Professional Documents
Culture Documents
Electrical Disturbances in LV Networks Due To Energization of MV Networks
Electrical Disturbances in LV Networks Due To Energization of MV Networks
Electrical Disturbances in LV Networks Due To Energization of MV Networks
net/publication/261096702
CITATIONS READS
0 43
5 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by G.D. Marques on 30 September 2015.
A statistical analysis was conducted, for each case, to find Two cases were reported where the clients were affected due
the cumulative distribution probability of the overvoltage to energization of the MV networks. One MV network is
amplitude, for different switching conditions. composed of 30kV overhead lines and the other is composed
of 15kV underground cables.
Field measurements on a MV network that supply several
distribution transformers were made to record switching A statistical analysis was conducted, for each case, to find the
transients and verify the models developed in a digital cumulative distribution probability of the overvoltage
transients software. magnitude, for different switching conditions.
The experimental results verify the digital models and they The closing of the energizing circuit breaker was simulated
represent the behavior of the MV network under electrical for a sample of 100 closing operations with different pole
disturbance conditions. closing times. The closing times followed a uniform
probability distribution. The peak voltage for each closing
OBJECTIVES operation was recorded as well as the closing times. The 2%
overvoltage probability was found to reach high enough
A distribution network is a complex system that is susceptible values to destroy electrical equipment at the customer’s end
for some system configurations.
to different kinds of disturbances [1]. These disturbances are
related to several factors such as lightning, faults and
First Case: Overhead MV Network
switching operations that can affect the operation of electrical
equipment of domestic or industrial clients. Domestic clients
The overhead network represented is shown in figure 1. The
have reported electrical equipment failures on energizing MV
figure shows the sequence of maneuvers that happen when the
networks (e.g. appliances, videos, TV, stereos).
electrical equipment were affected.
Overhead Line 30 kV
that purpose, data about the networks where clients were MV/LV
system.
MV/LV
PTD 0014
Due to the uncertainty of closing time of the circuit breaker MV/LV
MV/LV
poles, the electromagnetic transients program has an option to
perform a statistical analysis of the breaker closing angles and PTD 0008
produce the statistical distribution of the resulting Figure 1 – Scheme of the modeled overhead line
* Dr. Atef Morched is currently with CYME International T&D, Montreal, Canada
CIRED2005
Session No 2
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
Energization at 22h40m
Reposição às 22h:40m
637 [V]=1.95 pu
637 [V] =1.95 pu
De-energization of the red line
Simulação de seccionamento
at 17h10m
do troço vermelho
CIRED2005
Session No 2
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
VALIDATION
Voltage [V]
The tested system is shown in figure 6.
MV/LV
Time [s]
LXHIOV 240mm2 - 360m
MV/LV
Figure 8 – Voltages measured at LV terminals of distribution
Voltage
transformer – Opening the circuit breaker
MV/LV
MV/LV
LXHIOV 240mm2 - 215m To validate the EMTP models used in the simulation of the
MV/LV previous cases, the 15kV underground system was modeled in
LXHIOV 240mm2 - 530m a similar way and simulations were conducted to compare
MV/LV
LXHIOV 240mm2 - 440m with the measured results.
MV/LV
Current Phase 0
400
-200
Simulation EMTP
Several, opening and closing operations of the circuit breaker -300
Experimental
200
100
0
0 0,01 0,02 0,03 0,04 0,05
-100
-200
Voltage [V]
Simulation EMTP
-300
Experimental
-400
Time [s]
CIRED2005
Session No 2
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
Phase 8
400
300
200
100
0
0 0,01 0,02 0,03 0,04 0,05
-100
-200
Simulation EMTP
-300
Experimental
-400 > 1.1 pu
CONCLUSIONS
It has been observed from the experimental data that the poles
of the circuit breaker do not close simultaneously, as was
expected.
REFERENCES
CIRED2005
Session No 2