PROCEDURE NO. 6
FOR
INSTALLATION
IN
GOVERNMENT BUILDINGS
HONG KONG
?
HONG KONG SPECIAL ADMINISTRATIVE REGION GOVERNMENT
BSBTC-06
COPYRIGHT
1. This Testing and Commissioning Procedure is solely compiled for use on Low
Voltage Cubicle Switchboard Installation in Government Buildings of the Hong Kong
Special Administrative Region.
2. This Testing and Commissioning Procedure is copyrighted and all rights (including
subsequent amendment) are reserved.
3. It is hereby declared that the procedure contained therein may not be pertinent or
fully cover the Low Voltage Cubicle Switchboard Installation carried out by other
Government Departments or private sectors. Prior consent by the Director of Architectural
Services must be obtained for adoption of this testing and commissioning procedure for
Low Voltage Cubicle Switchboard Installation of other nature or locations.
BSBTC-06
TABLE OF CONTENT
Page
1. Introduction 1
2. General Requirements 1
4. Statutory Inspection/Commissioning 2
5. Calibrated Equipment 2
Appendix A Page
Part 2 : Declaration 1
3.3 State any other tests that are considered necessary to meet the design 7
intent
3.4 Comments 8
Appendix B Page
Testing and Commissioning progress chart for Low Voltage Cubicle Switchboard
Installation
BSBTC-06 I
B.S.B. Testing and Commissioning Procedure No. 6
Low Voltage Cubicle Switchboard Installation
1. Introduction
1.1 This procedure is intended to lay down the minimum testing and
commissioning requirements to be carried out by the Contractor on a new
Low Voltage Cubicle Switchboard Installation upon completion or on an
existing Low Voltage Cubicle Switchboard Installation after a major
alteration. Additional testing and commissioning (T & C) requirements
may be proposed by the Contractor as appropriate and agreed by the Project
Building Services Engineer (PBSE), e.g. for special equipment supplied
and/or installed by the Contractor.
1.2 This procedure is also written to facilitate the PBSE and Project Building
Services Inspector (PBSI) in carrying out the following aspects of work
with respect to T & C.
(i) To vet and approve the T & C procedures proposed and submitted by
the Contractor.
2. General Requirements
2.1 The Contractor shall submit the T&C procedures together with the Testing
and Commissioning progress chart in Appendix B to the PBSE for
approval. The submission shall be made at least one month before the
commencement of T&C.
2.2 Where tests are required to be witnessed by the PBSE/PBSI, the Contractor
shall give due advanced notice (usually not less than three working days)
and provide details of date, time and type of tests to be performed.
2.3 Upon completion of such T & C procedure, the Contractor shall complete
and sign a testing and commissioning certificate as Appendix A, to the
effect that the L.V. Cubicle Switchboard Installation has been tested and
commissioned in accordance with this and/or otherwise agreed procedures.
2.4 Before carrying out any test, the Contractor shall ensure installations
comply with the statutory requirements and regulations.
2.5 The Contractor shall provide any test certificate(s) for the equipment as
required in the Specification.
2.6 The Contractor shall carry out visual inspection in accordance with the
checklists as shown in Part 3 of Appendix A and abnormalities shall be
rectified before despatch of the cubicle switchboard to site.
BSBTC-06 1
2.7 The Contractor shall deliver the cubicle switchboard to site either in its
entirety or in transportation sections. In the latter case, the section shall be
reassembled on site.
2.8 The Contractor shall carry out the visual inspection again on those items
which may be affected during the transportation e.g. the tightness of bolt
and nuts, the alignments of the various sections of the switchboard etc.
3.2 The Contractor shall carry out the tests and inspections as shown in Part 3
and record the test results on Part 4 of Appendix A and as agreed between
the PBSE and the Contractor.
3.3 The Contractor shall provide all the necessary staff, labour, materials and
equipment for a thorough test and examination of the installation.
4. Statutory Inspection/Commissioning
4.1 After the proper testing and commissioning of the low voltage cubicle
switchboard installation, the Contractor shall notify the appropriate
Authority, through the PBSE, on the completion of the installation and its
readiness for inspection and testing.
5. Calibrated Equipment
BSBTC-06 2
Appendix A
1.4 * Contractor/Sub-Contractor :
1.5 PBSE :
1.6 PBSI :
Part 2 : Declaration
2.2 I also certify that site tests have been performed in accordance with the
requirements set out in Appendix A of this procedure and that the results
are satisfactory. A record of the tests has been prepared and submitted to
the PBSE.
Date
3.1.1.4 Labels have been properly provided and installed. *Yes/No *Yes/No
3.1.1.6 The layout of the TTA is in conformity with the *Yes/No *Yes/No
approved drawings.
3.1.1.8 Danger notices and operation instructions have been *Yes/No *Yes/No
adequately provided.
3.1.1.9 Earthing bar and earthing connections have been *Yes/No *Yes/No
provided.
3.1.1.10 Earth wire has been installed for hinged front panels *Yes/No *Yes/No
carrying L.V. equipment.
3.1.1.11 The bolts, nuts, washers and screws are of non-ferrous *Yes/No *Yes/No
material.
3.1.1.13 The compartmentation of the TTA conforms with the *Yes/No *Yes/No
specified requirements.
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
3.1.2.1 The busbar arrangements, including spacing and means *Yes/No *Yes/No
of support, conform with the type-tested drawings.
3.1.2.7 The bolts, nuts, screws etc. for busbar supports, busbar
connections have been checked for correct tightness. *Yes/No *Yes/No
3.1.3.1 The ACB ratings are in accordance with the approved *Yes/No *Yes/No
working drawings.
3.1.3.4 The number and rating of ACB/fuse switches are in *Yes/No *Yes/No
conformity with the approved working drawings.
3.1.3.5 The fuse ratings are in conformity with the approved *Yes/No *Yes/No
working drawings.
3.1.3.7 The contact surfaces of the ACB/fuse switches have *Yes/No *Yes/No
been kept clean.
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
3.1.4.1 The Power Co.’s meter control fuses, meter board, *Yes/No *Yes/No
cabling etc. have been properly installed.
3.1.4.2 The type and range of the measuring instruments are in *Yes/No *Yes/No
accordance with those approved.
3.1.4.3 Type and range of protective relays are in accordance *Yes/No *Yes/No
with those approved.
3.1.4.4 The operating voltage of the shunt trip coil complies *Yes/No *Yes/No
with the specification.
3.1.4.6 The battery voltage and charging current have been *Yes/No *Yes/No
checked and found satisfactory.
3.1.4.7 The capacity of the battery has been tested by tripping *Yes/No *Yes/No
the ACB and results are satisfactory.
3.1.4.8 The re-charging time of the battery complies with the *Yes/No *Yes/No
specification.
3.1.4.9 The control cables have been properly identified and *Yes/No *Yes/No
connected.
3.1.4.10 Rubber grommets have been provided for holes *Yes/No *Yes/No
through which control cables pass.
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
3.1.5.1. Proper facilities have been provided for fixing of *Yes/No *Yes/No
incoming/outgoing cables.
3.1.5.2. Adequate space has been allowed for fixing of *Yes/No *Yes/No
incoming/outgoing cables.
3.1.5.3. The cables for termination have been soldered or *Yes/No *Yes/No
properly fitted with sockets.
3.1.5.6. Proper identification has been provided for each cable. *Yes/No *Yes/No
3.1.6 Miscellaneous
3.1.6.2 Operating handles and keys c/w mounting board have *Yes/No *Yes/No
been provided.
3.1.6.3 Spare fuses as agreed c/w mounting board have been *Yes/No *Yes/No
provided.
3.1.6.6 Schematic diagram has been framed and installed. *Yes/No *Yes/No
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Building Services Branch, ArchSD Page 5 of 16 Filecode: SR066.doc
FORM NO. BS/SR066 Revision Date: 15 September 2000
Issue Date: 3 March 2000
Appendix A
3.2.3 The above test results have been recorded in the “Test *Yes/No *Yes/No
Records” as shown in Appendix A Part 4 of this
procedure.
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
3.4 Comments
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
R E
Y E
B E
R Y
Y B
B R
E N
R N
Y N
B N
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
4.1.3.1 The test shall be carried out with all switching devices closed
Earth R+Y+B+N
N R+Y+B+E
R Y+B+ N+E
Y B+R+N+E
B R+Y+N+E
4.1.3.2 After test at 4.1.3.1 another insulation test using 1000V megger shall be carried out with all
switching devices closed.
R E
Y E
B E
R Y
Y B
B R
E N
R N
Y N
B N
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Satisfactory (? )
Unsatisfactory (X) Remarks
NOT completed (NC)
NOT applicable (NA)
Measurement CT Y
Protection CT Y
R 50 1 5
R 50 1 10
R 100 0.5 10
Y 50 1 5
Y 50 1 10
Y 100 0.5 10
B 50 1 5
B 50 1 10
B 100 0.5 10
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
N 10 1 2.5
N 10 1 5
N 20 0.5 2
4.1.5.1 For overcurrent relays and earth fault relays set at specified settings
R-Y
Y-B
B-R
R-N
Y-N
B-N
Position
(Positions of test should include all joints and Resistance (MicroOhm)
connections. The followings are for reference
only.)
Joints on main busbars
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Satisfactory (? )
Item Check (where applicable) Unsatisfactory (X) Remarks
NOT completed (NC)
NOT applicable (NA)
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Satisfactory (? )
Item Check (where applicable) Unsatisfactory (X) Remarks
NOT completed (NC)
NOT applicable (NA)
Voltage (V)
R-E
Y-E
B-E
R-Y
Y-B
B-R
E-N
R-N
Y-N
B-N
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Witnessed by Signature(s)
(Name(s) of *PBSE/*PBSI)
Contract No .:
Contract Title :
Name of Contractor/sub-Contractor :
Testing and Commissioning Progress Chart for Low Voltage Cubicle Switchboard Installation
(Rev. )(1)
Dates (2) Remark
Activities Reference S A S A S A S A S A S A S A S A
to
Appendix A
1. Visual checks 3.1
Submission of
Record of Test
8. Temperature-rise 4.1.7
Limit Test
Submission of
Record of Test
Testing and Commissioning Progress Chart for Low Voltage Cubicle Switchboard Installation
(Rev. )(1)
Dates (2) Remark
Activities Reference S A S A S A S A S A S A S A S A
to
Appendix A
9. Function test 4.1.8
Submission of
Record of Test
Notes
* Delete if not applicable
(1) Insert revision no.
(2) Insert additional columns as necessary
S - schedule % completion
A - actual % completion