Professional Documents
Culture Documents
Group4 HW Chap 11
Group4 HW Chap 11
Name:
Problem 2:
C: 2/3 x 30/20= 1
The more the critical ratio is away from 1, the more the activity is away from the target.
Hence, for A, the reason for high critical ratio is that the budgeted cost is considerably higher than the
actual cost.
For D, budgeted cost is less than the actual incurred cost, the reason behind the critical ratio less than 1.
For E, the Actual Progress in terms of number of days is quite less than the scheduled progress.
Problem 3:
Estimate the time and the actual ratio by using the formular
While the ratio is greater than 1, the progess of project is good. And the progress of project is bad while
the ratio is less than 1.
The result of activity A and E is less than 1, it will be later than the schedule time.
The result of activity D is over 1.00, so it is earlier than the schedule time.
Problem 6:
Problem 8:
Activity 3-5 is 70%, so as per the budgeted cost, cost of activity 3-5 should be:
Budgeted cost for activity 3-5 for 70% completion = 405x70% = 283.50
= 400-283.50
= 116.50
By 40th day, activity 3-5 is 70% complete. So total time it should take would be
Actually, it has taken 40 days. Therefore, underage for days is 42.60-40 = 2.60 days
Problem 10:
The total budget of the project = Sum of budget for each 900+1200+1200+1800+1400+1500+800 =
$8800 activity =
Current week = 24
Earned value = Sum of %complete * budget of each activity = 100%*900 + 100%*1200 + 100%*1200 +
100%*1800 + 100%*1400 + 40%*1500 + 0%*800 = 900+1200+1200+1800+1400+600+0 = $7100
Since, Critical ratio > 1, the project is under control. Comment >