mostly owned by families. If
there is land that has never been utilized by the community, the land
becomes village asset (about 1 ha at 3 locations).
6. Cultural heritage
- There is no cultural heritage found in Sigulok Village
7. Perceptions of impacts
- It is expected that local community to be prioritized for workforce.
- Concern about possible negative impacts (vibration, landslide, etc.) has
been conveyed to the project proponent in forum.
191
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
192
Vrcnil
Komite Akreditasi Nasional
Laboratorium
Penguji
lP.739. IDN
No.RegistrasiKompctensi:
(}()75/LPJ/LABLING.l
/LRK/KLH
LAPORAN
HASILPENGUJIAN
N O M O RP E K E R J A ASNP:I - 1 8 0 3 1 1 9 A
N a m aP e l a n g g a n :
PTESCENVIRONMENT
INDONESIA
Sigulok
Sum aterUtar
a a
Personil
Penghubung:
lbuSteffani
Tanggal:
06April2018
PTSKYPACIFIC
INDONESIA
Tomon YasminSektorlll, Jl. YasminRaya No. 64, Koto Bogor 76713
Faks.: +62-251-8374400
Telepon: +62-251-8358700;
Website: www.skylob.co.
id
L a p o r a ni n i d i b u a t b e r d a s a r k a nh a s i lo b s e r v a syi a n g o b j e k t i fd a n i n d e p e n d e nt e r h a d a ps a m p e lp e l a n g g a ny a n g b e r s i f a tk h u s u sd a n r a h a s i a .D a t a h a s i l
p e n g u j i a ni,n t e r p r e t a s id, a n p e n d a p a t - p e n d a p ayta n g a d a d i d a l a m n y am e w a k i l ip e n i l a i a nt e r b a i kd a r i P T S k y P a c i f i cI n d o n e s i a .D a l a mh a l p e n g g u n a a n
l a p o r a ni n i , P T S k y P a c i f i cI n d o n e s i at i d a k m e m b u a t j a m i n a n s e c a r at e r s i r a t m a u p u n t e r s u r a t d a n t i d a k b e r t a n g g u n gj a w a b t e r h a d a p p r o d u k t i v i t a s ,
k e g i a t a no p e r a s i o n a la, t a u p u n k e r u g i a nl a i n n y ay a n g b e r s i f a tm a t e r i a lm a u p u n i m a t e r i a l .L a p o r a ni n i t i d a k d i p e r b o l e h k a nu n t u k d i g a n d a k a nk, e c u a l i
s e c a r au t u h k e s e l u r u h a n n ydaa n a t a sp e r s e t u j u a nt e r t u l i sd a r i P T S k yP a c i f i cI n d o n e s i a .
N o . D o k . :F S O P . S K Y - 1 7 . 1 No.Revisi/Terbit:
3/4 5 P I . ] , 8 0 3 1 1 9PAT E S CE N V I R O N M E NI N
TDONESIA
PTSKYPACIFICINDONESIA
ffi LaboratoriumPenguji
LP-739-IDN
i{*. &effi*lrasi i{g*tat*::*i :
ilc;5;t*t3.i/LAnL;NG-1 :t-t{xlxLX
B e r s a m ai n i d i s a m p a i k alna p o r a nh a s i lp e n g u j i a nu, n t u k :
N a m aP e l a n g g a n PTESCENVIRONMENT
INDONESIA
N a m aP e m o h o n INDONESIA
PTESCENVIRONMENT
P e r s o nPi le n g h u b u n g lbuSteffani
A l a m aLt e n g k a p Sigulok
S u m a t e rU
atara
T a n g g aCl o n t o hU j iD i T e r i m a L2 Maret2018
T a n g g aDl i l a p o r k a n 0 6 A p r i l2 0 1 8
C o n t o hU j i
Jumlah 3
J u m l aTh o t aH
l alaman 6 Halaman
( T e r m a s uSka m p uDl e p a n
)
Bogor,06 April2018
M a n a j eUr m u m
P TS K YP A C I F I N
CD O N E S I A
( Dr.lr. UndangKurnia,M.Sc.)
3/4 H a l a m a n1 d a r i 5
N o . D o k . :F S O P . S K Y - 1 7 . 1 No.Revisi/Terbit:
PTSKYPACIFICINDONESIA
ffi Laboratorium Penguji
1 P . 7 3 9- I D N
i$o. lqe{Jisira$i K{:}rn!ret€,16i :
00?5lLpJ/aA!3L;tiG.,'t /L&KIKLX
INFORMASI
CONTOH
UJI
N o m o rP e k e r j a a n : 5 P l - 1 8 0 3 1 1 9 4
N a m aP e l a n g g a n : P TE S CE N V I R O N M E N
I NTD O N E S I A
P e r s o nP
i l e n g h u b u n:gl b u S t e f f a n i
T a n g g aDl i l a p o r k a n : 0 6 A p r i l2 0 1 8
5Pr-1803119A-1/3 AP-1(Downstream) A i r P e r m u k a a n 08/03/20L8 15:30 12/03/20!8 13:00 72/03- 27/03 5 : 0 2 ' 0 8 ' 4 1 , 6B" T :0 9 8 "4 5 ' 0 8 , 1'
5Pr-1803119A-2/3 A P - 2( M i d d l e ) A i r P e r m u k a a n 08/03/2018 09:10 1,2/03/2018 13:00 72/03- 27/03 S:02' 08'47,1" 8 T :0 9 8 ' 4 5 ' 3 3 , 3 "
s Pr-1803119A-3/3 A P - 3( U p s t r e a m ) A i r P e r m u k a a n 08/03/2or8 Il:20 12/03/2078 13:00 72/03- 27/03 S ;0 2 ' 0 8 5
' 3 , 3 " B T :0 9 8 ' 4 6 ' 1 2 , 8 "
Bogor,06April2018 ,r7
M a n a j eTre k n i s
PT SKYI],
+,
( A g u : ;N u r j a m a n)
HASILPENGUJIAN
LAPORAN
ldentifikasi Tanggal Waktu Tanggal waktu
'dentitascontohuii Matriks I waktu Analisis
| I P e n s a m b i l a n Pense mbilal Penerimaan Penerimaan
I
Laboratorium | |
AP-1(Downstream) 15:30 t2/03/2018 L3:00 | 12/03-27/03
SPI-1803119A-1/3
| | Air Permukaan 08/03/2018
itstKA
1 iuhu
)1 1 D e v .3 " "c SNI06-6989.23:2005
23,0 1000 (Elektroda)
IKM,SKY-123
2 )adatanTerlarutTotal,TDS mg/L
50 n]'E/L A P H A2 5 4 0D : 2 0 1 2
3 )adatanTersuspensiTotal,TSS 80
tl ( I M I A
]H 7,48 6-9 SNI06-6989.11:2004
3 m8/L SNI 6989.72:2009
2 KebutuhanOksigenBiokimia,BOD5 b
13 25 m8/L SNI6989.73:2009
KebutuhanOksigenKimiawi,COD
7,86 4 ME/L A P H A4 5 0 0 - O G : 2 0 1 2
OksigenTerlarut,DO
FosfatTotal sebagaiP, P 0,043 Q,2 mg/L 5Nl06-6989.31:2005
14) n q 10 m8/L 4 5 0 0N 0 3 - B : 2 0 1 2
APHA
6 tlltrat sebagaiN, NO3-N
< 0,03 mc/L 5Nl06-6989.30:2005
7 A m m o n i aN
, HyN
0,2 m8/L SN6
I 989.19:2009
6 , l o r i d aC.l
< 0,001 0,02 'I,EIL (Spektrofotometri)
IKM.SKY-101
9 i i a n i d aC
. N'
< 0,09 m8/L 5Nl06-6989.29:2005
1( : l u o r i d aF, I,J
TOGAMTERLARUT
0,00061 1 m8/L A P H A3 1 2 5B : 2 0 1 2
tl Arsen,As
0,00017 0,2 MElL A P H A3 1 2 5B : 2 0 1 2
19 Kobalt,Co
0,0116 m8/L A P H A3 1 2 5B : 2 0 1 2
20 B a r i u m B
. a
0,3042 1 mg/t USEPAMETHOD200.7
2r Boron, B
0,0035 0,05 m8/L A P H A3 1 2 5B : 2 0 1 2
22 S e l e n i u mS, e
< 0,00003 0,01 m8/L A P H A3 1 2 58 : 2 0 1 2
23 Kadmium C ,d
0,004 0,05 'x'EIL A P H A3 5 0 0C r B : 2 0 1 2
24 {romHeksavalen,
Cr5*
0,0024 0,02 mc/t A P H A3 1 2 5B : 2 0 1 2
Cu
25 Tembaga,
0,28205 mg/L USEPAMETHOD
6020.A:1998
tl l e s i ,F e
0,00039 0,03 mc/L A P H A3 1 2 5B : 2 0 1 2
2-1 l'imbal,Pb
0,r4Lr2 ms/L A P H A3 1 2 5B : 2 0 1 2
2t M a n g a n ,M n
< 0,00004 0,002 mc/L U S E P AM E T H O D6 0 2 0 . A : 1 9 9 8
A i r R a k s aH
,B
0,0145 0,05 mg/L A P H A3 1 2 5B : 2 0 1 2
3C5eng,Zn
ill MIKROBIOLOGI
{r} 10 1000 MPN/100m1 A P H A9 2 2 3B : 2 0 1 2
1 KoliformFekal
(t) 5938 5000 MPN/100m1 9 2 2 3B : 2 0 1 2
APHA
2 (oliform Total
Keterangan:
'/'7
(S) Parameter sNl lso/lEc17025:2008
Sesuai
TidakTerakreditasi
{#f) Subkontrak
H a l a m a n3 d a r i 5
PTSKYPACIFIC
INDONESIAffi Laboratorium
Penguji
LP-739-IDN
1{*. 3e!ie:fasl !{sr}:pe;{:ns: :
i|,l?$lLia"'lLA*}1-iiilG-'i ;'i-RKl{Lti
LAPORAN
H A S I LP E N G U J I A N
ldentifikasi I I Tanggal Waktu Tanggal waktu
tdentitasContohUii Matriks I waktu anarisis
LaDoratoflum I| I
| Pensambilan P e n g a m b i l a nP e n e r i m a a n Penerimaan
I
S P I - 1 8 0 3 1 1 9 A - |2 / 3 A P - 2{ M i d d l e } | A i rp e r m u k a a n 08/03/2018 09:10 L2/03/2078 1"3:00 | 72/03-27/03
FISIKA
Suhu 20,8 Dev.3'
'c SN0I 6-6989.23:2005
')? a (Elektroda)
1 r a o a l a n t e f l a r u rt o r a t . l u 5 1000 mclL IKM,SKY-123
Padatan
Tersusoensi
Total.TSS 49 50 m8/L APHA2540 D:2012
tl K I M I A
1 ]H 5-9 S N I0 6 - 6 9 8 9 . 1 1 : 2 0 0 4
2 K e b u t u h a nO k s i g e nB i o k i m i aB, O D s 5 3 m8/t S N I6 9 8 9 . 7 2 : 2 0 0 9
3 K e b u t u h a nO k s i g e nK i m i a w iC
, OD 10 25 mg/ L S N I6 9 8 9 . 7 3 : 2 0 0 9
4 lksigenTerlarut, DO 10,82 4 ME/L APHA4500-OG:2012
5 FosfatTotal sebagaiP, P < 0,003 0,2 mt/L 5Nl 06-6989.31:2005
Nitrat sebagaiN, NOrN 0,8 10 mg/L A P H A4 5 0 0 N 0 3 - B ; 2 0 1 2
1 \ m m o n i aN, H r N < 0,03 m8/t SNI06-6989.30:2005
Klorida,
Cl- 0.5 mg/L 5 N l6 9 8 9 . 1 9 : 2 0 0 9
9 i i a n i d aC
, N < 0,001 0,02 ME/L I K M . S K Y - 1 0( S
1 p e k t r o f o t o m e t) f l
1t l u o r i d a I, < 0,09 ME/L 5Nl06-6989.29:2005
1 1 !itrlt sebagaiN, (NOr-N) 0,004 0,06 ms,/L A P H A4 5 0 0N O 2 - B : 2 0 1 2
T2 ;ulfat, SO4' 4 m8/L SN6
I 989.20:2009
1J ( l o r i nB e b a sC
, l2 0,02 0,03 mg/L I K M . S K Y - 1 0( K
0 olorimetri)
LOGAMTERLARUT
18 Arsen,
As 0,00053 1 ME/L A P H A3 1 2 5 B : 2 0 1 2
20 B a r i u m B
, a 0,0110 mc/L A P H A3 1 2 5B : 2 0 1 2
24 KromHeksavalen,
Cr" 0,003 0,05 mE/t A P H A3 5 0 0C rB : 2 0 1 2
25 Tembaga,
Cu 0,0015 0,02 m8/L A P H A3 1 2 5B : 2 0 1 2
8 e s i ,F e 0,28687 mc/L U SE P AM E T H O6D0 2 0 . 4 : 1 9 9 8
2', T i m b a l P
, b 0,00033 0,03 mc/L A P H A3 1 2 5B : 2 0 1 2
2t l M a n 8 a nM, n 0,18560 mglL A P H A3 1 2 5B : 2 0 1 2
z: Air Raksa,Hg < 0,00004 0,002 mE/t US EPAMETHOD6020.4:I.998
t l MIKROBIOLOGI
KOilIOrm feKat 13 1000 N4PN/100m1 APHA9223 Bt20t2
Keterangan:
Sesuai
{f) ParameterTidakTerakreditasi 5NllS0/lEC17025:2008
I##l Subkontrak
Hasil hanya berhubungan dengan contoh yang di uii dan laporan ini tidak boleh digandakan kecuali seluruhnya.
(
./
PTSKYPACIFIC
INDONESIA
IT*TJ:- Laboratorium
Penguji
LP-739-IDN
i\,!e-Registraei }{cnip€ten$i :
cE75l{-pJJLAt}LttCG-1lLqKlKLS
LAPORANHASILPENGUJIAN
'1"nt'.fi*lt' Tanggal Waktu Tanggal waktu
. | 'dentitascontohuii I uutrir., I waktu Anarisis
LaDoratonum | | P e n s a m b i l a n Peneambil P e n e r i m an
a Penerimaan
I
SPI-1803119A-3/3
| AP-3(Upstream) | Air Permukaan 08/03/2018 I1:20 1Z/0312018 13:00 | - 21/03
12/03
:ISIKA
tl KIMIA
1 pH 7\4 6-9 S N0
I 6-6989.11:2004
2 KebutuhanOksigenBiokimia,BOD, 5 3 mg/L SNI6989.72:2009
3 KebutuhanOksigenKimiawi,COD 10 25 mg/L SNI6989.73:2009
LOGAMTERTARUT
18 \rsen,As 0,00072 1 mg/t A P H A3 1 2 5B : 2 0 1 2
19 lobalt,Co 0,00017 o,z mc/t A P H A3 1 2 5B : 2 0 1 2
22 i e l e n i u m S
, e 0,0008 0,05 mc/L A P H A3 1 2 5 B : 2 0 1 2
2 3 (admiumC
, d 0,00010 0,01 mclL A P H A3 1 2 5B : 2 0 1 2
ill vltKRoBtoLoGl
(oliform Fekal lr) 6 1000 MPN/100m1" APHA9223B:2OLZ
(*) 4674 5000 lvlPN/100m1 A P H A9 2 2 3B : 2 0 1 2
2 (oliformTotal
(*) BML adalah Baku Mutu Lingkunganuntuk Baku Tingkat Air Permukaan, sesuai Peraturan Pemerintah No. 82 Tahun 2001 Tentang PengelolaanKualitasAir dan PengendalianPencem.
sesuaisNl lso/lEc17025:2008
{s} ParameterTidakTerakreditasi
{f#) Subkontrak
seluruhnya'
Hasil hanya berhubungandengan contoh yang di uii dan laporan ini tidak boleh digandakan kecuali
Vxnlu
Komite
Akreditasi
Nasional
Laboratorium
Penguii
1 P . 7 3. 9
IDN
No.Registrasi
Kompetensi
:
OO75/LPJ/LABLING.l
/LRK/KLH
LAPORANHASILPENGUJIAN
PEKERJAAN:
NOMOR SPI-18031198
NamaPelanggan:
INDONESIA
PTESCENVIRONMENT
Sigulok
SumaterUtar
a a
lbuSteffani
Penghubung:
Personil
06April2018
Tanggal:
INDONESIA
PTSKYPACIFIC
RayaNo.64,KotoBogor16113
Sektorttt,JI.Yosmin
TomanYasmin
Faks.: +62'251-8374400
Telepon: +62-251-8358700;
Website: www.skylob.co.id
N o . D o k . :F S O P . S K Y - 1 7 . 1 No.Revisi/Terbit:3/4 BT E S CE N V I R O N M E NI T
S P I . 1 8 0 3 1 1 9P NDONESIA
IND.NESIA VTIN
PTSKYPACIFIC Laboratorium Penguji
L P. 7 3 9. I D N
iiir',. i:;q :: i1;if ii 1 ; i': t :ll.:,il1.a:-,, I :
!t:*iti;.f .:li-,i.ili"lhl{i-:
lt"lill.i i-i'l
N a m aP e l a n g g a n P TE S CE N V I R O N M EIN
NTD O N E S I A
N a m aP e m o h o n P TE S CE N V I R O N M EIN
NTD O N E S I A
P e r s o nP
il enghubung lbu Steffani
A l a m a tL e n g k a p Sigulok
S u m a t e rU
a tara
T a n g g aCl o n t o hU j i D i T e r i m a 12 Maret2018
T a n g g aCl o n t o hU j i D i A n a l i s i s t 2 - 2 3 M a r e t2 0 1 8
T a n g g aDl i l a p o r k a n 0 6 A p r i l2 0 L 8
J u m l a hC o n t o hU j i 3
h otaH
JumlaT l alaman 6 Halaman
( T e r m a s uSka m p uDl e p a n)
B o g o r0, 6 A p r i l2 0 1 8
M a n a j eU
r mum
NDONESIA
P TS K YP A C I F I C
qkv-17 'l
H a l a m a nI d a r i 5
N o .R e v i s i f l e r b i3t :/ 4
IND.NESIA *gNX
PTSKYPACIFIC LaboratoriumPenguji
L P - 7 3 9. I D N
Ne. ilailis*vasiK*rmpelensi:
0fr?5lN_p",/LAmLtN*-t /LRKlKLi.l
INFORMASI UJI
CONTOH
N o m o rP e k e r j a a n : S P I - 1 8 0 3 1 1 9 8
N a m aP e l a n g g a n I NTD O N E S I A
: P TE S CE N V I R O N M E N
i l e n g h u b u n:gl b u S t e f f a n i
P e r s o nP
T a n g g aDl i l a p o r k a n : 0 6 A p r i l2 0 1 8
sPr-18031198-1/3 B-1(Downstream) Biota 0810312018 15i30 1,2103/2018 13:00 12103- 231o3 L 5 : 0 2 "0 8 ' 4 1 , 6 " B T : 0 9 8 ' 4 50 '8 , 1 "
sPr-18031198-2/3 B - 2( M i d d l e ) Biota 0810312078 09r10 L210312018 13:00 72103- 23/03 L S : 0 2 ' 0 8 ' 4 7 , 1 " B T : 0 9 8 ' 4 5
33,3"
sPt-18031198-3/3 B-3{Upstream) Biota 0810312018 77:2Q 72103/20].8 13:00 72103- 23103 L S : 0 2 ' 0 8 '5 3 , 3 " B T : 0 9 8 ' a162 . 8 '
Bogor,06April2018
@
M a n a j eTre k n i s
PTSKYPACIFIC INDONESIA
kecualiseluruhnya'
Hasilhanya berhubungandengancontoh yang di uii dan laporanini tidak boleh digandakan
3/4 2 d a r i5
Halaman
N o .D o k . :F S O P . S K Y - 1 7 . 1 No. Revisi/Terbit:
PTSKYPACIFIC
IND'NESIAffi LaboratoriumPenguji
LP-739-IDN
S*:.**;i*lr**i i{*;*':l*{er1$i:
0S75/Lf JILAALi l{{: -i I ;&i{iX :-tr
LAPORAN
HASILPENGUJIAN
Tanggal Waktu r angtal Waktu
ldentifikasiLaboratorium ldentitasContohUji Matriks Waktu Analisis
Pensambilan Penerimaan Penerimaan
HasilPengujian
VletodePengambilanContohBiota : SNI13-4717-1998 Metode Pengujian : APHA10200:2012
Phyto Plankton
B-1(Downstream) B-2 (Middlel 8-3(Upstream)
No. JenisOrganisme{Genero,
Cuaca:Berawan Cuaca: Cerah CuacaC
: erah
Sel/t (/.1 Sel/L l%l SeUL ('/.1
IACII.I-ARIOPHYCEAE
1 \chnontessp. 1,36
2 )ocillorio sp 50 4.52 50 7,94 10 0.98
3 occonetssp. 5 0.49
4 )iotomo sp 25 2,26 o,79 2,93
5 :rogilario sp. 325 29,41 420 66,67 100 9,76
6 Voviculq sp 6,33 20 1 1 7 0,98
7 Uitzchiosp. 30 20 3,1,7 30 2,93
)innulario sp. qc
8 95 8,60 0,79 5.37
110 q qq 45 7.14 5.37
9 ;urirello sp. 55
10 ;ynedrasp. 95 8,60 15 r.46
:HLOROPHYCEAI
11 ]ulbochoete so. 4,88
1 1 )edogoniumsp. 75 7.3)
)ediostrum sp, 25 2,44
14 >leurotaeniumsp, 10 0,90 o,49
IJ ;cenedesmussp, 5 0,45
Tetroedronsp. o,4s
1 a Treuborio sp. 5 0,79 0,49
:OSCINODISCOPHYCEAE
19 :oscinodiscussp. 10 0,90 5 0,49
]YANOPHYCEAE
\noboenosp. o,49
22 )scillatorio sp, 65 5,88
:UGTENOPHYCEAE
23 :.uglenosp. 5 0,45 5 o,79
24 )hocussp. o,79
25 Trochelomonassp. 55 4,98 5 0,79 5 o,49
VIEDIOPHYCEAE
26 limocosphenia
sp. 35 3.41
IYGNEMATOPHYCEAE
z7 IOStenum sp. 25 2,26 5 o,79 5 o,49
29 :-uostrumsP. 5 o,49
30 lyalotheco sp 150 14.63
LAPORAN
HASIL
PENGUJIAN
Tanggal Waktu I a nggal Waktu
ldentifikasi Laboratorium ldentitas Contoh Uii Matriks Waktu Analisis
PenEambilan Peneambilan Penerimaan Penerimaan
sPt-18031198-1/3 B - 1( D o w n s t r e a m ) Biota 08/03/2018 L5:30 rz/03/20t8 !3:00 12/03- 23/03
Hasil Pengujian
Metode PengambilanContoh Biota : SNI 13-4717-1998 Metode Penguiian : SNI06-3963-1995
ZooPlankton
B-1(Downstream) B-2(Middle) B-3(Upstream)
No, lenisOrganisme{6enero,f
C u a c a :B e r a w a n Cuaca: Cerah Cuaca: Cerah
}RANCHIOPODA
q 1 1 1 1 9,09
1 \lona sp. 9,09 5 5
:OPEPODA
2 Uoupliussp. r,0 18,18 10 22,22 5 9.09
IOTIFERA
3 ^qronotholco sp 5 9,09 5 1 11 1 ) 9.09
qna
4 \splanchna
sp 5
5 3tochionussp. 5 II.L7 f 9.09
6 )onochilussp. 5 11,11
7 :etdtelld sp. 5 9.09
d Vlonastylo sp. 10 18,18
TUBULINEA
9 \rcelta sp. 20 36,36 15 33 3 3 20 3t',36
10 )iffuqlio sp. 10 18,18
(elimpahan
(lnd./L) 55 100 45 100 )) 100
t a k s a( S ) o 7
( e a n c k a r a g a m a( n
H') L,642 1,577 t,768
) c m c r a t a a n( E ) 0,916 0,936 0,908
) o m i n a s (i D ) 0,223 0,270 0,207
Keteranganl
(f) Seluruh Parameter Telah Terakreditasisesual SNI l5O/lEC 17025i2008 dengan Nomor Sertifikat LP-739-lDN n
kecualiseluruhnya.
dengancontohyangdi uji danlaporanini tidakbolehdigandakan
Hasilhanyaberhubungan
PTSKYPACIFICINDONESIA
ffi Laboratorium Penguji
1 P . 7 3 9- I D N
$0. :qe*;iilrlsi X*rnretoir*: ;
0&75/LrJlL,l8t_:NS-1,:L$tK/K!_!.t
HASIL
LAPORAN PENGUJIAN
Tanggal Waktu Tanttal Waktu
ldentifikasi Iaboratorium ldentitascontohuii Matriks W a k t uA n a l i s i s
P e n a a m b i l a n P e n g a m b i l a n Penerimaan Penerimaan
Hasil Pengujian
vtetode Pengambilancontoh Biota : SNI 13-4717-1998 Metode Pengujian : SNI03-3401-1994
B-1(Downstream) B - 2( M i d d l e l B-3(Upstream)
No. JenisOrganisme1t6enero,/
Cuaca: Berawan Cuaca: Cerah C u a c a: C e r a h
INSECTA
1 Boetissp 38
2 sp
Chironomus 38 100,00
3 Philopotomus
sp. 38 50,00
OLIGOCHAETA
38 s0,00 76 66,67
sp
Lumbriculus
38 100 TO 100 1.14 100
K e l i m p a h a(nl n d . / m ' )
T a k s a( S ) I
K e a n e k a r a g a m a( H
n') 0,000 1,000 0,918
I , e m e r a t a a{nE ) 0,000 1,000 0,918
I ) o m i n a s(i D ) 1,000 0,500 0.5s5
Keterang. n:
tSl seluruh parameter Telah Terakreditasisesuai SNI ISO/lEC17025r2008dengan Nomor Sertifikat LP-739-lDN
q.
kecualiseluruhnYa'
dengancontohYangdi uji danlaporanini tidakbolehdigandakan
Hasilhanyaberhubungan
Vxail
KomiteAkreditasiNasional
Laboratorium
Penguji
L PN. O . D N
No. RagistrasiKompetensi:
OO75/LPJ/LABLING.l/LRK/KLH
LAPORANHASILPENGUJIAN
N O M O RP E K E R J A ASNP:I - 1 8 0 3 1 1 9 U
N a m aP e l a n g g a n :
PTESCENVIRONMENT
INDONESIA
Sigulok
Sum aterUtar
a a
P e r s o n iPl e n g h u b u n gl b: u S t e f f a n i
T a n g g a l0: 6 A p r i l2 0 1 8
PTSKYPACIFIC
INDONESIA
TomanYasmin RoyaNo.64,KotoBogor1611j
Sektorlll, Jl. Yosmin
Foks.: +62-257-8314400
Telepon: +62-251-8358700;
Website: www.skylab.co.id
L a p o r a ni n i d i b u a t b e r d a s a r k a nh a s i lo b s e r v a syi a n g o b j e k t i fd a n i n d e p e n d e nt e r h a d a ps a m p e lp e l a n g g a ny a n g b e r s i f a tk h u s u sd a n r a h a s i a D . atahasil
p e n g u j i a ni,n t e r p r e t a s id, a n p e n d a p a t - p e n d a p ayta n g a d a d i d a l a m n y am e w a k i l ip e n i l a i a nt e r b a i kd a r i P T S k y P a c i f i cI n d o n e s i a .D a l a mh a l p e n S S u n a a n
l a p o r a ni n i , P T S k y P a c i f i cI n d o n e s i at l d a k m e m b u a t j a m i n a n s e c a r at e r s i r a t m a u p u n t e r s u r a t d a n t i d a k b e r t a n g g u n gj a w a b t e r h a d a p p r o d u k t i v i t a s ,
k e g i a t a no p e r a s i o n a la, t a u p u n k e r u g i a nl a i n n y ay a n g b e r s i f a tm a t e r i a lm a u p u n i m a t e r i a l .L a p o r a ni n i t i d a k d i p e r b o l e h k a nu n t u k d i g a n d a k a nk, e c u a l i
s e c a r au t u h k e s e l u r u h a n n ydaa n a t a s p e r s e t u j u a nt e r t u l i sd a r i P TS k yP a c i f i cI n d o n e s i a .
N o . D o k . :F S O P . S K Y - I 7 . 1 No.Revisi/Terbit:3/4 P TE S CE N V I R O N M E NI T
5PI-1803119U NDONESIA
PTSKYPACIFIC
IND'NESIA YTEA' Kes::***,ir**iissi t{*ri*n;l
Laboratorium Penguji
LP-739-IDN
S0. qe*istri}$i K(intpstensl:
iJCTSirpJrL.Al.,r,.rltrG.
ri RK Kl rr
suiR p,E
NGANJARLAp.ffiry;HffiwBNpq A
B e r s a mian i d i s a m p a i k al a
n p o r a nh a s i p
l e n g u j i a nu,n t u k :
N a m aP e l a n g g a n P TE S CE N V I R O N M EIN
NTD O N E S I A
N a m aP e m o h o n P TE S CE N V I R O N M EIN
NTD O N E S I A
P e r s o nP
ilenghubung lbu Steffani
A l a m a tL e n g k a p Sigulok
S u m a t e rU
a tara
T a n g g aCl o n t o hU j i D i T e r i m a L 2 M a r e t2 0 L 8
T a n g g aCl o n t o hU j i D i A n a l i s i s t Z - 2 3 M a r e t2 0 1 8
T a n g g aDl i l a p o r k a n 0 6 A p r i l2 0 L 8
i u m l a hC o n t o hU j i 4
JumlaT
h otaH
l alaman 7 Halaman
( T e r m a s uSk a m p uD
l e p a n)
Bogor,06 April2018
M a n a j eU
r mum
P TS K YP A C I F I C
NDONESIA
( Dr.tr. Undang
Kurnia,M.Sc.)
3/4
No.Revisiflerbit: H a l a m a1nd a r i6
N o .D o k . F
: SOP.SKY-17.1
PTSKYPACIFIC
IND'NESIA YTWU i{oxlt* Akr**ii;;s: FJ*s!***;
LaboratoriumPenguji
LP-739-IDN
${1, tqdgislf:r$i K*ffipelen$i :
0 0 7 5 , L P J ' l A B L i N G - - 1 rR
r KIK: tl
INFORMASI
CONTOH
UJI
N o m o rP e k e r j a a n : S P I - 1 8 0 3 1 1 9 U
N a m aP e l a n g g a n : P TE S CE N V T R O N M EtN NTD O N E S I A
P e r s o n i l P e n g h u b u:n l6b u S t e f f a n i
T a n g g aDl i l a p o r k a n : 0 6 A p r i l2 0 1 8
ldentifikasi
ldentitasContoh Uji Tanggal Waktu Tanggal Waktu Waktu Koordinat
Laboratorium Matriks
P e n g a m b i l a nPengambilan
Penerimaan Penerimaan Analisis
Lintant Bujur
sPr-1803119U-1/4U A - 1( P e m u k i m a n ) U d a r aA m b i e n 09103/2018 20:00 72/03/2078 15:30 7210323/03 tS:02"08'33,2" B T :0 9 8 ' a 5 ' 3 0 , 1 '
sPr-1803119U-2/4UA-2(PowerHouse) U d a r aA m b i e n 70/03/2078 21:00 1.2/03/2078 15:30 72/03- 23/03 L S : 0 2 ' 0 8 ' 3 4 , 2B'T :0 9 8 ' 4 5 ' 1 8 , 4 "
5Pt-1803119U-3/4B S - 1( P e m u k i m a n ) U d a r aA m b i e n 09/03/2078 20:00 72/03/2078 15:30 72/03- 23/03 LS:02"08'33,2" 8 T :0 9 8 " 4 5 '3 0 , 1 "
sPr-1803119U-4/4BS-2(PowerHouse) U d a r aA m b i e n r0/03/201.8 21:00 12/03/2018 15:30 72103- 23103 L S : 0 2 ' 0 83 '4 , 2 " B T :0 9 8 ' 4 5 1 8 . 4 '
LAPORAN
HASILPENGUJIAN
ldentifikasi Tanggal Waktu Tanggal waktu
ldentitascontoh uji I Matriks I waktu lnarisis
Laboratorium Pensambilan PeneambilanPenerimaan PenerimaanI
S P I - 1 8 0 3 1 1 9 U - 1| / 4 U A - l( P e m u k i m a n ) | U d a r aA m b i e n 09/03/2018 20:00 t2/03/20t8 I);5U I r2lV5-251V5
KondisiLingkungan
SaatPengambilan
ContohU,iiUdaraAmbien
S u h uU d a r a" C : 18,8 Cuaca Berawan
K e l e m b a b aUnd a r a , % : 8 5 , 9 Arah Angln K eB a r a t
T e k a n aU n d a r am
, mHg : 653,2 Kecepatan
Angin,m/detik : 0,7- 2,3
K o o r d ni a t LS:02"08' 33,2"
BT:098"45' 30,1"
Hasil Pengujian
FISIKA
tl (IMIA
1 i u l f u rD i o k s i d S
a ,O , 64 9 0 0 / 1J a m u g / Nm 3 s N t1 9 - 7 1 1 9 . 7 - 2 0 0 5
2 l a r b o nM o n o k s i d C
a ,O I l4) 30000/1lam uelNmt I K A . S K Y - 0( 8C OM e t e r )
3 ! i t r o g e nD i o k s i d a
N,O , 58 400/1Jam /Nm3 sNr19-7119.2-2005
)ksidan,O, 48 235/L)am uelNm3 sNt 19-7119.8-2005
5 l i d r o k a r b o nH, C l o ) <13 /Nm3 S N I7 1 1 9 . 1 3 : 2 0 0 9
T l m a hH i t a m ,P b < 0,1 2/24)am s/Nm3 sNr19-7119.4-2005
Keterangan:
.\\r-
(') SMLadalahgakuMutu LingkunganuntukBakuMutu UdaraAmbienNasional,
SesuaiPeraturan
Pemerintah Nomor41 lahun 1999
RepublikIndonesia
(#) Parameter
TidakTerakreditasi
sesuai5Nl lso/lEc17025:2008
No.Revisifierbit:
3/4 n d a r i6
Italama3
No.Dok.:FSOP.SKY-17.1
IND'NESIA VTEAI
PTSKYPACIFIC Kt:mite,{kreditasiNasianal
Laboratorium Penguji
L P- 7 3 9 . I D N
No.Registra$i Kornpetensi i
087sit_P..t/LAALt
NG-1iLi{t{JKr-!{
LAPORANHASILPENGUJIAN
ldentifikasi
-. I Tanggal Waktu Tanggal waktu
. :- :- | ldentitasContohUji I Matriks I waktunnarisis
LaDoratonum | | Pensambilan Pensambilan Penerimaan Penerimaan I
5Pl-1803119U-2/4
| UA-z(PowerHouse) | UdaraAmbien LO/0312018 21:00 12/03/2018 15:30 | t2/03 23103
ContohUii UdaraAmbien
SaatPengambilan
KondisiLingkungan
:ISIKA
I Partikel Total,TSP
Tersuspensi 57 230lz4 Jam /Nm3 s N r1 9 - 7 1 1 9 , 3 - 2 0 0 5
Partikel< 10 |]m, PMro 19 rSOl24)am (Gravimetri
IK.SKY-148 & HVAS)
uglNmt
Partikel< 2.5 [m, PM2.s 9 65124 Jam (Gravimetri
lK.5KY-147 & HVAS)
uglNm'
tl KIMIA
SO,
SulfurDioksida, 60 900/1Jam uelNm3 sNt 19-7119.7-2005
< 1145 30000/1Jam gglNm' (COMeter)
IKA.SKY-08
KarbonMonoksida,
CO
N02
NitrogenDioksida, 52 400/1Jam us/Nm3 sNt 19-7119.2-2005
Keterangan: .\*t
SesuaiPeraturan
untukBakuMutu UdaraAmbienNasional,
(x) BMLadalahBakuMutu Lingkungan Nomor41 Tahun1999
RepublikIndonesia
Pemerintah
sesuaiSNIISO/lEC
lf) ParameterTidakTerakreditasi 17025;2008
kecualiseluruhnya'
dengancontohyangdi uji dan laporanini tidak bolehdigandakan
Hasilhanyaberhubungan
H a l a m a4nd a r i6
3/4
No,Revisi/ferbit:
No.Dok.:FSOP.SKY-17.1
PTSKYPACIFIC
IND'NESIA YrcAI K*r:lti: Akrsdi*s*i it*'xsi*r*ri
Laboratorium Penguji
L P- 7 3 9. I D N
N!*, X*gislrasi K.lnit$l€n:jj :
itsT5lt*p JlL,qE ;_:$s.,1 lt_ttKJKLr!
LAPORANHASILPENGUJIAN
ldentifikasi Tanggal Waktu Tanggal Waktu
' r e n t i t a sc o n t o hu j i ,.,rit, w a k t uA n a l i s i s
| | Pensambilan P e n e a m b i l a n Penerimaan Penerimaan
Laboratorium | |
contohUii Kebisingan
KondisiLintkunganSaatPengambilan
Cuaca; Berawan
; u h uU d a r a , ' C : 18,8
K e l e m b a b aUnd a ' a , % : 85,9
fekananUdara,mmHg : 653,2
Koordinat : LS0
: 2'08'33,2"
BT:098' 45' 30,1"
HasilPengujian
- 09:00) q1 7
pn
1 T i n g k aKt e b i s i n g a a d aP u k u0l 7 : 0 0( 0 5 : 0 0
2 T i n g k aKt e b i s i n g apna d aP u k u1l 0 : 0 0( 0 9 : 0 0- 1 1 : 0 0 ) s2,5
3 T i n g k aKt e b i s i n g a pna d aP u k u1l 5 r 0 014:00- 17:00) 64,3
p a d a P u k u l2 0 : 0 0 L7:O0
n g k a tK e b i s i n g a n - 22:001 49,r
pna d aP u k u2l 3 : 0 022:OO - 24:0Ol 45,2
5 f i n g k aK
t ebisinga 55+3 dB (A) TKM.SKY-14
{ S9 L M )
t e b i s i n g apna d aP u k u0l 1 : 0 02 a : 0 0' 0 3 : 0 0 )
f i n g k aK
padaPukul04:00(03:00- 06:00)
TingkatKebisingan
padaSiangHari,Lt
TingkatKebisingan 54,4
T i n g k aKt e b i s i n t apna d aM a l a mH a r i ,L M
Tinokat Kebisinsanselama 24 Jam, 1". 47,9
-sw9
Keterangan:
(#| Seluruh parameter Tetah Terakreditasi sesuai SNI ISO/lEC17025:2008 dengan Nomor Sertifikat LP-739-lDN
HasiIhanyaberhubungandengancontohyangdiuiidanIaporaninitidakboIehdigandakankecuaIiseluruhnya'
H a l a m a n5 d a r l 6
3,/4
No. Revisi/Terbit:
No. Dok,:FSOP.SKY-17.1
(
INDONESIAYI{A'II
PTSKYPACIFIC {.*iniil A*ra*lt;$i Sesie{*i
Laboratorium Penguji
LP-739-IDN
t*. R*gls{iasi {*ripeir*$i :
0 0 ' r ' i . e . . il "A 8 1 - ! l t G "! . . k 1 ( , i {: . t r
LAPORAN
HASILPENGUJIAN
--
tdentifikasi |
Laboratorium I tdentitascontoh Uji
Matriks Tantgal Waktu Tanggal Waktu
PengambilanPengambilanI penerimaan
sPl-18031
19U-4l4
PenerimaanW a k t uA n a l i s i s
BS-2(PowerHouse)
Udara
Ambien r0/03/20t8 27:00 t2/03/2018 1s:30
- 12/03 23/03
| I
KondisiLingkuntanSaatpengambilan
ContohUji Kebisingan
S u h uU d a r a , ' C : 20,7
K e l e m b a b a nU d a r a , y . : 77,7 Cuaca B er a w an
I e k a n a n U d a r a ,m m H g
: 653,2
(oordinat
: L 5 :0 2 "0 8 ' 3 4 , 2 ' ,
B T :0 9 8 ' 4 5 ,1 8 , 4 "
:]-- -
HASII BML* I SATUAN METODE
1 I I n g k aK
t ebisinga
pna d ap u k u 0
l 7 : 0 0( 0 6 : 0 0
_
- 09:00)
)L,t
Tingkat
Kebisingan
p.O.eutrt ruffio6-_ r-rr6iJ
- 57,O
3 Iingkat
Kebisingan
p.o.rrrrl riio-@oo-l76iJ
47,4
rinskat Kahi.ino.. ^-r- _ zztuul
- -v.ww t! t
",.ilillll7--ll--ll-li ,vv
56,9
5 Tingkat Kebisingan p.a. rrtrt Zf O6Il,Oo-_ zLoii
6 T i n g k aKt e b i s i n g a
pna d ap u k u0l 1 : 0 0( 2 a : 0 0
_t r J ; 0 0 ) /0+3 d B( A )
- 36,7
TKM.SKY-14
( S9 L M )
1 rinskat
Kebisingan
p.a,rutJElo[!ool offi
- 35,8
TingkatKebisingan
pra. SaniH.,.iI--.-
53,2
TingkatKebisingan
p.a. v.l..lJI--
- 42,0
TingkatKebisi
ngan r.b.i z+.t.-=IJ-
48,4
Hasilhanyaberhubungan
dengancontohyangdi uji dan laporanini tidak bolehdigandakan
kecualiseluruhnya.
N o ,D o k .F
: SOP.SKY-17.1
J17-763 ESIA Report Mini Hydro Power Plant 2x4 MW
in Sigulok, North Sumatera, Indonesia PT Aek Sibundong Energi
193