CB/DHQC/MEPI/FP & FD/B2 (002) 24th November 2020

Director,
Project Management Unit,
Defence Headquarters Complex Project,
Akuregoda Road,
Palawatta.

Dear Sir,

Advance Payment Guarantee


Reference to the letter DIMO/DHQC/B2/FP & FD/004 dated 12 th November 2020 addressed to
Director MEPI. The Contractor M/s. Diesel and Motor Engineering PLC. has now handed over to us
the Advance Payment Guarantee of the above contract.
Details of Advance Payment Guarantee are as follows.

1. Bond Number : 006D80820110001


2. Bank issued : Nations Trust Bank
3. Value of Performance Bond : LKR 30,196,056.00 (Sri Lanka Rupees Thirty Million
One Hundred Ninety Six Thousand Fifty Six Only)
4. Period of validity : Up to 23rd July 2021

Above Advance Payment Guarantee is acceptable. We herewith forward you the original of the same
for safe keeping.

Yours faithfully,
CENTRAL ENGINEERING CONSULTANCY BUREAU

…………………………
Eng. B. W. N. Rupasinghe
Director - MEPI
Encl.

CC: M/s. Diesel & Motor Engineering PLC


DGM(C&QS)

SC/HK