Project: Pekerjaan Tambahan Steam Pipeline Dari Pad 29 Ke Pad 7 Client: Geo Dipa Energy Owner: Geo Dipa Energy Location: Dieng REV: 1
Project: Pekerjaan Tambahan Steam Pipeline Dari Pad 29 Ke Pad 7 Client: Geo Dipa Energy Owner: Geo Dipa Energy Location: Dieng REV: 1
Project: Pekerjaan Tambahan Steam Pipeline Dari Pad 29 Ke Pad 7 Client: Geo Dipa Energy Owner: Geo Dipa Energy Location: Dieng REV: 1
CALCULATION
1 Piping Flexibility Analysis HCE 10A -HCE 29 1 A4 Set 200 200
2 Wall Thickness Calculation 1 A4 Set 32 32
DATASHEET
1 Spring Data Sheet 1 A4 Set 16 16 Optional
2 Manual Valve Datasheet 1 A4 Set 16 16 Optional
3 Special Item Datasheet 1 A4 Set 16 16 Optional
LIST
1 MTO Pipeline Material 1 A4 Sheet 24 24
2 Pipeline Work Volume (Dia-Inch) 1 A4 Sheet 24 24
3 MTO Pipe Insulation 1 A4 Sheet 24 24 Optional Optional Optional
4 MTO for Pipe Support 1 A4 Sheet 24 24 Optional Optional Optional