REPORT

PRELIMINARY

Name of Work: - High Level Bridge in 19th KM of Dumri-Nawadih-Phusro Road

road.

State : - Jharkhand

Division : - Road division, Dumka

Span Arrangement : - 2 x 16 m effective

Carriage width 16 m

Total Length of Bridge 33.2

Overall Length of Bridge & Approch :- 533.20 m

Estimated cost of Bridge & Approach :- Rs 45289200.00

Unit cost of Bridge & Approach :- Rs 84938.48

AUTHORITY AND PLAN

The above assignment has been given by EXECUTIVE ENGINEER

OFFICE OF THE EXECUTIVE ENGINEER ADVANCE PLANNING FIELD SURVEY DIVISION ROAD CONSTRUCTION DEPARTMENT (RCD) .

vide NIT no-

page FSDDUMKA
CHAPTER - 1
1
INTRODUCTION

The Chief Engineer, Central Design Organisation , Road Construction Department , Jharkhand ,

Ranchi has ordered to prepare Detailed Project Report (DPR) for High Level Bridge

in 19th KM of Dumri-Nawadih-Phusro Road near I.B. replacing the old bridge in Bokaro District in the state of Jharkhand.

With HL bridge in order to provide better road communication to the road users throughout the

year. The TBM was fixed on the platform of bridge slab top of road .

All levels have been taken with reference to this TBM. The DPR has been

prepared by this Division on the basis of approved alignment , span arrangement and road level &

other hydraulic particulars by SE, Advance Planning Circle, Ranchi, Jharkand.

2
SUB SOIL EXPLORATION :

Geotechnical and soil survey investigation have been prepared by Soil Investigation Division,

Advance Planning, RCD, Ranchi and report is being given by letter no.49 (enc) dt.02/02/13. The bore

log data and soil test report is being attached with this DPR.

3 FOUNDATION PROPOSED

As per soil profile , Open foundation has been proposed to suit the site condition,

as soft rock strata has been found at the reasonable depths at all two locations

i.e two bores on bank and three bores in river bed where sub soil exploration was carried out.

As for protection against scour, protecton work has been suggested.

4 SPAN ARRANGEMENT AND CARRIAGE WIDTH

The approved span arrangement is 2 x 16 m effective as per hydraulic details. The existing banks

of river at bridge site are firm & no erosion is there,hence the span arrangement of 2 x 16

m is suggested. It has been approved by SE, AP, Circle, Ranchi. The proposed bridge shall be of

2 lanes having carriage width of 11m with footpath. The overall width of slab shall be 16m.

The approved aligment of bridge is at Upstream site of bridge.

page FSDDUMKA
5 SUBSTRUCTURE

All abutments , piers and cantilever return walls and cap are proposed in Reinforced cement

concrete (RCC) in grade M-30 . All sub structures shall be solid . Abutment and piers have been

designed as RCC cracked section.

6 SUPERSTRUCTURE

The RCC T - beam and slab of two lane having carriage width 11m with footpath in grade

M - 30 concrete is proposed . The standard drawing of MOSRT & H for super structure of 16 m

effctive length with footpath has been adopted.

CHAPTER 2

2.1 INTRODUCTION

The following paragraph enlists the Detailed Design standards of the proposed Bridge.

2.2 Cross sectional width of the new bridge would be as follows :-

Width of clear carriageway 11 m

(without footpath)

Overall width of bridge 16 m

(without footpath)

2.3 GRADE OF CONCRETE

For Bridges

Foundation M - 30

Piers and Abutment and Wing wall M - 30

Abutment cap, Dirt wall, Return wall

pedestal, Tie beam,Pier cap M - 30

RCC T beam & Slab superstructure M - 30

Approach Slab M - 30

2.4 WATER FORCES

Forces due to water current have been considered in design as per IRC 6: 2017

page FSDDUMKA
2.5 LONGITUDINAL FORCES

In design of the bridge , longitudinal forces are computed as per IRC 6: 2017 arising from any one

or more of followings :

a) Tractive effort caused through acceleration of the driving wheels.

b) Braking effect resulting from application of the brakes to braked wheels.

Frictional resistance offered to the movement of free bearing due to change of

temperature or any other cause.

2.6 CENRTIFUGAL FORCES

Since bridge is not proposed on curve , centrifugal forces donot play any role in designing the

bridge. There fore it has not been considered in design.

2.7 EARTH PRESSURE

The proposed bridge designed to retain earth fills are proportional to withstand pressure

calculated in accordance with Coloumb's theory, subjected to modification that the centre of

pressure exerted by the backfill, when considered dry, is located at an elevation of 0.42 m of the

height of the wall above the base instead of 0.33 m of that height.

2.8 SEISMIC FORCES

Since the proposed bridge lies in seismic zone II which requires cosideration of seismic forces as

per IRC 6: 2017. There fore its consideration in design has been made. Importance factor has

been taken as 1.5 for bridge on highway. Thus seismic co efficient 0.075 has been taken in design.

2.9 TEMPERATURE EFFECTS

Temperature effects have been taken into consideration as per IRC 6: 2017.

page FSDDUMKA
2.10 BUOYANCY

100 % Buoyancy has been considered while checking stability of foundations. Pore pressure

upliftment limited to 15 % has been considered while checking stresses in sub structure

elements as per IRC 6: 2017.

2.11 LOAD COMBINATION

All members have been designed to sustain safely the most critical combination of various loads

and forces that co exists. Various load combinations as relevant with increase in permissible

stresses considered in the design as per IRC 6: 2017 has been taken.

2.12 IRC CODES FOLLOWED

IRC 5 : 1998

IRC 6 : 2017

IRC 112 : 2011

IRC 78 : 2014

IRC SP : 13 2004

IRC SP : 54 : 2000

2.13 STANDARD DRAWINGS

Standard drawings of MOSRT & H for 16 m effective span with footpath have been considered

for Super structures, RCC railing & Bearings.

2.14 APPRAOCH SLAB

Approach slab will be 3.5 m long on both sides . It will be 300 mm thick . It will be RCC in grade

M - 30 concrete. It will be laid over 150 mm thick leveling course in M -15 concrete.

page FSDDUMKA
2.15 APPROACH ROAD

The proposed bridge is on the downstream alignment and FRL of proposed bridge is at same level

but in order have smooth connectivity, approach road is provided.

2.16 DIVERSION ROAD

In order to maintain traffic flow on the road , diversion road would be the existing bridge.

CHAPTER - 3

3.1 MATERIALS

Basic construction material with their lead from the source of supply has been tabulated below

Cement 24.00 Boulder 26 Hume pipe 24.00

Steel 24.00 Chips 26 Bitumen 36

Stone metal 26 Moorum 5

3.2 LABOUR

Skilled and un skilled labours for carrying out different items of work involved in the construction

are locally available.

3.3 RATES

The basic schedule of rates for several items of works related to construction of bridge is

available in Current Schedule of Rates for NHSOR, Jharkhand. These rates are effective from

27/09/2012 along with carriage charge.

3.4 MISCELLANEOUS

To meet the expenditure to be incurred on the unforseen items during execution of works 1%

contigency of total cost have been provided under contigencies head .

page FSDDUMKA
3.5 QUALITY ASSURANCE / QUALITY CONTROL

To achieve high quality in works at site , a Quality Policy must be decided by Road Construction

Department in light of IRC 57 & 47 and effective monitoring there of is required at top level.

Quality, professional and capable contractor will be much helpful in achieving quality work.

Srengthening and modernisation of the existing quality system of the department has been quite

essential. Training to the lab staffs and Field officers / contractors are also essential to make

them consicous about quality. There after high quality in the field may be assured . For carrying

out quality tests to check quality tests to check quality at site

Site laboratory fully equipped and functional as MOSRT & H (4th edition) with graduate material

Engineer and adequate number of technical staffs to carry out routine tests as per MOSRT &H (4th

edition) for contractor must be essential to achieve quality work. Q-3 level of quality is proposed

for the above work.

3.6 SPECIFICATION

The complete work shall be executed strictly in accordance with " Specification for Road &

Bridge Works" 4th edition of MOSRT & H.

3.7 CONSTRUCTION PEROID

Construction peroid shall be 10 calendar months subject to regular cash flow.

DPR has been prepared in accordance with check lists issued by Chief Engineer , Central Design

Organisation, Road Construction Department, Ranchi, Jharkhand vide his letter no. 400 (encl.)

dated 29/3/08. and may be forwarded for Technical Sanction.

Assistant Engineer Executive Engineer

Advance Planning Advance Planning

FSD , Dumka FSD , Dumka

page FSDDUMKA
CHECK LIST OF THE ITEMS TO BE SUBMITTED ALONG WITH DPR OF BRIDGE PROJECT
SL. TICK MARK
NO. ITEMS SUBMITTED
1.0
PROJECT 1.1 Introductory I Name of the Scheme
REPORT Report II Authority and Plan provision
III Location of the bridge
(i) Name of the state,district &nearest town
Village
(ii) Name of the road and chainage of the
bridge site
(iii) Name of the river
IV Necessity of the bridge
V Geographical feature of the area
VI Measurable and nonmeasurable benefits
2.0 SITE 2.1 Site I Report on identification of alternative bridge
selection site,alignments with their merits,demerits
and probable cost.
II Alignment approved by the concerned S.E.
should be submitted along with DPR
2.2Details of I Description with sketches showing relevant
Existing bridge dimensions
/causeway II If Causeway
(i) Length and Depth of submergence
(ii) No. and size of vent
(iii) Frequency of interruption to Traffic
III If Bridge
(i) No. and length of span
(ii) Clear waterway
(iii) Silted up span if any
(iv) Sign of undue scour in foundation and
bank,observed scour if any
(v) Type of bank:erodible/firm
(vi) Type of construction:steel/Concrete
(vii) Rly. Bridge if any mentioning approx.
distance
(viii) Plane table sheet of site showing existing
Bridges if any, proposed bridge, nature of
river,exst. Approach road if any

3.Topo 3.1Topographic (i) Location of nearest GTS bench mark with


graphy Data level
3.2. Justification regarding depth of bore hole
3.3. Bore log data in embankment in case of high embankment
3.4.Disturbed/Undisturbed sample for the following
(i) Soil classification
(ii) Particle size distribution
(iii) Shear strength characteristics
(iv) Permeability where dewatering is expected
(v) Compressibility
(vi) Density,void ratio,Moisture content
(vii) Nature and type of rock where met and
bearing capacity
(viii) CBR Test Result for approach road
(ix) SPT Test Result
4.Structural Design.
4.1.Design of Foundation Element
4.2.Design of substructure
4.3.Design of superstructure
I

4.4.Design of Bearing
4.5.Design of approach Slab
4.6.Design of Protective work if required
4.7.Design of high approach embankment if required
4.8.Design of pavement in approaches
4.9Design of horizontal and vertical alignment of approaches
5. Detailed Estimate
5.1 Quantity and Cost estimates
(i) Preparatory works
(ii) Foundations
(iii) Substructure
(iv) Superstructure
(v) Protective work
(vi) Miscellaneous items
(vii) Sub estimate for approaches
(viii) Provision of centage charges like quality
control, contingencies etc.
(ix) Sub estimate for Diversion

5.2.Rates
(i) Schedule of Rates(mention year and name

of civil division to which S.O.R. is reffered


(ii) Schedule of Rates of NH(mention year to
which S.O.R. is reffered as applicable)
(iii) Analysis of rates including reference of
Data Book if any

5.3.Quarry /Material
Source/Lead charts(duly
approved by concerned
S.E.)
6.Detailed Working Drawing and Maps
(i) Index Map
(ii) Contour Plan
(iii) Site Plan
(iv) Catchment Area Map
(v) Longitudinal Section of the Stream
(vi) At least three cross section of the river
(vii) Bore Log Data
(viii) A General Arrangement Drawing of the
bridge superimposed on the cross section
of the river at the proposed site also
indicating the Bore Details
(ix) Detailed Drawing of substructure and
foundation
(x) Bar Bending schedule
(xi) Details of protective work drawn to a
suitable scale
(xii) Drawing of miscellaneous items like
bearings, expansion joints, wearing coat,
Railing , approach slab etc.
(xiii) Details of existing bridge if any
(xiv) Land Acquisition Plan if any (show the area
of land required)
(xv) Strip plan showing the location of
site,trees,ROW,& Road junction if any
(xvi) Plan ,Longitudinal and cross section of
approach road
(xvi) Detailed Drawing of CD works if any
II
REPORT
APPROACH ROAD
abstract of cost
analysis of rates
details of quantities
design of abutment
hudraulics of nala
sub surface exploration report
GENERAL ABSTRACT OF COST
INDEX

Sl. Description of Work Page No.


No.
1.0 CHECK LIST
2.0 REPORT 1-7
3.0 GENERAL ABSTRACT OF COST 8
4.0 ABSTRACT OF COST 9-13
5.0 ANALYSIS OF RATES 14-25
6.0 DETAILS OF QUANTITIES 26-32
7.0 DESIGN OF ABUTMENT 33-69
8.0 DESIGN OF PIER 70-98
9.0 HYDRAULICS 1-9
10.0 SOIL REPORT 99-100
11.0 APPROACH ROAD 101-110
12.0 ANNEXURES
(a) GAD
(b)REINFORCEMENT DETAILS
OF ABUTMENT
©REINFORCEMENT DETAILS
OF PIER
(d)REINFORCEMENT DETAILS
OF SUPERSTRUCTURE
List of Machinaries
Sl. Name of Equipment No.
N0.
1.0 Transit mixer 1
2.0 Concrete placer 1
3.0 Needle vibrator 2
4.0 Vibrator Nozzle 2
5.0 Compactor 1
6.0 Curing Machine 1
7.0 Fixed form paver 1
8.0 Paver Finisher 1
9.0 Trucks 2
10.0 Excavator 1
GENERAL ABSTRACT OF COST
NAME OF PROJECT :0

SL.NO. DESCRIPTION OF WORK ESTIMATED COST


1.0 ESTIMATE OF THE BRIDGE Rs. 22277125.51
2.0 ESTIMATE OF THE APPROACH ROAD Rs. 13834837.24
3.0 ESTIMATE OF THE DIVERSION ROAD Rs. 3309324.86
4.0 DISMANTLING COST Rs. 243540.00
SUB TOTAL A Rs. 39664827.60
G.S.T. @ 12% of A Rs. 4759779.31
SUB TOTAL B Rs. 44424606.91
Labour Cess 1% of B Rs. 444246.07
SUB TOTAL C Rs. 44868852.98
4.0 ADD FOR CONTIGENCY UPTO 1 CRORE Rs. 100000.00
5.0 ADD FOR CONTIGENCY ABOVE 1 CRORE Rs. 174344.26
6.0 COST OF CONSULTANCY Rs. 146000.00
Grand Total Rs. 45289197.25
(SAY) 45289200.00
In words:- FOUR CRORE FIFTY TWO LAKHS EIGHTY NINE THOUSAND TWO HUNDRED ONLY
ABSTRACT OF COST

SL. ITEMS OF WORK


NO.
QUANTITY UNIT RATE (RS) AMOUNT (RS)

BILL NO. 1 : FOUNDATION


1 E/W in excavation of foundn. Trenches for bridges with all
materials ,labour ,tools and plants,levelling and ramming the
foundation beds,dressing the sides ,removing roots,logs
,shrubs,and other loose and deleterious materials likely to
deteriorate,adequate provision against erosion,water pollution
anddrainage to keep the site free of water ,stacking the
excavated soil clear from the edge of excavation, and backfilling
the same with approved materials providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation all complete job as per design/drawing and technical
specification and MORT&H specification clause 304 and other
relevant clauses and direction of E/I(Excluding cost of dewatering
and shoring)

(I)ORDINARY SOIL 190.60 m3 x @ 63.00 Per m3 12007.926


(II) WEATHERED ROCK 303.29 m3 x @ 81.00 Per m3 24566.1336
(III)HARD ROCK 152.50 m3 x @ 412.00 Per m3 62828.352
2 Providing and laying of P.C.C.M15 levelling course 100 mm thick
in foundation
25.42 m3 x @ 4804.01 Per m3 122098.8147408
3 Providing PCC/RCC mechanically mixed concrete in Abutment
foundation, Pier Foundation, Pile Cap with graded stone
aggregate 40mm nominal size and clean coarse sand of FM 2
and above , well screened, free from all dirt ,dust shells and other
deleterious materials,including cost of all materials form work
,labour,handling material at site,centering and shuttering,
screening, mixing in cement mixer,placingin position,vibrating,hire
and running charges of concrete mixer and needle vibrater,
curing cost of water with all leads and lifts,all taxes and royalties,
incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other
lubricants,pay ofmachinary staff , providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as perdesign/ drawing and
technical specification and MORT&H specificationclauses and
other relevant clauses and direction of E/I(excluding cost of
reinforcement and it's cutting ,bending ,binding etc.)

M30 288.00 m3 x @ 5824.42 Per m3 1677432.7872


4 Providing HYSD bars in all types of RCC works in abutment
Foundation, pier Foundation, Pier Cap, Pile including cutting to
sizes,bending,binding,placing in position on cement cubeswith
cost of all materials,labour,tools and plants,all taxes,handling
materials at siteand incidental charges,all complete job as per
design/drawing and technical specification and MORT&H
specifications clauses and other relevant clauses and direction of
E/I

9.68 MT x @ 67937.31 Per MT 657796.113366639


SL. ITEMS OF WORK
NO.
QUANTITY UNIT RATE (RS) AMOUNT (RS)

BILL NO. 2 : SUBSTRUCTURE


5 Providing PCC/RCC mechanically mixed concrete in
abutment,Pier,wing wall,return wall,curtainwall, toe wall with
graded stone aggregate 40mm nominal size and clean coarse
sand of FM 2 and above , well screened, free from all dirt ,dust
shells and other deleterious materials,including cost of all
materials form work ,labour,handling material at site,centering
and shuttering, screening, mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and
needle vibrater, curing cost of water with all leads and lifts,all
taxes and royalties, incidental charges,hire and running charges
of machinery,depreciation, major/minor repair,POL and other
lubricants,pay ofmachinary staff , providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as perdesign/ drawing and
technical specification and MORT&H specificationclauses and
other relevant clauses and direction of E/I(excluding cost of
reinforcement and it's cutting ,bending ,binding etc.)

M30 87.63 m3 x @ 6120.42 Per m3 536334.738985566


6 Providing weep holes in PCC/RCC in abutment ,wing wall,return
wallwith 100mm dia A.C. pipes ,collar ,M.S. clamps including cost
of all materials and labour, ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation incidental charges,all taxes and royalty etc.all
complete job as per design/drawing and technical specification
and MORT&H specificationclauses and other relevant clauses
and direction of E/I
84.00 NO x @ 128.00 each 10752

7
Providing PCC/RCC mechanically mixed concrete in abutment
cap,pier cap ,crash barrier etc., with graded stone aggregate
20mm nominal size and clean coarse sand of FM 2 and above ,
well screened, free from all dirt ,dust shellsand other deleterious
materials,including cost of all materials form work
,labour,handling material at site, centering and
shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and
needle vibrater, curing cost of water with all leads and lifts,all
taxes and royalties,incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as per design/drawing and
technical specification and MORT&H specification clauses and
other relevant clauses and direction of E/I(excluding cost of
reinforcement and it's cutting ,bending ,binding etc.)

M30
98.35 m3 x @ 6599.55 Per m3 649095.01657056
8 Providing HYSD bars in all types of RCC works in
abutment,return wall ,pier shaft, abutment cap, pier capincluding
cutting to sizes,bending,binding,placing in position on cement
cubeswith cost of all materials,labour,tools and plants,all
taxes,handling materials at siteand incidental charges,all
complete job as per design/drawing and technical specification
and MORT&H specifications clauses and other relevant clauses
and direction of E/I

Fe 500 D 28.64 MT x @ 68080.31 Per MT 1949659.46736427


SL. ITEMS OF WORK
NO.
QUANTITY UNIT RATE (RS) AMOUNT (RS)

BILL NO. 3 : SUPERSTRUCTURE


9 Providing P.C.C.M15 ordinary grade mechanically mixed
concrete below approach slab ,as levelling course with graded
stone aggregate 40mm to 10mm size and clean coarse sand of
FM 2 and above , well screened, free from all dirt ,dust shellsand
other deleterious materials,including cost of all materials form
work ,labour,handling material at site,tools and plants, curing cost
of water with all leads and lifts,all taxes and royalties,incidental
charges,hire and running charges of
machinery,depreciation,major/minor repair,POL and other
lubricants,pay ofmachinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as perdesign/drawing and
technical specification and MORT&H specification clauses and
other relevant clauses and direction of E/I

CONCRETE UNDER APPROACH SLAB 16.17 m3 x @ 4658.01 Per m3 75320.083146

10 Providing PCC/RCC mechanically mixed concrete in Deck


slab,girder,bed block,and Foot path, with graded stone
aggregate20mm nominal size and clean coarse sand of FM 2 and
above , well screened, free from all dirt ,dust shellsand other
deleterious materials,including cost of all materials form work
,labour,handling material at site,centering and
shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and
needle vibrater, curing cost of water with all leads and lifts,all
taxes and royalties,incidental charges,hire and running charges of
machinery,depreciation,major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as per design/drawing and
technical specification and MORT&H specification clauses and
other relevant clauses and direction of E/I(excluding cost of
reinforcement and it's cutting ,bending ,binding etc.)

M35
TOTAL CONCRETE IN SUPERSTRUCTURE
(excluding railing)
731.93 m3 x @ 6637.55 Per m3 4858250.2783416
11 Reinforced Cement Concrete Crash Barrier (Provision of an
Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed
with M-40 grade concrete with HYSD reinforcement conforming to
IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion
joints filled with pre-moulded asphalt filler board, keyed to the
structure on which it is built and installed as per design given in
the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing
and at locations directed by the Engineer, all as specified)

M40 Crash Barrier

161.60 m x @ 1839.66 Per m 297288.907328


SL. ITEMS OF WORK
NO.
QUANTITY UNIT RATE (RS) AMOUNT (RS)

12 Providing precast RCC railing of M30 Grade, aggregate size not


exceeding 12 mm,true to the line and grade,tolerance of RCC
vertical post not to exceed 1 in 500,centre to centre spacing
between the vertical post not to exceed 2000mm, leaving
adequate space between vertical post for expansion,complete as
per approved drawing and Technical specification

161.60 m x @ 1819.47 Per m 294026.151616


13 Providing and laying Reinforced cement concrete wearing coat
M30 grade including reinforcement complete as per drawing and
Technical specification

66.66 m3 x @ 10767.08 Per m3 717733.846104


14 Providing and laying RCC Approach slab M30 grade including
reinforcement and formwork complete as per drawing and
Technical specifications
32.34 m3 x @ 9071.53 Per m3 293373.260796
15 Providing drainage spouts with 260mmx260mm M.S. grating 100
mm dia. 1.00m long G.I. pipe including cost of all labour and
materialall complete job as per design/drawing and technical
specification and MORT&H specification clauses and other
relevant clauses and direction of E/I

18.00 no x @ 885.00 each 15930


16 Supplying ,fitting and fixing elastomeric bearing conforming to
IRC 83(part -I) section-IX in position ,true to lines and level
including all accessories,neoprene w.r.l.m.s. plate ,all labour
including machinary inputs for various processing operations like
gas cutting .fabrication,converting into elastometric compound of
required specifications,for adding chemicals like primer for plates
and final bonding agents of plates to elastomer, for
pretreatment,bonding /vulcanizing of elastometric compound with
reinforcing steel plate,hire and running charge of machinery with
depreciation,major/minor repair,POL and other lubricants,pay of
machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic
regulation etc. all complete job as per design/drawing and
technical specification and MORT&H specification design/drawing
and technical specification and MORT&H specificationclauses
and other relevant clauses and direction of E/I

645120.00 cm3 x @ 0.78 per cm3 503193.6


17 Providing HYSD bars in all types of RCC works in Girder, Deck
slab ,bed ,block, abutment,return wall ,pier shaft, abutment cap,
pier capincluding cutting to sizes,bending,binding,placing in
position on cement cubeswith cost of all materials,labour,tools
and plants,all taxes,handling materials at siteand incidental
charges,all complete job as per design/drawing and technical
specification and MORT&H specifications clauses and other
relevant clauses and direction of E/I

SUPERSTRUCTURE 113.49 MT x @ 69308.31 per MT 7865800.10


18 Strip Seal Expansion Joint (Providing and laying of a strip seal
expansion joint catering to maximum horizontal movement upto
70 mm, complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.)

64.00 m x @ 9381.00 per m 600384


SL. ITEMS OF WORK
NO.
QUANTITY UNIT RATE (RS) AMOUNT (RS)

BILL NO. 4 : PROTECTION WORK


19 Back filling behind the abutment,wing wall and return wall
including foundation trenches with granular material combined
with all leads and lifts at site including cost of all
materials,labour,tools and plants,watering,cost of water with all
leads and lifts ,dressingand ramming,free from grass and other
loose deleterious materials likely to deteriorate,,providing
light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation all complete job as per design/drawing
and technical specification and MORT&H specification clause 304
and other relevant clauses and direction of E/I

521.36 m3 x @ 809.43 per m3 422005.46752


20
Providing filter media with stone metal grade-III conforming to
MORT&HTable 400-7,free from grass,dirt and debris and other
loose and deleterious materials likely to deteriorate,,providing
light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation incidental charges,all taxes and royalty
etc.all complete job as per design/drawing and technical
specification and MORT&H specification clause 305 and other
relevant clauses and direction of E/I

79.30 m3 x @ 2429.82 per m3 192675.32

21 Providing , laying,fitting,fixing stone boulder pitching duly packed


in slope of road embankment and approach with approved quality
of materials within 150m of worksite and all lift as per direction of
E/I including cost of all materials , labour

69.60 m3 x @ 1958.74 per m3 136333.2833856


22 Providing and laying Filter material underneath pitching in slopes
all complete as per drawing and Technical specification

17.40 m3 x @ 2600.82 per m3 45255.90


23 CONFIRMATORY BORING 80.00 m x @ 2000.00 per m 160000.00
24 Painting on concrete surface (Providing and applying 2 coats of
water based cement paint to unplastered concrete surface after
cleaning the surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 Sq.m. ) (Crash Barrier)
350.2548 m2 x @ 80.00 per m2 28020.38
25 Painting on concrete surface (Providing and applying 2 coats of
water based cement paint to unplastered concrete surface after
cleaning the surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 Sq.m. )(Hand rail)
451.5687 sqm X @ 80.00 per sq.m. 36125.50
Total in Bridge 22277125.5078274
DETAILS OF QUANTITY
0
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
BILL NO. 1 : FOUNDATION
1 E/W in excavation of foundn. Trenches for bridges with all materials ,labour ,tools and plants,levelling and m m m
ramming the foundation beds,dressing the sides ,removing roots,logs ,shrubs,and other loose and
deleterious materials likely to deteriorate,adequate provision against erosion,water pollution anddrainage
to keep the site free of water ,stacking the excavated soil clear from the edge of excavation, and
backfilling the same with approved materials providing light,barrier,danger signals,choukidar,making and
maintaining diversion,traffic regulation all complete job as per design/drawing and technical specification
and MORT&H specification clause 304 and other relevant clauses and direction of E/I(Excluding cost of
dewatering and shoring)

(I)ORDINARY SOIL
ABUTMENT A1 1.00 x 16.20 x 5.20 x 0.905 = 76.24
ABUTMENT A2 1.00 x 16.20 x 5.20 x 0.905 = 76.24
PIER P1 2.00 x 10.20 x 4.20 x 0.445 = 38.13

m3 Total 190.60
(II)WEATHERED ROCK
ABUTMENT A1 1.00 x 16.20 x 5.20 x 1.495 = 125.94
ABUTMENT A2 1.00 x 16.20 x 5.20 x 1.495 = 125.94
PIER P1 2.00 x 10.20 x 4.20 x 0.600 = 51.41

TOTAL 303.29
(III) HARD ROCK
ABUTMENT A1 1.00 x 16.20 x 5.20 x 0.600 = 50.54
ABUTMENT A2 1.00 x 16.20 x 5.20 x 0.600 = 50.54
PIER P1 2.00 x 10.20 x 4.20 x 0.600 = 51.41

Total 152.50
2 Providing and laying of P.C.C.M15 levelling course 100 mm thick in foundation

ABUTMENT A1 1.00 x 16.20 x 5.20 x 0.100 = 8.42


ABUTMENT A2 1.00 x 16.20 x 5.20 x 0.100 = 8.42
PIER P1 2.00 x 10.20 x 4.20 x 0.100 = 8.57

m3 Total 25.42
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
3 Providing PCC/RCC mechanically mixed concrete in Abutment foundation, Pier Foundation, Pile Cap
with graded stone aggregate 40mm nominal size and clean coarse sand of FM 2 and above , well
screened, free from all dirt ,dust shells and other deleterious materials,including cost of all materials form
work ,labour,handling material at site,centering and shuttering, screening, mixing in cement
mixer,placingin position,vibrating,hire and running charges of concrete mixer and needle vibrater, curing
cost of water with all leads and lifts,all taxes and royalties, incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other lubricants,pay ofmachinary staff , providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as perdesign/ drawing and technical specification and MORT&H specificationclauses and other
relevant clauses and direction of E/I(excluding cost of reinforcement and it's cutting ,bending ,binding etc.)
M30

ABUTMENT FOUNDATION
A1(OPEN) m3 2x 16.00 x 1.00 x 1.60 = 51.20
2x 16.00 x 2.30 x 1.10 = 80.96
2x 16.00 x 1.70 x 1.10 = 59.84

PIER FOUNDATION P1 (RECTANGULAR PART) m3 2.00 x 10.00 x 4.00 x 0.60 = 48.00


2 2.00 x 10.00 x 1.50 x 0.40 = 24.00
2.00 x 10.00 x 1.50 x 0.80 = 24.00

TOTAL 288.00
Providing HYSD bars in all types of RCC works in abutment Foundation, pier Foundation, Pier Cap, Pile
4 including cutting to sizes,bending,binding,placing in position on cement cubeswith cost of all
materials,labour,tools and plants,all taxes,handling materials at siteand incidental charges,all complete
job as per design/drawing and technical specification and MORT&H specifications clauses and other
relevant clauses and direction of E/I

ABUTMENT FOUNDATION MT 6.95


PIER FOUNDATION MT 2.73
TOTAL 9.68
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT

BILL NO. 2 : SUBSTRUCTURE


5 Providing PCC/RCC mechanically mixed concrete in abutment,Pier,wing wall,return wall,curtainwall, toe
wall with graded stone aggregate 40mm nominal size and clean coarse sand of FM 2 and above , well
screened, free from all dirt ,dust shells and other deleterious materials,including cost of all materials form
work ,labour,handling material at site,centering and shuttering, screening, mixing in cement
mixer,placingin position,vibrating,hire and running charges of concrete mixer and needle vibrater, curing
cost of water with all leads and lifts,all taxes and royalties, incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other lubricants,pay ofmachinary staff , providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as perdesign/ drawing and technical specification and MORT&H specificationclauses and other
relevant clauses and direction of E/I(excluding cost of reinforcement and it's cutting ,bending ,binding etc.)
M30
GRADE

ABUTMENT SHAFT-A1 m3 1x 16.00 x 1.00 x 0.787 = 12.59

ABUTMENT SHAFT A2 1X 16.00 x 1.00 x 1.887 = 30.19

PIER (AVG)
PIER STEM P1 m3 2 x 9.00 x 1.00 x 1.487 = 26.77
PIER NOSING m3 2 x area= 0.79 x 1.487 = 2.33
SOLID RETURN WALL(II) m3 4 x 2.30 x 5.705 x 0.300 15.75

TOTAL 87.63
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
6 Providing weep holes in PCC/RCC in abutment ,wing wall,return wallwith 100mm dia A.C. pipes ,collar
,M.S. clamps including cost of all materials and labour, ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation incidental charges,all taxes and
royalty etc.all complete job as per design/drawing and technical specification and MORT&H
specificationclauses and other relevant clauses and direction of E/I

No. 84

7
Providing PCC/RCC mechanically mixed concrete in abutment cap,pier cap ,crash barrier etc., with
graded stone aggregate 20mm nominal size and clean coarse sand of FM 2 and above , well screened,
free from all dirt ,dust shellsand other deleterious materials,including cost of all materials form work
,labour,handling material at site, centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater, curing cost of water with
all leads and lifts,all taxes and royalties,incidental charges,hire and running charges of
machinery,depreciation, major/minor repair,POL and other lubricants,pay of machinary staff ,providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification clauses and other
relevant clauses and direction of E/I(excluding cost of reinforcement and it's cutting ,bending ,binding etc.)

(a)RCC M-30
ABUTMENT CAP
RECTANGULAR PART 2x 16.00 x 1.05 x 0.3 = 10.08
HAMMER HEAD
RECTANGULAR PART 2x 13.5 x 1.3 x 0.6 = 21.06
TRAPEZOIDAL PART 2x 11.25 x 1.3 x 1.10 = 32.175

DIRT WALL 2x 16.00 x 0.30 x 3.044 = 29.22


BRACKET 2x 15.40 x 0.25 x 0.18 = 1.39
2x 15.40 x 0.25 x 0.06 = 0.23
PEDESTRAL 30 1x 0.80 x 0.70 x 0.250 = 4.20

Total 98.35
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
8
Providing HYSD bars in all types of RCC works in abutment,return wall ,pier shaft, abutment cap, pier
capincluding cutting to sizes,bending,binding,placing in position on cement cubeswith cost of all
materials,labour,tools and plants,all taxes,handling materials at siteand incidental charges,all complete
job as per design/drawing and technical specification and MORT&H specifications clauses and other
relevant clauses and direction of E/I

ABUTMENT SHAFT MT 3.50


ABUTMENT CAP MT 0.79
DIRTWALL MT 3.20
RETURN WALL MT 0.22
BRACKET MT 0.65
PEDESTRAL MT 0.55
PIER SHAFT MT 4.94
HAMMER HEAD MT 14.80
Total 28.638
BILL NO. 3 : SUPERSTRUCTURE
9 Providing P.C.C.M15 ordinary grade mechanically mixed concrete below approach slab ,as levelling
course with graded stone aggregate 40mm to 10mm size and clean coarse sand of FM 2 and above , well
screened, free from all dirt ,dust shellsand other deleterious materials,including cost of all materials form
work ,labour,handling material at site,tools and plants, curing cost of water with all leads and lifts,all taxes
and royalties,incidental charges,hire and running charges of machinery,depreciation,major/minor
repair,POL and other lubricants,pay ofmachinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete job as
perdesign/drawing and technical specification and MORT&H specification clauses and other relevant
clauses and direction of E/I

CONCRETE UNDER APPROACH SLAB m3 2x 3.5 x 15.4 x 0.15 = 16.17


SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
10 Providing PCC/RCC mechanically mixed concrete in Deck slab,girder,bed block,and Foot path, with
graded stone aggregate20mm nominal size and clean coarse sand of FM 2 and above , well screened,
free from all dirt ,dust shellsand other deleterious materials,including cost of all materials form work
,labour,handling material at site,centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater, curing cost of water with
all leads and lifts,all taxes and royalties,incidental charges,hire and running charges of
machinery,depreciation,major/minor repair,POL and other lubricants,pay of machinary staff ,providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification clauses and other
relevant clauses and direction of E/I(excluding cost of reinforcement and it's cutting ,bending ,binding etc.)

M35
TOTAL CONCRETE IN SUPERSTRUCTURE m3 3.00 243.98 731.934
(excluding railing)
Total 731.93
11 Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and medians, constructed with M-40 grade
concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and
installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24
June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as
specified) M40
Crash Barrier

m 3x 24.6 X 2 = 147.6
APPROACH SLAB m 2x 3.5 X 2 = 14
Total 161.60
12 Providing precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm,true to the line and
grade,tolerance of RCC vertical post not to exceed 1 in 500,centre to centre spacing between the vertical
post not to exceed 2000mm, leaving adequate space between vertical post for expansion,complete as per
approved drawing and Technical specification
m 3 x 24.6 X 2 = 147.6
m 2 x 3.5 x 2 = 14
APPROACH SLAB
Total 161.60
13 Providing and laying Reinforced cement concrete wearing coat M30 grade including reinforcement
complete as per drawing and Technical specification

m3 3x 24.6 x 11 x 0.075 = 60.89


2x 3.5 x 11 x 0.075 = 5.78
Total 66.66
14 Providing and laying RCC Approach slab M30 grade including reinforcement and formwork complete as
per drawing and Technical specifications

m3 2x 3.5 x 15.4 x 0.30 = 32.34


SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT
15
Providing drainage spouts with 260mmx260mm M.S. grating 100 mm dia. 1.00m long G.I. pipe including
cost of all labour and materialall complete job as per design/drawing and technical specification and
MORT&H specification clauses and other relevant clauses and direction of E/I
No. 3x 6 18
16 Supplying ,fitting and fixing elastomeric bearing conforming to IRC 83(part -I) section-IX in position ,true to
lines and level including all accessories,neoprene w.r.l.m.s. plate ,all labour including machinary inputs for
various processing operations like gas cutting .fabrication,converting into elastometric compound of
required specifications,for adding chemicals like primer for plates and final bonding agents of plates to
elastomer, for pretreatment,bonding /vulcanizing of elastometric compound with reinforcing steel
plate,hire and running charge of machinery with depreciation,major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation etc. all complete job as per design/drawing and technical specification and
MORT&H specification design/drawing and technical specification and MORT&H specificationclauses
and other relevant clauses and direction of E/I

cm3 30 x 56 x 40 x 9.6 = 645120


17 Providing HYSD bars in all types of RCC works in Girder, Deck slab ,bed ,block, abutment,return wall ,pier
shaft, abutment cap, pier capincluding cutting to sizes,bending,binding,placing in position on cement
cubeswith cost of all materials,labour,tools and plants,all taxes,handling materials at siteand incidental
charges,all complete job as per design/drawing and technical specification and MORT&H specifications
clauses and other relevant clauses and direction of E/I

SUPERSTRUCTURE MT 3.00 x 37.83 = 113.49


18
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum
horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
m 4.00 x 16.00 = 64
SL.
NO. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
HEIGHT

BILL NO. 4: PROTECTION WORK


19 Back filling behind the abutment,wing wall and return wall including foundation trenches with granular
material combined with all leads and lifts at site including cost of all materials,labour,tools and
plants,watering,cost of water with all leads and lifts ,dressingand ramming,free from grass and other loose
deleterious materials likely to deteriorate,,providing light,barrier,danger signals,choukidar,making and
maintaining diversion,traffic regulation all complete job as per design/drawing and technical specification
and MORT&H specification clause 304 and other relevant clauses and direction of E/I

Area(m2) Width(av.)

ABUTMENT A1 1x 14.37 x 16.00 = 229.88


ABUTMENT A2 1x 18.22 x 16.00 = 291.48

m3 Total 521.36
20 Providing filter media with stone metal grade-III conforming to MORT&HTable 400-7,free from grass,dirt
and debris and other loose and deleterious materials likely to deteriorate,,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation incidental charges,all taxes and
royalty etc.all complete job as per design/drawing and technical specification and MORT&H specification
clause 305 and other relevant clauses and direction of E/I

ABUTMENT A1 1x 16 x 3.58 x 0.6 = 34.37


ABUTMENT A2 1x 16 x 4.68 x 0.6 = 44.93
m3 Total = 79.30

21 Providing , laying,fitting,fixing stone boulder pitching duly packed in slope of road embankment and
approach with approved quality of materials within 150m of worksite and all lift as per direction of E/I
including cost of all materials , labour
m3 2 x(2X 27.1 + 3.8 )x 0.6 = 69.60
Total 69.60
22 Providing and laying Filter material underneath pitching in slopes all complete as per drawing and
=
Technical specification m3 2 x(2X 27.1 + 3.8 x 0.15 17.40
23
CONFIRMATORY BORING m 4 20 = 80
24 Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered
concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ =
of 1 litre for 2 Sq.m. ) (Crash Barrier) m2 6 x 24.6 2.373 350.25
25 Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered
concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @
of 1 litre for 2 Sq.m. )(Hand rail) sqm 234 1.595 0.69 257.529
168 1.1 1.05 194.040
TOTAL 451.569
REINFORCEMENT QUANTITY
LENGTH WIDTH NO DIA OF BAR THICKNESS THICKNESS THICKNESS LENGTH OF BAR SPACING NO OF BAR WT PER M QUANTITY (KG)
AT TIP OF SHAFT AT BASE

ABUTMENT FOUNDATION
A1/A2, OPEN FOUNDATION
16.00 1.70
TOE 2 20 0.6 1.0 1.60 3.8 150 107 2.46 2004.46
2 12 0.6 1.0 1.60 17.8 150 11 0.89 347.49
2 10 0.6 1.0 2.54 4.21 200 80 0.62 414.87
2 10 0.6 1.0 17.00 200 16 0.62 335.23
16.00 2.30
HEEL 2 20 0.6 1.0 2.30 5.02 150 107 2.46 2647.97
2 12 0.6 1.0 2.30 17.8 150 15 0.89 473.85
2 10 0.6 1.0 1.60 3.8 200 80 0.62 374.66
2 10 0.6 1.0 17.0 200 17 0.62 356.18

TOTAL IN ABUTMENT FOUNDATION = 6954.71


ABUTMENT SHAFT
NO. HEIGHT LENGTH WIDTH DEPTH OF THICKNESS DIA OF LENGTH OF NO. OF BAR NO. OF BAR WT PER M QUANTITY (KG)
OF OF HEEL AT OF ABUT. MAIN BAR BAR ON EACH ON BOTH
SHAFT SHAFT BASE CAP FACE FACE
2 0.787 16.00 1.0 1.6 0.3 16 4.287 107 214 1.58 2894.52
2 10 34.3 150 5 0.62 211.37
2 10 1.2 150 268 0.62 395.62
Total in abutment shaft1 = 3501.50
ABUTMENT CAP
2 16.00 1.05 0.3 12 16.6 12 0.89 353.53
2 16.00 1.05 0.3 12 2.3 150 107 0.89 436.76
Total in abut. Cap = 790.29
REINFORCEMENT QUANTITY
DIRT WALL
No. Ht. Length Thickness Th. Abut cap
2 3.344 16.00 0.3 16 4.24 150 107 1.58 1432.74
2 12 16 200 17 0.89 482.73
2 12 4.244 200 107 0.89 805.92
2 12 16 200 17 0.89 474.78

Total in dirt wall 3196.16


SOLID RETURN WALL
no. depth
4 0.30 2.3 16 3.30 2 1.58 41.65
4 0.30 2.3 12 0.90 120 19 0.89 60.70
4 0.30 2.3 12 0.90 100 23 0.89 73.47
4 2.9 0.30 12 2.9 150 2 0.89 20.59
4 2.9 0.30 12 2.9 150 2 0.89 20.59

Total in R/Wall = 216.99

PIER OPEN FOUNDATION


NO LENGTH WIDTH THICKNESS THICKNESS THICKNESS DIA OF LENGTH OF SPACING NO OF BAR WT PER M QUANTITY
AT TIP AT BASE OF SHAFT BAR BAR

2 10.00 4.00 0.6 1.4 1 20 5.2 150 67 2.46 1709.00


2 12 11.2 200 20 0.89 397.54
2 1.5 10 5.60 200 50 0.62 345.09
2 10 11.2 200 20 0.62 276.07
Total in pier foundation = 2727.69
PIER SHAFT
no. ht length of width of depth of Thickness dia of Length of spacing no. of bar wt. per Quantity
shaft shaft heel at of pier main bar bar of bar on both m length
base cap face
2 1.487 9.00 1.0 1.4 1.70 16 6.087 100 192 1.58 3687.35
2 12 19.8 200 14 0.89 491.95
2 12 1.2 200 357 0.89 760.04
Total in pier shaft = 4939.338
HAMMER HEAD
no length width depth dia of bar length spacing no. wt.per m quantity
2 13.5 1.30 1.6 32 14.5 14 6.31 2561.92
2 13.5 1.30 1.6 32 14.5 120 11 6.31 1982.44
2 16 17.0 100 135 1.58 7240.89
2 12 30.3 7 0.89 376.92
2 12 13.2 120 113 0.89 2635.47
Total in hammer head = 14797.63
PEDESTAL
30 0.80 0.70 0.25 12 2.05 150 5 0.89 291.06
30 0.80 0.70 0.25 12 2.05 150 5 0.89 254.67
Total in Pedestral = 545.73
Analysis of rates for Bridge work
(1)E/W in excavation of foundation trenches in
(i) Ordinary Soil (Rate Vide item no.12.1B(i) of NH S.O.R.) 61.08
(ii) Ordinary Soil (Rate Vide item no.12.1B(ii) of NH S.O.R.) per m3 Rs. 69.81

(iii) Ordinary Rock(Rate Vide item no.12.1(II)B of NH S.O.R.) per m3 Rs. 75.63
(iv) Hard Rock Rate Vide item no.12.1(iv)A of NH S.O.R.) per m3 Rs. 388.81
(2) Providing steel liner 10mm thick ------------
Basic rate vide item no.12.22 of N.H.S.O.R. per MT Rs. 65376.96
Carriage of steel 1.05 x 359.30 Rs. 377.27
Rs. 66411.77
(3) Bored cast insitu M35 grade R.C.C. piles -----------
Basic rate vide item no.12.25 of N.H.S.O.R. per m Rs. 10568.64
Carriage of materials
cement 0.474 MT x Rs. 359.30 = Rs. 170.31
sand 0.51 m3 x Rs. 349.32 = Rs. 178.15
Metal 0.305 m3 x Rs. 487.61 = Rs. 148.72
chips 0.275 m3 x Rs. 459.72 = Rs. 126.42
Finished rate per m = Rs. 10003.69

(4) Providing and laying P.C.C. M15 Levelling course under the pile cap
Basic rate vide item no.12.39 of N.H.S.O.R. per m3 Rs. 3776.64
Carriage of materials
cement 0.275 MT x Rs. 359.30 = Rs. 98.81
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.54 m3 x Rs. 487.61 = Rs. 263.31
chips 0.36 m3 x Rs. 459.72 = Rs. 165.50
Finished rate per m3 = Rs. 4506.06

(5) Providing R.C.C.M35 in pile cap


Basic rate vide item no.12.38 D(i) of N.H.S.O.R. per m3 Rs. 4998.72
Carriage of materials
cement 0.422 MT x Rs. 359.30 = Rs. 151.62
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 5778.50
(6) Pile load test on single vertical
Basic rate vide item no.12.37 of N.H.S.O.R. per MT Rs. 5138.88

(7) Back filling behind the abutment, wing wall with Granular Material
Basic rate Vide item no.13.9 A of NH S.O.R. per m3 Rs. 524.16
Carriage of material
Moorum 1.2 m3 x Rs. 213.22 Rs. 255.86
Finished rate per m3 = Rs. 787.82
(8) Providing and laying of Filter media
Basic rate vide item no.13.10 of N.H.S.O.R. per m3 Rs. 1330.56
Carriage of material
Metal 1.2 m3 x Rs. 459.72 Rs. 551.66
Finished rate per m3 = Rs. 1901.05
(9) Providing and laying P.C.C. M15 Grade levelling course below approach slab
Basic rate vide item no.14.10 of N.H.S.O.R. per m3 Rs. 3793.92
Carriage of materials
cement 0.275 MT x Rs. 359.30 = Rs. 98.81
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.54 m3 x Rs. 487.61 = Rs. 263.31
chips 0.36 m3 x Rs. 459.72 165.50
Finished rate per m3 = Rs. 4523.52

(10) (a)P.C.C. M15 - Using Concrete mixer


Basic rate vide item no.12.8(A) of N.H.S.O.R. per m3 Rs. 3944.64
Carriage of materials
cement 0.275 MT x Rs. 359.30 = Rs. 98.81
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.54 m3 x Rs. 487.61 = Rs. 263.31
chips 0.36 m3 x Rs. 459.72 165.50
Finished rate per m3 = Rs. 4675.74
(11) (b)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.12.8 (B) of N.H.S.O.R. per m3 Rs. 4425.60
Carriage of materials
cement 0.347 MT x Rs. 359.30 = Rs. 124.68
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.36 m3 x Rs. 487.61 = Rs. 175.54
chips 0.54 m3 x Rs. 459.72 = Rs. 248.25
Finished rate per m3 = Rs. 5182.57

(12) ©R.C.C. M25 - Using concrete mixer


Basic rate vide item no.12.8 (E) of N.H.S.O.R. per m3 Rs. 4838.40
Carriage of materials
cement 0.403 MT x Rs. 359.30 = Rs. 144.80
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 5609.68

(13) (d)R.C.C. M30 - Using concrete mixer FOUNDATION


Basic rate vide item no.12.8 (G)I of N.H.S.O.R. per m3 Rs. 4850.88
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 5623.74

(14) Providing P.C.C. M10 mechanically mixed concrete in abutment or pier foundation -do-do-
Basic rate vide item no.12.4 of N.H.S.O.R. per m3 Rs. 3611.52
Carriage of materials
cement 0.23 MT x Rs. 359.30 = Rs. 82.64
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
Metal 0.9 m3 x Rs. 487.61 = Rs. 438.85
Finished rate per m3 = Rs. 4333.10
(15) Providing P.C.C./R.C.C.in Substructure -do-do-
(a)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.13.5 (E)(p)I of N.H.S.O.R. per m3 Rs. 4707.84
Carriage of materials
cement 0.347 MT x Rs. 359.30 = Rs. 124.68
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 5457.49

(16) (a)R.C.C. M25 - Using Concrete mixer


Basic rate vide item no.13.5 (F)(p)I of N.H.S.O.R. per m3 Rs. 5131.20
Carriage of materials
cement 0.403 MT x Rs. 359.30 = Rs. 144.80
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 5905.41
(b)R.C.C. M25 - Using Concrete mixer
Basic rate vide item no.14.1 (B)(i)p of N.H.S.O.R. per m3 Rs. 5935.00
Carriage of materials
cement 0.403 MT x Rs. 359.30 = Rs. 144.80
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 6717.25

(17) (a)R.C.C. M30 - Using Concrete mixer SUBSTRUCTURE


Basic rate vide item no.13.5 (G)(p)I of N.H.S.O.R. per m3 Rs. 5371.00
Upto 5.0 m height
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 6149.06
(b)R.C.C. M30 - Using concrete mixer
Basic rate vide item no.13.5 (G)(q)I of N.H.S.O.R. per m3 Rs. 5522.00
upto 5.0 m to 10.0 m height
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 6301.57
(C)R.C.C. M35 - Using concrete mixer
Basic rate vide item no.13.5 (H.)(q)I of N.H.S.O.R. per m3 Rs. 5612.00
upto 5.0 m to 10.0 m height
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 6392.47
(18) (a)R.C.C. M35 - Using Concrete mixer

SUPERSTRUCTURE

Basic rate vide item no.14.1 D(i)(q) of N.H.S.O.R. per m3 Rs. 6166.00
Carriage of materials

cement 0.422 MT x Rs. 359.30 = Rs. 151.62


sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
Finished rate per m3 = Rs. 6957.45

(19) Providing weep holes -do-do-


Basic rate vide item no.13.8 of N.H.S.O.R. each Rs. 120.96
Carriage of A.C. Pipe 1.05 m Rs. 0.00
Rs. 122.17

(20) supplying ,fitting and placing HYSD bars -do-do-

(a) Foundation
Basic rate vide item no.12.40 of N.H.S.O.R. per MT Rs. 53467.20
carriage of steel
1.05 MT x Rs. 359.30 Rs. 377.27
Finished rate per MT = Rs. 54382.91

(b) Sub Structure


Basic rate vide item no.13.6 of N.H.S.O.R. per MT Rs. 53594.88
carriage of steel
1.05 MT x Rs. 359.30 Rs. 377.27
Finished rate per MT = Rs. 54511.87

(c) Super Structure


Basic rate vide item no.14.2of N.H.S.O.R. per MT Rs. 54696.00
carriage of steel
1.05 MT x Rs. 359.30 Rs. 377.27
Finished rate per MT = Rs. 55624.00

(21) Providing and laying M30 Grade c.c. wearing coat including reinforcement
Basic rate vide item no.14.4 of N.H.S.O.R. per m3 Rs. 8668.80
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
steel 0.075 MT x Rs. 359.30 Rs. 26.95
Finished rate per m3 = Rs. 9507.05

(22) Construction of insitu R.C.C.crash barrier of M40 grade -do-do-


Basic rate vide item no.14.6 of N.H.S.O.R. per m Rs. 2514.00
Carriage of materials
cement 0.043 MT x Rs. 359.30 = Rs. 15.45
sand 0.045 m3 x Rs. 349.32 = Rs. 15.72
chips 0.089 m3 x Rs. 459.72 = Rs. 40.92
steel 0.028 MT x Rs. 359.30 Rs. 10.06
Finished rate per m = Rs. 2622.11
(23) Construction of insitu R.C.C. railing of M30 grade -do-do-
Basic rate vide item no.14.6 of N.H.S.O.R. per m Rs. 1460.16
Carriage of materials
cement 0.035 MT x Rs. 359.30 = Rs. 12.58
sand 0.038 m3 x Rs. 349.32 = Rs. 13.27
chips 0.076 m3 x Rs. 459.72 = Rs. 34.94
steel 0.018 MT x Rs. 359.30 Rs. 6.47
Finished rate per m = Rs. 1542.69
(24) Providing P.C.C./R.C.C.in Substructure -do-do-
(a)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.8.22 of N.H.S.O.R. per m3 Rs. 2413.44
Carriage of materials
cement 0.1041 MT x Rs. 359.30 = Rs. 37.40
sand 0.135 m3 x Rs. 349.32 = Rs. 47.16
chips 0.27 m3 x Rs. 459.72 = Rs. 124.12
steel 0.028 MT x Rs. 359.30 Rs. 10.06
Finished rate per m3 = Rs. 2658.51

(25) Drainage spouts -do-do-


Basic rate vide item no.14.9 of N.H.S.O.R. each Rs. 852.28

(26) Providing and laying R.C.C.M30 in approach slab -do-do-


Basic rate vide item no.14.11 of N.H.S.O.R. per m3 Rs. 7344.96
Carriage of materials
cement 0.407 MT x Rs. 359.30 = Rs. 146.24
sand 0.45 m3 x Rs. 349.32 = Rs. 157.19
chips 0.90 m3 x Rs. 459.72 = Rs. 413.75
steel 0.050 MT x Rs. 359.30 Rs. 17.97
Finished rate per m3 = Rs. 8160.90

(27) Providing painting two coats on unplastered concrete surface -do-do-


Basic rate vide item no.14.16 of N.H.S.O.R. per m2 Rs. 72.72

(28) Providing and fixing of retro-reflectorised ,cautionary,mandatory and


informatory sign -do-do-
(i) 90 cm. triangle Basic rate vide item no.8.4(i) of N.H.S.O.R. Each Rs. 4723.89
60 cm.
(ii) Strip triangle
Seal Basic rate
Expansion Joint (Providing andvide itemofno.8.4(ii)
laying a strip of N.H.S.O.R.
seal expansion Each Rs. 2925.28
joint
(iii) 80 catering
cm.x60 cm. to maximum horizontal movement
Basic rate vide item upto 70 mm,
no.8.4(vi) complete
of N.H.S.O.R. Each Rs. 5929.10
(29) as per approved drawings and standard specifications to be installed by Rs. 8496.60
14.22
(30) the manufacturer/supplier or their authorised representative ensuring
Supplying, fitting and fixing in position true to line and level elastomeric
13.14 compliance to the manufacturer's instructions for installation.)
bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of
MoRTH specifications complete including all accessories as per drawing
and Technical Specifications.
Rs. 0.70

(31) Supplying, fitting and fixing in position true to line and level POT-PTFE Rs. 171.84
bearing
ABSTRACT OF COST FOR APPROACH ROAD

Sl.No. Items of work Quantity Rate Amount


1.00 GENERAL
Cutting of trees along with branches and
their removal from the work site as per
MOSRT&H Specification Cl. No.201 with the
1.01 following girth sizes
a) 300mm to 600m m 0 No. @ Rs. 199.00 Each Rs. 0.00
a) 600mm to 900m m 0 No. @ Rs. 333.00 Each Rs. 0.00
a) 900mm to 1800m m 7 No. @ Rs. 681.00 Each Rs. 4767.00
a) >1800 mm 0 No. @ Rs. 1321.00 Each Rs. 0.00

2.00 EARTH WORK


Clearing and Grubbing the road land,
(Clearing and grubbing the road land
including uprooting rank
vegetation,grass,bushes,shrubs,saplings
and trees girth upto 300mm ,removal of
2.01 stumps of trees cut earlier and disposal of
unserviceable materials and stacking of
sercviceable materials to be used or
auctioned upto a lead of 1000 mts. including
removal and disposal of organic soil not
exceeding 150mm in thickness. 0.65 hect @ Rs. 39340.00 per hect Rs. 25492.32

Excavation for roadwork in soil with hydraulic


excavator of 0.9 cum bucket capacity
including cutting and loading in tippers,
trimming bottom and side slopes, in
accordance with requirements of lines,
2.02
grades and cross sections, and transporting
to the embankment location within all lifts
and lead upto 1000m (including royality @
Rs. 15.00 per cum but excluding watering,
rolling & compaction) 3726.60 m3 @ Rs. 117.00 per m3 Rs. 436012.20

Construction of embankment with approved


material obtained fromborrow pits with all
leads and lifts ,trasporting to site
,spreading ,grading to required slope and
2.03
compacting to meet requirement of table300-
2 including cost of watering ,rolling and
compaction all complete as per specification
and direction of E/I 17567.7 m3 @ Rs. 210.00 per m3 Rs. 3689217.00
Construction of embankment with approved
materials deposited at site from road way
cutting and excavation from drain and
foundationof other structures graded and
2.04 compacted to meet requirement of table 300-
2 including cost of watering ,rolling and
compaction all complete as per specification
and direction of E/I
Rolling with vibratory Roller 13841.10 m3 @ Rs. 134.00 per m3 Rs. 1854707.40

Providing , laying,fitting,fixing stone boulder


pitching duly packed in slope of road
embankment and approach with approved
2.05
quality of materials within 150m of worksite
and all lift as per direction of E/I including
cost of all materials , labour 72.00 m3 @ Rs. 1958.74 per m3 Rs. 141029.57

Providing and laying Filter material

2.06 underneath pitching in slopes all complete

as per drawing and Technical specification 36.0 m3 @ Rs. 2600.82 per m3 Rs. 93629.66
Construction of Subgrade and Earthen
Shoulders (Construction of subgrade and
earthen shoulders with approved material
2.07 obtained from borrow pits with all lifts &
leads, transporting to site, spreading,
grading to required slope and compacted to
meet requirement of table No. 300-2) 986.08 m3 @ Rs. 235.0 per m3 Rs. 231727.86

3.0 GRANULAR SUB BASE


Construction of granular sub-base by
providing coarse graded material, spreading
in uniform layers with motor grader on
prepared surface, mixing by mix in place
3.01 method with rotavator at OMC, and
compacting with vibratory roller to achieve
the desired density, complete as per clause
401.
GSB Gr-I 837.84 m3 @ Rs. 2007.79 per m3 Rs. 1682210.06
4.0 BASE COURSE
Wet Mix Macadam (Providing, laying,
spreading and compacting graded stone
aggregate to wet mix macadam specification
including premixing the Material with water at
OMC in mechanical mix plant carriage of
4.01
mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base
course on well prepared surface and
compacting with vibratory roller to achieve
the desired density.) 715.20 m3 @ Rs. 2217.99 per m3 Rs. 1586309.94

5.0 BITUMINOUS SURFACE


Providing and applying primer coat with
bitumen emulsion on prepared surface of
granular base including clearing of the road
5.01 surface and spraying primer @0.60 kg/sqm
using mechanical means . As per
MOSRT&H specification 502 (4th revision )
& as per direction of E/I. 2760.0 m2 @ Rs. 29.66 per m2 Rs. 81866.79

Providing and applying tack coat with

bitumen emulsion using emulsion pressure

5.02 distributor at the rate of 0.20 kg per sqm on

the prepared bituminous/granular surface

cleaned with mechanical broom. 5520 m2 @ Rs. 10.55 per m2 Rs. 58257.86

Providing and laying Bituminous Concrete

5.03 wearing course complete as per drawing and

Technical Specifications as per Clause 509 110.40 m3 @ Rs. 9303.40 per m3 Rs. 1027095.88
Providing and laying Dense Graded

Bituminous Macadam (DBM) complete as


5.04
per Technical Specifications as per Clause

507 276.0 m3 @ Rs. 8343.71 per m3 Rs. 2302864.58

6.0 Miscellaneous work


Providing and laying of hot applied
thermoplastic compound 2.5mmthick
including reflectorising glass beads
@250gms / sq.m. area ,thickness of 2.5mm
6.01
is exclusive of surface applied glass beads
as per IRC:35.The finished surface to be
level,uniform and free from streaks .and
holes 113.94 m2 @ Rs. 548.00 per m2 Rs. 62439.12

Providing and fixing of retro- reflectorised


cautionary, mandatory and informatory sign
as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported
on a mild steel angle iron post 75 mm x 75
6.02
mm x 6 mm firmly fixed to the ground by
means of properly designed foundation with
M15 grade cement concrete 45 cm x 45 cm
x 60 cm, 60 cm below ground level as per
approved drawing
80 cmx60cm Rectangular 0 nos. @ Rs. 12464.00 Each Rs. 0.00

6.03

Type - A, "W" : Metal Beam Crash Barrier


(Providing and erecting a "W" metal beam
crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm
above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 1.8 m high,
1.1 m below ground/road level, all steel parts
and fitments to be galvanised by hot dip
process, all fittings to conform to IS:1367
and IS:1364, metal beam rail to be fixed on
the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long
complete as per clause 810) 160 m @ Rs 3004.00 per m Rs 480640
Road Markers/Road Stud with Lense
Reflector (Providing and fixing of road stud
6.04 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit,
fitted with lense reflectors, installed in
concrete or asphaltic surface by drilling hole
30 mm upto a depth of 60 mm and bedded
in a suitable bituminous grout or epoxy
mortar, all as per BS 873 part 4:1973) 180 nos 244.00 per No Rs. 43920
Supplying and installation of delineators

(road way indicators, hazard markers, object

markers), 80-100 cm high above ground

level, painted black and white in 15 cm wide


6.04
strips, fitted with 80 x 100 mm rectangular or

75 mm dia circular reflectorised panels at the

top, buried or pressed into the ground and

conforming toIRC-79 and the drawings. 50 nos. @ Rs. 653.00 Each Rs. 32650.00

Total Rs. 13834837.237


DETAIL OF QUANTITY FOR APPROACH ROAD

Length of approach road = 360 = 360 m


Taper portion in Approach road = 120 m (combined both sides)

Sl. Items of work No. Length Breadth Depth Quantity Unit


No. m m m
1.00 GENERAL
1.01 Cutting of trees along with branches and
their removal from the work site as per

MOSRT&H Specification Cl. No.201 with

the following girth sizes


a) 300mm -600mm 0 0 Nos.
b)600mm-900mm 0 0 Nos.
c)900mm-1800mm 7 7 Nos.
d) >1800mm 0 0 Nos.

1.02 Dismantling of flexible pavements and


disposal of dismantled materials up to
a lead of 1000 metres, stacking
serviceable and unserviceable
materials separately
(i) Bituminous Course by mechanical
means 0.00 x 7.0 x 1 = 0 m3
2.00 EARTHWORK
2.01 Clearing and Grubbing the road land,
(Clearing and grubbing the road land
including uprooting rank
vegetation,grass,bushes,shrubs,saplings
and trees girth upto 300mm ,removal of
stumps of trees cut earlier and disposal of
unserviceable materials and stacking of
sercviceable materials to be used or
auctioned upto a lead of 1000 mts.
including removal and disposal of organic
soil not exceeding 150mm in thickness. 360 x 18 0.648 Hect.

2.02 Excavation for roadwork in soil with


hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in
tippers, trimming bottom and side slopes,
in accordance with requirements of lines,
grades and cross sections, and
transporting to the embankment location
within all lifts and lead upto 1000m
(including royality @ Rs. 15.00 per cum
but excluding watering, rolling &
compaction) Quantity as per calculation chart 3726.60 m3

A47
2.03 Construction of embankment with

approved material obtained fromborrow

pits with all leads and lifts ,trasporting to

site ,spreading ,grading to required slope

and compacting to meet requirement of

table300-2 including cost of watering

,rolling and compaction all complete as

per specification and direction of E/I


Rolling with vibratory Roller Quantity as per calculation chart 17567.70 m3

2.04 Construction of embankment with


approved materials deposited at site from
road way cutting and excavation from
drain and foundation of other structures
graded and compacted to meet
requirement of table 300-2 including cost
of watering ,rolling and compaction all
complete as per specification and
direction of E/I
Rolling with vibratory Roller Quantity as per calculation chart 13841.10 m3

2.05 Providing , laying,fitting,fixing stone

boulder pitching duly packed in slope of

road embankment and approach with

approved quality of materials within 150m

of worksite and all lift as per direction of

E/I including cost of all materials , labour 4x 20.0 x 3.0 x 0.3 = 72 m3

2.06 Providing and laying Filter material


underneath pitching in slopes all
complete as per drawing and Technical
specification 4x 20.0 x 3.0 x 0.15 = 36 m3

A48
2.07 Construction of Subgrade and Earthen
Shoulders (Construction of subgrade and
earthen shoulders with approved material
obtained from borrow pits with all lifts &
leads, transporting to site, spreading,

grading to required slope and compacted


to meet requirement of table No. 300-2)
Approach Taper portion
2 x 120.0 x 2.795 x 0.49 = 328.692
Approach to road 2 x 240.0 x 2.795 x 0.49 = 657.384
986.08 m3

A49
3.00 GRANULAR SUB BASE
3.01 Construction of granular sub-base by
providing coarse graded material,
spreading in uniform layers with motor
grader on prepared surface, mixing by
mix in place method with rotavator at
OMC, and compacting with vibratory
roller to achieve the desired density,
complete as per clause 401.
GSB Gr-I
Drainage layer

Approach Taper portion 1 x 120.0 x 16.2 x 0.1 = 193.92


Approach to road 1 x 240.0 x 14.2 x 0.1 = 339.84
GSB Layer

Approach Taper portion 1 x 120.00 x 9.78 x 0.10 = 117.36


Approach to road 1 x 240.0 x 7.78 x 0.10 = 186.72
837.84 m3
4.00 BASE COURSE
4.01 Wet Mix Macadam (Providing, laying,
spreading and compacting graded stone
aggregate to wet mix macadam
specification including premixing the
Material with water at OMC in mechanical
mix plant carriage of mixed Material by
tipper to site, laying in uniform layers with
paver in sub- base / base course on well
prepared surface and compacting with
vibratory roller to achieve the desired
density.)
1ST LAYER
Approach Taper portion 1 x 120.00 x 9.28 x 0.125 = 139.2
Approach to road 1 x 240.0 x 7.28 x 0.125 = 218.4
2ND LAYER
Approach Taper portion 1 x 120.00 x 9.28 x 0.125 = 139.2 m3
Approach to road 1 x 240.00 x 7.28 x 0.125 = 218.4 m3
m3
715.20 m3

A50
5.00 BITUMINOUS WORK
5.01 Providing and applying primer coat with
bitumen emulsion on prepared surface of

granular base including clearing of the

road surface and spraying primer @0.60

kg/sqm using mechanical means . As per

MOSRT&H specification 502 (4th

revision ) & as per direction of E/I.


Approach Taper portion 1 x 120.00 x 9 = 1080.00 m2
Approach to road 1 240.00 x 7.0 1680.00 m2
2760.00 m2
5.02 Providing and applying tack coat with
bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg
per sqm on the prepared
bituminous/granular surface cleaned with
mechanical broom.
Approach Taper portion 2 120.00 x 9 2160.0 m2
Approach to road 2 240.00 x 7 3360.0 m2
5520 m2
5.03 Providing and laying Bituminous
Concrete wearing course complete as per
drawing and Technical Specifications as
per Clause 509
Approach Taper portion 1 120.00 x 9 x 0.04 = 43.2 m3
Approach to road 1 240.00 x 7 x 0.04 = 67.2 m3
110.40 m3
5.04 Providing and laying Dense Graded

Bituminous Macadam (DBM) complete as

per Technical Specifications as per

Clause 507
Approach Taper portion 1 120.00 x 9 x 0.100 = 108 m3
Approach to road 1 240.00 x 7 x 0.100 = 168 m3
276 m3

A51
6.00 MISC. WORK
6.01 Providing and laying of hot applied
thermoplastic compound 2.5mmthick
including reflectorising glass beads
@250gms / sq.m. area ,thickness of
2.5mm is exclusive of surface applied
glass beads as per IRC:35.The finished
surface to be level,uniform and free from
streaks .and holes
edge 2 x 360 x 0.15 = 108 m2
Centre 1 x 360 x 0.10 x 0.33 = 5.94 m2
113.940 m2
6.02 Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory
sign as per IRC :67 made of high
intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle
iron post 75 mm x 75 mm x 6 mm firmly
fixed to the ground by means of properly
designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm,
60 cm below ground level as per
approved drawing
80 cmx60cm Rectangular 0.0 Nos.
6.03

Type - A, "W" : Metal Beam Crash Barrier


(Providing and erecting a "W" metal beam
crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm
above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 1.8 m
high, 1.1 m below ground/road level, all
steel parts and fitments to be galvanised
by hot dip process, all fittings to conform
to IS:1367 and IS:1364, metal beam rail
to be fixed on the vertical post with a
spacer of channel section 150 x 75 x 5
mm, 330 mm long complete as per clause
810) 2x 80 160.0 m

Road Markers/Road Stud with Lense


Reflector (Providing and fixing of road
stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and
grit, fitted with lense reflectors, installed in
concrete or asphaltic surface by drilling
hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or
epoxy mortar, all as per BS 873 part
6.04 4:1973) 3x 360 / 6 180 Nos

6.05 Supplying and installation of delineators


(road way indicators, hazard markers,
object markers), 80-100 cm high above
ground level, painted black and white in
15 cm wide strips, fitted with 80 x 100 mm
rectangular or 75 mm dia circular
reflectorised panels at the top, buried or
pressed into the ground and conforming
toIRC-79 and the drawings. 50 Nos.

A52
CALCULATION OF E/W IN FILLING OR CUTTING IN APPROACH ROAD ROAD.

Towards (Length of Approach Road =240mm) (GUMLA SIDE)


chainage area of E/W area of E/W Av.area Av. Area length volume in volume in
in filling in cutting in filling in cutting filling cutting
m m2 m2 m2 m2 m m3 m3
0.00 65.6
60.00 33.6 0.0 49.6 0 60 2976.00 0.00
120.00 9.1 7.70 21.35 3.85 60 1281.00 231.00
240.00 1.32 6.12 5.21 6.91 120 625.20 829.20
4882.20 1060.20
Towards (Length of Approach Road =120 m) (BIRMITHRAPUR SIDE)
0.00 65.6
30.00 49.6 0 57.6 0 30 1728.00 0.00
60.00 9.1 7.28 29.35 3.64 30 880.50 109.20
120.00 1.32 7.28 5.21 7.28 60 312.60 436.80
12685.50 2666.40

Total volume of E/W in Filling = 17567.70 m3

Total volume of E/W in cutting = 3726.60 m3

Earth to be obtained from borrow pit = 13841.10 m3

A53
Estimate for proposed Diversion Road
Length of Diversion= 355 m

Assume avg embankment ht.= 1m


Item no. Item Unit Qty Rate Amount (Rs) Remarks
1 EARTHWORK
Construction of embankment
with approved material
obtained from borrow pits with
all lifts & leads, transporting to
site, grading to reqd slope &
compacting to meet reqirement
of table 300.2, including cost of
watering, rolling & compaction
with vib roller as per MOSRT & H
sp.cl. 305 vide NHSR 3.16
Quanty = 100 x 5279.644 210.00 1108725.24
((7.5+7.5+2x1.6+2x1.6)/2 x 1.6-
5.5x0.4)-3.14*0.6^2*15=
1475.044 cum

cum
2 GRANULAR SUB BASE COURSE
Construction of granular sub
base course by providing coarse
graded material Quantity =
100x5.5x0.2 = 110 cum 390.5 2007.79 784043.53

cum
3 GRANULAR BASE COURSE
WBM GR-II
3.1 Proviidng,laying,spreading &
compacting aggregates of
specific sizes to WBM
specification including spreading
in uniform thickness,packing,
rolling with roller 8-10 tonnes in
stages to proper grade &
camber, applying & brooming
requisite type of screening
materials to fill interices of 195.25 2475.44 483330.60
coarse aggregates, watering &
compacting to reqd density.
Quantity= 100x 5.5x1x
0.1=55cum

cum
WBM GR-III
Proviidng,laying,spreading &
compacting aggregates of
specific sizes to WBM
specification including spreading
in uniform thickness,packing,
rolling with roller 8-10 tonnes in
stages to proper grade &
camber, applying & brooming
requisite type of screening
materials to fill interices of
coarse aggregates, watering & 195.25 2456.90 479709.57
compacting to reqd density.
Quantity= 100x 5.5x 0.1= 55cum

cum
4 BITUMINUOUS WORK

Providing & applying primer coat


with bitumen emulsion on
4.1 prepared surface of granular 0 29.66 0.00
Base including clearing of road
surface & spraying primer at the
rate of 0.60 kg/ sqm using
mechanical means per MOSRT &
H sp.cl.502. sqm
Providing 20mm thick Premix
4.2 carpet Quantity= 100x5.5=550 1952.5 156.69 305940.93
sqm sqm
4.3 Seal coat type B sqm 0.00
Total 3161749.87
5 Cost of HP culverts in 1 rows 1.0 m dia 15 147574.99

G.total 3309324.86
Rate Analysis for Road Works for Diversion
Sl.no. Item Quantity Unit Rate (Rs) Finished rate

1 Construction of embankment with material 1 cum 210.00 210.00


obtained from borrow pits NHSOR 3.16 (ii)
2 GSB vide NHSR 4.2 (i) 1 cum 1060.00
Carriage Charge
Stone metal 0.448 cum 756.64 338.97
Stone chips 0.576 cum 951.52 548.08
Sand 0.256 cum 237.28 60.74
Total 2007.79
3 WBM
3.1 WBM Gr II vide NHSR 4.9 A (ii) (c ) 1 cum 1303.00
Carriage charge
Stone metal grade III 1.21 cum 756.64 915.53
Screening material Type B( 11.2 mm aggregate) 0.27 cum 951.52 256.91
Total 2475.44
3.2 WBM Gr III vide NHSR 4.9A (iii) (b) 1 cum 1313.00
Carriage charge
Stone metal grade III 1.21 cum 756.64 915.53
Screening material Type B( 11.2 mm aggregate) 0.24 cum 951.52 228.36
Total 2456.90
4 Bituminuous Work
4.1 Prime coat emulsion NHSR 5.1 1 sqm 29.66 29.66
4.2 Premix carpet NHSR 5.11 Type B 131.00
Carriage Charge
Stone metal graded 0.027 sqm 756.64 20.43
Bitumen 0.0019 MT 2769.80 5.26
Total 156.69
4.3 Seal coat Type B NHSR 5.12(ii) 46.00
Carriage Charge
Sand 1 cum 237.28 237.28
Bitumen 0.1132 MT 2769.80 313.54
Total 596.82
5 HP culvert
5.1 Earthwork in ordinary soil vide NHSR 3.3 130.00
5.2 PCC M-15 NHSR 12.8 A 3852.00
Carriage charge
Stone chips 0.86 cum 951.52 818.31
Sand 0.43 cum 237.28 102.03
Cement 0.33 MT 342.20 112.93
Total 4885.26
Course rubble stone masonary in CM (1:3) NHSR 3098.00
5.3 13.4 A
Carriage charge
Stone boulder 1 cum 773.12 773.12
Sand 0.35 cum 237.28 83.05
Cement 0.17 MT 342.20 58.17
Total 4012.34

A56
Sl.no. Item Quantity Unit Rate (Rs) Finished rate
5.4 Laying Boulder apron NHSR 15.11 1074.00
Carriage charge
Stone boulder 1.2 cum 773.12 927.74
Total 2001.74
5.5 Boulder pitching on slope NHSR 15.4 1031.00
Stone boulder & spalls 1.2 cum 773.12 927.74
Total 1958.74
5.6 Filter material below pitching NHSR 15.5 1459.00
Sand 1.2 cum 237.28 284.74
Total 1743.74
5.7 Laying NP 4 HP pipe NHSR 9.3 B
Laying charge 14502.00
Carriage charge
NP 4 pipe 2230.10
Total 16732.10
5.8 Tucking point NHSR 13.2 556.00
sand 0.01 237.28 2.37
Cement 0.004 342.20 1.37
Total 559.74
5.9 Back filling 122.00

A57
Estimate of Dismanting of structure

No. LENGTH WIDTH/AREA DEPTH QUANTITY

RCC 3 24.6 12 1.1 974.16 m3


Dismantling of Structures (Dismantling of existing structures like
culverts, bridges, retaining walls and other structure comprising of
2.4 masonry, cement concrete, wood work, steel work, including T&P
(ii) b and scaffolding wherever necessary, sorting the dismantled material,
disposal of unserviceable material and stacking the serviceable RCC
material with all lifts and lead of 1000 metres)

Removal of existing asphaltic wearing coat comprising of 50 mm


2.5 (i)
thick asphaltic concrete laid over 12 mm thick mastic asphalt B 3 24.6 11 0.075 60.89 m3
a
including disposal with all lift and lead upto 1000m. (wearing course)

A58
Estimate of Dismanting of structure

Sl.No. Items of work Quantity Rate Amount

974.16 per cum X 222 = 216263.52


Dismantling of Structures (Dismantling of existing structures like culverts,
bridges, retaining walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding wherever
2.4 (ii) b
necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000
metres)

Removal of existing asphaltic wearing coat comprising of 50 mm thick


2.5 (i) a asphaltic concrete laid over 12 mm thick mastic asphalt including disposal 60.89 per cum x 448 = 27276.48
with all lift and lead upto 1000m. (wearing course)

TOTAL = 243540.00

A59
Lead chart Basic rate of Carriage of Materials
NAME OF PROJECT : Rate of Carriage of materials as per S.O.R of NH Division
Multiplyi Total Lead on Lead on Lead on Hauling Hauling Hauling Loading
Charges
Charges on Charges on and Rate
MATERIAL ng Lead surfaced unsurfaced Kutcha on Unit
Name of unSurfaced Kutcha Unloading (Rs.)
Source TOTAL Lead Surfaced
Material
Sl. No. in Km. Factor (Km) Road Road Road Road Road Road Charges
1.0 Sand Chhinda 2 SAND 1.60 2 0 0 2 8.40 10.10 20.40 172.00 237.3 per m3
2.0 Chips Kolebira 58 CHIPS 1.60 58 58 0 0 8.40 10.10 20.40 172.00 951.5 per m3
3.0 Metal Kolebira 40 METAL 1.74 40 40 0 0 8.40 10.10 20.40 172.00 756.6 per m3
4.0 Boulder Kolebira 40 BOULDER 1.67 40 40 0 0 8.40 10.10 20.40 212.00 773.1 per m3
5.0 Moorum Local 5 MOORUM 1.33 5 5 0 0 8.40 10.10 20.40 172.00 227.86 per m3
6.0 Bitumen Namkum 297 BITUMEN 1.00 297 297 0 0 8.40 10.10 20.40 275.00 2769.8 per MT
7.0 Cement Simdega 8 CEMENT 1.00 8 8 0 0 8.40 10.10 20.40 275.00 342.20 per MT
8.0 Steel Simdega 8 STEEL 1.00 8 8 0 0 8.40 10.10 20.40 275.00 342.20 per MT
9.0 Hume Pipe Ranchi 175 H.P. 1.33 175 175 0 0 8.40 10.10 20.40 275.00 2230.10 Per m
Analysis of rates for Bridge work

(1)E/W in excavation of foundation trenches in


(i) Ordinary Soil (Rate Vide item no.12.1B(i) of NH S.O.R.) ### 59.15
(ii) Ordinary Soil (Rate Vide item no.12.1B(ii) of NH S.O.R.) per m3 Rs.
### 66.90
(iii) Ordinary Rock(Rate Vide item no.12.1(II)B of NH S.O.R.) per m3 Rs.
### 75.63
(iv) Hard Rock Rate Vide item no.12.1(iv)A of NH S.O.R.) per m3 Rs.
### 357.78
(2) Providing steel liner 10mm thick ------------
Basic rate vide item no.12.22 of N.H.S.O.R. per MT Rs.
### 75164.16
Carriage of steel 1.05 x 743.00 Rs.
### 780.15
Rs.
### 76703.75
(3) Bored cast insitu M35 grade R.C.C. piles -----------
Basic rate vide item no.12.25 of N.H.S.O.R. per m Rs.
### 10801.92
Carriage of materials
cement 0.474 MT x Rs. 743.00 = Rs.
### 352.18
sand 0.51 m3 x Rs. 1047.28 = Rs.
### 534.11
Metal 0.305 m3 x Rs. 833.03 = Rs.
### 254.07
chips 0.275 m3 x Rs. 1049.68 = Rs.
### 288.66
Finished rate per m = Rs.
### 10932.09

(4) Providing and laying P.C.C. M15 Levelling course under the pile cap
Basic rate vide item no.12.39 of N.H.S.O.R. per m3 Rs.
### 3796.80
Carriage of materials
cement 0.275 MT x Rs. 743.00 = Rs.
### 204.33
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.54 m3 x Rs. 833.03 = Rs.
### 449.84
chips 0.36 m3 x Rs. 1049.68 = Rs.
### 377.88
Finished rate per m3 = Rs.
### 5353.12

(5) Providing R.C.C.M30 in pile cap


Basic rate vide item no.12.38 C(i) of N.H.S.O.R. per m3 Rs.
### 5010.24
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 6795.92
(6) Pile load test on single vertical
Basic rate vide item no.12.37 of N.H.S.O.R. per MT Rs.
### 5138.88

(7) Back filling behind the abutment, wing wall with Granular Material
Basic rate Vide item no.13.9 A of NH S.O.R. per m3 Rs.
### 460.80
Carriage of material
Moorum 1.2 m3 x Rs. 270.76 Rs.
### 324.92
Finished rate per m3 = Rs.
### 793.57
(8) Providing and laying of Filter media
Basic rate vide item no.13.10 of N.H.S.O.R. per m3 Rs.
### 1170.24
Carriage of material
Metal 1.2 m3 x Rs. 1049.68 Rs.
### 1259.62
Finished rate per m3 = Rs.
### 2454.15

(9) Providing and laying P.C.C. M15 Grade levelling course below approach slab
Basic rate vide item no.14.10 of N.H.S.O.R. per m3 Rs.### 3811.20
Carriage of materials
cement 0.275 MT x Rs. 743.00 = Rs.
### 204.33
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.54 m3 x Rs. 833.03 = Rs.
### 449.84
chips 0.36 m3 x Rs. 1049.68 ### 377.88
Finished rate per m3 = Rs.
### 5367.67

(10) (a)P.C.C. M15 - Using Concrete mixer


Basic rate vide item no.12.8(A) of N.H.S.O.R. per m3 Rs.
### 3962.88
Carriage of materials
cement 0.275 MT x Rs. 743.00 = Rs.
### 204.33
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.54 m3 x Rs. 833.03 = Rs.
### 449.84
chips 0.36 m3 x Rs. 1049.68 ### 377.88
Finished rate per m3 = Rs.
### 5520.86
(11) (b)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.12.8 (B) of N.H.S.O.R. per m3 Rs.
### 4524.48
Carriage of materials
cement 0.347 MT x Rs. 743.00 = Rs.
### 257.82
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.36 m3 x Rs. 833.03 = Rs.
### 299.89
chips 0.54 m3 x Rs. 1049.68 = Rs.
### 566.83
Finished rate per m3 = Rs.
### 6181.50
(12) ©R.C.C. M25 - Using concrete mixer
Basic rate vide item no.12.8 (E) of N.H.S.O.R. per m3 Rs.
### 4958.40
Carriage of materials
cement 0.403 MT x Rs. 743.00 = Rs.
### 299.43
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 6740.56

(13) (d)R.C.C. M30 - Using concrete mixer


Basic rate vide item no.12.8 (G)I of N.H.S.O.R. per m3 Rs.
### 4972.80
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 6758.10

(14) Providing P.C.C. M10 mechanically mixed concrete in abutment or pier foundation -do-do-
Basic rate vide item no.12.4 of N.H.S.O.R. per m3 Rs.
### 3621.12
Carriage of materials
cement 0.23 MT x Rs. 743.00 = Rs.
### 170.89
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
Metal 0.9 m3 x Rs. 833.03 = Rs.
### 749.73
Finished rate per m3 = Rs.
### 5063.14

(15) Providing P.C.C./R.C.C.in Substructure -do-do-


(a)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.13.5 (E)(p)I of N.H.S.O.R. per m3 Rs.
### 4787.52
Carriage of materials
cement 0.347 MT x Rs. 743.00 = Rs.
### 257.82
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 6525.94

(16) (b)R.C.C. M25 - Using Concrete mixer Sub structure


Basic rate vide item no.13.5 (F)(p)I of N.H.S.O.R. per m3 Rs.
### 5257.92
Carriage of materials
cement 0.403 MT x Rs. 743.00 = Rs.
### 299.43
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7043.07
(16)a (b)R.C.C. M25 - Using Concrete mixer Super-structure
Basic rate vide item no.14.1 (B)(i)p of N.H.S.O.R. per m3 Rs.
### 5935.00
Carriage of materials
cement 0.403 MT x Rs. 743.00 = Rs.
### 299.43
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7726.92

(17) (c)R.C.C. M30 - Using Concrete mixer


Basic rate vide item no.13.5 (G)(p)I of N.H.S.O.R. per m3 Rs.
### 5285.76
Upto 5.0 m height
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7074.19
B (e)R.C.C. M30 - Using concrete mixer
Basic rate vide item no.12.8 (G)(q)I of N.H.S.O.R. per m3 Rs.
### 5434.56
upto 5.0 m to 10.0 m height
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7224.48

(18) (d)R.C.C. M35 - Using Concrete mixer


Basic rate vide item no.13.5 (H) of N.H.S.O.R. per m3 Rs.
### 5414.40
Carriage of materials
cement 0.422 MT x Rs. 743.00 = Rs.
### 313.55
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7215.37
(19) Providing P.C.C./R.C.C.in Superstructure
(i) Solid Slab Super Structure,height-upto 5m
(a)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.14.1 C-i(p) of N.H.S.O.R. per m3 Rs.
### 5784.96
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7578.38

Providing P.C.C./R.C.C.in Superstructure


B (i) Solid Slab Super Structure,height-5 to 10m
(a)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.14.1 C-i(q) of N.H.S.O.R. per m3 Rs.
### 6025.92
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7821.75

(20) (ii) T-Beam Super Structure,height upto 5m


(a)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.14.1 C-ii(p) of N.H.S.O.R. per m3 Rs.
### 6025.92
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 7821.75

B (ii) T-Beam Super Structure,height 5-10m


(a)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.14.1 C-ii(q) of N.H.S.O.R. per m3 Rs.
### 6266.88
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
Finished rate per m3 = Rs.
### 8065.12

(21) Providing weep holes -do-do-


Basic rate vide item no.13.8 of N.H.S.O.R. each Rs.
### 119.04
Carriage of A.C. Pipe 1.05 m Rs.
### 7.23
Rs.
### 127.54

(22) supplying ,fitting and placing HYSD bars -do-do-

(a) Foundation
Basic rate vide item no.12.40 of N.H.S.O.R. per MT Rs.
### 66451.20
carriage of steel
1.05 MT x Rs. 743.00 Rs.
### 780.15
Finished rate per MT = Rs.
### 67903.66

(b) Sub Structure


Basic rate vide item no.13.6 of N.H.S.O.R. per MT Rs.
### 66553.92
carriage of steel
1.05 MT x Rs. 743.00 Rs.
### 780.15
Finished rate per MT = Rs.
### 68007.41

(c) Super Structure


Basic rate vide item no.14.2of N.H.S.O.R. per MT Rs.
### 67403.52
carriage of steel
1.05 MT x Rs. 743.00 Rs.
### 780.15
Finished rate per MT = Rs.
### 68865.51

(23) Providing and laying M30 Grade c.c. wearing coat including reinforcement
Basic rate vide item no.14.4 of N.H.S.O.R. per m3 Rs.
### 9818.88
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
steel 0.075 MT x Rs. 743.00 Rs.
### 55.73
Finished rate per m3 = Rs.
### 11708.92

(24) Construction of insitu R.C.C. railing of M30 grade -do-do-


Basic rate vide item no.14.6 of N.H.S.O.R. per m Rs.
### 1666.56
Carriage of materials
cement 0.035 MT x Rs. 743.00 = Rs.
### 26.01
sand 0.038 m3 x Rs. 1047.28 = Rs.
### 39.80
chips 0.076 m3 x Rs. 1049.68 = Rs.
### 79.78
steel 0.018 MT x Rs. 743.00 Rs.
### 13.37
Finished rate per m = Rs.
### 1843.77
(15) Providing P.C.C./R.C.C.in Substructure -do-do-
(a)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.8.22 of N.H.S.O.R. per m3 Rs.
### 2735.04
Carriage of materials
cement 0.1041 MT x Rs. 743.00 = Rs.
### 77.35
sand 0.135 m3 x Rs. 1047.28 = Rs.
### 141.38
chips 0.27 m3 x Rs. 1049.68 = Rs.
### 283.41
steel 0.028 MT x Rs. 743.00 Rs.
### 20.80
Finished rate per m3 = Rs.
### 3290.57

(25) Drainage spouts -do-do-


Basic rate vide item no.14.9 of N.H.S.O.R. each Rs.
### 878.46
(26) Providing and laying R.C.C.M30 in approach slab -do-do-
Basic rate vide item no.14.11 of N.H.S.O.R. per m3 Rs.
### 8190.72
Carriage of materials
cement 0.407 MT x Rs. 743.00 = Rs.
### 302.40
sand 0.45 m3 x Rs. 1047.28 = Rs.
### 471.28
chips 0.90 m3 x Rs. 1049.68 = Rs.
### 944.71
steel 0.050 MT x Rs. 743.00 Rs.
### 37.15
Finished rate per m3 = Rs.
### 10045.72

(27) Providing painting two coats on unplastered concrete surface -do-do-


Basic rate vide item no.14.16 of N.H.S.O.R. per m2 Rs.
### 64.96

(28) Providing and fixing of retro-reflectorised ,cautionary,mandatory and


informatory sign -do-do-
(i) 90 cm. triangle Basic rate vide item no.8.4(i) of N.H.S.O.R. Each Rs.
### 4892.60
(ii) 60 cm. triangle Basic rate vide item no.8.4(ii) of N.H.S.O.R. Each Rs.
### 3093.99
(iii) 80 cm.x60 cm. Basic rate vide item no.8.4(vi) of N.H.S.O.R. Each Rs.
### 6097.81
(29)
14.22 Strip Seal Expansion Joint (Providing and laying of a strip seal
expansion joint catering to maximum horizontal movement upto 70
mm, complete as per approved drawings and standard
Rs.
###
specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
8487.88
(30)
Supplying, fitting and fixing in position true to line and level
13.14
elastomeric bearing conforming to IRC: 83 (Part-II) section IX and
clause 2005 of MoRTH specifications complete including all
accessories as per drawing and Technical Specifications.
Rs.
### 0.70
Analysis of rates for Approach Road
1.0 Clearing and Grubbing Item No. 2.3 of NH S.O.R. per hectare Rs.
### 32664.85
2.0 Shifting of Telephone/Electric poles
Item No. 2.14 of NH S.O.R. per pole Rs.
### 100.84
3.0 cutting of trees Item No. 2.1 of NH S.O.R.
(a) Girth from 0.3m to 0.60m Each Rs.
### 149.32
(a) Girth from 0.6m to 0.90m Each Rs.
### 255.97
(a) Girth from 0.9m to 1.80m Each Rs.
### 512.92
(a) Girth >1.80 m Each Rs.
### 986.08
4.0 Dismantalling of flexible pavement granular courses
by manual means
Item No.2.5 IA of NH S.O.R. per m3 Rs.
### 282.15
Bituminous courses mechaniclly per m3 Rs.
### 146.41
5.0 E/W in cutting
(a) in ordinary soil Item No. 3.6(i) of NH S.O.R.(excluding watering) per m3 Rs.
### 99.87

(b) soft rock excluding watering,rolling etc. Rs.


### 116.35
(c) hard rock (blasting prohibited) Item No. 3.8 of NH S.O.R. per m3 Rs.
### 481.89
mechanically
6.0 E/W in filling
(a)Earth obtained from cutting of road,drain
Item No. 3.17 of NH S.O.R. per m3 Rs.
### 122.17
(b) Earth obtained from borrow pits
Item No. 3.16 of NH S.O.R. per m3 Rs.
### 188.10

7.0 Disposal of Earth with 5.0Km Additional lead Rs.

8.0 Providing coarse graded GSB with Grading -I material


Basic rate vide item no.4.2 of N.H.S.O.R. per m3 Rs.
### 1011.84
Carriage of materials
Metal 0.448 MT x Rs. 833.03 = Rs.
### 373.20
chips 0.576 m3 x Rs. 1049.68 = Rs.
### 604.62
Sand 0.256 m3 x Rs. 1047.28 = Rs.
### 268.10
Finished rate per m3 = Rs.
### 2280.33

9.0 providing WMM


Basic rate vide item no.4.12 of N.H.S.O.R. per m3 Rs.
### 1238.40
Carriage of materials
Metal 0.396 MT x Rs. 833.03 = Rs.
### 329.88
chips 0.528 m3 x Rs. 1049.68 = Rs.
### 554.23
sand 0.396 m3 x Rs. 1047.28 = Rs.
### 414.72
Finished rate per m3 = Rs.
### 2562.61

10.0 WBM Gr-I ### 966.72


Metal 0.64 MT x Rs. 833.03 ### 533.14
chips 0.253 m3 m3Rs. 1049.68 ### 265.57
Moorum 0.384 m3 m3Rs. 270.76 ### 103.97
### 1888.10

10.0 Providing WBM Gr-II with screening material Type"B"


Basic rate vide item no.4.9 A ii (c) of N.H.S.O.R. per m3 Rs.
### 1060.80
Carriage of materials
Metal 1.21 MT x Rs. 833.03 = Rs.
### 1007.97
chips 0.16 m3 m3Rs. 1049.68 = Rs.
### 167.95
Moorum 0.08 m3 m3Rs. 270.76 = Rs.
### 21.66
Rs.
### 2280.96
11.0 Providing WBM Gr-III with screening material Type"B"
Basic rate vide item no.4.9 A iii (b)of N.H.S.O.R. per m3 Rs.
### 1087.68
Carriage of materials
Metal 1.21 MT x Rs. 833.03 = Rs.
### 1007.97
chips 0.24 m3 x Rs. 1049.68 = Rs.
### 251.92
Moorum 0.08 m3 m3Rs. 270.76 = Rs.
### 21.66
12.0 Providing Prime Coat Rs.
### 2392.92

Basic rate vide item no.5.1 of N.H.S.O.R. per m3 Rs.


### 33.60
Carriage of materials
bitumen 0.0006 MT x Rs. 1093.40 = Rs.
### 0.66
Finished rate per m3 = Rs.
### 34.60

13.0 Providing Tack coat


Basic rate vide item no.5.2 of N.H.S.O.R. per m3 Rs.
### 11.52
Carriage of materials
bitumen 0.0002 MT x Rs. 1093.40 = Rs.
### 0.22
Finished rate per m3 = Rs.
### 11.86

15.0 providing B.M. Gr-I VG-30


A Basic rate vide item no.5.3 of N.H.S.O.R. per m3 Rs.
### 7211.52
Carriage of materials
bitumen 0.072 MT x Rs. 1093.40 = Rs.
### 78.72
chips 1.42 m3 x Rs. 1049.68 = Rs.
### 1490.55
Finished rate per m3 = Rs.
### 8868.60

15.0 providing B.M. Gr-II VG-30


B Basic rate vide item no.5.3 of N.H.S.O.R. per m3 Rs.
### 7142.40
Carriage of materials
bitumen 0.072 MT x Rs. 1093.40 = Rs.
### 78.72
chips 1.42 m3 x Rs. 1049.68 = Rs.
### 1490.55
Finished rate per m3 = Rs.
### 8798.79
16.0 providing D.B.M.(Grading I) VG-30
A Basic rate vide item no.5.6 of N.H.S.O.R. per m3 Rs.
### 8653.44
Carriage of materials
bitumen 0.0981 MT x Rs. 1093.40 = Rs.
### 107.26
chips 1.444 m3 x Rs. 1049.68 = Rs.
### 1515.74
Finished rate per m3 = Rs.
### 10379.20
16.0 providing D.B.M.(Grading II) VG-30
B Basic rate vide item no.5.6 of N.H.S.O.R. per m3 Rs.
### 8728.32
Carriage of materials
bitumen 0.0981 MT x Rs. 1093.40 = Rs.
### 107.26
chips 1.444 m3 x Rs. 1049.68 = Rs.
### 1515.74
Finished rate per m3 = Rs.
### 10454.83

17.0 providing B.C. (Gading I) CRMB


A Basic rate vide item no.5.8 of N.H.S.O.R. per m3 Rs.
### 10244.16
Carriage of materials
bitumen 0.1178 MT x Rs. 1093.40 = Rs.
### 128.80
chips 1.462 m3 x Rs. 1049.68 = Rs.
### 1534.63
Finished rate per m3 = Rs.
### 12026.67

17.0 providing B.C. (Gading II) CRMB


B Basic rate vide item no.5.8 of N.H.S.O.R. per m3 Rs.
### 10093.44
Carriage of materials
bitumen 0.1178 MT x Rs. 1093.40 = Rs.
### 128.80
chips 1.462 m3 x Rs. 1049.68 = Rs.
### 1534.63
Finished rate per m3 = Rs.
### 11874.44

19.0 20mm thick open graded pre mix carpet VG-30


Basic rate vide item no.5.10 of N.H.S.O.R. Rs.
### 138.24
Carriage of materials
Bitumen 0.0025 MT x Rs. 1093.40 Rs.
### 2.69
chips 0.027 m3 x Rs. 1049.68 Rs.
### 28.34
Finished rate per m3 Rs.
### 170.96

20.0 Liquid seal coat type "A" VG-30


Basic Rate per m2 vide item no.5.12 of NH S.O.R. Rs.
### 69.12
Carriage of materials
Bitumen 0.00098 MTx 1093.40 Rs.
### 1.07
chips 0.009 m3x 1049.68 Rs.
### 9.45
Finished rate per m3 Rs.
### 80.44

21.0 Providing and erecting


direction and place
identification retro
reflectorised sign -do-do- Basic Rate Vide item no.8.5 of NH S.O.R. Each Rs.
### 11278.39

22.0 Painting lines , dashes,


arrows etc. on roads in two
coats on new surface Basic Rate Vide item no.8.11 of NH S.O.R. Per m2 Rs.
### 63.02
Upto 10 cm
23.0 Road marking with hot applied
thermoplastic compound with
reflectorising glass beads on
bituminous surface Basic Rate Vide item no.8.13 of NH S.O.R. Per m2 Rs.
### 498.37

24.0 supplying and installation of


delineators(road way
indicaters,hazard
markers,object markers,) -do-
do-
supplying and installation of
delineators(road way
indicaters,hazard
markers,object markers,) -do-
do- Basic Rate Vide item no.8.15 of NH S.O.R. Each Rs.
### 589.52
26.0 providing and fixing at site
precast F.I. post Item no. 8.14 of NH SOR

(i) 5th kilometre stone (precast) ### 2467.63


Ordinary Kilometer stone ###
(ii) 1523.24
(Precast) ###
(iii) Hectometer stone (Precast) 440.20

27.0 Providing and laying Pitching on slopes laid over well prepared
filter media
Basic rate vide item no.15.4(A) of N.H.S.O.R. per m2 Rs.
### 830.40
Carriage of boulders
1.2 m3 x Rs. 889.66 Rs.
### 1067.59
Finished rate per m3 = Rs.
### 1916.97
28.0 Providing and laying filter material underneath pitching
Basic rate vide item no.15.5 of N.H.S.O.R. per m2 Rs.
### 1285.44
Carriage of metal
1.2 m3 x Rs. 1049.68 = Rs.
### 1259.62
Finished rate per m3 = Rs.
### 2570.51

Stone masonry work in cement mortar 1:3


29.0 for substructure complete as per drawing Basic Rate Rs.
### 2763.84
and Technical
Random Specifications
Rubble Masonry in foundation cement 0.51 MT 743.00 Rs.
### 378.93
Item No. 12.7( b) Mortar 1:3 Sand 1.05 m3 1047.28 Rs.
### 1099.64
Stone masonry work in cement mortar 1:3 Rs.
### 4284.84
30.0 for substructure complete as per drawing Basic Rate Rs.
### 2791.68
and Technical
Random Specifications
Rubble Masonry in substructur cement 0.51 MT 743.00 Rs.
### 378.93
Item No. 13.4 A Mortar 1:3 Sand 1.05 m3 1047.28 Rs.
### 1099.64
Plain/Reinforced cement concrete in sub- Rs.
### 4312.96
31.0 structure complete as per drawing and
technical
Structure specifications
PCC Grade M15 13.5A(p) Basic Rate Rs.
### 4192.32
carriage Rs.
### 1503.32
Finished Rate Rs.
### 5752.60
concrete pipe for culverts on first class
32.0
bedding of granular material in single row
1200 dia Np4 pipe NH SOR 9.2 B Basic Rate Rs.
### 5278.08
In single row Sand 0.0072 x 1047.28 Rs.
### 7.54
Chips 0.40 x 1049.68 Rs.
### 419.87
Cement 0.0056 x 743.00 Rs.
### 4.16
H.P. 1x 911.63 Rs.
### 911.63
Rs.
### 6687.50
concrete pipe for culverts on first class
33.0
bedding of granular material in single row
1200 dia Np4 pipe NH SOR 9.3 B Basic Rate Rs.
### 12883.20
In double row Sand 0.0072 x 1047.28 Rs.
### 7.54
Chips 0.40 x 1049.68 Rs.
### 419.87
Cement 0.0056 x 743.00 Rs.
### 4.16
H.P. 1x 911.63 Rs.
### 911.63
Rs.
### 14368.67
34.0 Flexible Apron :Construction of flexible apron with Basic Rs.
### 830.40
stone boulders weighing not less than 40 kg in river Boulder 1 889.66 Rs.
### 889.66
bed.Without crate Rs.
### 1737.26
Item No. 15.1 of N.H. SOR

Analysis of Rates for Diversion


1.0 E/W in excavation of Foundation Trenches-do-
A. By Manual means:-
(i) Ordinary soil Rate per m3 vide item no.12.1-I-A(i) of NH S.O.R. Rs.###
(ii) ordinary Rock Rate per m3 vide item no.12.1-II-A(i) of NH S.O.R. Rs.###
(iii)Hard rock Rate per m3 vide item no.12.1-III-A of NH S.O.R. Rs.###
( blasting required)
B.By Mechanical means:-
(i) Ordinary soil Rate per m3 vide item no.12.1-I-B(i) of NH S.O.R. Rs.###
(ii) ordinary Rock Rate per m3 vide item no.12.1-II-B(i) of NH S.O.R. Rs.###
(iii)Hard rock Rate per m3 vide item no.12.1-IV-A of NH S.O.R. Rs.###
(Blasting prohibited)
2.0 Providing P.C.C. M10 in foundation
Rate per m3 vide item no.9.1 of NH S.O.R. Rs.
###
Carriage of Materials
Cement 0.23 MT @ Rs. 743.00 per MT = Rs.
###
Sand 0.45 m3 @ Rs. 1047.28 per m3 = Rs.
###
Metal 0.90 m3 @ Rs. 833.03 per m3 = Rs.
###
Finished rate per m3 = Rs.
###
3.0 Laying R.C.C./Prestressed pipe NP4 -do- 1000 mm dia
in single row Rate per m vide item no.9.2(A) of NH S.O.R. Rs.
###
Carriage of Materials
Cement 0.0056 MT @ Rs. 743.00 per MT = Rs.
###
Chips 0.360 m3 @ Rs. 1049.68 per m3 = Rs.
###
Sand 0.0040 m3 @ Rs. 1047.28 per m3 = Rs.
###
H.P. 1.00 m @ Rs. 911.63 per m = Rs.
###
Finished rate per m Rs.
###
Basic rate of Carriage of Materials
Rate of Carriage of materials as per S.O.R of NH Division
Multiplyi Total Lead on Lead on Lead on Hauling Hauling Hauling Loading
Charges Charges on Charges on and Rate
MATERIAL ng Lead surfaced unsurfaced Kutcha on Unit
unSurfaced Kutcha Unloading (Rs.)
Surfaced
Factor (Km) Road Road Road Road Road Road Charges
SAND 1.6 5 5 0 0 2.30 2.80 5.60 73.00 91.40 per m3
CHIPS 1.6 24 24 0 0 2.30 2.80 5.60 73.00 161.32 per m3
METAL 1.74 24 24 0 0 2.30 2.80 5.60 73.00 169.05 per m3
BOULDER 1.67 24 24 0 0 2.30 2.80 5.60 73.00 165.18 per m3
MOORUM 1.33 5 5 0 0 2.30 2.80 5.60 73.00 88.30 per m3
BITUMEN 1 36 36 0 0 2.30 2.80 5.60 163.00 245.80 per MT
CEMENT 1 24 24 0 0 2.30 2.80 5.60 163.00 218.20 per MT
STEEL 1 24 24 0 0 2.30 2.80 5.60 163.00 218.20 per MT
H.P. 1.33 24 24 0 0 2.30 2.80 5.60 163.00 236.42 Per m
Earth 1.33 10 10 0 0 2.30 2.80 5.60 73.00 103.59 per m3
Analysis of rates for Bridge work
(1)E/W in excavation of foundation trenches in
(i)Ordinary Soil (Rate Vide item no.12.1B(i) of NH S.O.R.) 45.45
(ii)Ordinary Soil (Rate Vide item no.12.1B(ii) of NH S.O.R.) per m3 Rs. 51.51
(iii)Ordinary Rock(Rate Vide item no.12.1(II)B of NH S.O.R.) per m3 Rs. 57.57
(iv)Hard Rock Rate Vide item no.12.1(iv)A of NH S.O.R.) per m3 Rs. 332.29
(2)Providing steel liner 10mm thick ------------
Basic rate vide item no.12.22 of N.H.S.O.R. per MT Rs. 80793.00
Carriage of steel 1.05 x 218.20 Rs. 229.11
Rs. 81832.33
(3)Bored cast insitu M35 grade R.C.C. piles -----------
Basic rate vide item no.12.25 of N.H.S.O.R. per m Rs. 10618.00
Carriage of materials
cement 0.474 MT x Rs. 218.20 = Rs. 103.43
sand 0.51 m3 x Rs. 91.40 = Rs. 46.61
Metal 0.305 m3 x Rs. 169.05 = Rs. 51.56
chips 0.275 m3 x Rs. 161.32 = Rs. 44.36
Finished rate per m = Rs. 10972.60

(4)Providing and laying P.C.C. M15 Levelling course under the pile cap
Basic rate vide item no.12.39 of N.H.S.O.R. per m3 Rs. 3762.00
Carriage of materials
cement 0.275 MT x Rs. 218.20 = Rs. 60.01
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.54 m3 x Rs. 169.05 = Rs. 91.29
chips 0.36 m3 x Rs. 161.32 = Rs. 58.08
Finished rate per m3 = Rs. 4052.62

(5)Providing R.C.C.M30 in pile cap


Basic rate vide item no.12.38 C(i) of N.H.S.O.R. per m3 Rs. 5154.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5483.42
(6)Pile load test on single vertical
Basic rate vide item no.12.37 of N.H.S.O.R. per MT Rs. 5300.00

(7)Back filling behind the abutment, wing wall with Granular Material
Basic rate Vide item no.13.9 A of NH S.O.R. per m3 Rs. 361.00
Carriage of material
Moorum 1.2 m3 x Rs. 88.30 Rs. 105.95
Finished rate per m3 = Rs. 471.62
(8)Providing and laying of Filter media
Basic rate vide item no.13.10 of N.H.S.O.R. per m3 Rs. 865.00
Carriage of material
Metal 1.2 m3 x Rs. 161.32 Rs. 193.58
Finished rate per m3 = Rs. 1069.17

(9)Providing and laying P.C.C. M15 Grade levelling course below approach slab
Basic rate vide item no.14.10 of N.H.S.O.R. per m3 Rs. 3776.00
Carriage of materials
cement 0.275 MT x Rs. 218.20 = Rs. 60.01
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.54 m3 x Rs. 169.05 = Rs. 91.29
chips 0.36 m3 x Rs. 161.32 58.08
Finished rate per m3 = Rs. 4066.76
(10)Providing P.C.C. /R.C.C. mechanically mixed concrete in foundation -do-do-
(a)P.C.C. M15 - Using Concrete mixer
Basic rate vide item no.12.8(A) of N.H.S.O.R. per m3 Rs. 3926.00
Carriage of materials
cement 0.275 MT x Rs. 218.20 = Rs. 60.01
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.54 m3 x Rs. 169.05 = Rs. 91.29
chips 0.36 m3 x Rs. 161.32 58.08
Finished rate per m3 = Rs. 4218.26
(11) (b)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.12.8 (B) of N.H.S.O.R. per m3 Rs. 4557.00
Carriage of materials
cement 0.347 MT x Rs. 218.20 = Rs. 75.72
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.36 m3 x Rs. 169.05 = Rs. 60.86
chips 0.54 m3 x Rs. 161.32 = Rs. 87.11
Finished rate per m3 = Rs. 4870.03

(12) ©R.C.C. M25 - Using concrete mixer


Basic rate vide item no.12.8 (E) of N.H.S.O.R. per m3 Rs. 5099.00
Carriage of materials
cement 0.403 MT x Rs. 218.20 = Rs. 87.93
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5426.99

(13) (d)R.C.C. M30 - Using concrete mixer


Basic rate vide item no.12.8 (G)I of N.H.S.O.R. per m3 Rs. 5118.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5447.06

(14)Providing P.C.C. M10 mechanically mixed concrete in abutment or pier foundation -do-do-
Basic rate vide item no.12.4 of N.H.S.O.R. per m3 Rs. 3544.00
Carriage of materials
cement 0.23 MT x Rs. 218.20 = Rs. 50.19
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
Metal 0.9 m3 x Rs. 169.05 = Rs. 152.14
Finished rate per m3 = Rs. 3825.33

(15)Providing P.C.C./R.C.C.in Substructure -do-do-


(a)R.C.C. M20 - Using Concrete mixer
Basic rate vide item no.13.5 (E) of N.H.S.O.R. per m3 Rs. 4854.00
Carriage of materials
cement 0.347 MT x Rs. 218.20 = Rs. 75.72
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5167.19

(16) (b)R.C.C. M25 - Using Concrete mixer


Basic rate vide item no.13.5 (F) of N.H.S.O.R. per m3 Rs. 5407.00
Carriage of materials
cement 0.403 MT x Rs. 218.20 = Rs. 87.93
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5738.07
(17) (c)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.13.5 (G)p of N.H.S.O.R. per m3 Rs. 5439.00
Upto 5.0 m height
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5771.27

(e)R.C.C. M30 - Using concrete mixer


Basic rate vide item no.13.5 (G)q of N.H.S.O.R. per m3 Rs. 5592.00
upto 5.0 m to 10.0 m height
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5925.80
(18) (d)R.C.C. M35 - Using Concrete mixer
Basic rate vide item no.13.5 (H) of N.H.S.O.R. per m3 Rs. 5592.00
Carriage of materials
cement 0.422 MT x Rs. 218.20 = Rs. 92.08
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 5929.10

(19)Providing P.C.C./R.C.C.in Superstructure -do-do-


(i) Solid Slab Super Structure
(a)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.14.1 (C-i) of N.H.S.O.R. per m3 Rs. 5950.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 6287.38

(20) (ii) T-Beam Super Structure


(a)R.C.C. M30 - Using Concrete mixer
Basic rate vide item no.14.1 (C-ii) of N.H.S.O.R. per m3 Rs. 5741.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
Finished rate per m3 = Rs. 6076.29

(21) Providing weep holes -do-do-


Basic rate vide item no.13.8 of N.H.S.O.R. each Rs. 116.15

(22) supplying ,fitting and placing HYSD bars -do-do-


(a) Foundation
Basic rate vide item no.12.40 of N.H.S.O.R. per MT Rs. 73526.00
carriage of steel
1.05 MT x Rs. 218.20 Rs. 229.11
Finished rate per MT = Rs. 74492.66

(b) Sub Structure


Basic rate vide item no.13.6 of N.H.S.O.R. per MT Rs. 73611.00
carriage of steel
1.05 MT x Rs. 218.20 Rs. 229.11
Finished rate per MT = Rs. 74578.51
(c) Super Structure
Basic rate vide item no.14.2of N.H.S.O.R. per MT Rs. 74365.00
carriage of steel
1.05 MT x Rs. 218.20 Rs. 229.11
Finished rate per MT = Rs. 75340.05

(23) Providing and laying M30 Grade c.c. wearing coat including reinforcement
Basic rate vide item no.14.4 of N.H.S.O.R. per m3 Rs. 10391.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
steel 0.075 MT x Rs. 218.20 Rs. 16.37
Finished rate per m3 = Rs. 10789.32

(24) Construction of precast R.C.C. railing of M30 grade -do-do-


Basic rate vide item no.14.6 of N.H.S.O.R. per m Rs. 1857.00
Carriage of materials
cement 0.035 MT x Rs. 218.20 = Rs. 7.64
sand 0.038 m3 x Rs. 91.40 = Rs. 3.47
chips 0.076 m3 x Rs. 161.32 = Rs. 12.26
steel 0.018 MT x Rs. 218.20 Rs. 3.93
Finished rate per m = Rs. 1903.14

(25) Drainage spouts -do-do-


Basic rate vide item no.14.9 of N.H.S.O.R. each Rs. 878.70

(26) Providing and laying R.C.C.M30 in approach slab -do-do-


Basic rate vide item no.14.11 of N.H.S.O.R. per m3 Rs. 8596.00
Carriage of materials
cement 0.407 MT x Rs. 218.20 = Rs. 88.81
sand 0.45 m3 x Rs. 91.40 = Rs. 41.13
chips 0.90 m3 x Rs. 161.32 = Rs. 145.19
steel 0.050 MT x Rs. 218.20 Rs. 10.91
Finished rate per m3 = Rs. 8970.86

(27) Providing painting two coats on unplastered concrete surface -do-do-


Basic rate vide item no.14.16 of N.H.S.O.R. per m2 Rs. 1875.57

(28) Providing and fixing of retro-reflectorised ,cautionary,mandatory and


informatory sign -do-do-
(a)90 cm. equilateral triangle Basic rate vide item no.8.4(i) of N.H.S.O.R. Each Rs. 4848.00
(b)60 cm. equilateral triangle Basic rate vide item no.8.4(ii) of N.H.S.O.R. Each Rs. 3121.91
( c )60 cm.x60 cm. sqare Basic rate vide item no.8.4(vii) of N.H.S.O.R. Each Rs. 7714.38
(29)
14.22 Strip Seal Expansion Joint (Providing and laying of a strip seal
expansion joint catering to maximum horizontal movement upto 70
mm, complete as per approved drawings and standard
Rs. 8146.66
specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.)

(30)
Supplying, fitting and fixing in position true to line and level
13.14
elastomeric bearing conforming to IRC: 83 (Part-II) section IX and
clause 2005 of MoRTH specifications complete including all
accessories as per drawing and Technical Specifications.
Rs. 0.67
Analysis of rates for Approach Road
1.0 Clearing and Grubbing Item No. 2.3 of NH S.O.R. per hectare Rs. 28146.68
2.0 Shifting of Telephone/Electric poles
Item No. 2.14 of NH S.O.R. per pole Rs. 87.87
3.0 cutting of trees Item No. 2.1 of NH S.O.R.
(a) Girth from 0.3m to 0.60m Each Rs. 121.20
(a) Girth from 0.6m to 0.90m Each Rs. 211.09
(a) Girth from 0.9m to 1.80m Each Rs. 417.13
(a) Girth >1.80 m Each Rs. 797.90
4.0 Dismantalling of flexible pavement
Item No.2.5 of NH S.O.R. per m3 Rs. 353.50

5.0 E/W in cutting


(a) in ordinary soil Item No. 3.6 of NH S.O.R. per m3 Rs. 53.53
(b) soft rock Item No. 3.7 of NH S.O.R. per m3 Rs. 65.65
(c) hard rock (blasting prohibited) Item No. 3.8 of NH S.O.R. per m3 Rs. 279.77

6.0 E/W in filling


(a)Earth obtained from cutting of road,drain
Item No. 3.17 of NH S.O.R. per m3 Rs. 125.24
(b) Earth obtained from borrow pits
Item No. 3.16 of NH S.O.R. per m3 Rs. 159.58

7.0 Disposal of Earth with 5.0Km Additional lead Rs. 104.63

8.0 Providing coarse graded GSB with Grading -I material


Basic rate vide item no.4.2 of N.H.S.O.R. per m3 Rs. 668.00
Carriage of materials
Metal 0.448 MT x Rs. 169.05 = Rs. 75.73
chips 0.576 m3 x Rs. 161.32 = Rs. 92.92
Sand 0.256 m3 x Rs. 91.40 = Rs. 23.40
Finished rate per m3 = Rs. 868.65

9.0 providing WMM


Basic rate vide item no.4.12 of N.H.S.O.R. per m3 Rs. 811.00
Carriage of materials
Metal 0.396 MT x Rs. 169.05 = Rs. 66.94
chips 0.528 m3 x Rs. 161.32 = Rs. 85.18
sand 0.396 m3 x Rs. 91.40 = Rs. 36.19
Finished rate per m3 = Rs. 1009.31

10.0 Providing WBM Gr-II with screening material Type"B"


Basic rate vide item no.4.9 A ii (c) of N.H.S.O.R. per m3 Rs. 867.00
Carriage of materials
Metal 1.21 MT x Rs. 169.05 = Rs. 204.55
chips 0.16 m3 m3Rs. 161.32 = Rs. 25.81
Moorum 0.08 m3 m3Rs. 88.30 = Rs. 7.0636
Rs. 1115.47
11.0 Providing WBM Gr-III with screening material Type"B"
Basic rate vide item no.4.9 A iii (b)of N.H.S.O.R. per m3 Rs. 998.00
Carriage of materials
Metal 1.21 MT x Rs. 169.05 = Rs. 204.55
chips 0.24 m3 x Rs. 161.32 = Rs. 38.72
Moorum 0.08 m3 m3Rs. 88.30 = Rs. 7.0636
12.0 Providing Prime Coat Rs. 1260.81
Basic rate vide item no.5.1 of N.H.S.O.R. per m3 Rs. 31.00
Carriage of materials
bitumen 0.0006 MT x Rs. 245.80 = Rs. 0.15
Finished rate per m3 = Rs. 31.46

13.0 Providing Tack coat


Basic rate vide item no.5.2 of N.H.S.O.R. per m3 Rs. 11.00
Carriage of materials
bitumen 0.0002 MT x Rs. 245.80 = Rs. 0.05
Finished rate per m3 = Rs. 11.16
14.0 BUSG
Basic rate vide item no.5.5 of N.H.S.O.R. per m2 Rs. 243.00
bitumen 0.003 MT x Rs. 245.80 = Rs. 0.74
chips 0.013 m3 x Rs. 161.32 = Rs. 2.10
Metal 0.10 m3 x Rs. 169.05 = Rs. 16.90

Finished rate per m2 = Rs. 265.37

15.0 providing B.M. Gr-I


A Basic rate vide item no.5.3 of N.H.S.O.R. per m3 Rs. 5653.00
Carriage of materials
bitumen 0.072 MT x Rs. 245.80 = Rs. 17.70
chips 1.42 m3 x Rs. 161.32 = Rs. 229.07
Finished rate per m3 = Rs. 5958.77

15.0 providing B.M. Gr-II


B Basic rate vide item no.5.3 of N.H.S.O.R. per m3 Rs. 5617.00
Carriage of materials
bitumen 0.072 MT x Rs. 245.80 = Rs. 17.70
chips 1.42 m3 x Rs. 161.32 = Rs. 229.07
Finished rate per m3 = Rs. 5922.41

16.0 providing D.B.M.(Grading I)


A Basic rate vide item no.5.6 of N.H.S.O.R. per m3 Rs. 7347.00
Carriage of materials
bitumen 0.0981 MT x Rs. 245.80 = Rs. 24.11
chips 1.444 m3 x Rs. 161.32 = Rs. 232.95
Finished rate per m3 = Rs. 7680.10
16.0 providing D.B.M.(Grading II)
B Basic rate vide item no.5.6 of N.H.S.O.R. per m3 Rs. 7403.00
Carriage of materials
bitumen 0.0981 MT x Rs. 245.80 = Rs. 24.11
chips 1.444 m3 x Rs. 161.32 = Rs. 232.95
Finished rate per m3 = Rs. 7736.66

17.0 providing B.C. (Gading I)


A Basic rate vide item no.5.8 of N.H.S.O.R. per m3 Rs. 8747.00
Carriage of materials
bitumen 0.1178 MT x Rs. 245.80 = Rs. 28.96
chips 1.462 m3 x Rs. 161.32 = Rs. 235.85
Finished rate per m3 = Rs. 9101.92

17.0 providing B.C. (Gading II)


B Basic rate vide item no.5.8 of N.H.S.O.R. per m3 Rs. 8638.00
Carriage of materials
bitumen 0.1178 MT x Rs. 245.80 = Rs. 28.96
chips 1.462 m3 x Rs. 161.32 = Rs. 235.85
Finished rate per m3 = Rs. 8991.83

18.0 providing S.D.B.C. Gr-I


A Basic rate vide item no.5.7 of N.H.S.O.R. per m3 Rs. 7766.00
Carriage of materials
bitumen 0.115 MT x Rs. 245.80 = Rs. 28.27
chips 1.46 m3 x Rs. 161.32 = Rs. 235.53
Finished rate per m3 = Rs. 8110.09

18.0 providing S.D.B.C. Gr-II


B Basic rate vide item no.5.7 of N.H.S.O.R. per m3 Rs. 8336.00
Carriage of materials
bitumen 0.115 MT x Rs. 245.80 = Rs. 28.27
chips 1.46 m3 x Rs. 161.32 = Rs. 235.53
Finished rate per m3 = Rs. 8685.79
19.0 20mm thick open graded pre mix carpet
Basic rate vide item no.5.10 of N.H.S.O.R. Rs. 117.00
Carriage of materials
Bitumen 0.0025 MT x Rs. 245.80 Rs. 0.60
chips 0.027 m3 x Rs. 161.32 Rs. 4.36
Finished rate per m3 Rs. 123.18

20.0 Liquid seal coat type "A"


Basic Rate per m2 vide item no.5.12 of NH S.O.R. Rs. 64.00
Carriage of materials
Bitumen 0.00098 MTx 245.80 Rs. 0.24
chips 0.009 m3x 161.32 Rs. 1.45
Finished rate per m3 Rs. 66.35

21.0 Providing and erecting


direction and place
identification retro
reflectorised sign -do-do- Basic Rate Vide item no.8.5 of NH S.O.R. Each Rs. 10996.88

22.0 Painting lines , dashes,


arrows etc. on roads in two
coats on new surface Basic Rate Vide item no.8.11 of NH S.O.R. Per m2 Rs. 64.64

23.0 Road marking with hot applied


thermoplastic compound with
reflectorising glass beads on
bituminous surface Basic Rate Vide item no.8.13 of NH S.O.R. Per m2 Rs. 413.09

24.0 supplying and installation of


delineators(road way
indicaters,hazard
markers,object markers,) -do-
do- Basic Rate Vide item no.8.15 of NH S.O.R. Each Rs. 565.60
26.0 providing and fixing at site
precast F.I. post Item no. 8.14 of NH SOR

(i) 5th kilometre stone (precast) 2430.06


Ordinary Kilometer stone 1499.85
(ii)
(Precast) 441.37
(iii) Hectometer stone (Precast)

27.0 Providing and laying Pitching on slopes laid over well prepared
filter media
Basic rate vide item no.15.4(A) of N.H.S.O.R. per m2 Rs. 729.00
Carriage of boulders
1.2 m3 x Rs. 165.18 Rs. 198.22
Finished rate per m3 = Rs. 936.49
28.0 Providing and laying filter material underneath pitching
Basic rate vide item no.15.5 of N.H.S.O.R. per m2 Rs. 967.00
Carriage of metal
1.2 m3 x Rs. 161.32 = Rs. 193.58
Finished rate per m3 = Rs. 1172.19

Stone masonry work in cement mortar 1:3


29.0 for substructure complete as per drawing Basic Rate Rs. 2803.00
and Technical
Random RubbleSpecifications
Masonry in foundation cement 0.51 MT 218.20 Rs. 111.28
Item No. 12.7( b) Sand 1.05 m3 91.40 Rs. 95.97
Stone masonry work in cement mortar 1:3 Rs. 3040.35
30.0 for substructure complete as per drawing Basic Rate Rs. 2867.00
and Technical
Random RubbleSpecifications
Masonry in substructur cement 0.51 MT 218.20 Rs. 111.28
Item No. 13.4 A Sand 1.05 m3 91.40 Rs. 95.97
Rs. 3104.99
Plain/Reinforced cement concrete in sub-
31.0 structure complete as per drawing and
technical
Structure specifications
PCC Grade M15 13.5A(p) Basic Rate Rs. 4153.00
carriage Rs. 250.50
Finished Rate Rs. 4447.53
concrete pipe for culverts on first class
32.0
bedding of granular material in single row
1200 dia Np4 pipe NH SOR 9.2 B Basic Rate Rs. 7106.00
In single row Sand 0.0072 x 91.40 Rs. 0.66
Chips 0.40 x 161.32 Rs. 64.53
Cement 0.0056 x 218.20 Rs. 1.22
H.P. 1x 236.42 Rs. 236.42
Rs. 7482.91

33.0 Flexible Apron :Construction of flexible apron 1 m Basic Rs. 639.00


thick comprising of loose stone boulders weighing Boulder 1 165.18 Rs. 165.184
not less than 40 kg beyond curtain wall. Rs. 812.23
DETAILS OF QUANTITY
BRIDGE ON NILANJAN RIVER, KOLKOLE TO BARAINI ROAD 5X24.6 M

SL. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY


NO. HEIGHT

BILL NO. 1 : FOUNDATION


1 E/W in excavation of foundn. Trenches for bridges with all materials ,labour ,tools and m3 m m m
plants,levelling and ramming the foundation beds,dressing the sides ,removing
roots,logs ,shrubs,and other loose and deleterious materials likely to
deteriorate,adequate provision against erosion,water pollution anddrainage to keep the
site free of water ,stacking the excavated soil clear from the edge of excavation, and
backfilling the same with approved materials providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation all complete job
as per design/drawing and technical specification and MORT&H specification clause
304 and other relevant clauses and direction of E/I(Excluding cost of dewatering and
shoring)
(I)ORDINARY SOIL
ABUTMENT A1 1.00 x 12.20 x 4.70 x 4.00 = 229.36
ABUTMENT A2 1.00 x 12.20 x 4.70 x 3.00 = 172.02
PIER P1 1.00 x 10.20 x 4.40 x 2.00 = 89.76
PIER P2 1.00 x 10.20 x 4.40 x 2.00 = 89.76
PIER P3 1.00 x 10.20 x 4.40 x 2.00 = 89.76
PIER P4 1.00 x 10.20 x 4.40 x 2.00 = 89.76
m3 Total 580.90
(II)SOFT ROCK
ABUTMENT A1 1.00 x 12.20 x 4.70 x 4.00 = 229.36
ABUTMENT A2 1.00 x 12.20 x 4.70 x 3.00 = 172.02
PIER P1 1.00 x 10.20 x 4.40 x 2.00 = 89.76
PIER P2 1.00 x 10.20 x 4.40 x 2.00 = 89.76
PIER P3 1.00 x 10.20 x 4.40 x 2.00 = 89.76
PIER P4 1.00 x 10.20 x 4.40 x 2.00 = 89.76
m3 Total 670.66
(III)HARD ROCK
ABUTMENT A1 1.00 x 12.20 x 4.70 x 0.70 = 40.14
ABUTMENT A2 1.00 x 12.20 x 4.70 x 0.70 = 40.14
PIER P1 1.00 x 10.20 x 4.40 x 0.70 = 31.42
PIER P2 1.00 x 10.20 x 4.40 x 0.70 = 31.42
PIER P3 1.00 x 10.20 x 4.40 x 0.70 = 31.42
PIER P4 1.00 x 10.20 x 4.40 x 0.70 = 31.42
m3 Total 174.52

2 Providing and laying of P.C.C.M15 levelling course 100 mm thick in foundation

ABUTMENT A1 1 x 12.2 x 4.7 x 0.1 = 5.73


ABUTMENT A2 1 x 12.2 x 4.7 x 0.1 = 5.73
PIER 2 x 10.2 x 4.4 x 0.1 = 8.98
m3 Total 20.44

3 Filling annular space around founding in rock as per technical specification


ABUTMENT A1 1 x 33.8 x 0.3 x 0.6 = 6.08
ABUTMENT A2 1 x 33.8 x 0.3 x 0.6 = 6.08
PIER 2 x 29.2 x 0.3 x 0.6 = 10.51
m3 22.68

4 Back filling behind the abutment,wing wall and return wall including foundation
trenches with granular material combined with all leads and lifts at site including cost of
all materials,labour,tools and plants,watering,cost of water with all leads and lifts
,dressingand ramming,free from grass and other loose deleterious materials likely to
deteriorate,,providing light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation all complete job as per design/drawing and technical
specification and MORT&H specification clause 304 and other relevant clauses and
direction of E/I

Area(m2) Width(av.)

ABUTMENT A1 1 x 19.15 x 12 = 229.824


ABUTMENT A2 1 x 15.52 x 12 = 186.192

m3 Total 416.02
5
Providing filter media with stone metal grade-III conforming to MORT&HTable 400-
7,free from grass,dirt and debris and other loose and deleterious materials likely to
deteriorate,,providing light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation incidental charges,all taxes and royalty etc.all complete job
as per design/drawing and technical specification and MORT&H specification clause
305 and other relevant clauses and direction of E/I

ABUTMENT A1 1 x 12 x 7.99 x 0.6 = 57.528


ABUTMENT A2 1 x 12 x 6.46 x 0.6 = 46.512
m 3
Total = 104.04
SL. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
NO. HEIGHT
6.0 Providing P.C.C.M15 ordinary grade mechanically mixed concrete below approach
slab ,as levelling course with graded stone aggregate 40mm to 10mm size and clean
coarse sand of FM 2 and above , well screened, free from all dirt ,dust shellsand other
deleterious materials,including cost of all materials form work ,labour,handling material
at site,tools and plants, curing cost of water with all leads and lifts,all taxes and
royalties,incidental charges,hire and running charges of
machinery,depreciation,major/minor repair,POL and other lubricants,pay ofmachinary
staff ,providing light,barrier,danger signals,choukidar,making and maintaining
diversion,traffic regulation etc. all complete job as perdesign/drawing and technical
specification and MORT&H specification clauses and other relevant clauses and
direction of E/I

CONCRETE UNDER APPROACH SLAB m3 2 x 3.5 x 11.4 x 0.15 = 11.97

7.0 Providing PCC/RCC mechanically mixed concrete in abutment,Pier,wing wall,return


wall,curtainwall, toe wall with graded stone aggregate 40mm nominal size and clean
coarse sand of FM 2 and above , well screened, free from all dirt ,dust shells and other
deleterious materials,including cost of all materials form work ,labour,handling material
at site,centering and shuttering, screening, mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater,
curing cost of water with all leads and lifts,all taxes and royalties, incidental
charges,hire and running charges of machinery,depreciation, major/minor repair,POL
and other lubricants,pay ofmachinary staff , providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as perdesign/ drawing and technical specification and MORT&H
specificationclauses and other relevant clauses and direction of E/I(excluding cost of
reinforcement and it's cutting ,bending ,binding etc.)

ABUTMENT SHAFT-A1 m3 1 x 12.00 x 1.00 x 5.30 = 63.60

ABUTMENT SHAFT A2 1 X 12.00 x 1.00 x 3.78 = 45.36

PIER
(I) PIER STEM P1 m3 1 x 9.00 x 1.00 x 6.20 = 55.80
PIER NOSING m3 1 x area= 0.79 x 6.20 = 4.87
(II) PIER STEM P2 m3 1 x 9.00 x 1.00 x 6.88 = 61.92
PIER NOSING m3 1 x area= 0.79 x 6.88 = 5.40
RETURN WALL(I) 4 x 3.50 x 0.50 x 0.30 = 2.10
(II) 4 x 3.50 x 1.165 x 0.30 = 4.89
ABUTMENT
HEEL SLAB 2 x 2.00 x 12.00 x 1.10 = 52.80
TOE SLAB 2 x 1.50 x 12.00 x 1.10 = 39.60
RECTANGULAR 2 x 1.00 x 12.00 x 1.60 = 38.40
PIER FOUNDATION (I) RECTANGULAR PORTION 2 x 10.00 x 4.20 x 0.60 = 50.40
2 2 x 10.00 x 1.60 x 0.40 = 25.60
2 x 10.00 x 1.00 x 0.80 = 16.00
450.74
8.0 Providing weep holes in PCC/RCC in abutment ,wing wall,return wallwith 100mm dia
A.C. pipes ,collar ,M.S. clamps including cost of all materials and labour, ,providing
light,barrier,danger signals,choukidar,making and maintaining diversion,traffic
regulation incidental charges,all taxes and royalty etc.all complete job as per
design/drawing and technical specification and MORT&H specificationclauses and
other relevant clauses and direction of E/I

No. 160

9.0
Providing PCC/RCC mechanically mixed concrete in abutment cap,pier cap ,crash
barrier etc., with graded stone aggregate 20mm nominal size and clean coarse sand of
FM 2 and above , well screened, free from all dirt ,dust shellsand other deleterious
materials,including cost of all materials form work ,labour,handling material at site,
centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater,
curing cost of water with all leads and lifts,all taxes and royalties,incidental charges,hire
and running charges of machinery,depreciation, major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification
clauses and other relevant clauses and direction of E/I(excluding cost of reinforcement
and it's cutting ,bending ,binding etc.)

(a)RCC M-30
ABUTMENT CAP 2 x 12.00 x 1.05 x 0.3 = 7.56
PIER CAP 2 x 10.00 x 1.2 x 0.3 = 7.20
DIRT WALL 2 x 12.00 x 0.3 x 2.8 = 20.16
BRACKET 2 x 11.40 x 0.20 x 0.18 = 0.82
2 x 11.40 x 0.20 x 0.12 = 0.27
PEDESTRAL 8 3 x 0.80 x 0.70 x 0.25 = 3.36

Total 39.37
SL. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
NO. HEIGHT
10.0 Providing PCC/RCC mechanically mixed concrete in Deck slab,girder,bed block,and
Foot path, with graded stone aggregate20mm nominal size and clean coarse sand of
FM 2 and above , well screened, free from all dirt ,dust shellsand other deleterious
materials,including cost of all materials form work ,labour,handling material at
site,centering and shuttering,screening,mixing in cement mixer,placingin
position,vibrating,hire and running charges of concrete mixer and needle vibrater,
curing cost of water with all leads and lifts,all taxes and royalties,incidental charges,hire
and running charges of machinery,depreciation,major/minor repair,POL and other
lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification
clauses and other relevant clauses and direction of E/I(excluding cost of reinforcement
and it's cutting ,bending ,binding etc.)

(a)RCC M-30
TOTAL CONCRETE IN SUPERSTRUCTURE m3 3 116.93 350.79
(excluding railing)
Total 350.79
11.0 Providing precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm,true
to the line and grade,tolerance of RCC vertical post not to exceed 1 in 500,centre to
centre spacing between the vertical post not to exceed 2000mm, leaving adequate
space between vertical post for expansion,complete as per approved drawing and
Technical specification

x
m 2 24.6 3 = 147.6
APPROACH m 4 x 3.5 = 14
Total 161.6
12.0 Providing and laying Reinforced cement concrete wearing coat M30 grade including
reinforcement complete as per drawing and Technical specification

m3 3 x 24.6 x 10.9 x 0.075 = 60.3315


2 x 3.5 x 10.9 x 0.075 = 5.7225
Total 66.054
13.0 Providing and laying RCC Approach slab M30 grade including reinforcement and
formwork complete as per drawing and Technical specifications

m3 2 x 3.5 x 10.9 x 0.30 = 22.89


14.0

Providing HYSD bars in all types of RCC works in Girder, Deck slab ,bed ,block,
abutment,return wall ,pier shaft, abutment cap, pier capincluding cutting to
sizes,bending,binding,placing in position on cement cubeswith cost of all
materials,labour,tools and plants,all taxes,handling materials at siteand incidental
charges,all complete job as per design/drawing and technical specification and
MORT&H specifications clauses and other relevant clauses and direction of E/I
ABUTMENT SHAFT MT #REF!
ABUTMENT FOUNDATION MT #REF!
ABUTMENT CAP MT #REF!
DIRTWALL MT #REF!
RETURN WALL MT #REF!
BRACKET MT 0.18
PEDESTRAL MT #REF!
PIER FOUNDATION MT #REF!
PIER SHAFT MT #REF!
PIER HAMMER HEAD MT #REF!
SUPERSTRUCTURE MT 5 22.04 110.20

Total #REF!
15.0 Providing , laying,fitting,fixing stone boulder pitching duly packed in slope of road
embankment and approach with approved quality of materials within 150m of worksite
and all lift as per direction of E/I including cost of all materials , labour

x(2X )x
m3 2 277.3 + 151.6 0.6 = 847.44
847.44
16.0 Providing and laying Filter material underneath pitching in slopes all complete as per
x(2X x
drawing and Technical specification m3 2 277.3 + 151.6 0.15 = 211.86

Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per approved drawings and
17.0 4 x 12
standard specifications to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for installation.)
m = 48

Providing drainage spouts with 260mmx260mm M.S. grating 100 mm dia. 1.00m long
G.I. pipe including cost of all labour and materialall complete job as per design/drawing
18.0
and technical specification and MORT&H specification clauses and other relevant
clauses and direction of E/I
No. 24 24
19.0 Supplying ,fitting and fixing elastomeric bearing conforming to IRC 83(part -I) section-
IX in position ,true to lines and level including all accessories,neoprene w.r.l.m.s.
plate ,all labour including machinary inputs for various processing operations like gas
cutting .fabrication,converting into elastometric compound of required specifications,for
adding chemicals like primer for plates and final bonding agents of plates to elastomer,
for pretreatment,bonding /vulcanizing of elastometric compound with reinforcing steel
plate,hire and running charge of machinery with depreciation,major/minor repair,POL
and other lubricants,pay of machinary staff ,providing light,barrier,danger
signals,choukidar,making and maintaining diversion,traffic regulation etc. all complete
job as per design/drawing and technical specification and MORT&H specification
design/drawing and technical specification and MORT&H specificationclauses and
other relevant clauses and direction of E/I

cm3 24 x 50 x 36 x 9.6 = 414720


SL. ITEMS OF WORK UNIT NO LENGTH BREADTH DEPTH/ QUANTITY
NO. HEIGHT
20.0 CONFIRMATORY BORING 40