Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Structural Engineering International

ISSN: 1016-8664 (Print) 1683-0350 (Online) Journal homepage: https://www.tandfonline.com/loi/tsei20

The First Extradosed Bridge in Slovenia

Viktor Markelj (Structural Eng., Manager) (Lecturer)

To cite this article: Viktor Markelj (Structural Eng., Manager) (Lecturer) (2010) The First
Extradosed Bridge in Slovenia, Structural Engineering International, 20:4, 462-467, DOI:
10.2749/101686610793557645

To link to this article: https://doi.org/10.2749/101686610793557645

Published online: 23 Mar 2018.

Submit your article to this journal

Article views: 16

View related articles

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=tsei20
The First Extradosed Bridge in Slovenia
Viktor Markelj, Structural Eng., Manager, PONTING d.o.o. Maribor; Lecturer, Faculty of Civil Engineering,
University of Maribor, Slovenia. Contact: viktor.markelj@ponting.si

Abstract the bridge, the lake is 250 m wide and 430 m proved to be the best solution
about 5 m deep. The surrounding ter- for bridging the obstacles. There was
This paper presents the conceptual rain is very flat. The main problem was no dilemma in arriving at the cross
design and technical solutions for the the lake itself, particularly the shores section: taking into consideration the
bridge over the artificial lake of Ptuj that house all the facilities and equip- road curvature and torsion, bridge
(power plant reservoir on the Drava ment for the operation of the reservoir installation and maintenance, a box
River) on the new south main road, (safety embankments, sealing curtain girder of maximum feasible height of
which connects the city of Ptuj with the and drainage), the sewer pipes on both 2,70 m was selected. The slenderness
Maribor–Zagreb motorway. sides and the stream beyond the right ratio L/H = 100 m/2,7 m = 37 was obvi-
The horizontal axis of the 430,0 m long bank of the lake. ously too large for a normal concrete
and 18,0 m wide bridge has a radius of continuous girder structure of constant
For specific locations, it was necessary
curvature of R = 460,0 m. The bridge is depth. The usual prestressed concrete
to take into account the relative vicin-
designed as an “extrados bridge,” repre- girder with a variable height, con-
ity of the old town of Ptuj with its old
senting an intermediate form between structed by the free cantilever method,
castle. This being a site of historical
girder bridges and cable-stayed bridges. would require a girder height of 5,0 to
heritage, very strict restrictions were
Structural spans of the bridge are 65 + 5,8 m (L/20–L/17) at the support. This
imposed in order to preserve the views
100 + 100 + 100 + 65 = 430 m. In the cross would close the navigation channel
of the old city. This limited the height
section the bridge is a mono-cellular, and was not acceptable for this reason.
of structures (in this case, pylons) to a
box-shaped, longitudinally prestressed It was therefore necessary to support
maximum of 10 m.
concrete girder; H = 2,70 m, with classic the structure from above, for example,
prestressing tendons inside and addi- The following were other signifi- by cables through the pylon. However,
tional exterior extrados cables over the cant restrictions and conditions that taking into consideration the cultural
low pylons. affected the technical design of the heritage of the region and the need to
bridge: protect the view of the city, a restric-
The conceptual design won the open tion of a maximum pylon height of
design competition in 2004 and the final – severe restrictions on the support 10 m was imposed on structural ele-
tender design was completed in March layout due to the slurry wall on the ments located on the upper side of the
2005. The construction of the innova- banks of the lake; carriageway.
tively designed “extrados bridge” started – road geometry with a sharp radius
in November 2005, and the bridge was The solution to this problem was the
of curvature of R = 460 m;
opened for traffic in May 2007. use of a new system in bridge building,
– low elevation of the bridge and the
the so-called “extrados” bridge, which
Keywords: extrados bridge; prestressed required waterway and shipping
is a kind of intermediate step between
concrete; stay cables; deviator; saddle. clearance of 4,0 m underneath;
the cable-stayed and the girder bridges.
– difficult foundation conditions in
In this case, the bridge girder could
the lake because of the rocky bed
Introduction be more slender than a normal con-
located 20 to 30 m below the water
tinuous girder, and the pylon could be
level;
In May 2004, the municipality of lower than the pylon for cable-stayed
– other obstacles (existing sewage and
Ptuj and Motorway Company in the systems.
other municipal water ditches and
Republic of Slovenia announced an
streams, the existing discharge facil-
anonymous competition to select the Structure Description
ity, sharp crossing of the road with
best design solution for a bridge over
the left bank of the river);
the Drava River near Ptuj, the oldest The bridge length between the expan-
– two-way carriageway of width
city in Slovenia. On the basis of the sion joints is 433 m and the total width
8,10 m and a separate lane of width 2
winning design, the tender design was is 18,70 m. The static system is a contin-
× 3,10 m for pedestrians and cyclists.
prepared in 2005; later in September uous externally prestressed box struc-
that year, and the construction con- Design Concept ture 2,7 m high, constructed according
tract for EUR 8,8 million was signed. to the so-called system of the “extra-
The bridge, named “Puch Bridge” after The design concept of the bridge was dos” bridge with structural spans of 65
the famous Slovenian inventor, was the result of a search for the optimal + 100 + 100 + 100 + 65 = 430 m. In its
opened to traffic in May 2007. response to the very difficult condi- entire length, the bridge lies in the cur-
tions for spanning the lake. Owing to vature R = 460 m (Fig. 1).
Environmental Conditions the many restrictions, the bridge con- The entire structure is continuous with
and Other Restrictions cept required large spans, but at the expansion joints only on abutments.
The Ptuj Lake is the largest artifi- same time, a relatively shallow struc- Two central supports have longitudi-
cial lake in Slovenia, with a length of ture was necessary. nally fixed bearings and carry all hori-
over 5 km, width up to 1,2 km and The longitudinal disposition with the zontal loadings, while the transverse
depth up to 15 m. At the location of spans of 65 + 100 + 100 + 100 + 65 = horizontal loadings are carried by all the

462 Technical Report Structural Engineering International 4/2010

x086.indd 462 28/10/10 11:33 AM


430

65 100 100 100 65

1 2 3 4 5 6

Channel River Drava lake Stream

3 4
430
2 5
100
100
100 6
1
65
65

3,1+01,80

3,2+01,8
0

3,3+
3,0+

01,8
01,8

0
0

3,3
2,9

+6
+3

6,8
6,8

0
0

Fig. 1: Spans 65 + 100 + 100 + 100 + 65 = 430 m in curvature R = 460 m

supports. Three of the four intermediate Supports 3 and 4 have fixed pot bear- account as well as the execution fea-
supports are located in the reservoir. ings at the top, while supports 1, 2 and sibility, structure maintenance and the
5, 6 have longitudinally movable and hydraulic consequences. For piers, the
transversally fixed bearings. foundation on eight piles of diameter
The Substructure and Foundation
Φ1,50 m with the oval-shaped “float-
The substructure consists of two abut- The bearings summary is given in ing” pile head was foreseen in the
ments and four intermediate piers, Table 1. design. As the superstructure lies on
three of which are located in the res- The intermediate piers are relatively a curve, the piles are arranged asym-
ervoir and one on the shore. All the low, 2,4 m thick and about 8 m wide, metrically so that they are uniformly
supports are on deep foundation with of a full cross section and are fixed loaded under the permanent load (the
piles of diameter Φ 1,50 m. Owing to into the pile head at the bottom intermediate supports are more loaded
the low and relatively stiff supports, a (Fig. 2). on the inner side of the curvature—on
rigid connection between the piers and the bearings, the ratio is 58–42%). At
the girder is not possible; however, all At the foundation in the lake, the soil the pile head surface, it was simple
the supports have bearings at the top. mechanics data had to be taken into to perform the temporary supporting
during the cantilever construction.

Support in axis Bearing (kN)


Superstructure
Outside curve Inside curve
Abutment1 PNe 6100 PNe 5400
The superstructure consists of three
main elements:
Pier 2 PNe 21 700 PNe 28 200
Pier 3 PN 23 000 PN 28 200 – girder roadway structure;
Pier 4 PN 23 000 PN 28 200 – low pylons;
– inclined cables.
Pier 5 PNe 21 700 PNe 28 200
The roadway structure is a trapezoi-
Abutment 6 PNe 6100 PNe 5400
dal prestressed RC box of structural
PNe—pot bearing movable in longitudinal direction. PN—pot bearing fixed. height 2,70 m (Fig. 3). The web thick-
Table 1: Bridge bearings ness is 0,50 m, the upper slab is 18,16 m

Structural Engineering International 4/2010 Technical Report 463

x086.indd 463 28/10/10 11:33 AM


2 7,5 : 1, so that the cables, because of the
Drazenci Ptuj Drazenci Ptuj route curvature, do not interfere with
the clearance. The deviators for extra-
dos cables in each pylon are designed
to make possible the replacement of
3,0%
3,0%
individual cables. The pylons are ver-
3,0%

tically prestressed on the tension side


with dywidag bars with Φ = 40 WR
(950/1050 MPa), with 11 bars on the
inner side of the radius, and with 5 bars
on the outer side. Thus the loading due
Drava Drava Water
to the structure curvature is compen-
sated. The strength of the concrete for
the pylons is C45/55.
Gravel

Inclined “Extrados” Cables


Sand/clay In addition to the bonded tendons
(negative and positive) in the girder
Gravel and vertical prestressing bars in short
Sand /clay pylons, there is also the third type of
prestressing element, namely, low
Marl base inclined stays, also known as extrados
cables. To maintain uniformity, all the
extrados cables are of the same bear-
ing capacity and with equal number
Fig. 2: Characteristic river pier
(31) of bearing strands with the sec-
tion 150 mm2. The cables are 46 to 88
m long with the stressing force from
3600 to 3800 kN.
Each inclined cable consists of the
18,70
following:
0,50 3,10 1,70 4,05 4,05 1,70 3,10 0,50 – the free length;
– two equal anchorages on the girder
beam;
– deviator or saddle located on the
Drazenci Ptuj
short pylon (Fig. 4).

Free Length
3,0% k.niv.
3,0% 3,0% Extrados cables consist of 31 mono-
strands of 15,7 mm (cross section
150 mm2) in the outer PE protection
2,70

pipe that has been grouted with the


cement mortar.
The composition of the free length of
the inclined cable is as follows:
– Bearing element: seven-wire strand
Fig. 3: Stay cables anchored adjacent to concrete webs (Units: m) with nominal diameter of 15,7 mm
and the section 150 mm2 and of
quality 1570/1770 MPa with a very
low relaxation (<2,5% at the stress
wide and the bottom slab 9,10 m. The and additionally with 2 × 5 pairs of
0,7fu in the 2000 h test);
slab thickness varies from 0,22 to 0,50 extrados cables, 31 strands of diam-
– Internal corrosion protection: wire
m. The cantilever is 4,24 m long, at the eter 15,7 mm. They support the box at
galvanizing with zinc, grease protec-
fixing point 0,50 m thick and rebar a spacing of 5 m, adjacent to the webs,
tion—in PE 80, protection of mini-
reinforced. Owing to the flow of com- so that the force flows directly into the
mal thickness 1,5 mm (all together
pression stresses, the thickness of the longitudinal load-carrying system and
the so-called monostrand);
lower slab is enlarged to 0,80 m at the represents no problem.
– External protection: protection
supports. The structure is made of con-
The superstructure also includes short pipe of dense polyethylene PE, size
crete of compressive strength C45/50.
pylons of total height 8,5 m (L/11,8), 180/10,2 mm. The protection pipe is
The superstructure is prestressed with two on each support. The pylons with of black polyethylene, co-extruded
internal bonded tendons (negative in the cross section 1,20 m/2,80 m are with the external cover in dull white
the cantilever and positive in the span) inclined outwards with an inclination colour RAL 9002, UV-stabilized.

464 Technical Report Structural Engineering International 4/2010

x086.indd 464 28/10/10 11:33 AM


– static test on individual strands;
– dynamic test on individual strands
according to fib recommendations
for extrados cables, which means the
stress modification Δs = 140 MPa
with s k = 0,55fu and in 2 × 106 load-
ing cycles.
The durability of the inclined stays
anchorages is assured by the material
selection and the selected corrosion
protection system. The anchorage head
and the winding nut are made of rust-
resistant alloy, all the other anchorage
elements are hot galvanized. The inner
and upper part of the anchorage and
cable are additionally grouted with
cement mortar; the head, wedges and
strands, making possible subsequent
prestressing, are grouted with greases
Fig. 4: Short pylons with saddles and vertical prestressing bars in the protection cap.

Saddle

φ355,6
φ180
For anchoring and the transition
6260 through the pylon respectively the
so-called deviating saddle or deviator
550/5

was used. This solution is being used at


50

extrados bridges, as the cable-breaking


550

550
angle is smaller than in cable-stayed
bridges. In this case, the curvature
Fig. 5: Stay-cable anchorage system (Units: mm) radius of 4,60 m for a length of about
2,2 m was used.
The deviator consists of two bent steel
pipes, namely, of the external pipe
φ323,6 2200
φ193,7

(Φ = 323,6/7,1 mm) and the internal


deviator pipe (Φ = 193,7/5,6 mm).
φ193,7

Within the deviating pipes, the course


φ323,6

of the settled parallel strands was


achieved with PE spacers, assuring dis-
PEHD

φ180

tance between individual strands and


PEHD
φ180

the pipe. Inside the deviation pipe, the


PE cover and the grease were removed
from the monostrands. The prepared
strands were thereafter grouted with a
fast curing acrylic resin mortar, which
is chemically neutral to the galvanized
wires.
The detail of the deviator is shown
Fig. 6: The saddle consisting of two bent steel tubes (Units: mm) in Fig. 6. The external pipes for the
deviators were inserted in a group
into the pylon with the auxiliary steel
After construction, the space bet- The anchorage and system have been
structure, assuring a more exact place-
ween the monostrands and external used and verified on numerous bridges
ment into the inclined pylon, accord-
PE cover was grouted with cement with inclined stays, having more strict
ing to the shop drawings. Owing to the
mortar to achieve an additional requirements than those with extra-
horizontal curvature of the road and
mechanical resistance and prevent dos cables. In addition, dynamic tests
the vertical curvature of the elevation,
water condensation in the pipe. of the entire anchorage for s k = 0,45fu,
each deviator in the pylon has its own
Δs = 200 MPa and 2 × 106 cycles were
position.
Anchorage carried out.
Each inclined stay has two anchorages As the system used had additional
into the girder structure. The typical modifications (galvanized wires) espe- Construction
anchorage VT 31-150 SK has been cially for the bridge over the Drava
used with a minor modification at the River, two additional tests were per- The bridge erection, lasting from
external head protection (Fig. 5). formed, with positive results: October 2005 till May 2007, was a very

Structural Engineering International 4/2010 Technical Report 465

x086.indd 465 28/10/10 11:34 AM


demanding task. The foundation in
the lake was carried out with artificial
islands that were built with the help of
steel sheet piles. This was followed by
deep foundation with piles of diame-
ter Φ 1,50 m and of length 25 to 30 m,
reaching the marl base. The transpor-
tation of equipment and material on
the lake was carried out through heavy
barges.
The bridge deck was built by the bal-
anced cantilever method with the help
of inclined extrados cables. Movable
scaffolding with segment length of 5 m
was used for erection. Since the super-
Fig. 7: The balanced cantilever construction with the help of “extrados cables”
structure is of a constant height, the
scaffold was not modified as for the
usual variable height girders. The set-
ting and prestressing of stay cables was
performed. Doing this saved time, con-
sequently reducing the duration of a
single construction stage to one week,
which is normal.
One of the particularities of the
construction was the “extrados
cables”, which were assembled near
the bridge and then mounted as a
whole through saddles in the pylon
Fig. 8: Bridge construction to anchorages (Fig. 7). Prestressing
was performed with mono jacks from
both sides, using the strand-by-strand
method.
The stressing protocol ensured that
each strand in the stay cable was ten-
sioned with the same force at the end
of the tensioning procedure. Cables
have an ultimate load capacity of 8200
kN; in service stage being loaded with
approximately 4000 kN.
Very complex was also the monitor-
Fig. 9: Completed bridge ing of deformations in construction
stages, due to the flexible cantile-
vered deck of the bridge (Figs. 8-11).
The construction of such a bridge
would not have been possible without
the most modern software solutions
in the field of cable-stayed bridges
and the most accurate surveying
equipment.

Conclusion
The solution employing the so
called “extradosed bridge” system
managed to ingeniously overcome
numerous restrictions and difficul-
ties imposed on the Drava River
spanning. The sharp curvature, which
confronted design and building with
a very challenging task, was success-
fully carried out by using some new
design solutions and original struc-
Fig. 10: Bridge over the Drava River at Ptuj, Slovenia tural details.

466 Technical Report Structural Engineering International 4/2010

x086.indd 466 28/10/10 11:34 AM


SEI Data Block

Owner:
DARS, d.d., Motorway Company,
Celje, Slovenia
Structural design:
PONTING, d.o.o., Maribor, Slovenia
Contractors:
SCT, d.d., Ljubljana, Slovenia
Porr AG, Wien, Austria
Bridge type: Concrete extrados bridge
Bridge size: L = 433 m,
W = 18,70 m, A = 8097 m2
Concrete (m3): 9488
Reinforced steel (t): 1300
High quality steel
for cables (kg): 189 900
Fig. 11: Night view of the heritage town and its new bridge
High quality steel
The bridge provided the city of Ptuj cultural heritage; moreover, it has for stays (kg): 99 060
a solution for their traffic problems the potential to become a new archi- Total cost (EUR million): 8,8
and a unique engineering structure. tectural landmark and symbol for the Service date: May 2007
In addition to that, the bridge does modern city of Ptuj on its southern
not compete with the city’s urban border.

SED 12 - New Structural Engineering Document Published IABSE

Structural Engineering Documents


This SED book provides case studies of structural rehabilitation, repair,
retrofitting, strengthening, and upgrading of structures. Selected stud- 12
ies are presented in this SED and cover a variety of structural types from
different countries.

This document is a summary of practices to help structural engineers. Case Studies of


The reader will discover different approaches to put forward strength- Rehabilitation, Repair,
ening or rehabilitation projects. Even identical technical problems
could have very different efficient solutions, as discussed in the papers, Retrofitting, and
considering structural, environmental, economic factors, as well as Strengthening
contractor and designer experience, materials, etc.
of Structures
Price:
CHF 40 for Members, CHF 70 for Non-Members

www.iabse.org/publications/onlinshop
International Association for Bridge and Structural Engineering IABSE
Association Internationale des Ponts et Charpentes AIPC
Internationale Vereinigung für Brückenbau und Hochbau IVBH

Structural Engineering International 4/2010 Technical Report 467

x086.indd 467 28/10/10 11:34 AM

You might also like