PRELIMINARY
road.
State : - Jharkhand
Carriage width 16 m
OFFICE OF THE EXECUTIVE ENGINEER ADVANCE PLANNING FIELD SURVEY DIVISION ROAD CONSTRUCTION DEPARTMENT (RCD) .
page FSDDUMKA
CHAPTER - 1
1
INTRODUCTION
The Chief Engineer, Central Design Organisation , Road Construction Department , Jharkhand ,
Ranchi has ordered to prepare Detailed Project Report (DPR) for High Level Bridge
in 19th KM of Dumri-Nawadih-Phusro Road near I.B. replacing the old bridge in Bokaro District in the state of Jharkhand.
With HL bridge in order to provide better road communication to the road users throughout the
year. The TBM was fixed on the platform of bridge slab top of road .
All levels have been taken with reference to this TBM. The DPR has been
prepared by this Division on the basis of approved alignment , span arrangement and road level &
2
SUB SOIL EXPLORATION :
Geotechnical and soil survey investigation have been prepared by Soil Investigation Division,
Advance Planning, RCD, Ranchi and report is being given by letter no.49 (enc) dt.02/02/13. The bore
log data and soil test report is being attached with this DPR.
3 FOUNDATION PROPOSED
As per soil profile , Open foundation has been proposed to suit the site condition,
as soft rock strata has been found at the reasonable depths at all two locations
i.e two bores on bank and three bores in river bed where sub soil exploration was carried out.
The approved span arrangement is 2 x 16 m effective as per hydraulic details. The existing banks
of river at bridge site are firm & no erosion is there,hence the span arrangement of 2 x 16
m is suggested. It has been approved by SE, AP, Circle, Ranchi. The proposed bridge shall be of
2 lanes having carriage width of 11m with footpath. The overall width of slab shall be 16m.
page FSDDUMKA
5 SUBSTRUCTURE
All abutments , piers and cantilever return walls and cap are proposed in Reinforced cement
concrete (RCC) in grade M-30 . All sub structures shall be solid . Abutment and piers have been
6 SUPERSTRUCTURE
The RCC T - beam and slab of two lane having carriage width 11m with footpath in grade
M - 30 concrete is proposed . The standard drawing of MOSRT & H for super structure of 16 m
CHAPTER 2
2.1 INTRODUCTION
The following paragraph enlists the Detailed Design standards of the proposed Bridge.
(without footpath)
(without footpath)
For Bridges
Foundation M - 30
Approach Slab M - 30
Forces due to water current have been considered in design as per IRC 6: 2017
page FSDDUMKA
2.5 LONGITUDINAL FORCES
In design of the bridge , longitudinal forces are computed as per IRC 6: 2017 arising from any one
or more of followings :
Since bridge is not proposed on curve , centrifugal forces donot play any role in designing the
The proposed bridge designed to retain earth fills are proportional to withstand pressure
calculated in accordance with Coloumb's theory, subjected to modification that the centre of
pressure exerted by the backfill, when considered dry, is located at an elevation of 0.42 m of the
height of the wall above the base instead of 0.33 m of that height.
Since the proposed bridge lies in seismic zone II which requires cosideration of seismic forces as
per IRC 6: 2017. There fore its consideration in design has been made. Importance factor has
been taken as 1.5 for bridge on highway. Thus seismic co efficient 0.075 has been taken in design.
Temperature effects have been taken into consideration as per IRC 6: 2017.
page FSDDUMKA
2.10 BUOYANCY
100 % Buoyancy has been considered while checking stability of foundations. Pore pressure
upliftment limited to 15 % has been considered while checking stresses in sub structure
All members have been designed to sustain safely the most critical combination of various loads
and forces that co exists. Various load combinations as relevant with increase in permissible
stresses considered in the design as per IRC 6: 2017 has been taken.
IRC 5 : 1998
IRC 6 : 2017
IRC 78 : 2014
IRC SP : 13 2004
IRC SP : 54 : 2000
Standard drawings of MOSRT & H for 16 m effective span with footpath have been considered
Approach slab will be 3.5 m long on both sides . It will be 300 mm thick . It will be RCC in grade
M - 30 concrete. It will be laid over 150 mm thick leveling course in M -15 concrete.
page FSDDUMKA
2.15 APPROACH ROAD
The proposed bridge is on the downstream alignment and FRL of proposed bridge is at same level
In order to maintain traffic flow on the road , diversion road would be the existing bridge.
CHAPTER - 3
3.1 MATERIALS
Basic construction material with their lead from the source of supply has been tabulated below
3.2 LABOUR
Skilled and un skilled labours for carrying out different items of work involved in the construction
3.3 RATES
The basic schedule of rates for several items of works related to construction of bridge is
available in Current Schedule of Rates for NHSOR, Jharkhand. These rates are effective from
3.4 MISCELLANEOUS
To meet the expenditure to be incurred on the unforseen items during execution of works 1%
page FSDDUMKA
3.5 QUALITY ASSURANCE / QUALITY CONTROL
To achieve high quality in works at site , a Quality Policy must be decided by Road Construction
Department in light of IRC 57 & 47 and effective monitoring there of is required at top level.
Quality, professional and capable contractor will be much helpful in achieving quality work.
Srengthening and modernisation of the existing quality system of the department has been quite
essential. Training to the lab staffs and Field officers / contractors are also essential to make
them consicous about quality. There after high quality in the field may be assured . For carrying
Site laboratory fully equipped and functional as MOSRT & H (4th edition) with graduate material
Engineer and adequate number of technical staffs to carry out routine tests as per MOSRT &H (4th
edition) for contractor must be essential to achieve quality work. Q-3 level of quality is proposed
3.6 SPECIFICATION
The complete work shall be executed strictly in accordance with " Specification for Road &
DPR has been prepared in accordance with check lists issued by Chief Engineer , Central Design
Organisation, Road Construction Department, Ranchi, Jharkhand vide his letter no. 400 (encl.)
page FSDDUMKA
CHECK LIST OF THE ITEMS TO BE SUBMITTED ALONG WITH DPR OF BRIDGE PROJECT
SL. TICK MARK
NO. ITEMS SUBMITTED
1.0
PROJECT 1.1 Introductory I Name of the Scheme
REPORT Report II Authority and Plan provision
III Location of the bridge
(i) Name of the state,district &nearest town
Village
(ii) Name of the road and chainage of the
bridge site
(iii) Name of the river
IV Necessity of the bridge
V Geographical feature of the area
VI Measurable and nonmeasurable benefits
2.0 SITE 2.1 Site I Report on identification of alternative bridge
selection site,alignments with their merits,demerits
and probable cost.
II Alignment approved by the concerned S.E.
should be submitted along with DPR
2.2Details of I Description with sketches showing relevant
Existing bridge dimensions
/causeway II If Causeway
(i) Length and Depth of submergence
(ii) No. and size of vent
(iii) Frequency of interruption to Traffic
III If Bridge
(i) No. and length of span
(ii) Clear waterway
(iii) Silted up span if any
(iv) Sign of undue scour in foundation and
bank,observed scour if any
(v) Type of bank:erodible/firm
(vi) Type of construction:steel/Concrete
(vii) Rly. Bridge if any mentioning approx.
distance
(viii) Plane table sheet of site showing existing
Bridges if any, proposed bridge, nature of
river,exst. Approach road if any
4.4.Design of Bearing
4.5.Design of approach Slab
4.6.Design of Protective work if required
4.7.Design of high approach embankment if required
4.8.Design of pavement in approaches
4.9Design of horizontal and vertical alignment of approaches
5. Detailed Estimate
5.1 Quantity and Cost estimates
(i) Preparatory works
(ii) Foundations
(iii) Substructure
(iv) Superstructure
(v) Protective work
(vi) Miscellaneous items
(vii) Sub estimate for approaches
(viii) Provision of centage charges like quality
control, contingencies etc.
(ix) Sub estimate for Diversion
5.2.Rates
(i) Schedule of Rates(mention year and name
5.3.Quarry /Material
Source/Lead charts(duly
approved by concerned
S.E.)
6.Detailed Working Drawing and Maps
(i) Index Map
(ii) Contour Plan
(iii) Site Plan
(iv) Catchment Area Map
(v) Longitudinal Section of the Stream
(vi) At least three cross section of the river
(vii) Bore Log Data
(viii) A General Arrangement Drawing of the
bridge superimposed on the cross section
of the river at the proposed site also
indicating the Bore Details
(ix) Detailed Drawing of substructure and
foundation
(x) Bar Bending schedule
(xi) Details of protective work drawn to a
suitable scale
(xii) Drawing of miscellaneous items like
bearings, expansion joints, wearing coat,
Railing , approach slab etc.
(xiii) Details of existing bridge if any
(xiv) Land Acquisition Plan if any (show the area
of land required)
(xv) Strip plan showing the location of
site,trees,ROW,& Road junction if any
(xvi) Plan ,Longitudinal and cross section of
approach road
(xvi) Detailed Drawing of CD works if any
II
REPORT
APPROACH ROAD
abstract of cost
analysis of rates
details of quantities
design of abutment
hudraulics of nala
sub surface exploration report
GENERAL ABSTRACT OF COST
INDEX
7
Providing PCC/RCC mechanically mixed concrete in abutment
cap,pier cap ,crash barrier etc., with graded stone aggregate
20mm nominal size and clean coarse sand of FM 2 and above ,
well screened, free from all dirt ,dust shellsand other deleterious
materials,including cost of all materials form work
,labour,handling material at site, centering and
shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and
needle vibrater, curing cost of water with all leads and lifts,all
taxes and royalties,incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as per design/drawing and
technical specification and MORT&H specification clauses and
other relevant clauses and direction of E/I(excluding cost of
reinforcement and it's cutting ,bending ,binding etc.)
M30
98.35 m3 x @ 6599.55 Per m3 649095.01657056
8 Providing HYSD bars in all types of RCC works in
abutment,return wall ,pier shaft, abutment cap, pier capincluding
cutting to sizes,bending,binding,placing in position on cement
cubeswith cost of all materials,labour,tools and plants,all
taxes,handling materials at siteand incidental charges,all
complete job as per design/drawing and technical specification
and MORT&H specifications clauses and other relevant clauses
and direction of E/I
M35
TOTAL CONCRETE IN SUPERSTRUCTURE
(excluding railing)
731.93 m3 x @ 6637.55 Per m3 4858250.2783416
11 Reinforced Cement Concrete Crash Barrier (Provision of an
Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed
with M-40 grade concrete with HYSD reinforcement conforming to
IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion
joints filled with pre-moulded asphalt filler board, keyed to the
structure on which it is built and installed as per design given in
the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing
and at locations directed by the Engineer, all as specified)
(I)ORDINARY SOIL
ABUTMENT A1 1.00 x 16.20 x 5.20 x 0.905 = 76.24
ABUTMENT A2 1.00 x 16.20 x 5.20 x 0.905 = 76.24
PIER P1 2.00 x 10.20 x 4.20 x 0.445 = 38.13
m3 Total 190.60
(II)WEATHERED ROCK
ABUTMENT A1 1.00 x 16.20 x 5.20 x 1.495 = 125.94
ABUTMENT A2 1.00 x 16.20 x 5.20 x 1.495 = 125.94
PIER P1 2.00 x 10.20 x 4.20 x 0.600 = 51.41
TOTAL 303.29
(III) HARD ROCK
ABUTMENT A1 1.00 x 16.20 x 5.20 x 0.600 = 50.54
ABUTMENT A2 1.00 x 16.20 x 5.20 x 0.600 = 50.54
PIER P1 2.00 x 10.20 x 4.20 x 0.600 = 51.41
Total 152.50
2 Providing and laying of P.C.C.M15 levelling course 100 mm thick in foundation
m3 Total 25.42
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
3 Providing PCC/RCC mechanically mixed concrete in Abutment foundation, Pier Foundation, Pile Cap
with graded stone aggregate 40mm nominal size and clean coarse sand of FM 2 and above , well
screened, free from all dirt ,dust shells and other deleterious materials,including cost of all materials form
work ,labour,handling material at site,centering and shuttering, screening, mixing in cement
mixer,placingin position,vibrating,hire and running charges of concrete mixer and needle vibrater, curing
cost of water with all leads and lifts,all taxes and royalties, incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other lubricants,pay ofmachinary staff , providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as perdesign/ drawing and technical specification and MORT&H specificationclauses and other
relevant clauses and direction of E/I(excluding cost of reinforcement and it's cutting ,bending ,binding etc.)
M30
ABUTMENT FOUNDATION
A1(OPEN) m3 2x 16.00 x 1.00 x 1.60 = 51.20
2x 16.00 x 2.30 x 1.10 = 80.96
2x 16.00 x 1.70 x 1.10 = 59.84
TOTAL 288.00
Providing HYSD bars in all types of RCC works in abutment Foundation, pier Foundation, Pier Cap, Pile
4 including cutting to sizes,bending,binding,placing in position on cement cubeswith cost of all
materials,labour,tools and plants,all taxes,handling materials at siteand incidental charges,all complete
job as per design/drawing and technical specification and MORT&H specifications clauses and other
relevant clauses and direction of E/I
PIER (AVG)
PIER STEM P1 m3 2 x 9.00 x 1.00 x 1.487 = 26.77
PIER NOSING m3 2 x area= 0.79 x 1.487 = 2.33
SOLID RETURN WALL(II) m3 4 x 2.30 x 5.705 x 0.300 15.75
TOTAL 87.63
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
6 Providing weep holes in PCC/RCC in abutment ,wing wall,return wallwith 100mm dia A.C. pipes ,collar
,M.S. clamps including cost of all materials and labour, ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation incidental charges,all taxes and
royalty etc.all complete job as per design/drawing and technical specification and MORT&H
specificationclauses and other relevant clauses and direction of E/I
No. 84
7
Providing PCC/RCC mechanically mixed concrete in abutment cap,pier cap ,crash barrier etc., with
graded stone aggregate 20mm nominal size and clean coarse sand of FM 2 and above , well screened,
free from all dirt ,dust shellsand other deleterious materials,including cost of all materials form work
,labour,handling material at site, centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater, curing cost of water with
all leads and lifts,all taxes and royalties,incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other lubricants,pay of machinary staff ,providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification clauses and other
relevant clauses and direction of E/I(excluding cost of reinforcement and it's cutting ,bending ,binding etc.)
(a)RCC M-30
ABUTMENT CAP
RECTANGULAR PART 2x 16.00 x 1.05 x 0.3 = 10.08
HAMMER HEAD
RECTANGULAR PART 2x 13.5 x 1.3 x 0.6 = 21.06
TRAPEZOIDAL PART 2x 11.25 x 1.3 x 1.10 = 32.175
Total 98.35
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
8
Providing HYSD bars in all types of RCC works in abutment,return wall ,pier shaft, abutment cap, pier
capincluding cutting to sizes,bending,binding,placing in position on cement cubeswith cost of all
materials,labour,tools and plants,all taxes,handling materials at siteand incidental charges,all complete
job as per design/drawing and technical specification and MORT&H specifications clauses and other
relevant clauses and direction of E/I
M35
TOTAL CONCRETE IN SUPERSTRUCTURE m3 3.00 243.98 731.934
(excluding railing)
Total 731.93
11 Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and medians, constructed with M-40 grade
concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and
installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24
June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as
specified) M40
Crash Barrier
m 3x 24.6 X 2 = 147.6
APPROACH SLAB m 2x 3.5 X 2 = 14
Total 161.60
12 Providing precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm,true to the line and
grade,tolerance of RCC vertical post not to exceed 1 in 500,centre to centre spacing between the vertical
post not to exceed 2000mm, leaving adequate space between vertical post for expansion,complete as per
approved drawing and Technical specification
m 3 x 24.6 X 2 = 147.6
m 2 x 3.5 x 2 = 14
APPROACH SLAB
Total 161.60
13 Providing and laying Reinforced cement concrete wearing coat M30 grade including reinforcement
complete as per drawing and Technical specification
Area(m2) Width(av.)
m3 Total 521.36
20 Providing filter media with stone metal grade-III conforming to MORT&HTable 400-7,free from grass,dirt
and debris and other loose and deleterious materials likely to deteriorate,,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation incidental charges,all taxes and
royalty etc.all complete job as per design/drawing and technical specification and MORT&H specification
clause 305 and other relevant clauses and direction of E/I
21 Providing , laying,fitting,fixing stone boulder pitching duly packed in slope of road embankment and
approach with approved quality of materials within 150m of worksite and all lift as per direction of E/I
including cost of all materials , labour
m3 2 x(2X 27.1 + 3.8 )x 0.6 = 69.60
Total 69.60
22 Providing and laying Filter material underneath pitching in slopes all complete as per drawing and
=
Technical specification m3 2 x(2X 27.1 + 3.8 x 0.15 17.40
23
CONFIRMATORY BORING m 4 20 = 80
24 Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered
concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ =
of 1 litre for 2 Sq.m. ) (Crash Barrier) m2 6 x 24.6 2.373 350.25
25 Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered
concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @
of 1 litre for 2 Sq.m. )(Hand rail) sqm 234 1.595 0.69 257.529
168 1.1 1.05 194.040
TOTAL 451.569
REINFORCEMENT QUANTITY
LENGTH WIDTH NO DIA OF BAR THICKNESS THICKNESS THICKNESS LENGTH OF BAR SPACING NO OF BAR WT PER M QUANTITY (KG)
AT TIP OF SHAFT AT BASE
ABUTMENT FOUNDATION
A1/A2, OPEN FOUNDATION
16.00 1.70
TOE 2 20 0.6 1.0 1.60 3.8 150 107 2.46 2004.46
2 12 0.6 1.0 1.60 17.8 150 11 0.89 347.49
2 10 0.6 1.0 2.54 4.21 200 80 0.62 414.87
2 10 0.6 1.0 17.00 200 16 0.62 335.23
16.00 2.30
HEEL 2 20 0.6 1.0 2.30 5.02 150 107 2.46 2647.97
2 12 0.6 1.0 2.30 17.8 150 15 0.89 473.85
2 10 0.6 1.0 1.60 3.8 200 80 0.62 374.66
2 10 0.6 1.0 17.0 200 17 0.62 356.18
(iii) Ordinary Rock(Rate Vide item no.12.1(II)B of NH S.O.R.) per m3 Rs. 75.63
(iv) Hard Rock Rate Vide item no.12.1(iv)A of NH S.O.R.) per m3 Rs. 388.81
(2) Providing steel liner 10mm thick ------------
Basic rate vide item no.12.22 of N.H.S.O.R. per MT Rs. 65376.96
Carriage of steel 1.05 x 359.30 Rs. 377.27
Rs. 66411.77
(3) Bored cast insitu M35 grade R.C.C. piles -----------
Basic rate vide item no.12.25 of N.H.S.O.R. per m Rs. 10568.64
Carriage of materials
cement 0.474 MT x Rs. 359.30 = Rs. 170.31
sand 0.51 m3 x Rs. 349.32 = Rs. 178.15
Metal 0.305 m3 x Rs. 487.61 = Rs. 148.72
chips 0.275 m3 x Rs. 459.72 = Rs. 126.42
Finished rate per m = Rs. 10003.69
(4) Providing and laying P.C.C. M15 Levelling course under the pile cap
Basic rate vide item no.12.39 of N.H.S.O.R. per m3 Rs. 3776.64
Carriage of materials
cement 0.275 MT x Rs. 359.30 = Rs. 98.81
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.54 m3 x Rs. 487.61 = Rs. 263.31
chips 0.36 m3 x Rs. 459.72 = Rs. 165.50
Finished rate per m3 = Rs. 4506.06
(7) Back filling behind the abutment, wing wall with Granular Material
Basic rate Vide item no.13.9 A of NH S.O.R. per m3 Rs. 524.16
Carriage of material
Moorum 1.2 m3 x Rs. 213.22 Rs. 255.86
Finished rate per m3 = Rs. 787.82
(8) Providing and laying of Filter media
Basic rate vide item no.13.10 of N.H.S.O.R. per m3 Rs. 1330.56
Carriage of material
Metal 1.2 m3 x Rs. 459.72 Rs. 551.66
Finished rate per m3 = Rs. 1901.05
(9) Providing and laying P.C.C. M15 Grade levelling course below approach slab
Basic rate vide item no.14.10 of N.H.S.O.R. per m3 Rs. 3793.92
Carriage of materials
cement 0.275 MT x Rs. 359.30 = Rs. 98.81
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.54 m3 x Rs. 487.61 = Rs. 263.31
chips 0.36 m3 x Rs. 459.72 165.50
Finished rate per m3 = Rs. 4523.52
(14) Providing P.C.C. M10 mechanically mixed concrete in abutment or pier foundation -do-do-
Basic rate vide item no.12.4 of N.H.S.O.R. per m3 Rs. 3611.52
Carriage of materials
cement 0.23 MT x Rs. 359.30 = Rs. 82.64
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.9 m3 x Rs. 487.61 = Rs. 438.85
Finished rate per m3 = Rs. 4333.10
(15) Providing P.C.C./R.C.C.in Substructure -do-do-
(a)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.13.5 (E)(p)I of N.H.S.O.R. per m3 Rs. 4707.84
Carriage of materials
cement 0.347 MT x Rs. 359.30 = Rs. 124.68
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 5457.49
SUPERSTRUCTURE
Basic rate vide item no.14.1 D(i)(q) of N.H.S.O.R. per m3 Rs. 6166.00
Carriage of materials
(a) Foundation
Basic rate vide item no.12.40 of N.H.S.O.R. per MT Rs. 53467.20
carriage of steel
1.05 MT x Rs. 359.30 Rs. 377.27
Finished rate per MT = Rs. 54382.91
(21) Providing and laying M30 Grade c.c. wearing coat including reinforcement
Basic rate vide item no.14.4 of N.H.S.O.R. per m3 Rs. 8668.80
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
steel 0.075 MT x Rs. 359.30 Rs. 26.95
Finished rate per m3 = Rs. 9507.05
(31) Supplying, fitting and fixing in position true to line and level POT-PTFE Rs. 171.84
bearing
ABSTRACT OF COST FOR APPROACH ROAD
as per drawing and Technical specification 36.0 m3 @ Rs. 2600.82 per m3 Rs. 93629.66
Construction of Subgrade and Earthen
Shoulders (Construction of subgrade and
earthen shoulders with approved material
2.07 obtained from borrow pits with all lifts &
leads, transporting to site, spreading,
grading to required slope and compacted to
meet requirement of table No. 300-2) 986.08 m3 @ Rs. 235.0 per m3 Rs. 231727.86
cleaned with mechanical broom. 5520 m2 @ Rs. 10.55 per m2 Rs. 58257.86
Technical Specifications as per Clause 509 110.40 m3 @ Rs. 9303.40 per m3 Rs. 1027095.88
Providing and laying Dense Graded
6.03
conforming toIRC-79 and the drawings. 50 nos. @ Rs. 653.00 Each Rs. 32650.00
A47
2.03 Construction of embankment with
A48
2.07 Construction of Subgrade and Earthen
Shoulders (Construction of subgrade and
earthen shoulders with approved material
obtained from borrow pits with all lifts &
leads, transporting to site, spreading,
A49
3.00 GRANULAR SUB BASE
3.01 Construction of granular sub-base by
providing coarse graded material,
spreading in uniform layers with motor
grader on prepared surface, mixing by
mix in place method with rotavator at
OMC, and compacting with vibratory
roller to achieve the desired density,
complete as per clause 401.
GSB Gr-I
Drainage layer
A50
5.00 BITUMINOUS WORK
5.01 Providing and applying primer coat with
bitumen emulsion on prepared surface of
Clause 507
Approach Taper portion 1 120.00 x 9 x 0.100 = 108 m3
Approach to road 1 240.00 x 7 x 0.100 = 168 m3
276 m3
A51
6.00 MISC. WORK
6.01 Providing and laying of hot applied
thermoplastic compound 2.5mmthick
including reflectorising glass beads
@250gms / sq.m. area ,thickness of
2.5mm is exclusive of surface applied
glass beads as per IRC:35.The finished
surface to be level,uniform and free from
streaks .and holes
edge 2 x 360 x 0.15 = 108 m2
Centre 1 x 360 x 0.10 x 0.33 = 5.94 m2
113.940 m2
6.02 Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory
sign as per IRC :67 made of high
intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle
iron post 75 mm x 75 mm x 6 mm firmly
fixed to the ground by means of properly
designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm,
60 cm below ground level as per
approved drawing
80 cmx60cm Rectangular 0.0 Nos.
6.03
A52
CALCULATION OF E/W IN FILLING OR CUTTING IN APPROACH ROAD ROAD.
A53
Estimate for proposed Diversion Road
Length of Diversion= 355 m
cum
2 GRANULAR SUB BASE COURSE
Construction of granular sub
base course by providing coarse
graded material Quantity =
100x5.5x0.2 = 110 cum 390.5 2007.79 784043.53
cum
3 GRANULAR BASE COURSE
WBM GR-II
3.1 Proviidng,laying,spreading &
compacting aggregates of
specific sizes to WBM
specification including spreading
in uniform thickness,packing,
rolling with roller 8-10 tonnes in
stages to proper grade &
camber, applying & brooming
requisite type of screening
materials to fill interices of 195.25 2475.44 483330.60
coarse aggregates, watering &
compacting to reqd density.
Quantity= 100x 5.5x1x
0.1=55cum
cum
WBM GR-III
Proviidng,laying,spreading &
compacting aggregates of
specific sizes to WBM
specification including spreading
in uniform thickness,packing,
rolling with roller 8-10 tonnes in
stages to proper grade &
camber, applying & brooming
requisite type of screening
materials to fill interices of
coarse aggregates, watering & 195.25 2456.90 479709.57
compacting to reqd density.
Quantity= 100x 5.5x 0.1= 55cum
cum
4 BITUMINUOUS WORK
G.total 3309324.86
Rate Analysis for Road Works for Diversion
Sl.no. Item Quantity Unit Rate (Rs) Finished rate
A56
Sl.no. Item Quantity Unit Rate (Rs) Finished rate
5.4 Laying Boulder apron NHSR 15.11 1074.00
Carriage charge
Stone boulder 1.2 cum 773.12 927.74
Total 2001.74
5.5 Boulder pitching on slope NHSR 15.4 1031.00
Stone boulder & spalls 1.2 cum 773.12 927.74
Total 1958.74
5.6 Filter material below pitching NHSR 15.5 1459.00
Sand 1.2 cum 237.28 284.74
Total 1743.74
5.7 Laying NP 4 HP pipe NHSR 9.3 B
Laying charge 14502.00
Carriage charge
NP 4 pipe 2230.10
Total 16732.10
5.8 Tucking point NHSR 13.2 556.00
sand 0.01 237.28 2.37
Cement 0.004 342.20 1.37
Total 559.74
5.9 Back filling 122.00
A57
Estimate of Dismanting of structure
A58
Estimate of Dismanting of structure
TOTAL = 243540.00
A59
Lead chart Basic rate of Carriage of Materials
NAME OF PROJECT : Rate of Carriage of materials as per S.O.R of NH Division
Multiplyi Total Lead on Lead on Lead on Hauling Hauling Hauling Loading
Charges
Charges on Charges on and Rate
MATERIAL ng Lead surfaced unsurfaced Kutcha on Unit
Name of unSurfaced Kutcha Unloading (Rs.)
Source TOTAL Lead Surfaced
Material
Sl. No. in Km. Factor (Km) Road Road Road Road Road Road Charges
1.0 Sand Chhinda 2 SAND 1.60 2 0 0 2 8.40 10.10 20.40 172.00 237.3 per m3
2.0 Chips Kolebira 58 CHIPS 1.60 58 58 0 0 8.40 10.10 20.40 172.00 951.5 per m3
3.0 Metal Kolebira 40 METAL 1.74 40 40 0 0 8.40 10.10 20.40 172.00 756.6 per m3
4.0 Boulder Kolebira 40 BOULDER 1.67 40 40 0 0 8.40 10.10 20.40 212.00 773.1 per m3
5.0 Moorum Local 5 MOORUM 1.33 5 5 0 0 8.40 10.10 20.40 172.00 227.86 per m3
6.0 Bitumen Namkum 297 BITUMEN 1.00 297 297 0 0 8.40 10.10 20.40 275.00 2769.8 per MT
7.0 Cement Simdega 8 CEMENT 1.00 8 8 0 0 8.40 10.10 20.40 275.00 342.20 per MT
8.0 Steel Simdega 8 STEEL 1.00 8 8 0 0 8.40 10.10 20.40 275.00 342.20 per MT
9.0 Hume Pipe Ranchi 175 H.P. 1.33 175 175 0 0 8.40 10.10 20.40 275.00 2230.10 Per m
Analysis of rates for Bridge work
(4) Providing and laying P.C.C. M15 Levelling course under the pile cap
Basic rate vide item no.12.39 of N.H.S.O.R. per m3 Rs.
### 3796.80
Carriage of materials
cement 0.275 MT x Rs. 743.00 = Rs.
### 204.33
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.54 m3 x Rs. 833.03 = Rs.
### 449.84
chips 0.36 m3 x Rs. 1049.68 = Rs.
### 377.88
Finished rate per m3 = Rs.
### 5353.12
(7) Back filling behind the abutment, wing wall with Granular Material
Basic rate Vide item no.13.9 A of NH S.O.R. per m3 Rs.
### 460.80
Carriage of material
Moorum 1.2 m3 x Rs. 270.76 Rs.
### 324.92
Finished rate per m3 = Rs.
### 793.57
(8) Providing and laying of Filter media
Basic rate vide item no.13.10 of N.H.S.O.R. per m3 Rs.
### 1170.24
Carriage of material
Metal 1.2 m3 x Rs. 1049.68 Rs.
### 1259.62
Finished rate per m3 = Rs.
### 2454.15
(9) Providing and laying P.C.C. M15 Grade levelling course below approach slab
Basic rate vide item no.14.10 of N.H.S.O.R. per m3 Rs.### 3811.20
Carriage of materials
cement 0.275 MT x Rs. 743.00 = Rs.
### 204.33
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.54 m3 x Rs. 833.03 = Rs.
### 449.84
chips 0.36 m3 x Rs. 1049.68 ### 377.88
Finished rate per m3 = Rs.
### 5367.67
(14) Providing P.C.C. M10 mechanically mixed concrete in abutment or pier foundation -do-do-
Basic rate vide item no.12.4 of N.H.S.O.R. per m3 Rs.
### 3621.12
Carriage of materials
cement 0.23 MT x Rs. 743.00 = Rs.
### 170.89
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.9 m3 x Rs. 833.03 = Rs.
### 749.73
Finished rate per m3 = Rs.
### 5063.14
(a) Foundation
Basic rate vide item no.12.40 of N.H.S.O.R. per MT Rs.
### 66451.20
carriage of steel
1.05 MT x Rs. 743.00 Rs.
### 780.15
Finished rate per MT = Rs.
### 67903.66
(23) Providing and laying M30 Grade c.c. wearing coat including reinforcement
Basic rate vide item no.14.4 of N.H.S.O.R. per m3 Rs.
### 9818.88
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
steel 0.075 MT x Rs. 743.00 Rs.
### 55.73
Finished rate per m3 = Rs.
### 11708.92
27.0 Providing and laying Pitching on slopes laid over well prepared
filter media
Basic rate vide item no.15.4(A) of N.H.S.O.R. per m2 Rs.
### 830.40
Carriage of boulders
1.2 m3 x Rs. 889.66 Rs.
### 1067.59
Finished rate per m3 = Rs.
### 1916.97
28.0 Providing and laying filter material underneath pitching
Basic rate vide item no.15.5 of N.H.S.O.R. per m2 Rs.
### 1285.44
Carriage of metal
1.2 m3 x Rs. 1049.68 = Rs.
### 1259.62
Finished rate per m3 = Rs.
### 2570.51
(4)Providing and laying P.C.C. M15 Levelling course under the pile cap
Basic rate vide item no.12.39 of N.H.S.O.R. per m3 Rs. 3762.00
Carriage of materials
cement 0.275 MT x Rs. 218.20 = Rs. 60.01
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.54 m3 x Rs. 169.05 = Rs. 91.29
chips 0.36 m3 x Rs. 161.32 = Rs. 58.08
Finished rate per m3 = Rs. 4052.62
(7)Back filling behind the abutment, wing wall with Granular Material
Basic rate Vide item no.13.9 A of NH S.O.R. per m3 Rs. 361.00
Carriage of material
Moorum 1.2 m3 x Rs. 88.30 Rs. 105.95
Finished rate per m3 = Rs. 471.62
(8)Providing and laying of Filter media
Basic rate vide item no.13.10 of N.H.S.O.R. per m3 Rs. 865.00
Carriage of material
Metal 1.2 m3 x Rs. 161.32 Rs. 193.58
Finished rate per m3 = Rs. 1069.17
(9)Providing and laying P.C.C. M15 Grade levelling course below approach slab
Basic rate vide item no.14.10 of N.H.S.O.R. per m3 Rs. 3776.00
Carriage of materials
cement 0.275 MT x Rs. 218.20 = Rs. 60.01
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.54 m3 x Rs. 169.05 = Rs. 91.29
chips 0.36 m3 x Rs. 161.32 58.08
Finished rate per m3 = Rs. 4066.76
(10)Providing P.C.C. /R.C.C. mechanically mixed concrete in foundation -do-do-
(a)P.C.C. M15 - Using Concrete mixer
Basic rate vide item no.12.8(A) of N.H.S.O.R. per m3 Rs. 3926.00
Carriage of materials
cement 0.275 MT x Rs. 218.20 = Rs. 60.01
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.54 m3 x Rs. 169.05 = Rs. 91.29
chips 0.36 m3 x Rs. 161.32 58.08
Finished rate per m3 = Rs. 4218.26
(11) (b)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.12.8 (B) of N.H.S.O.R. per m3 Rs. 4557.00
Carriage of materials
cement 0.347 MT x Rs. 218.20 = Rs. 75.72
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.36 m3 x Rs. 169.05 = Rs. 60.86
chips 0.54 m3 x Rs. 161.32 = Rs. 87.11
Finished rate per m3 = Rs. 4870.03
(14)Providing P.C.C. M10 mechanically mixed concrete in abutment or pier foundation -do-do-
Basic rate vide item no.12.4 of N.H.S.O.R. per m3 Rs. 3544.00
Carriage of materials
cement 0.23 MT x Rs. 218.20 = Rs. 50.19
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.9 m3 x Rs. 169.05 = Rs. 152.14
Finished rate per m3 = Rs. 3825.33
(23) Providing and laying M30 Grade c.c. wearing coat including reinforcement
Basic rate vide item no.14.4 of N.H.S.O.R. per m3 Rs. 10391.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
steel 0.075 MT x Rs. 218.20 Rs. 16.37
Finished rate per m3 = Rs. 10789.32
(30)
Supplying, fitting and fixing in position true to line and level
13.14
elastomeric bearing conforming to IRC: 83 (Part-II) section IX and
clause 2005 of MoRTH specifications complete including all
accessories as per drawing and Technical Specifications.
Rs. 0.67
Analysis of rates for Approach Road
1.0 Clearing and Grubbing Item No. 2.3 of NH S.O.R. per hectare Rs. 28146.68
2.0 Shifting of Telephone/Electric poles
Item No. 2.14 of NH S.O.R. per pole Rs. 87.87
3.0 cutting of trees Item No. 2.1 of NH S.O.R.
(a) Girth from 0.3m to 0.60m Each Rs. 121.20
(a) Girth from 0.6m to 0.90m Each Rs. 211.09
(a) Girth from 0.9m to 1.80m Each Rs. 417.13
(a) Girth >1.80 m Each Rs. 797.90
4.0 Dismantalling of flexible pavement
Item No.2.5 of NH S.O.R. per m3 Rs. 353.50
27.0 Providing and laying Pitching on slopes laid over well prepared
filter media
Basic rate vide item no.15.4(A) of N.H.S.O.R. per m2 Rs. 729.00
Carriage of boulders
1.2 m3 x Rs. 165.18 Rs. 198.22
Finished rate per m3 = Rs. 936.49
28.0 Providing and laying filter material underneath pitching
Basic rate vide item no.15.5 of N.H.S.O.R. per m2 Rs. 967.00
Carriage of metal
1.2 m3 x Rs. 161.32 = Rs. 193.58
Finished rate per m3 = Rs. 1172.19
4 Back filling behind the abutment,wing wall and return wall including foundation
trenches with granular material combined with all leads and lifts at site including cost of
all materials,labour,tools and plants,watering,cost of water with all leads and lifts
,dressingand ramming,free from grass and other loose deleterious materials likely to
deteriorate,,providing light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation all complete job as per design/drawing and technical
specification and MORT&H specification clause 304 and other relevant clauses and
direction of E/I
Area(m2) Width(av.)
m3 Total 416.02
5
Providing filter media with stone metal grade-III conforming to MORT&HTable 400-
7,free from grass,dirt and debris and other loose and deleterious materials likely to
deteriorate,,providing light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation incidental charges,all taxes and royalty etc.all complete job
as per design/drawing and technical specification and MORT&H specification clause
305 and other relevant clauses and direction of E/I
PIER
(I) PIER STEM P1 m3 1 x 9.00 x 1.00 x 6.20 = 55.80
PIER NOSING m3 1 x area= 0.79 x 6.20 = 4.87
(II) PIER STEM P2 m3 1 x 9.00 x 1.00 x 6.88 = 61.92
PIER NOSING m3 1 x area= 0.79 x 6.88 = 5.40
RETURN WALL(I) 4 x 3.50 x 0.50 x 0.30 = 2.10
(II) 4 x 3.50 x 1.165 x 0.30 = 4.89
ABUTMENT
HEEL SLAB 2 x 2.00 x 12.00 x 1.10 = 52.80
TOE SLAB 2 x 1.50 x 12.00 x 1.10 = 39.60
RECTANGULAR 2 x 1.00 x 12.00 x 1.60 = 38.40
PIER FOUNDATION (I) RECTANGULAR PORTION 2 x 10.00 x 4.20 x 0.60 = 50.40
2 2 x 10.00 x 1.60 x 0.40 = 25.60
2 x 10.00 x 1.00 x 0.80 = 16.00
450.74
8.0 Providing weep holes in PCC/RCC in abutment ,wing wall,return wallwith 100mm dia
A.C. pipes ,collar ,M.S. clamps including cost of all materials and labour, ,providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic
regulation incidental charges,all taxes and royalty etc.all complete job as per
design/drawing and technical specification and MORT&H specificationclauses and
other relevant clauses and direction of E/I
No. 160
9.0
Providing PCC/RCC mechanically mixed concrete in abutment cap,pier cap ,crash
barrier etc., with graded stone aggregate 20mm nominal size and clean coarse sand of
FM 2 and above , well screened, free from all dirt ,dust shellsand other deleterious
materials,including cost of all materials form work ,labour,handling material at site,
centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater,
curing cost of water with all leads and lifts,all taxes and royalties,incidental charges,hire
and running charges of machinery,depreciation, major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification
clauses and other relevant clauses and direction of E/I(excluding cost of reinforcement
and it's cutting ,bending ,binding etc.)
(a)RCC M-30
ABUTMENT CAP 2 x 12.00 x 1.05 x 0.3 = 7.56
PIER CAP 2 x 10.00 x 1.2 x 0.3 = 7.20
DIRT WALL 2 x 12.00 x 0.3 x 2.8 = 20.16
BRACKET 2 x 11.40 x 0.20 x 0.18 = 0.82
2 x 11.40 x 0.20 x 0.12 = 0.27
PEDESTRAL 8 3 x 0.80 x 0.70 x 0.25 = 3.36
Total 39.37
SL. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
NO. HEIGHT
10.0 Providing PCC/RCC mechanically mixed concrete in Deck slab,girder,bed block,and
Foot path, with graded stone aggregate20mm nominal size and clean coarse sand of
FM 2 and above , well screened, free from all dirt ,dust shellsand other deleterious
materials,including cost of all materials form work ,labour,handling material at
site,centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater,
curing cost of water with all leads and lifts,all taxes and royalties,incidental charges,hire
and running charges of machinery,depreciation,major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification
clauses and other relevant clauses and direction of E/I(excluding cost of reinforcement
and it's cutting ,bending ,binding etc.)
(a)RCC M-30
TOTAL CONCRETE IN SUPERSTRUCTURE m3 3 116.93 350.79
(excluding railing)
Total 350.79
11.0 Providing precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm,true
to the line and grade,tolerance of RCC vertical post not to exceed 1 in 500,centre to
centre spacing between the vertical post not to exceed 2000mm, leaving adequate
space between vertical post for expansion,complete as per approved drawing and
Technical specification
x
m 2 24.6 3 = 147.6
APPROACH m 4 x 3.5 = 14
Total 161.6
12.0 Providing and laying Reinforced cement concrete wearing coat M30 grade including
reinforcement complete as per drawing and Technical specification
Providing HYSD bars in all types of RCC works in Girder, Deck slab ,bed ,block,
abutment,return wall ,pier shaft, abutment cap, pier capincluding cutting to
sizes,bending,binding,placing in position on cement cubeswith cost of all
materials,labour,tools and plants,all taxes,handling materials at siteand incidental
charges,all complete job as per design/drawing and technical specification and
MORT&H specifications clauses and other relevant clauses and direction of E/I
ABUTMENT SHAFT MT #REF!
ABUTMENT FOUNDATION MT #REF!
ABUTMENT CAP MT #REF!
DIRTWALL MT #REF!
RETURN WALL MT #REF!
BRACKET MT 0.18
PEDESTRAL MT #REF!
PIER FOUNDATION MT #REF!
PIER SHAFT MT #REF!
PIER HAMMER HEAD MT #REF!
SUPERSTRUCTURE MT 5 22.04 110.20
Total #REF!
15.0 Providing , laying,fitting,fixing stone boulder pitching duly packed in slope of road
embankment and approach with approved quality of materials within 150m of worksite
and all lift as per direction of E/I including cost of all materials , labour
x(2X )x
m3 2 277.3 + 151.6 0.6 = 847.44
847.44
16.0 Providing and laying Filter material underneath pitching in slopes all complete as per
x(2X x
drawing and Technical specification m3 2 277.3 + 151.6 0.15 = 211.86
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per approved drawings and
17.0 4 x 12
standard specifications to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for installation.)
m = 48
Providing drainage spouts with 260mmx260mm M.S. grating 100 mm dia. 1.00m long
G.I. pipe including cost of all labour and materialall complete job as per design/drawing
18.0
and technical specification and MORT&H specification clauses and other relevant
clauses and direction of E/I
No. 24 24
19.0 Supplying ,fitting and fixing elastomeric bearing conforming to IRC 83(part -I) section-
IX in position ,true to lines and level including all accessories,neoprene w.r.l.m.s.
plate ,all labour including machinary inputs for various processing operations like gas
cutting .fabrication,converting into elastometric compound of required specifications,for
adding chemicals like primer for plates and final bonding agents of plates to elastomer,
for pretreatment,bonding /vulcanizing of elastometric compound with reinforcing steel
plate,hire and running charge of machinery with depreciation,major/minor repair,POL
and other lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification
design/drawing and technical specification and MORT&H specificationclauses and
other relevant clauses and direction of E/I