Professional Documents
Culture Documents
The First Extradosed Bridge in Slovenia
The First Extradosed Bridge in Slovenia
To cite this article: Viktor Markelj (Structural Eng., Manager) (Lecturer) (2010) The First
Extradosed Bridge in Slovenia, Structural Engineering International, 20:4, 462-467, DOI:
10.2749/101686610793557645
Article views: 16
Abstract the bridge, the lake is 250 m wide and 430 m proved to be the best solution
about 5 m deep. The surrounding ter- for bridging the obstacles. There was
This paper presents the conceptual rain is very flat. The main problem was no dilemma in arriving at the cross
design and technical solutions for the the lake itself, particularly the shores section: taking into consideration the
bridge over the artificial lake of Ptuj that house all the facilities and equip- road curvature and torsion, bridge
(power plant reservoir on the Drava ment for the operation of the reservoir installation and maintenance, a box
River) on the new south main road, (safety embankments, sealing curtain girder of maximum feasible height of
which connects the city of Ptuj with the and drainage), the sewer pipes on both 2,70 m was selected. The slenderness
Maribor–Zagreb motorway. sides and the stream beyond the right ratio L/H = 100 m/2,7 m = 37 was obvi-
The horizontal axis of the 430,0 m long bank of the lake. ously too large for a normal concrete
and 18,0 m wide bridge has a radius of continuous girder structure of constant
For specific locations, it was necessary
curvature of R = 460,0 m. The bridge is depth. The usual prestressed concrete
to take into account the relative vicin-
designed as an “extrados bridge,” repre- girder with a variable height, con-
ity of the old town of Ptuj with its old
senting an intermediate form between structed by the free cantilever method,
castle. This being a site of historical
girder bridges and cable-stayed bridges. would require a girder height of 5,0 to
heritage, very strict restrictions were
Structural spans of the bridge are 65 + 5,8 m (L/20–L/17) at the support. This
imposed in order to preserve the views
100 + 100 + 100 + 65 = 430 m. In the cross would close the navigation channel
of the old city. This limited the height
section the bridge is a mono-cellular, and was not acceptable for this reason.
of structures (in this case, pylons) to a
box-shaped, longitudinally prestressed It was therefore necessary to support
maximum of 10 m.
concrete girder; H = 2,70 m, with classic the structure from above, for example,
prestressing tendons inside and addi- The following were other signifi- by cables through the pylon. However,
tional exterior extrados cables over the cant restrictions and conditions that taking into consideration the cultural
low pylons. affected the technical design of the heritage of the region and the need to
bridge: protect the view of the city, a restric-
The conceptual design won the open tion of a maximum pylon height of
design competition in 2004 and the final – severe restrictions on the support 10 m was imposed on structural ele-
tender design was completed in March layout due to the slurry wall on the ments located on the upper side of the
2005. The construction of the innova- banks of the lake; carriageway.
tively designed “extrados bridge” started – road geometry with a sharp radius
in November 2005, and the bridge was The solution to this problem was the
of curvature of R = 460 m;
opened for traffic in May 2007. use of a new system in bridge building,
– low elevation of the bridge and the
the so-called “extrados” bridge, which
Keywords: extrados bridge; prestressed required waterway and shipping
is a kind of intermediate step between
concrete; stay cables; deviator; saddle. clearance of 4,0 m underneath;
the cable-stayed and the girder bridges.
– difficult foundation conditions in
In this case, the bridge girder could
the lake because of the rocky bed
Introduction be more slender than a normal con-
located 20 to 30 m below the water
tinuous girder, and the pylon could be
level;
In May 2004, the municipality of lower than the pylon for cable-stayed
– other obstacles (existing sewage and
Ptuj and Motorway Company in the systems.
other municipal water ditches and
Republic of Slovenia announced an
streams, the existing discharge facil-
anonymous competition to select the Structure Description
ity, sharp crossing of the road with
best design solution for a bridge over
the left bank of the river);
the Drava River near Ptuj, the oldest The bridge length between the expan-
– two-way carriageway of width
city in Slovenia. On the basis of the sion joints is 433 m and the total width
8,10 m and a separate lane of width 2
winning design, the tender design was is 18,70 m. The static system is a contin-
× 3,10 m for pedestrians and cyclists.
prepared in 2005; later in September uous externally prestressed box struc-
that year, and the construction con- Design Concept ture 2,7 m high, constructed according
tract for EUR 8,8 million was signed. to the so-called system of the “extra-
The bridge, named “Puch Bridge” after The design concept of the bridge was dos” bridge with structural spans of 65
the famous Slovenian inventor, was the result of a search for the optimal + 100 + 100 + 100 + 65 = 430 m. In its
opened to traffic in May 2007. response to the very difficult condi- entire length, the bridge lies in the cur-
tions for spanning the lake. Owing to vature R = 460 m (Fig. 1).
Environmental Conditions the many restrictions, the bridge con- The entire structure is continuous with
and Other Restrictions cept required large spans, but at the expansion joints only on abutments.
The Ptuj Lake is the largest artifi- same time, a relatively shallow struc- Two central supports have longitudi-
cial lake in Slovenia, with a length of ture was necessary. nally fixed bearings and carry all hori-
over 5 km, width up to 1,2 km and The longitudinal disposition with the zontal loadings, while the transverse
depth up to 15 m. At the location of spans of 65 + 100 + 100 + 100 + 65 = horizontal loadings are carried by all the
1 2 3 4 5 6
3 4
430
2 5
100
100
100 6
1
65
65
3,1+01,80
3,2+01,8
0
3,3+
3,0+
01,8
01,8
0
0
3,3
2,9
+6
+3
6,8
6,8
0
0
supports. Three of the four intermediate Supports 3 and 4 have fixed pot bear- account as well as the execution fea-
supports are located in the reservoir. ings at the top, while supports 1, 2 and sibility, structure maintenance and the
5, 6 have longitudinally movable and hydraulic consequences. For piers, the
transversally fixed bearings. foundation on eight piles of diameter
The Substructure and Foundation
Φ1,50 m with the oval-shaped “float-
The substructure consists of two abut- The bearings summary is given in ing” pile head was foreseen in the
ments and four intermediate piers, Table 1. design. As the superstructure lies on
three of which are located in the res- The intermediate piers are relatively a curve, the piles are arranged asym-
ervoir and one on the shore. All the low, 2,4 m thick and about 8 m wide, metrically so that they are uniformly
supports are on deep foundation with of a full cross section and are fixed loaded under the permanent load (the
piles of diameter Φ 1,50 m. Owing to into the pile head at the bottom intermediate supports are more loaded
the low and relatively stiff supports, a (Fig. 2). on the inner side of the curvature—on
rigid connection between the piers and the bearings, the ratio is 58–42%). At
the girder is not possible; however, all At the foundation in the lake, the soil the pile head surface, it was simple
the supports have bearings at the top. mechanics data had to be taken into to perform the temporary supporting
during the cantilever construction.
Free Length
3,0% k.niv.
3,0% 3,0% Extrados cables consist of 31 mono-
strands of 15,7 mm (cross section
150 mm2) in the outer PE protection
2,70
Saddle
φ355,6
φ180
For anchoring and the transition
6260 through the pylon respectively the
so-called deviating saddle or deviator
550/5
550
angle is smaller than in cable-stayed
bridges. In this case, the curvature
Fig. 5: Stay-cable anchorage system (Units: mm) radius of 4,60 m for a length of about
2,2 m was used.
The deviator consists of two bent steel
pipes, namely, of the external pipe
φ323,6 2200
φ193,7
φ180
Conclusion
The solution employing the so
called “extradosed bridge” system
managed to ingeniously overcome
numerous restrictions and difficul-
ties imposed on the Drava River
spanning. The sharp curvature, which
confronted design and building with
a very challenging task, was success-
fully carried out by using some new
design solutions and original struc-
Fig. 10: Bridge over the Drava River at Ptuj, Slovenia tural details.
Owner:
DARS, d.d., Motorway Company,
Celje, Slovenia
Structural design:
PONTING, d.o.o., Maribor, Slovenia
Contractors:
SCT, d.d., Ljubljana, Slovenia
Porr AG, Wien, Austria
Bridge type: Concrete extrados bridge
Bridge size: L = 433 m,
W = 18,70 m, A = 8097 m2
Concrete (m3): 9488
Reinforced steel (t): 1300
High quality steel
for cables (kg): 189 900
Fig. 11: Night view of the heritage town and its new bridge
High quality steel
The bridge provided the city of Ptuj cultural heritage; moreover, it has for stays (kg): 99 060
a solution for their traffic problems the potential to become a new archi- Total cost (EUR million): 8,8
and a unique engineering structure. tectural landmark and symbol for the Service date: May 2007
In addition to that, the bridge does modern city of Ptuj on its southern
not compete with the city’s urban border.
www.iabse.org/publications/onlinshop
International Association for Bridge and Structural Engineering IABSE
Association Internationale des Ponts et Charpentes AIPC
Internationale Vereinigung für Brückenbau und Hochbau IVBH