Professional Documents
Culture Documents
Hydrology and Sediment
Hydrology and Sediment
Hydrology and Sediment
CHAPTER 2
HYDROLOGY AND SEDIMENT
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Table of Contents
I
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
The dam site is approximately 2200m above sea level in elevation. Ninety
percent of the drainage area is above El.3000m, and only 10% of the drainage
area is between El.2000m and El.3000m. Please refer to Figure 2.1 for the river
system.
2-1
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
The gauging stations located on the Kunhar River are constructed, operated and
managed by the Surface Water Hydrological Project (SWHP) of WAPDA. At this
stage, the flow and sediment data have been collected at Naran, Khanian and
Garhi Habibullah stations. Naran station is located 13km upstream from dam site;
Khanian and Garhi Habibullah stations are located about 16km and 80km
downstream from the dam site respectively. All the 3 stations are sited on
2-2
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
relatively flat parts of the river and the river courses there are generally straight.
Staff gauges are equipped in all the 3 stations, and they are observed hourly
during the flood season. At other time of the year, they are observed every 4
hours from 08:00 to 16:00 in one day. The data sources are shown in details in
Table 2.2-1.
Flow gauges and climate stations are sited by SK Hydro at the dam site in 2006,
but the data series are too short to be used in design. Data obtained at Garhi
Habibullaj gauge station are not used in design because it is far from the site
dam and the topographical condition there is quite different from that in the river
basin upstream from the dam site. Thus, the design is done based on data
observed at Naran and Khanian stations.
2.2.2 Rainfall
Rainfall data recorded in the major rainfall stations in and close to the drainage
area are shown in Table 2.2-2。
Elevation
Station Period Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Tot
(m)
Naran 2363 1962-2010 196 223 269 229 163 69 76 60 60 85 65 121 1616
2.3 Climate
In general, the climate of the Suki Kinari project area is governed by two wind
systems. One is the monsoon which persists during the summer months of June
2-3
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
to September; and the second system includes the Easterly and Westerlies Belts
which dominate the winter months of November to March. Spring and autumn
months are transition periods.
The rainfall data observed at Naran Meteorological Station shows the annual
mean rainfall near the dam site is 1,616mm, with uneven distribution over the
year. The maximum rainfall occurs in March at 269mm; while the minimum
2-4
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2.4 Runoff
The runoff pattern in the Khunar River is dominated by the effects of snowmelt,
with the peak flows occurring in June or July.
The daily mean flow data observed at Naran Station 13km upstream from the
dam site between 1960 and 2009 give the mean annual flow is 46.9m3/s
(equivalent to the mean annual runoff at 1480 Mm 3), and the runoff depth is
1421mm. The annual average runoff does not vary significantly from year to year,
ranging from the minimum of 30.6m3/s in 2007 to the maximum of 63.5m3/s in
1992, and the extremes ratio between the maximum and the minimum is 2.07.
The monthly average runoff at Naran station is shown in Figure 2.4-1, and the
curve of the safety ratio of ten-day average runoff at Naran station is shown in
Figure 2.4-2. Almost 90% of the annual runoff occurs from April to October and
2-5
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-6
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-7
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-8
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Table 2.4-2 Ten-day Flow at Suki Kinari Dam Site In: m3/s
Year Month 1 2 3 4 5 6 7 8 9 10 11 12
First ten days 19.4 17.3 18.6 25.1 47.3 176.7 221.4 99.3 54.6 27.1 17.8 15.4
1960 Middle ten days 18.8 16.5 21.5 28.7 84.3 157.5 174.6 87.7 44.0 22.6 17.3 14.7
Last ten days 17.5 16.6 23.4 30.1 110.7 179.9 131.2 73.0 35.6 19.4 15.4 15.6
First ten days 14.4 14.6 13.1 15.6 34.3 166.9 199.5 106.5 59.1 30.7 16.0 15.4
1961 Middle ten days 14.7 15.1 13.5 17.3 52.9 196.2 179.9 74.4 48.0 24.3 15.2 15.4
Last ten days 14.5 15.1 14.7 24.2 74.0 176.4 151.7 75.8 44.1 19.5 15.6 15.2
First ten days 17.0 12.4 10.2 14.9 58.5 139.7 183.5 117.5 49.2 26.2 14.7 14.3
1962 Middle ten days 16.7 12.6 10.4 20.9 58.1 166.8 151.4 82.5 42.5 21.2 15.1 13.8
Last ten days 14.7 10.4 12.5 41.5 92.8 197.5 184.8 63.3 34.8 17.9 14.3 13.9
First ten days 13.2 9.8 11.1 16.7 66.2 180.7 184.2 104.3 52.9 22.9 16.5 16.3
1963 Middle ten days 12.4 10.2 13.1 31.9 58.6 192.9 170.5 90.8 35.9 20.9 16.3 16.5
Last ten days 10.7 11.1 16.1 32.9 96.1 191.8 125.3 66.8 26.8 18.9 16.3 16.5
First ten days 14.3 7.1 12.2 19.9 75.9 113.4 314.8 150.3 71.4 31.6 19.2 14.0
1964 Middle ten days 11.0 9.4 14.2 26.2 124.0 189.0 221.8 133.1 55.5 26.9 15.1 14.6
Last ten days 8.5 11.7 14.9 37.4 94.5 250.2 175.9 98.3 38.0 20.6 14.0 13.4
First ten days 13.0 12.5 10.2 11.7 46.2 210.7 297.4 152.5 74.5 34.9 17.8 14.7
1965 Middle ten days 13.3 12.4 11.0 15.4 83.2 290.8 308.2 110.6 54.6 26.9 17.5 13.1
Last ten days 12.5 13.0 11.9 15.3 119.5 340.2 267.6 99.0 41.4 23.0 16.6 12.7
First ten days 12.6 10.5 10.8 21.7 55.5 179.6 178.2 146.3 76.5 30.0 19.3 14.0
1966 Middle ten days 12.1 10.6 11.5 28.0 61.2 326.2 203.8 107.7 55.2 28.1 15.6 13.0
Last ten days 11.1 10.7 12.0 33.2 103.3 407.4 207.4 80.2 37.1 24.0 14.2 12.0
First ten days 12.2 9.1 16.4 13.9 48.8 188.1 290.8 151.2 53.0 32.7 18.1 12.2
1967 Middle ten days 12.6 12.3 13.2 19.4 91.4 203.9 215.2 123.9 50.5 27.0 15.9 11.7
Last ten days 11.7 12.0 13.4 48.4 124.2 279.0 191.9 70.9 38.5 22.8 13.1 11.2
2-9
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Year Month 1 2 3 4 5 6 7 8 9 10 11 12
First ten days 11.0 9.1 13.0 16.5 55.1 187.2 255.6 153.6 55.3 32.0 22.0 16.9
1968 Middle ten days 9.8 10.9 14.1 22.2 59.3 252.8 200.8 118.7 52.8 25.7 18.3 17.4
Last ten days 9.1 12.7 13.4 53.4 110.2 263.3 150.3 71.2 44.9 21.8 17.0 16.7
First ten days 17.0 17.5 15.8 40.2 70.8 207.5 275.2 175.6 56.3 29.1 25.3 19.0
1969 Middle ten days 16.8 13.3 19.0 38.6 106.8 272.2 276.4 124.1 44.2 27.3 21.7 16.0
Last ten days 14.4 15.2 32.1 36.9 133.9 271.5 221.6 67.4 33.5 24.4 19.8 15.2
First ten days 15.4 16.8 16.4 28.5 68.6 209.8 147.2 80.4 66.5 26.2 19.7 15.5
1970 Middle ten days 15.5 16.7 16.3 39.6 141.0 162.6 107.5 77.3 45.2 24.3 18.0 14.9
Last ten days 16.8 16.6 17.3 72.1 189.1 182.9 73.6 78.2 28.2 24.3 15.5 14.5
First ten days 14.6 12.4 16.7 38.8 63.7 201.2 88.5 78.5 39.6 18.5 13.8 12.2
1971 Middle ten days 14.1 12.8 17.2 41.2 78.0 147.4 83.0 55.5 27.2 15.6 12.8 12.1
Last ten days 13.3 11.2 24.4 60.4 169.4 126.5 83.4 55.9 25.1 14.1 12.1 12.2
First ten days 11.5 12.8 14.7 18.4 42.4 204.3 264.6 129.6 65.1 29.2 21.8 17.6
1972 Middle ten days 10.9 12.9 16.3 22.1 83.1 418.8 218.3 85.0 48.2 26.7 19.3 17.3
Last ten days 12.8 13.6 17.9 31.1 151.1 404.5 188.5 79.6 34.8 23.5 18.9 17.1
First ten days 17.3 17.3 16.6 43.0 151.9 293.1 242.3 98.6 55.9 28.1 18.0 13.4
1973 Middle ten days 16.1 17.4 16.1 54.2 160.5 321.6 172.8 77.5 45.2 24.1 15.5 14.1
Last ten days 18.0 17.7 24.1 94.2 199.7 295.4 122.0 58.1 37.7 20.8 14.6 14.5
First ten days 14.0 12.6 17.0 23.7 79.2 119.2 155.0 89.7 36.3 22.4 15.8 12.1
1974 Middle ten days 13.9 12.3 18.4 37.0 76.7 191.4 169.6 65.3 28.8 20.4 14.8 12.1
Last ten days 13.5 12.9 20.8 52.8 84.1 128.7 127.6 51.9 27.1 17.6 12.9 12.3
First ten days 12.3 11.5 12.7 16.8 81.2 196.1 144.6 100.1 57.3 25.4 18.1 15.4
1975 Middle ten days 12.0 11.6 13.7 21.7 112.8 219.4 171.5 95.5 46.6 23.2 17.0 16.1
Last ten days 11.7 12.1 15.0 38.8 184.9 154.5 103.0 64.9 31.5 20.2 17.8 15.2
First ten days 14.7 13.4 13.0 14.4 56.2 184.1 197.0 125.0 56.1 29.2 20.8 21.4
2-10
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Year Month 1 2 3 4 5 6 7 8 9 10 11 12
1976 Middle ten days 14.0 12.4 13.6 17.7 109.0 176.7 185.9 81.7 45.2 25.1 16.0 18.1
Last ten days 14.0 13.2 13.4 36.9 140.5 132.7 128.5 62.5 37.3 23.5 20.9 15.2
First ten days 14.1 15.7 10.3 32.9 43.2 146.1 181.6 66.8 44.4 24.2 21.3 14.6
1977 Middle ten days 16.0 13.6 15.6 44.4 79.6 123.7 157.2 66.2 36.7 20.5 18.2 16.9
Last ten days 17.0 12.0 23.3 36.2 132.1 216.1 90.6 58.2 30.7 23.6 16.8 14.3
First ten days 13.2 12.5 10.8 17.8 79.6 209.7 215.7 94.8 38.4 28.0 21.4 15.4
1978 Middle ten days 15.6 11.4 12.2 12.2 117.2 223.9 127.0 71.9 26.6 22.5 20.1 16.9
Last ten days 14.5 11.2 15.4 51.4 159.4 267.2 111.7 57.0 26.7 18.2 18.6 19.1
First ten days 17.0 11.6 24.2 27.0 71.4 99.7 266.5 108.5 48.1 26.9 16.5 22.1
1979 Middle ten days 15.1 10.3 16.2 40.8 78.6 228.0 240.8 79.9 38.8 22.8 16.2 20.0
Last ten days 13.9 8.9 18.5 59.5 69.2 323.3 148.7 59.9 31.1 19.4 17.2 20.0
First ten days 19.4 13.0 11.5 24.9 86.7 247.5 201.4 99.7 46.6 27.7 21.9 23.9
1980 Middle ten days 16.9 12.4 10.6 42.7 109.9 244.3 162.4 74.2 37.7 28.8 16.9 21.1
Last ten days 15.2 12.2 14.3 67.9 157.1 233.6 131.6 53.7 31.9 26.1 11.3 17.4
First ten days 15.3 10.8 6.3 20.7 107.4 196.1 168.0 116.8 26.2 24.7 16.0 21.6
1981 Middle ten days 14.9 9.3 7.8 39.8 193.6 197.1 147.3 69.0 26.8 21.4 15.2 19.7
Last ten days 13.3 7.5 12.9 67.2 233.8 205.3 121.4 36.1 27.1 18.5 11.5 17.5
First ten days 15.1 7.5 12.0 16.9 41.8 130.7 182.2 100.7 34.5 21.9 20.1 21.8
1982 Middle ten days 11.6 7.0 12.4 19.4 68.6 173.5 129.3 62.3 28.4 19.6 19.8 19.8
Last ten days 7.9 8.9 14.9 28.5 79.2 181.7 126.3 42.6 24.8 18.7 18.4 17.4
First ten days 14.9 12.7 11.9 14.2 32.0 115.4 201.9 166.3 70.3 26.7 18.2 20.6
1983 Middle ten days 13.6 12.5 11.7 17.8 42.0 221.5 146.4 111.0 50.5 22.7 18.6 20.4
Last ten days 13.0 12.3 13.5 24.6 77.4 221.9 197.2 99.6 33.5 21.6 19.6 20.4
First ten days 20.0 18.2 16.6 17.0 50.5 271.6 103.8 72.4 43.6 19.6 14.0 11.2
1984 Middle ten days 19.0 15.0 17.0 18.5 76.2 255.8 96.0 64.4 33.6 17.6 12.3 11.0
2-11
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Year Month 1 2 3 4 5 6 7 8 9 10 11 12
Last ten days 18.4 14.6 16.4 37.6 155.5 146.2 86.6 45.5 25.6 15.5 11.7 10.9
First ten days 10.9 11.1 11.2 24.0 53.6 140.6 99.5 94.0 32.0 27.6 16.2 12.2
1985 Middle ten days 10.7 11.0 13.2 38.0 72.2 102.1 105.1 64.8 30.2 24.1 14.4 11.2
Last ten days 10.8 10.9 16.4 49.6 103.3 75.9 87.4 47.4 26.6 17.8 13.3 10.8
First ten days 10.6 10.9 10.7 11.7 64.1 88.7 318.7 151.6 59.4 32.0 20.0 14.9
1986 Middle ten days 10.7 10.9 11.8 22.0 85.2 186.6 226.8 120.3 49.5 24.7 16.2 14.4
Last ten days 10.8 10.8 10.4 38.5 91.0 399.2 197.4 79.9 41.4 22.8 15.1 13.9
First ten days 13.3 12.9 12.2 14.6 40.4 158.0 206.9 151.0 84.8 26.7 19.5 13.3
1987 Middle ten days 13.0 12.6 12.9 17.8 55.0 158.0 164.3 129.7 55.1 30.9 16.5 11.3
Last ten days 12.9 12.5 13.9 31.7 95.6 171.1 187.9 111.1 45.9 22.6 16.1 10.6
First ten days 9.4 7.1 6.6 25.0 84.1 209.6 226.4 81.4 33.8 18.1 13.8 11.5
1988 Middle ten days 8.2 6.7 6.8 53.4 125.7 184.1 159.8 59.5 28.8 17.3 13.8 11.1
Last ten days 7.8 6.7 10.8 72.9 171.6 225.7 122.8 44.0 22.4 15.2 12.1 10.7
First ten days 11.5 11.5 13.6 23.9 43.6 343.0 169.8 138.2 51.2 30.1 22.2 15.4
1989 Middle ten days 11.5 11.7 16.9 28.8 81.3 210.2 141.4 94.7 45.8 29.6 17.0 13.8
Last ten days 11.4 11.8 17.7 29.9 157.8 190.9 158.8 72.2 36.4 24.7 17.2 13.1
First ten days 12.2 10.2 7.6 11.4 116.5 172.9 181.2 113.4 53.4 26.6 25.9 11.7
1990 Middle ten days 12.1 9.1 10.0 24.3 242.9 204.0 157.8 76.0 46.2 22.3 21.0 9.9
Last ten days 13.2 8.2 11.9 35.7 218.0 221.8 130.4 59.9 45.8 20.2 15.6 7.1
First ten days 6.5 4.6 3.9 16.8 55.9 220.9 252.5 185.3 90.9 35.7 25.5 19.0
1991 Middle ten days 6.2 3.8 4.3 45.3 72.5 255.6 270.1 163.7 59.2 30.1 24.2 17.7
Last ten days 5.5 3.7 4.7 43.4 137.9 279.4 198.1 128.1 50.5 27.3 19.5 16.5
First ten days 15.7 12.3 12.4 16.8 28.2 219.3 300.2 160.1 157.9 51.2 27.6 20.8
1992 Middle ten days 14.5 11.8 12.8 18.9 79.8 282.1 256.9 137.2 68.2 45.7 23.8 18.5
Last ten days 13.5 12.6 16.2 21.2 161.7 314.1 198.5 99.6 54.4 35.1 23.4 17.3
2-12
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Year Month 1 2 3 4 5 6 7 8 9 10 11 12
First ten days 15.7 13.3 9.6 5.2 47.6 267.8 252.6 87.8 51.8 41.9 31.0 20.4
1993 Middle ten days 14.6 12.6 6.2 8.6 115.3 254.6 182.7 77.4 41.5 53.8 27.2 17.6
Last ten days 13.7 12.4 5.2 26.7 185.6 217.8 143.8 59.6 34.2 46.4 23.7 15.5
First ten days 21.2 19.7 18.9 25.8 75.0 121.1 272.0 104.9 58.6 36.0 25.6 23.2
1994 Middle ten days 20.5 19.8 18.6 44.8 93.4 152.0 259.9 79.3 55.1 30.1 24.6 22.7
Last ten days 20.0 19.2 19.0 55.1 105.2 195.8 158.0 65.0 40.7 27.0 24.0 22.0
First ten days 22.3 15.7 11.6 12.8 70.7 153.0 216.7 119.5 56.6 32.2 18.9 14.2
1995 Middle ten days 20.1 13.0 11.1 24.3 104.8 248.6 211.4 98.9 44.2 26.2 13.1 18.9
Last ten days 18.6 12.1 10.6 39.2 90.7 175.3 200.1 72.6 36.9 24.8 10.4 15.3
First ten days 12.8 9.5 7.1 7.5 62.6 237.9 258.2 183.5 75.7 37.0 25.3 21.2
1996 Middle ten days 11.2 8.3 6.4 21.4 90.6 321.6 240.7 143.6 43.8 31.1 24.6 19.5
Last ten days 10.5 7.5 5.4 35.1 129.7 304.3 199.5 92.2 33.9 28.6 22.8 16.2
First ten days 14.4 13.3 11.2 8.2 33.5 107.5 127.5 60.5 31.1 24.4 18.7 12.1
1997 Middle ten days 13.2 12.8 9.6 8.2 40.3 160.7 133.8 44.9 26.6 20.8 15.8 10.2
Last ten days 12.7 12.0 8.8 21.1 94.7 191.9 119.4 51.2 24.4 19.6 13.6 8.5
First ten days 7.3 4.6 3.7 3.0 21.1 117.4 157.7 84.8 40.1 22.8 17.6 14.3
1998 Middle ten days 6.1 4.1 3.4 4.1 46.6 111.2 160.2 66.9 30.0 20.3 16.8 14.5
Last ten days 5.1 3.7 3.0 11.0 122.0 125.0 113.2 52.7 26.3 18.3 14.6 13.8
First ten days 13.0 9.3 6.2 6.2 113.0 235.8 146.7 60.3 50.7 28.2 22.6 15.8
1999 Middle ten days 11.8 7.7 5.3 19.0 222.8 242.7 106.0 51.9 40.3 25.9 20.9 13.7
Last ten days 10.7 7.2 4.5 64.4 249.7 214.9 73.7 51.3 33.9 25.1 17.8 11.6
First ten days 10.6 11.3 10.0 20.3 144.6 150.2 119.2 91.8 50.0 29.5 23.4 17.4
2000 Middle ten days 11.1 11.1 9.9 61.5 226.1 176.0 122.2 80.4 38.6 32.5 21.4 16.6
Last ten days 10.6 10.5 13.0 80.0 184.8 153.6 108.4 78.3 41.8 28.5 18.8 15.2
First ten days 15.5 14.8 14.3 32.1 86.0 95.1 68.7 44.2 35.5 22.5 17.8 17.4
2-13
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Year Month 1 2 3 4 5 6 7 8 9 10 11 12
2001 Middle ten days 15.8 14.8 15.4 42.2 122.2 96.9 70.0 41.6 32.0 20.4 18.4 17.2
Last ten days 15.0 15.5 29.1 56.7 104.3 74.2 59.3 38.0 24.2 18.0 17.9 17.4
First ten days 15.4 11.2 8.2 36.1 73.2 197.1 135.2 68.7 43.2 25.9 18.1 16.3
2002 Middle ten days 13.6 10.0 8.3 61.3 104.9 202.7 98.0 65.8 31.4 22.7 18.4 14.9
Last ten days 12.2 9.3 19.2 75.1 188.4 182.5 88.8 60.2 25.7 18.6 18.5 17.1
First ten days 16.5 11.1 8.7 9.1 22.6 189.8 207.9 100.7 54.6 28.3 21.5 13.3
2003 Middle ten days 13.4 9.4 8.9 13.8 35.0 230.9 172.4 80.2 47.7 24.8 18.1 11.9
Last ten days 12.5 8.5 8.6 17.3 51.3 238.8 140.8 64.1 37.1 23.5 15.0 11.2
First ten days 10.3 7.6 5.8 8.1 52.7 95.4 107.6 78.3 44.6 22.9 16.0 13.0
2004 Middle ten days 9.2 7.4 5.1 24.2 71.9 144.1 114.7 63.0 35.4 20.2 14.4 12.0
Last ten days 8.5 6.3 4.8 34.5 77.0 128.1 96.1 59.9 31.2 19.3 13.9 10.8
First ten days 12.6 9.4 6.6 7.4 50.9 149.4 223.6 118.8 55.7 57.8 40.4 25.7
2005 Middle ten days 15.9 6.2 8.0 6.9 62.4 205.3 227.5 103.7 59.8 53.7 34.2 24.8
Last ten days 13.4 5.5 7.8 20.5 96.5 206.6 158.4 79.0 52.3 45.3 27.7 23.0
First ten days 21.3 13.2 10.0 7.0 30.2 65.2 152.1 87.6 47.4 26.5 14.5 10.5
2006 Middle ten days 20.0 11.0 8.6 7.0 25.6 100.1 149.0 70.9 40.9 21.1 13.8 8.6
Last ten days 16.2 10.9 7.7 10.6 35.3 156.2 100.8 56.8 32.0 16.5 13.1 7.5
First ten days 6.2 3.4 3.2 13.2 112.1 117.5 170.5 118.4 67.4 45.6 23.7 17.4
2007 Middle ten days 5.0 2.4 8.5 17.7 165.0 181.6 153.2 107.8 59.6 36.4 20.5 15.5
Last ten days 3.9 1.7 10.2 21.0 127.7 219.2 138.8 95.1 54.1 28.5 21.2 13.3
First ten days 12.7 5.4 4.7 17.2 97.7 196.3 132.4 86.2 58.6 35.3 19.6 16.2
2008 Middle ten days 10.5 5.4 5.8 31.4 121.8 210.8 127.0 72.7 52.3 28.9 16.9 14.2
Last ten days 8.8 5.1 7.4 61.6 158.5 163.5 97.0 74.4 44.9 24.2 13.9 12.7
2-14
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-15
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
upstream gauging station. In the Feasibility Study Report, the runoff series at
Khanian station is extended using daily runoff data, and the mean annual
discharge at dam site calculated to be 60.3m3/s, which is basically the same
(only 1% difference) as the result in this report.
The average runoff depth in the drainage area between Naran and Khanian
stations is observed to be 1733mm during the period 1960-1968, which is higher
than the runoff depth of 1504mm observed at Naran station. If area ratio method
is taken to calculate the flow at dam site on the basis of that at Naran station, the
result might be smaller. In this report, the calculation is more accurate, and the
annual average flow at dam site is 60.9m3/s.
2.5 Flood
2-16
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
in the observation at Naran station in the flood event in 1992. As a result, the
value of the design flood calculated based on flood peaks observed at Naran
station in period of 1960-2008 might be smaller than the real one.
As for the 10000-year flood, the sampling error of 10000-year flood is 24.76%,
which is over 20%. As a result, the calculated 10000-year flood discharge is
increased by 20% to 1963m3/s, which is smaller than the result recommended
result in 2012 the study in 2012. Therefore, the 10000-year flood discharge
recommended in the 2012 study is adopted in this study.
Table 2.5-1 Design Flood at Dam Site in 2012 Study In: m3/s
Results from
Results from Regional Results
Return period (year)
Statistics method comprehensive recommended
method
5 362 390 390
10 431 460 460
50 932 820 820
100 1145 980 980
1000 1845 1510 1510
10000 2545 2030 2030
2-17
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-18
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-19
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
5 498
10 587
50 1047
100 1251
1000 1928
10000 2592
2.6 Sediment
The natural river channel in the reservoir area is 35 to 40m wide, with the
riverbed gradient of 1.3%. The reservoir area is 3,040m long, and it narrows from
280m wide near dam site to 200m wide at about 1,800m upstream of the dam,
and further to 50m wide at the upper end of the reservoir. The total reservoir
storage is 9.07 million m3 with the normal pool level at El.2,275m. The dead
storage is 4.44 million m3 with the minimum operating water level at El.2,265m.
The intake gate of power station is located in the left bank. The sand sill
upstream from the intake has its crest at El.2,254m, which is 10m higher than the
invert of bottom outlet in the dam. A 185m long stilling basin is provided behind
the water intake, which is divided into two chambers, each having a wetted area
of about 200m2. The mean flow velocity in the chamber is 0.29m/s.
The study team of Pakistan had performed about 1,000 sampling of suspended
load at Naran Station from 1960 to 2005, and concluded that the content of
suspended load was relative to the landslide and river bank erosion, but not
closely related to the amount of discharge in the river. Landslide generally
happens in heavy rain; however, earthquake and thawing could also trigger
landslide. For example, it is observed that the content of suspended load is only
0.055kg/m3 when the flow is 400m3/s (5-year flood); but that content is up to
1.5kg/m3 when the flow is only 19m3/s. It is shown in Figure 2.6-1 the
relationship between flow and sediment content.
The suspended load is usually estimated using the relationship between daily
2-20
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
content of suspended load and daily discharge, which is established on the basis
of long-term sampling and testing. Since the daily discharge is not closely
related to the daily sediment content for this river, the monthly average content
of suspended load during the period of 1960-2005 is derived using the
relationship between monthly sediment content and monthly discharge, which is
established during the sediment sampling. It is estimated the mean annual
suspended load at dam site is 342,000t.
Sampling of bed load was made from May 25, 2011 to June 15, 2011. On the
basis of bed load sampling and analysis of previous data, the ratio between bed
load and suspended load is estimated to be 25%. In this way, the mean annual
bed load is 85,500t, and the mean annual sediment load at dam site is 427,500t.
The discharge of Kunhar River and sediment load at dam site is presented in
Table 2.6-1.
In terms of gradation of sand samples, the grain size of suspended load varies
between 0.01mm to 5mm, with D50 at about 0.02mm.The grain size of bed load
varies between 0.1mm to 10mm, with D50 at about 1mm. The gradation of
suspended load is shown in Figure 2.6-2.
2-21
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-22
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
The size of grain primarily falls in the range of 0.5-1mm. The bed load consists of
65% of quartz (of which 85% is simple quartz and 15% is compound quartz),
15% of feldspar (including common feldspar and plagioclase), and 20% of rock
debris (including limestone, silica, gneiss, schist, firestone, etc.).
The Feasibility Study Report in 2008 provides the relation curve between water
level and discharge under the dam and at tailrace of the power station, as shown
in Table 2.7-1.
Table 2.7-1 Stage-Discharge Relation Under Dam and at Tailrace of the Power
Station
Stage-Discharge Relation Stage-Discharge
Immediately D/S from Dam Relation at Tailrace of Plant
H(m) Q(m3/s) H(m) Q(m3/s)
2233.60 150 1346.00 250
2234.65 374 1347.76 500
2235.07 500 1350.62 1000
2236.30 1000 1351.76 1230
2238.39 2100 1353.01 1500
2239.76 3000 1355.08 2000
2240.30 3777 1358.54 3000
1363.16 4656
Considering that Suki Kinari reservoir has a relatively small live storage, an
automatic hydrological telemetry and forecast system should be provided to
protect the project from flood risk, make better advantage of water resources,
optimize project operation, and enhance the benefits of the project. The system
collects, transmits, and processes the rainfall and temperature data in Kunhar
River basin; then the system performs flow yielding analysis, formulates a flood
forecast, and performs flood routing analysis. Then the system provides
recommendations of project operation according to the hydrological conditions
at dam site.
It is planned to construct the system at a lower elevation in the drainage area in
order to make it easier for operation and maintenance of the system. It keeps the
system operating stably and reliably and being free from the disturbance of
extreme weather conditions and geological disasters.
There are some rainfall stations in the drainage basin, but it is not clear about
2-23
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
2-24
SUKI KINARI HYDROPOWER PROJECT
FEASIBILITY STUDY REPORT Chapter 2 Hydrology and Sediment
Printer Set 1
Air conditioning Set 2
Control and transmission equipment Set 17
Water level gauge Set 2
Rainfall instrument Set 15
Power supply Set 17
cabinet Set 17
Hydrologic monitoring cableway and
Set 1
flow meter
Auxiliary civil works Lot 1
2-25