Professional Documents
Culture Documents
Annex I Cost Estimate Final Ok-26
Annex I Cost Estimate Final Ok-26
Annex I Cost Estimate Final Ok-26
Volume I
MAIN REPORT
DETAIL SURVEY, DESIGN AND COST ESTIMATE OF
Chap (Mahendra Pul) to Nar Road Project
Ch-0+000 to 9+681
Manang District
June-2021
Submitted By
Pioneer Architect and Consulting Engineers Pvt. Ltd.
0
ANNEX-I
DETAIL QUANTITY AND COST ESTIMATE
Province Government
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Gandaki Province
Pokhara, Nepal
SALIENT FEATURES
1 Project Name: - Chap (Mahendra Pul) to Nar Road Project Ch-0+000 to 9+681
2 Location: Manang District
Geographical location:
i) Province Gandaki Province
ii) Zone: Gandaki
iii) District: Manang
Geographical feature:
i) Climate: Temperate & Sub Alpine
ii) Geology: High-Hill Terrain (BMS and Rock)
iii) Hydrology: Precipitation Controlled By Monsoon.
iv) Meteorology: Unevenly Distributed precipitation Controlled By Monsoon.
Terrian : High-Hill terrian
3 Length Of Road
i) Length: 9.681 KM
ii) Start: CH: 0+000 Chap (Mahendra Pul)
iii) End: CH: 9+681 Nar
4 Geometrics
Right Of Way: 20 m ( 10 m from Each Side) Proposed
Formation Width: 5.25 m (0.75m shoulder each side)
Carriage Way Width: 3.75 m
Design Speed 30 Km/hr
Shoulder Width: 1m (each side )
Maximum Grade 12%
Minimum Grade 1%
Camber of Carriageway 2.5%
Camber of Shoulder 3%
Maximum super elevation 7%
Pavement
Sub Base 200 mm thick
Base 150 mm thick
Premix Carpet 30 mm Thick
5 Cross Drainage (Slab Culvert)
i) 1m span Slab Culvert 11.00 Nos.
ii) 6 m Span Slab Culvert 1.00 No.
iii) 4 m Span Slab Culvert 2.00 Nos.
iv) 90 mm dia Hume Pipe Culvert 7.00 Nos.
Side Drain
Lined Drain (Rectangular) 9680.52 m
6 Structures
Gabion Wall (Cu.m) 11489.00 Retaining/Protection wall
Plumb Concrete Wall (Cu.m) 1758.82 Retaining & Breast/Protection wall
7 Earth Work
E/W in Excavation Cu.m 254036.94 Road including Hard Rock
Foundation Cu.m 20201.13 Drain, Cross Drainage & Retaining Structure
Abstract of Cost
Item Rate
Description Unit Quantity Amount (NRs) Remarks
No. (NRs)
1 General
Insurances for the loss of damage to works, plant,
material, equipment, property and personnel injury or
death and commission of bank security and
1.1 performance guarantee all complete, as per
specification (SS/SP-117) and instruction of engineer
including third party insurance.
PS 1.00 6000000.00 6,000,000.00
Abstract of Cost
Item Rate
Description Unit Quantity Amount (NRs) Remarks
No. (NRs)
#NAME? ### #NAME?
SubTotal Part 2 #NAME?
Earthworks
Road way excavation in all type of soil and rocks
including necessary haulage, disposal at safe tipping
#REF! site and lift all complete, as per specification (SS/SP-
905) and instruction of Engineer
### 4988.17 229.51 1,144,830.73 #REF!
Structure foundation excavation for all types of soil/rock
by both manual and mechanical means as per drawing
and technical specification, including Construction of
#REF!
shoring and bracing,removal of stumps and other
deleterious matter, and backfilling with approved materials
with instruction of engineer. (Spc. Clau 907) ### 0.00 #NAME? #NAME? #REF!
Formation of Embankment including, compaction
in layers not exceeding 150mm. Compacted depth,
#REF! watering and haulage, etc. all complete, as per
specification (SS/SP-909) and instruction of Engineer
### 55822.73 324.07 18,090,733.18 #REF!
Haulage of materials by tipper/truck/tractor excluding cost
of loading, unloading and stacking at approved
#REF!
environmentally safe tipping sites beyond the initial lead of
1 Km. (Spc. Clau. 800) ### #NAME? #NAME?
SubTotal Part 3 #NAME?
4 Pavement Works
Preparation of sub-grade for rehabilitation or other similar
works ( filling or cutting depth of 10 to 20 cm ) in common Rate &
#REF!
soil, all complete as per specification (SS/SP-1003) and Qty
instruction of Engineer. ### #REF! 24.72 #REF! Corrected
Providing and laying granular Sub-base on prepared
surface, mixing at OMC, and compacting to achieve the
#REF!
desired density, complete as per Drawing and Technical Rate
Specifications- by Mechanical means. (Spc. Clau 1201) ### #REF! 2155.81 #REF! Corrected
Providing and laying Crusher Run Macadam on a prepared
surface, spreading and mixing , watering and compacting
#REF! to form a layer of Base course as per Drawing and
Technical Specifications by Mix in Place Method for 45 mm Rate
maximum size. (Spc. Clau 1204) ### #REF! 5207.17 #REF! Corrected
Abstract of Cost
Item Rate
Description Unit Quantity Amount (NRs) Remarks
No. (NRs)
Providing and applying prime coat MC 30/70 with Hot
Bitumen ( including cutter) on prepared surface of granular
#REF! base including cleaning of road surface and spraying by
Mechanical means as per Technical Specification. (Spc.
Clau 1302)13.1 ### #REF! 200.71 #REF! #REF!
#REF!
Abstract of Cost
Item Rate
Description Unit Quantity Amount (NRs) Remarks
No. (NRs)
#REF! #REF! ### #REF! #NAME? #REF! Qty High
#REF! #REF! ### #REF! #NAME? #REF!
#REF! #REF! ### #REF! #NAME? #REF!
#REF! #REF! ### #REF! #NAME? #REF!
#REF! #REF! ### #REF! #NAME? #REF!
#REF! #REF!
#REF! ### 100.00 #NAME? #NAME?
#REF! ### #REF! #NAME? #REF!
#REF! ### #REF! #NAME? #REF!
6.0 Road Furnitures and Traffic Safety Measures #NAME?
Abstract of Cost
Item Rate
Description Unit Quantity Amount (NRs) Remarks
No. (NRs)
Planting containerized tree and shrub seedlings, including
pitting, transplanting, composting and mulching, on slopes
7.2 < 30o . Pit size 30 cm diameter x depth mix Compost with Nos 2,163.00 57.72 124,858.77
soil and back fill into pit to 1/4 of the pit volume. (Spc. Clau
2807)
#REF!
Check Norms
SUMMARY OF COST
Project Name: Chap (Mahendra Pul) to Nar Road Project
Ch-0+000 to 9+681
S.N. Description of works Amount (NRs) Remarks
1 General Item 5,460,000.00 1.21%
2 Site Clearance 918,484.88 0.20%
3 Earth Work 104,357,742.65 23.09%
4 Pavement 117,302,636.70 25.95%
5 Cross Drainage Structures 31,721,158.52 7.02%
6 Retaining Structure 117,998,902.63 26.11%
7 Side Drain 69,655,985.51 15.41%
8 Road Furnitures and Traffic Safety Measures 1,831,928.27 0.41%
9 Bio - engineering Works 1,696,788.42 0.38%
10 Day Works (If Instructed By the Engineer) 1,019,944.85 0.23%
Base Cost (PS) 5,200,000.00
Base Cost Without PS 446,763,572.42
Sub Total A 451,963,572.42 100.00%
4% Contingencies of Sub-total A 18,078,542.90
Add 13% VAT of Sub-total of Base Cost 58,079,264.42
10% Physical Contingencies of Sub-total A 45,196,357.24
10% Price Adjustment of Sub-total A 45,196,357.24
Grand Total (Including VAT and Contingencies) 618,514,094.22
Cost per Km 63,892,651.86
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
1 General Item
Insurances for the loss of damage to works,
plant, material, equipment, property and
personnel injury or death and commission of
bank security and performance guarantee all
1.1 complete, as per specification (SS/SP-117)
and instruction of engineer including third
party insurance.
PS 1.00 2,000,000.00 2,000,000.00
1.2 Monthly Rent for Site Office Month 24.00 10,000.00 240,000.00
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
2 Site Clearance
Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300 mm,
removal of stumps of trees cut earlier and
disposal of unserviceable materials and
2.1 stacking of serviceable Material to be used or
auctioned, up to a lead of 1000 meters
including removal and disposal of top organic
soil not exceeding 150 mm in thickness. (Spc.
Clau 201)
Sqm 29043.00 31.63 918,484.88
Sub total Part 2 918,484.88
3 Earth Work
Roadway excavation in all types of soil/rock
by both manual and mechanical means as per
drawing and technical specification, including
removal of stumps and other deleterious
3.1
matter, with all lifts and lead as drawing and
instruction of engineer. (Spc. Clau 905)
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Providing and laying Crusher Run Macadam
on a prepared surface, spreading and mixing ,
watering and compacting to form a layer of
4.3 Base course as per Drawing and Technical
Specifications by Mix in Place Method for 45
mm maximum size. (Spc. Clau 1204)
Cum 8349.78 5207.17 43,478,780.65
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Providing and laying of hand pack Stone
soling with 150 to 200 mm thick stones and
5.3 packing with smaller stone on prepared
surface as per Drawing and Technical
Specifications.
Cum 200.23 7556.88 1,513,118.65
Providing and laying of Machine mixed non
structural Cement Concrete M15/40 including
5.4 compaction,curing,testing & form work
complete as per Drawing and Technical
Specifications. (Spc. Clau 2000)
Cum 254.32 16210.01 4,122,544.60
Providing and laying of Machine mixed
Reinforced Cement Concrete M20/20 for the
5.5 road pavement including form work as per
Drawing and Technical Specifications
(Spc.Clau 2000) 20.8 A.
Cum 178.15 17906.77 3,190,002.31
Providing and laying , fitting and placing
HYSD bar reinforcement in sub-structure
5.6 complete as per Drawing and Technical
Specifications. (Spc. Clau 2014)
Mt 20.26 128892.75 2,611,365.53
Providing and laying 110mm dia. ,
(2.5kg/cm2 ) HDPE pipes for weep holes as
5.7 directed by engineer.(SS/SP 700) for stone
masonry works
Rm 39.60 494.77 19,592.81
Providing and laying of Machine mixed
Cement Concrete M25/20 for the super
structure ,deck,slab,girder etc including
5.8
compaction,curing,testing & form work
completecomplete as per Drawing and
Technical Specifications. (Spc. Clau 2000) Cum 78.50 21028.49 1650631.35
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Backfilling in layers in foundation
pits,trenches, etc, including compaction and
watering etc. complete using locally available
6.2 material as per drawing and technical
specification and instruction of engineer.
(Spc. Clau 908).
Cum 7759.41 715.19 5,549,463.69
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Providing and laying Machine Made Heavy
zinc coated Hexagonal mesh type 100 mm x
120 mm, mesh wire 3 mm, selvage wire 3.9
mm, lacing wire 2.4 mm Gabion boxes
/mattresses, placing in position including
stretching; forming compartments; tying the
sides and diaphragms with binding wire in
each mesh; tying with bracing wires and tie
6.7 wires; and tying down the lid complete as per
specification. Providing and filling
stone/boulder in gabion boxes/mattress etc..
Including dressing, bedding, bonding all
complete as per Drawing and Technical
Specifications. (Spc. Clau 2401)
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Supply and erecting Traffic sign in place
including 50mm dia. Steel tube, 2mm thick
steel plates, cement concrete, painting, writing
8.1 and supporting steel angle nut and bolt etc. all
complete, as per specification (SS/SP-1501)
and instruction of Engineer.
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
60cm dia Circular, 60 cm equilateral triangle
a) and 60cm x 45 cm rectangular shaped sign
(single post ) Nos 58.00 3622.45 210,102.14
1.2m x0.75m size bigger traffic sign
b) (Information Board)with back support and
two or more post. Nos 2.00 9643.13 19,286.27
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
9 Bio - engineering Works
Planting rooted grass slips on the slopes <45o
including preparation of slips on site. a max of
5 cm depth with metal rod or Operation
includes digging planting hole to hard-wood
9.1
peg, depending on the nature of the soil. The
planting drills should be space. (Spc. Clau
2807)
Sqm 2420.25 658.72 1,594,267.08
10.3 Material
a) Cement mt 2.00 22324.21 44,648.42
b) Reinforcement( 8,10,12,16) mt 1.00 99627.21 99,627.21
c) Aggregate (10-40) cum 10.00 3795.00 37,950.00
d) Sand Cum 10.00 3105.00 31,050.00
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Sub- Total 10.3 213,275.63
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
1 General Item
Insurances for the loss of damage to
works, plant, material, equipment,
property and personnel injury or death
and commission of bank security and
1.1 performance guarantee all complete, as
per specification (SS/SP-117) and
instruction of engineer including third
party insurance.
PS 1.00 2,000,000.00 2,000,000.00
1.2 Monthly Rent for Site Office Month 24.00 10,000.00 240,000.00
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
2 Site Clearance
Clearing and grubbing road land
including uprooting rank vegetation,
grass, bushes, shrubs, saplings and trees
girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of
unserviceable materials and stacking of
2.1 serviceable Material to be used or
auctioned, up to a lead of 1000 meters
including removal and disposal of top
organic soil not exceeding 150 mm in
thickness. (Spc. Clau 201)
Sqm 29043.00 31.63 918,484.88
Sub total Part 2 918,484.88
3 Earth Work
Roadway excavation in all types of
soil/rock by both manual and mechanical
means as per drawing and technical
specification, including removal of
3.1 stumps and other deleterious matter, with
all lifts and lead as drawing and
instruction of engineer. (Spc. Clau 905)
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
4 Pavement
Preparation of sub-grade for
rehabilitation or other similar works
( filling or cutting depth of 10 to 20 cm )
4.1 in common soil, all complete as per
specification (SS/SP-1003) and
instruction of Engineer.
Sqm 55822.73 24.72 1,379,726.10
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Providing and laying , fitting and placing
HYSD bar reinforcement in sub-structure
5.6 complete as per Drawing and Technical
Specifications. (Spc. Clau 2014)
Mt 20.26 128892.75 2,611,365.53
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Providing and laying of Machine mixed
non structural Cement Concrete M15/40
including compaction,curing,testing &
6.4 form work complete as per Drawing and
Technical Specifications. (Spc. Clau
2000)
Cum 131.15 16210.01 2,125,942.91
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
6 Side Drain
Earthwork in excavation for Side Drain
in all types of soil and rocks including
shoring , struting, bracing, sheeting and
7.1 disposal, all complete, as per
specification (SS/SP-905) and instruction
of Engineer.
Cum 7357.20 319.07 2,347,481.84
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Standard Kilometer stone (placed at each
a) km distance) Nos 8.00 6315.82 50,526.59
Abstract of Cost
Item
Description Unit Quantity Rate (NRs) Amount (NRs) Remarks
No.
Sub total Part 9 1,696,788.42
Day Works (If Instructed By the
9 Engineer)
Labor (refer day works schedule)
10.1 including contractor's overhead and profit
10.3 Material
a) Cement mt 2.00 22324.21 44,648.42
b) Reinforcement( 8,10,12,16) mt 1.00 99627.21 99,627.21
c) Aggregate (10-40) cum 10.00 3795.00 37,950.00
d) Sand Cum 10.00 3105.00 31,050.00
Sub- Total 10.3 213,275.63
Providing and laying Random rubble Masonry work in cement mortar 1:4 in
5.9 structure including dressing,scaffolding,curing , preparation of motar, Cum 971.47
complete as per Drawing and Technical Specifications (Spc. Clau 2607) 26.5
Providing and Laying Reinforced cement concrete NP3 Hume pipe Flush
5.11 jointed pipe for culverts including fixing with cement mortar 1:2 as per
Drawing and Technical Specifications.( Spc. Clau 701)
a) 900 mm internal dia. Rm 52.50
Providing and filling with graded previous (filter material) in layer with
5.12 necessary watering and compaction as per specification and instruction of Cum 113.22
Engineer
Providing, making and fixing of three layers of 50mm dia GI Hand rail
including RCC post of M20 grade concrete with size of 0.15 x 0.15 x 1m
5.14 Rm 38.16
and 1.5m center to center all complete as per drawing specification ( SS/SP-
1804,1805 & 2000) and instruction of Engineer.
6 Retaining Structure
Earth work in excavation for foundation of structure for all types of soil/rock
by both manual and mechanical means as per drawing and technical
6.1 specification, including Construction of shoring and bracing,removal of Cum 10,583.10
stumps and other deleterious matter, and backfilling with approved materials
with instruction of engineer. (Spc. Clau 907)
Backfilling in layers in foundation pits,trenches, etc, including compaction
6.2 and watering etc. complete using locally available material as per drawing Cum 7,759.41
and technical specification and instruction of engineer. (Spc. Clau 908).
Providing and laying of hand pack Stone soling with 150 to 200 mm thick
6.3 stones and packing with smaller stone on prepared surface as per Drawing Cum 196.73
and Technical Specifications.
Providing and laying of Machine mixed non structural Cement Concrete
6.4 M15/40 including compaction,curing,testing & form work complete as per Cum 131.15
Drawing and Technical Specifications. (Spc. Clau 2000)
Providing and laying Coursed rubble stone masonry in cement mortar (1:4)
6.5 including scaffolding, curing, preparation of mortar etc. all complete as per Cum 1,758.82
specification (SS/SP - 2606) and instruction of Engineer
Providing and laying Machine Made Heavy zinc coated Hexagonal mesh
type 100 mm x 120 mm, mesh wire 3 mm, selvage wire 3.9 mm, lacing wire
2.4 mm Gabion boxes /mattresses, placing in position including stretching;
forming compartments; tying the sides and diaphragms with binding wire in
6.7 Cum 11,489.00
each mesh; tying with bracing wires and tie wires; and tying down the lid
complete as per specification. Providing and filling stone/boulder in gabion
boxes/mattress etc.. Including dressing, bedding, bonding all complete as
per Drawing and Technical Specifications. (Spc. Clau 2401)
Providing and laying 110mm dia. ,(2.5kg/cm2 ) HDPE pipes for weep holes
6.90 Rm 1,422.05
as directed by engineer.(SS/SP 700) for stone masonry works
10.1 Labor (refer day works schedule) including contractor's overhead and profit
a) Skilled labour MD 100.00
b) Unskilled labour MD 150.00
10.2 Plant / Equipment
The rates shall include all cost of operating on site as fuel, lubricant, driver
and associated labour wages, overhead and profit only time actually
employed open the work shall be paid.
a) Tipper Hr 50.00
b) JCB backoe/Loader Hr 50.00
c) Excavator Hr 50.00
d)Water Bowser (For Control Dust) Hr 70.00
10.3 Material
a) Cement mt 2.00
b) Reinforcement( 8,10,12,16) mt 1.00
c) Aggregate (10-40) cum 10.00
d) Sand Cum 10.00
Gabion Wall
Retaining Wall 1 Refer attached sheet GW 11489.00
Total 11489.00 Cum
7 Side Drain
Earthwork in excavation for Side Drain in all
types of soil and rocks including shoring ,
7.1 struting, bracing, sheeting and disposal, all
complete, as per specification (SS/SP-905)
and instruction of Engineer.
a) Type A (Rectangular) (Deduction
50m length for cross draianage
structure) 1 9680.52 0.95 0.80 7357.20
Total 7,357.20 Cum
10 Day Works
Day works shall be executed only on the
written instruction of the Project Manager:
Labor (refer day works schedule)
10.1 including contractor's overhead and
profit
a) Skilled labour 100.00 Man Day
b) Unskilled labour 150.00 Man Day
a) Tipper 50.00 Hr
b) JCB backoe/Loader 50.00 Hr
10.3 Material
a) Cement mt 4.00 2.00 mt
b) Reinforcement( 8,10,12,16) mt 2.00 1.00 mt
c) Aggregate (10-40) cum 30.00 10.00 cum
d) Sand Cum 30.00 10.00 Cum
Site Clearance
Chainage
S.No Length Average Width Area Remarks
From To m m (sq.m)
1 0+000 1+500 1500.00 3.00 4500
2 1+500 4+500 3000.00 3.00 9000
3 4+500 9+681 5181.00 3.00 15543
4 9681.00 3.00 29043
6
Providing, mixing ,laying and
compaction of Premix carpet 1 9,650.52 3.75 0.03 1,085.68
Carriageway (Deduction 30m length for
cross drainage structure)
Extra widening on sharp curves 50 40.00 2.50 0.03 150.00
Providing, mixing ,laying and
compaction of Premix carpet 1 9,650.52 1.50 0.03 434.27
Shoulder(Deduction 30m length for
cross drainage structure)
Total 1,669.96 Cum
7
Providing and laying seal coat sealing
the voids in a Bituminous surface
(Deduction 30m length for cross
drainage structure) 1 9,650.52 3.75 36,189.45
Extra widening on sharp curves 50 40.00 2.50 5000.00
Providing and laying seal coat sealing
the voids in a Bituminous surface
(Deduction 30m length for cross
drainage structure) 1 9650.52 1.50 14475.78
Total 55,665.23 Sqm
Bridge
S.N. Chainage Span (m) Remark
1 1+060 Water Underground 30 Fu River
2 1+220 20 Nar Khola
Assumptions:
Head Wall U/S Length= 5.00 m Pipe Internal Dia= 0.90 m
Head Wall D/S Length= 8.00 m Thickness of Pipe= 0.10 m
Head Wall U/S Width= 0.45 m Overall Dia= 1.10 m
Head Wall D/S Width= 0.45 m Pipe Length= 7.50 m
Head Wall Cushion = 1.00 m PCC= 0.10 m
Head Wall Height D/S= 2.45 m Soiling
PCC for Pipe Bed rectangular 0.15 m
Head Wall Height U/S= 2.40 m portion=
PCC for Pipe Bed curvilinear 0.20 m
Foundation below Pipe of Head Wall U/S= 0.30 m portion= 0.16 m
Foundation below Pipe of Head Wall D/S= 0.35 m Catch Pit Width= 1.50 m
Carriage Way= 5.50 m Gabion Height= 1.00 m
Shoulder= 0.75 m
Area of
1 4.98 1.38 0.16 1.10 Pipe Sector
Deduction of Pipe Portion 1 4.98 0.13 - 0.63 0.1266
5.34 Cum
5. Formwork
i) Head Wall 1 18.94 0.10 1.89
ii) At Catchpit 1 18.32 0.10 1.83
iii) for Bedding Concrete 2 4.98 0.36 3.59
7.31 Sqm
Measurement
S.No. Description of Works No Quantity Unit Remarks
Length Bredth Height
Excavations in ordinary soil for structures
including cutting of slope, shoring, shuttering,
1.0 planking, ordinary sealing and disposal of matreials
up to a lead 50 m. along the lead route in Ordinary
soil.
In Two layers
3 Stone Soling
i) Abutment 2 9.00 3.24 0.15 8.75 L=(2S+2E)/2, B=F1
ii) Wing Wall 4 4.85 1.99 0.15 5.78
i) Aprons U/S and Down Steam 2 8.20 3.90 0.30 19.19 L=(2S+2E)/2, B=F1
ii) Middle Portion 1 9.00 4.00 0.30 10.80
Total 44.52 Cum
6 Reinforcement
i) Bar Bending Schedule of kerb:
Mark a6 10 5.54 @ 0.62kg/m 34.35
Bar Bending schedule of Abutment
ii)
Seat:
Mark s1 18 9.00 @ 0.62kg/m 100.44
Mark s2 92 1.97 @ 0.62kg/m 112.37
Mark s3 148 0.60 @ 1.58kg/m 140.30
Bar Bending schedule of
iii)
Culvert(Excluding Abutment Seat):
Mark a1 61 5.04 @ 2.47kg/m 759.38
Mark a2 27 8.90 @ 0.89kg/m 213.87
Mark a3 46 5.04 @ 0.62kg/m 143.74
Mark a4 27 9.59 @ 0.62kg/m 160.54
Mark a4' 27 8.90 @ 0.62kg/m 148.99
Mark a5 2 8.90 @ 0.89kg/m 15.84
Total 1,829.81 Kg
7 Formwork
i) Abutment Capping 2 9.00 1.10 19.80 P=(2*T+2*T2)*W
ii) Slab side faces 1 28.28 0.40 11.31 P=2*(S+2*(A-T1))+2*W
Footpath 4 5.54 0.15 3.32
iii) Slab bottom face 1 4.00 9.00 36.00
iv) Abutment Base 2 24.48 0.45 22.03
v) Wing Wall Base 4 13.68 0.45 24.62
Total 117.08 Sqm
10 Back Filling
i) 50 % of E/W of Abutment 0.5 268.27 134.14
ii) 50 % of E/W of Wing walls 0.5 96.88 48.44
Total 182.57 Cum
0.57
2* 9nos 39
2* required for both side 2,500.00
2*2
5.04
1.05
5.04
1.05
1.05
1.05
13.47
147500
+2*(A-T1))+2*W
23.4
32 40
6.33 9.89
Province Government
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Gandaki Province
Pokhara, Nepal
3 Stone Soling
i) Abutment 2 9.00 3.24 0.15 8.75 L=(2S+2E)/2, B=F1
ii) Wing Wall 4 4.85 1.99 0.15 5.78
i) Aprons U/S and Down Steam 2 10.20 3.90 0.30 23.87 L=(2S+2E)/2, B=F1
ii) Middle Portion 1 9.00 6.00 0.30 16.20
Total 54.60 Cum
6 Reinforcement
i) Bar Bending Schedule of kerb:
Mark a6 10 8.00 @ 0.62kg/m 49.60
Bar Bending schedule of Abutment
ii)
Seat:
Mark s1 18 9.00 @ 0.62kg/m 100.44
Mark s2 92 1.97 @ 0.62kg/m 112.37
Mark s3 148 0.60 @ 1.58kg/m 140.30
Bar Bending schedule of
iii)
Culvert(Excluding Abutment Seat):
Mark a1 61 7.04 @ 2.47kg/m 1,060.72
Mark a2 37 8.90 @ 0.89kg/m 293.08
Mark a3 46 7.04 @ 0.62kg/m 200.78
Mark a4 37 9.59 @ 0.62kg/m 219.99
Mark a4' 37 8.90 @ 0.62kg/m 204.17
Mark a5 2 8.90 @ 0.89kg/m 15.84
Total 2,397.29 Kg
7 Formwork
i) Abutment Capping 2 9.00 1.10 19.80 P=(2*T+2*T2)*W
ii) Slab side faces 1 32.28 0.40 12.91 P=2*(S+2*(A-T1))+2*W
Footpath 4 8.00 0.15 4.80
iii) Slab bottom face 1 6.00 9.00 54.00
iv) Abutment Base 2 24.48 0.45 22.03
v) Wing Wall Base 4 13.68 0.45 24.62
Total 138.16 Sqm
10 Back Filling
i) 50 % of E/W of Abutment 0.5 268.27 134.14
ii) 50 % of E/W of Wing walls 0.5 96.88 48.44
Total 182.57 Cum
0.57
Wing Wall
D=
D1=
E=
F=
A= 1.00 m F1=
2* 9nos 39 B= 0.00 m G=
2* required for both side 2,500.00 L= 8.40 m
2*2
7.04
1.05
7.04
1.05
1.05
1.05
13.47
147500
+2*(A-T1))+2*W
23.4
32 40
6.33 9.89
Wing Wall
3m
4m
2.6 m
5.12 m
4.43 m
1.39 m
Province Government
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Gandaki Province
Pokhara, Nepal
Project Name: Chap (Mahendra Pul) to Nar Road Project
Ch-0+000 to 9+681
Detailed Estimate of Earth Work Excavation in Foundation for Masonry Retaining and Breast Wall
Foundation
Soil Classification Back Filling in
Chainage Excavation
Length Structures
S.N. Cut Area Structure OS HS OR Hard Rock
Cut Volume Area Volume
From To
m (m2) (m3) % m3 % m3 % m3 % m3 (m2) (m3)
Retaining Wall
1 1+190 1+210 20.00 1.47 29.40 30 8.82 40 11.76 25 7.35 5 1.47 0.39 7.80
2 1+250 1+270 20.00 2.66 53.20 30 15.96 40 21.28 25 13.30 5 2.66 0.81 16.20
3 3+010 3+025 15.00 2.66 39.90 30 11.97 40 15.96 25 9.98 5 2.00 0.81 12.15
4 3+410 3+430 20.00 9.23 184.60 30 55.38 30 55.38 30 55.38 10 18.46 5.50 110.00
5 3+830 3+850 20.00 0.81 16.20 30 4.86 30 4.86 30 4.86 10 1.62 0.81 16.20
6 3+870 3+890 20.00 1.32 26.40 30 7.92 30 7.92 30 7.92 10 2.64 1.32 26.40
7 4+610 4+630 20.00 1.23 24.60 35 8.61 50 12.30 10 2.46 5 1.23 1.23 24.60
8 4+630 4+650 20.00 3.84 76.80 35 26.88 50 38.40 10 7.68 5 3.84 3.84 76.80
9 4+650 4+670 20.00 2.14 42.80 35 14.98 50 21.40 10 4.28 5 2.14 2.14 42.80
10 4+670 4+690 20.00 2.14 42.80 35 14.98 50 21.40 10 4.28 5 2.14 2.14 42.80
11 4+690 4+710 20.00 4.44 88.80 35 31.08 50 44.40 10 8.88 5 4.44 4.44 88.80
12 4+710 4+730 20.00 2.14 42.80 35 14.98 50 21.40 10 4.28 5 2.14 2.14 42.80
13 7+110 7+130 20.00 2.62 52.40 45 23.58 40 20.96 10 5.24 5 2.62 1.15 23.00
14 7+130 7+150 20.00 2.14 42.80 45 19.26 40 17.12 10 4.28 5 2.14 2.14 42.80
15 7+150 7+170 20.00 1.89 37.80 45 17.01 40 15.12 10 3.78 5 1.89 1.89 37.80
Sub Total Retaining Wall 295.00 801.30 276.27 329.66 143.94 51.43 610.95
Total 295.00 801.30 276.27 329.66 143.94 51.43 610.95
Right
Right
Left
Right
Left
Left
Left
Left
Left
Left
Left
Left
Right
Right
Right
m m m m3 m m m3
3 Stone Soling
i) Abutment 2 9.00 3.24 0.15 8.75 L=(2S+2E)/2, B=F1
ii) Wing Wall 4 4.85 1.99 0.15 5.78
i) Aprons U/S and Down Steam 2 8.20 3.90 0.30 19.19 L=(2S+2E)/2, B=F1
ii) Middle Portion 1 9.00 4.00 0.30 10.80
Total 44.52 Cum
6 Reinforcement
i) Bar Bending Schedule of kerb:
Mark a6 10 5.54 @ 0.62kg/m 34.35
Bar Bending schedule of Abutment
ii)
Seat:
Mark s1 18 9.00 @ 0.62kg/m 100.44
Mark s2 92 1.97 @ 0.62kg/m 112.37
Mark s3 148 0.60 @ 1.58kg/m 140.30
Bar Bending schedule of
iii)
Culvert(Excluding Abutment Seat):
Mark a1 61 5.04 @ 2.47kg/m 759.38
Mark a2 27 8.90 @ 0.89kg/m 213.87
Mark a3 46 5.04 @ 0.62kg/m 143.74
Mark a4 27 9.59 @ 0.62kg/m 160.54
Mark a4' 27 8.90 @ 0.62kg/m 148.99
Mark a5 2 8.90 @ 0.89kg/m 15.84
Total 1,829.81 Kg
7 Formwork
i) Abutment Capping 2 9.00 1.10 19.80 P=(2*T+2*T2)*W
ii) Slab side faces 1 28.28 0.40 11.31 P=2*(S+2*(A-T1))+2*W
Footpath 4 5.54 0.15 3.32
iii) Slab bottom face 1 4.00 9.00 36.00
iv) Abutment Base 2 24.48 0.45 22.03
v) Wing Wall Base 4 13.68 0.45 24.62
Total 117.08 Sqm
10 Back Filling
i) 50 % of E/W of Abutment 0.5 268.27 134.14
ii) 50 % of E/W of Wing walls 0.5 96.88 48.44
Total 182.57 Cum
6 Reinforcement
i) Bar Bending Schedule of kerb:
Mark a6 10 8.00 @ 0.62kg/m 49.60
Bar Bending schedule of Abutment
ii)
Seat:
Mark s1 18 9.00 @ 0.62kg/m 100.44
Mark s2 92 1.97 @ 0.62kg/m 112.37
Mark s3 148 0.60 @ 1.58kg/m 140.30
Bar Bending schedule of
iii)
Culvert(Excluding Abutment Seat):
Mark a1 61 7.04 @ 2.47kg/m 1,060.72
Mark a2 37 8.90 @ 0.89kg/m 293.08
Mark a3 46 7.04 @ 0.62kg/m 200.78
Mark a4 37 9.59 @ 0.62kg/m 219.99
Mark a4' 37 8.90 @ 0.62kg/m 204.17
Mark a5 2 8.90 @ 0.89kg/m 15.84
Total 2,397.29 Kg
7 Formwork
i) Abutment Capping 2 9.00 1.10 19.80 P=(2*T+2*T2)*W
ii) Slab side faces 1 32.28 0.40 12.91 P=2*(S+2*(A-T1))+2*W
Footpath 4 8.00 0.15 4.80
iii) Slab bottom face 1 6.00 9.00 54.00
iv) Abutment Base 2 24.48 0.45 22.03
v) Wing Wall Base 4 13.68 0.45 24.62
Total 138.16 Sqm
10 Back Filling
3 Stone Soling
i) Abutment 2 9.00 4.76 0.15 12.85
ii) Wing Wall 4 5.12 1.99 0.15 6.11
i) Aprons U/S and Down Steam 2 10.43 4.13 0.30 25.85
ii) Middle Portion 1 9.00 6.00 0.30 16.20
Total 61.00 Cum
6 Reinforcement
i) Bar Bending Schedule of kerb:
Mark a6 10 8.00 @ 0.62kg/m 49.60
Bar Bending schedule of
ii)
Abutment Seat:
Mark s1 18 9.00 @ 0.62kg/m 100.44
Mark s2 92 2.75 @ 0.62kg/m 156.86
Mark s3 148 0.60 @ 1.58kg/m 140.30
Bar Bending schedule of
iii) Culvert(Excluding Abutment
Seat):
Mark a1 61 7.40 @ 2.47kg/m 1,114.96
Mark a2 38 8.90 @ 0.89kg/m 301.00
Mark a3 46 7.40 @ 0.62kg/m 211.05
Mark a4 38 9.59 @ 0.62kg/m 225.94
Mark a4' 38 8.90 @ 0.62kg/m 209.68
Mark a5 2 8.90 @ 0.89kg/m 15.84
Total 2,525.67 Kg
7 Formwork
i) Abutment Capping 2 9.00 1.60 28.80
ii) Slab side faces 1 33.00 0.55 18.15
Footpath 4 8.00 0.15 4.80
iii) Slab bottom face 1 6.00 9.00 54.00
iv) Abutment Base 2 27.52 0.45 24.77
10 Back Filling
i) 50 % of E/W of Abutment 0.5 565.49 282.74
ii) 50 % of E/W of Wing walls 0.5 132.80 66.40
Total 349.14 Cum
Nos
0.975
Mark a6
Mark s1
Mark s2
Mark s3
Mark a1
Mark a2
Mark a3
Mark a4
Mark a4'
Mark a5
Remarks
L=(2S+2E)/2, B=F1
L=(2S+2E)/2, B=F1
L=(2S+2E)/2, B=F1
L=(2S+2E)/2, B=F1
L=S+2*(A-T1)
P=(2*T+2*T2)*W
P=2*(S+2*(A-T1))+2*W
6.0 Providing and fixing of 110mm HDP pipe for weep holes 12.0 0.30 3.600 R.m.
12mm dia Vertical main bar in Abutement rear side @200mm c/c 60.0 2.22 0.890 118.495
8mm dia Distribution bar in Abutement @150mm c/c 48.0 6.44 0.396 122.412
12mm dia Extra Vertical bar in Abutement for return
8.0 2.64 0.890 18.797
wall@120mm c/c
Slab
16mm dia Main bar @200mm c/c 82.0 3.04 1.580 393.862 In Two layers
8mm dia distribution bar @150mm c/c 28.0 6.96 0.395 76.978 "
Kerb
12mm dia U bar @300mm c/c 18.0 1.59 0.890 25.472
10mm dia Longitudinal bar @300mm c/c 8.0 2.52 0.620 12.499
Return /Wing wall
12mm dia Top bar @120mm c/c 8.0 3.18 0.890 22.642 Both side
12mm dia Bottom bar @120mm c/c 8.0 3.32 0.890 23.610 "
10mm dia Horizontal bar @200mm c/c in rectangular part 40.0 2.62 0.625 65.500 "
10mm dia Horizontal bar @200mm c/c in Triangular part 32.0 1.27 0.620 25.197 "
8mm dia Vertical bar @250mm c/c 64.0 1.50 0.396 37.889
1560.426 Mt.
#REF!
Quantity Estimate of Causeway
Assumptions:
Span = 12.00 m
Slab Width = 7.00 m
Slab thickness = 0.20 m
Bed PCC thickness 0.075 m
Bed Stone Soling 0.15 m
Total Depth = 0.43 m
Main Bars = 12 dia @ 300 c/c
Distribution Bar 12 dia @ 300 c/c
Side Slope = 7.00% Longitudinal Beam Thickness 0.4 m
Longitudinal dowel bars = 12 dia @ 300 c/c Height of D/S Protection Work = 2 m
Transverse dowel bars = 12 dia @ 300 c/c U/S Longitudinal Beam Height 1 m
Stirrups 8 dia @ 300 c/c Longitudinal Beam Thickness 0.3 m
Length Breadth Height
Description of Works Nos. Quantity Units
(m) (m) (m)
1. Earthwork in Excavation
Middle portion 1 4.00 7.00 0.425 11.90 m³
Approaching portion 2 4.01 7.00 0.425 23.86 m³
U/S Cutoff CRRM 0 8.00 1.00 0.500 -
D/S ProtectionCRRM Wall 1 12.00 1.25 1.500 22.50
U/S Gabion Protection 1 8.00 3.00 0.500 12.00
D/S Gabion Protection 1 8.00 3.00 0.500 12.00
82.26 m³
5. Reinforcement
a) Main bar T1(12mm Ф) (6 Panal) 86 3.70 @ 0.89kg/m 283.20 kg.
b) Distribution bar T2(12mm Ф) (6 Panal) 76 4.20 @ 0.89kg/m 284.09 kg.
c) U/S Longitudinal Beam Main Bar 6 4.20 @ 0.89kg/m 22.43 kg.
d) D/S Longitudinal Beam Main Bar 6 4.20 @ 0.89kg/m 22.43 kg.
e) U/SLongitudinal Beam Stirrup 42 2.48 @ 0.39kg/m 40.62 kg.
f) D/S Longitudinal Beam Stirrup 42 2.28 @ 0.39kg/m 37.35 kg.
g) Main Bar Transverse Beam 4 3.70 @ 0.89kg/m 13.17 kg.
h) Transverse Beam Stirrup 51 2.28 @ 0.39kg/m 45.35 kg.
i) Longitudinal joint (12mm Ф) 41 0.75 @ 0.89kg/m 27.37 kg.
j) Transverse joint(12mm Ф) 48 0.75 @ 0.89kg/m 32.04 kg.
Total Reinforcement Qty = 808.04 kg.
Providing, making and fixing of three layers of 50mm dia GI Hand rail
including RCC post of M20 grade concrete with size of 0.15 x 0.15 x
5.14 Rm 4,092.00
1m and 1.5m center to center all complete as per drawing specification (
SS/SP-1804,1805 & 2000) and instruction of Engineer.
6 Retaining Structure
Earth work in excavation for foundation of structure for all types of soil/rock by
both manual and mechanical means as per drawing and technical
6.1 specification, including Construction of shoring and bracing,removal of stumps Cum 319.07
and other deleterious matter, and backfilling with approved materials with
instruction of engineer. (Spc. Clau 907)
Backfilling in layers in foundation pits,trenches, etc, including compaction and
6.2 watering etc. complete using locally available material as per drawing and Cum 715.19
technical specification and instruction of engineer. (Spc. Clau 908).
Providing and laying of hand pack Stone soling with 150 to 200 mm thick
6.3 stones and packing with smaller stone on prepared surface as per Drawing and Cum 7,556.88
Technical Specifications.
ok
ok
0k
OK
OK
ok
ok
ok
ok
ok
ok
ok
ok
Roy
Transporta Total Rate Adopted
District Collection alty
S.N. Description Unit tion Rate ( C + R + Rate Remarks
Rate (D) Rate (C) (
( Tp ) Tp)
R)
1 Gravel
a ( 5 - 70 mm size) m3 1300.00 2266.00 1560.28 3826.28 1300.00
b ( 5 - 40 mm size) m 3
1300.00 3399.00 1560.28 4959.28 1650.00
c ( 5 - 20 mm size) m 3
1300.00 4532.00 1560.28 6092.28 1650.00
d ( 5 - 08 mm size) m 3
1300.00 6798.00 1560.28 8358.28 1650.00
e ( 40 - 70 mm size) m3 1300.00 4532.00 1560.28 6092.28 1650.00
f ( 70 - 100 mm size) m3 1300.00 3399.00 1560.28 4959.28 1650.00
Rubble of required size m
3
2 1800.00 1586.20 1338.12 2924.32 1800.00 Manang
3 Broken Aggregates
a ( 70 - 100 mm) m3 1699.50 1338.12 3037.62 3037.62
b ( 40 - 70 mm) m3 2266.00 1338.12 3604.12 3604.12
c ( 20 - 40 mm) m3 4240.00 3399.00 1338.12 4737.12 3300.00 Manang
d ( 10 - 20 mm) m3 4240.00 4532.00 1338.12 5870.12 3300.00 Manang
e ( 5 - 10 mm) m3 4240.00 6798.00 1338.12 8136.12 3300.00 Manang
4 Washing Sand m 3
2700.00 1699.50 1278.76 2978.26 2700.00 Manang
5 Brick nos. 16.00 0.00 16.00 Lamjung
6 Wood 0.00 0.00
a wood ( uttis) m3 49392.00 0.00 49392.00
b Local Sal wood m3 155232.00 0.00 155232.00
c Timber Planks cum 21,500 0.00 21500.00
7 Stone dust m3 880.00 0.00 880.00
8 Rubble m3 1800.00 1586.20 1338.12 2924.32 1800.00
9 OPC Cement mt. 17000.00 2412.36 2412.36 19412.36 Lamjung
10 Water KL 250.00 250.00 250.00 0.25
11 Bitumen 80/100 Grade kg 70.00 4.90 4.90 74.90
12 Emulsion (MC) kg 68.00 4.90 4.90 72.90
13 Reinforcement steel mt. 84000.00 2632.36 2632.36 86632.36Lamjung Rate
13 Reinforcement (Tor Steel)
a 8 mm dia mt. 84000.00 2632.36 2632.36 86632.36 86632.35512
b 10 - 22 mm dia mt. 84000.00 2632.36 2632.36 86632.36Lamjung Rate
c 25 - 32 mm dia mt. 84000.00 2632.36 2632.36 86632.36Lamjung Rate
d 4.75 - 7 mm dia mt. 84000.00 2632.36 2632.36 86632.36Lamjung Rate
14 Binding Wire kg 120.00 2.63 2.63 122.63Lamjung Rate
Roy
Transporta Total Rate Adopted
District Collection alty
S.N. Description Unit tion Rate ( C + R + Rate Remarks
Rate (D) Rate (C) (
( Tp ) Tp)
R)
Roy
Transporta Total Rate Adopted
District Collection alty
S.N. Description Unit tion Rate ( C + R + Rate Remarks
Rate (D) Rate (C) (
( Tp ) Tp)
R)
Roy
Transporta Total Rate Adopted
District Collection alty
S.N. Description Unit tion Rate ( C + R + Rate Remarks
Rate (D) Rate (C) (
( Tp ) Tp)
R)
Roy
Transporta Total Rate Adopted
District Collection alty
S.N. Description Unit tion Rate ( C + R + Rate Remarks
Rate (D) Rate (C) (
( Tp ) Tp)
R)
Roy
Transporta Total Rate Adopted
District Collection alty
S.N. Description Unit tion Rate ( C + R + Rate Remarks
Rate (D) Rate (C) (
( Tp ) Tp)
R)
Travel Time (T) for truck to be used for this activity shall be determined as follows:
T = 2 * { d1/v1 + d2/v2 + d3/v3 + …………. Dn/vn}, where d1, d2, d3 … dn and v1, v2, v3……vn are the streches of
distances to be travelled and corresponding average speeds on these streches.
Fuel
Amount of
DoR Fuel Quantity Total Rate
S.N. Equipment Unit Fuel used Remarks
Rate(NR.) Rate Liter per (Wet Lease)
per hour
Hour
E1 Asphalt Concrete Plant Hour 400.00 85.97 7.00 601.81 1,001.81 upto 10 ton
E14 Pneumatic Roller Hour 1,200.00 85.97 7.00 601.81 1,801.81 upto 20 ton
Roller 3 wheel ( Up to
E15 Hour 700.00 85.97 4.00 343.89 1,043.89
12 ton )
Roller vib, Self
E16 Hour 1,200.00 85.97 10.00 859.73 2,059.73 11 ton
propelled
Roller vib, Self
E17 Hour 550.00 85.97 7.00 601.81 1,151.81 upto 3 Ton
propelled
E18 Tipper (6mt) Hour 450.00 85.97 7.50 644.80 1,094.80
Fuel
Amount of
DoR Fuel Quantity Total Rate
S.N. Equipment Unit Fuel used Remarks
Rate(NR.) Rate Liter per (Wet Lease)
per hour
Hour
E29 Water Browser Hour 550.00 85.97 5.50 472.85 1,022.85 upto 6 kL
E30 Water Pump Hour 200.00 85.97 0.35 30.00 230.00 upto 6" dia
E34 Excavator with Breaker Hour 2,100.00 85.97 15.00 1,289.60 3,389.60
E35 Sprayer Hour 260.00 85.97 5.00 429.00 689.00 upto 1KL
E37 Hot Mix Plant Hour 750.00 85.97 1.50 128.00 878.00
E38 Road Marking Machine Hour 260.00 85.97 5.00 429.00 689.00
Assumptions:
Abutment Height = 2.07 m Catch pit wall height = 1.65 m
Pavement Thickness = 0.32 m Pipe length = 7.50 m
Diameter of Pipe = 0.60 m Thickness of Pipe = 0.075 m
Overall diameter = 0.750 m
2. Back Fill
i) Carriage way 1 5.93 0.94 1.86 10.35
Deduction for pipe -1 5.27 0.45 - 2.39
ii) Hill Side Wall 1 3.68 0.27 1.65 1.64
iii) Catchpit side walls 2 1.50 0.30 1.65 1.46
11.06 Cum
3. Stone Soling
i) Catchpit soling 1 3.68 3.68 0.15 2.03
ii) Below Head Wall 1 3.00 1.24 0.15 0.56
iii) Below Pipe Portion 1 5.81 0.94 0.15 0.82
3.41 Cum
4. Concrete Works (M15/40)
i) Catchpit 1 3.68 3.68 0.10 1.35
ii) Below Head Wall 1 3.00 1.24 0.10 0.37
iii) Below hume pipe 1 7.50 0.94 0.10 0.70
1 7.50 0.94 0.16 1.13
Deduction of Pipe Portion 1 7.50 0.07 - 0.52
3.04 Cum
Length Breadth Height
Description of Works Nos. Quantity Units
(m) (m) (m)
5. Formwork
i) Below Head Wall 1 8.48 0.10 0.85
ii) At Catchpit 1 15.12 0.10 1.51
iii) for Bedding Concrete 2 7.50 0.26 3.90
6.26 Sqm
9. Gabion Works
i) U/S Protection works 1 3.00 1.00 1.00 3.00
ii)D/S Protection 1 3.00 2.00 1.00 6.00
1 3.00 1.00 1.00 3.00
12.00 Cum
10. Geo-textile 9.00 2.00 18.00 Sqm
GOVERNMENT OF NEPAL
MINISTRY OF PHYSICAL INFRASTRUCTURE AND TRANSPORT
DEPARTMENT OF ROADS
Mid Hill West (Puspalal) Highway Project
TULSIPUR,DANG
Comparison of Cost
Err:509
Err:509
Err:509
Total Quantity as
S.N. Description Unit Quantity of Rate Amount (NRs) per Amount (NRs) Variation % Remarks
Joint Survey Agreement
### Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
### Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
### Err:509
Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Total Quantity as
S.N. Description Unit Quantity of Rate Amount (NRs) per Amount (NRs) Variation % Remarks
Joint Survey Agreement
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509
### Err:509
Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
### Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
### Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Total Quantity as
S.N. Description Unit Quantity of Rate Amount (NRs) per Amount (NRs) Variation % Remarks
Joint Survey Agreement
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
### Err:509
Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Total Quantity as
S.N. Description Unit Quantity of Rate Amount (NRs) per Amount (NRs) Variation % Remarks
Joint Survey Agreement
Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
### Err:509
Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 ### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Sub Total Err:509 Err:509 Err:509 -
Err:509 Err:509 Err:509 Err:509
Err:509
Err:509
Err:509
GOVERNMENT OF NEPAL
MINISTRY OF PHYSICAL INFRASTRUCTURE AND TRANSPORT
DEPARTMENT OF ROADS
Tulasipur,Dang
Summary of Quantity
Project: Belkhet-Binayak Road
Work: Upgrading to Blacktop Standard (0+000 km to 14+956 Km)
Location: Achham
Pavement Total
S.N. Description Drain HPC 60 HPC 450 HPC 600 HPC 900 EMP MRW Gabion Pavement Unit
Work Quantity
### General
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 Err:509
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
Pavement Total
S.N. Description Drain HPC 60 HPC 450 HPC 600 HPC 900 EMP MRW Gabion Pavement Unit
Work Quantity
### Err:509 Err:509
### Err:509 Err:509
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 0
0 Err:509 Err:509
0 Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
Pavement Total
S.N. Description Drain HPC 60 HPC 450 HPC 600 HPC 900 EMP MRW Gabion Pavement Unit
Work Quantity
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 0
0 Err:509 Err:509
0 Err:509 Err:509
### Err:509 0
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
### Err:509 Err:509
0 Err:509 0
### Err:509 0
### Err:509 0
0 Err:509 Err:509
0 Err:509 Err:509
### Err:509 0
0 Err:509 Err:509
0 Err:509 Err:509
Province Government
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Gandaki Province
Pokhara, Nepal
0
Chap (Mahendra Pul) to Nar Road Project
SUMMARY OF COST
Chainage : Ch-0+000 to 9+681
13 0.50 - - 0.15 - -
- - - - - - - 0.10 2
14 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
15 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
16 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
17 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
18 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
19 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
20 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
21 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
22 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
23 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
24 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
25 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
26 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
27 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
28 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
29 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
30 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
31 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
32 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
33 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
34 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
35 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
36 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
37 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
38 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
39 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
40 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
41 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
42 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
43 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
44 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
45 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
46 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
47 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
48 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
49 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
50 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
51 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
52 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
53 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
54 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
55 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
56 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
57 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
58 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
59 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
60 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
61 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
62 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
63 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
64 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
65 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
66 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
67 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
68 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
69 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
70 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
71 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
72 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
73 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
74 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
75 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
76 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
77 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
78 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
79 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
80 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
81 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
82 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
83 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
84 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
85 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
86 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
87 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
88 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
89 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
90 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
91 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
92 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
93 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
94 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
95 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
96 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
97 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
98 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
99 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
100 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
101 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
102 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
103 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
104 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
105 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
106 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
107 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
108 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
109 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
110 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
111 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
112 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
113 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
114 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
115 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
116 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
117 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
118 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
119 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
120 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
121 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
122 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
123 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
124 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
125 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
126 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
127 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
128 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
129 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
130 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
131 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
132 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
133 - 0.50 - - - - - - - 0.15 - - 0.10 - 2
- - - - - -
Form Work in foundation
Length
Height Quantity
(L+B)
m m (m2)
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
0.000 0.10 -
-
Quantity Estimate of RCC Cantilever Retaining Wall
Chainage Length Height Concrete M20/20 Blinding Concrete Filter Material Weephole Geo-textile Form Work Area (m2)
S.N.
From To (L) (H) Area Volume Breadth Thicknes Area Volume Height Thicknes Area Volume No Length (m2) HXL BXT2 (H-T2)X(T1+T)/2 Total Area
1 3010 3030 20 6 4.338 86.76 3.60 0.05 0.18 3.60 4.00 0.25 1.00 20.00 5 2.00 0.16 120.00 2.16 5.76 127.92
2 3970 3990 20 5 3.352 67.04 3.00 0.05 0.15 3.00 3.00 0.25 0.75 15.00 4 1.40 0.13 100.00 1.80 4.76 106.56
3 4250 4270 20 4 2.9 58.00 2.60 0.05 0.13 2.60 2.00 0.25 0.50 10.00 3 1.05 0.09 80.00 1.56 3.76 85.32
4 4290 4310 20 6 4.338 86.76 3.60 0.05 0.18 3.60 4.00 0.25 1.00 20.00 5 2.00 0.16 120.00 2.16 5.76 127.92
5 4730 4750 20 6 4.338 86.76 3.60 0.05 0.18 3.60 4.00 0.25 1.00 20.00 5 2.00 0.16 120.00 2.16 5.76 127.92
6 4750 4770 20 6 4.338 86.76 3.60 0.05 0.18 3.60 4.00 0.25 1.00 20.00 5 2.00 0.16 120.00 2.16 5.76 127.92
7 5037.5 5050 12.5 6 4.338 86.76 3.60 0.05 0.18 2.25 4.00 0.25 1.00 12.50 5 2.00 0.16 75.00 2.16 5.76 82.92
8 5050 5070 20 5 3.352 67.04 3.00 0.05 0.15 3.00 3.00 0.25 0.75 15.00 4 1.40 0.13 100.00 1.80 4.76 106.56
9 5090 5110 20 6 4.338 86.76 3.60 0.05 0.18 3.60 4.00 0.25 1.00 20.00 5 2.00 0.16 120.00 2.16 5.76 127.92
10 5170 5190 20 5 3.352 67.04 3.00 0.05 0.15 3.00 3.00 0.25 0.75 15.00 4 1.40 0.13 100.00 1.80 4.76 106.56
11 5210 5230 20 5 3.352 67.04 3.00 0.05 0.15 3.00 3.00 0.25 0.75 15.00 4 1.40 0.13 100.00 1.80 4.76 106.56
12 6510 6530 20 5 3.352 67.04 3.00 0.05 0.15 3.00 3.00 0.25 0.75 15.00 4 1.40 0.13 100.00 1.80 4.76 106.56
13 6530 6550 20 5 3.352 67.04 3.00 0.05 0.15 3.00 3.00 0.25 0.75 15.00 4 1.40 0.13 100.00 1.80 4.76 106.56
Total 980.80 40.85 212.50 21.45 1.79 1447.20
Quantity Estimate for Earth Work Excavation in foundation of RCC Cantilever Retaining Wall
Cut Soil Classification Back Filling
Chainage Length Height Cut Area Volume All Type of Soil Hard Rock Area Volume
S.N.
From To (L) (H) (m2) (m3) % (m3) % (m3) (m2) (m3)
1 3+010.00 3+030.00 20 6 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
2 3+970.00 3+990.00 20 5 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
3 4+250.00 4+270.00 20 4 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
4 4+290.00 4+310.00 20 6 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
5 4+730.00 4+750.00 20 6 #N/A #N/A 90 #N/A 10 #N/A #N/A #N/A
6 4+750.00 4+770.00 20 6 #N/A #N/A 90 #N/A 10 #N/A #N/A #N/A
7 5+037.50 5+050.00 12.5 6 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
8 5+050.00 5+070.00 20 5 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
9 5+090.00 5+110.00 20 6 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
10 5+170.00 5+190.00 20 5 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
11 5+210.00 5+230.00 20 5 #N/A #N/A 60 #N/A 40 #N/A #N/A #N/A
12 6+510.00 6+530.00 20 5 #N/A #N/A 80 #N/A 20 #N/A #N/A #N/A
13 6+530.00 6+550.00 20 5 #N/A #N/A 80 #N/A 20 #N/A #N/A #N/A
Total #N/A #N/A #N/A #N/A
Quantity Estimate for Rainforcement of RCC Cantilever Retaining Wall
High Yield Steel Rainforcement
Chainage
S.N S1 S2 S3 S4
Length Height Spacing Spacing Spacing Spacing
. Length Total Length Total Weight Length Total Length Total
From To ∅mm (mm) No Weight ∅mm (mm) No ∅mm (mm) No Weight ∅mm (mm) No Weight
S1 Length S2 Length (Kg.) S3 Length S4 Length
1 3+010 3+030 20 6 12 180 113 6.52 736.76 654.90 20 135 41 20.4 836.4 2065.19 12 180 31 20.24 627.44 557.72 12 180 113 6.52 736.76 654.90
2 3+970 3+990 20 5 12 200 101 5.47 552.47 491.08 16 110 41 20.32 833.12 1316.54 12 200 23 20.24 465.52 413.80 12 200 101 5.47 552.47 491.08
3 4+250 4+270 20 4 12 200 101 4.47 451.47 401.31 16 150 24 20.32 487.68 770.65 12 200 18 20.24 364.32 323.84 12 200 101 4.47 451.47 401.31
4 4+290 4+310 20 6 12 180 113 6.52 736.76 654.90 20 135 41 20.4 836.4 2065.19 12 180 31 20.24 627.44 557.72 12 180 113 6.52 736.76 654.90
5 4+730 4+750 20 6 12 180 113 6.52 736.76 654.90 20 135 41 20.4 836.4 2065.19 12 180 31 20.24 627.44 557.72 12 180 113 6.52 736.76 654.90
6 4+750 4+770 20 6 12 180 113 6.52 736.76 654.90 20 135 41 20.4 836.4 2065.19 12 180 31 20.24 627.44 557.72 12 180 113 6.52 736.76 654.90
7 5+038 5+050 12.5 6 12 180 71 6.52 462.92 411.48 20 135 41 12.9 528.9 1305.93 12 180 31 12.74 394.94 351.06 12 180 71 6.52 462.92 411.48
8 5+050 5+070 20 5 12 200 101 5.47 552.47 491.08 16 110 41 20.32 833.12 1316.54 12 200 23 20.24 465.52 413.80 12 200 101 5.47 552.47 491.08
9 5+090 5+110 20 6 12 180 113 6.52 736.76 654.90 20 135 41 20.4 836.4 2065.19 12 180 31 20.24 627.44 557.72 12 180 113 6.52 736.76 654.90
10 5+170 5+190 20 5 12 200 101 5.47 552.47 491.08 16 110 41 20.32 833.12 1316.54 12 200 23 20.24 465.52 413.80 12 200 101 5.47 552.47 491.08
11 5+210 5+230 20 5 12 200 101 5.47 552.47 491.08 16 110 41 20.32 833.12 1316.54 12 200 23 20.24 465.52 413.80 12 200 101 5.47 552.47 491.08
12 6+510 6+530 20 5 12 200 101 5.47 552.47 491.08 16 110 41 20.32 833.12 1316.54 12 200 23 20.24 465.52 413.80 12 200 101 5.47 552.47 491.08
13 6+530 6+550 20 5 12 200 101 5.47 552.47 491.08 16 110 41 20.32 833.12 1316.54 12 200 23 20.24 465.52 413.80 12 200 101 5.47 552.47 491.08
Total 253 Sub-Total 7034 Sub-Total 20302 Sub-Total 5946 Sub-Total 7034
Department of Road
Mid Hill West (Puspalal) Highway Project
TULSIPUR,DANG
Err:509
Quantity Estimate of Road Works
S.N. Description of Item No Length Breadth Height Quantity Remark
1 Sub Grade Preparation 1 16954.00 9.00 152586.00
Extra widening on sharp curves 30 40.00 2.50 3000.00
Total 155586.00 Sq m
2 Gravel Sub Base Preparation 1 16954.00 9.00 0.20 30517.20
Extra widening on sharp curves 30 40.00 2.50 0.20 600.00
Total 31117.20 Cu m
3 Crushed Stone Base Preparation 1 16954.00 7.00 0.30 35603.40
Extra widening on sharp curves 30 40.00 2.50 0.30 900.00
Total 36503.40 Cu m
4 Prime Coat for DBST and Emulsion 1 16954.00 7.00 118678.00 0.9 lit/ m2
Extra widening on sharp curves 30 40.00 2.50 3000.00
Total 109510.20 lit
5 Bitumen for 1st Coat (For carraige
way and Shoulder) 1 16954.00 7.00 118678.00 1.2 lit/ m2
Extra widening on sharp curves 30 40.00 2.50 3000.00
Total 146013.60 lit
6 Bitumen for 2nd Coat (For carraige
way and Shoulder) 1 16954.00 7.00 118678.00 1.0 lit/ m2
Extra widening on sharp curves 30 40.00 2.50 3000.00
Total 121678.00 lit
8 20 mm nominal size aggregate for
1st Coat (For carraige way and
Shoulder) 1 16954.00 7.00 118678.00
Extra widening on sharp curves 30 40.00 2.50 3000.00
121678.00 Sq m
Total application rate 20 kg / sq m 2433.56 Mt
9 10 mm nominal size aggregate for 2
nd Coat (For carraige way and
Shoulder) 1 16954.00 7.00 118678.00
Extra widening on sharp curves 30 40.00 2.50 3000.00
Total 121678.00 Sq m
Total application rate 12 kg / sq m 1460.14 Mt
10
Anti-stripping agents: Supplying and
application of Anti-stripping agents
conforming to IS: 14982:2001 @
0.5% all complete as per the
instruction of Engineer. ( SP - 1313,
1d )
1 st Coat 146013.60 lit
2 nd Coat 121678.00 lit
Total 1338.46 kg
11 Scarifying existing Bitumenous
pavement, Subbase and base upto
20 cm depth and breaking down,
removal of oversized particles Only 50% of total width
1 st Coat 1 16954.00 7.00 59339.00 Sq m
Total 59339.00 Sq m
Summary of rates(Old)
Specification
S.N. Norms No Description Unit Rate ( NRs.)
Clause No.
Providing and placing manually mixed M15/40 cement concrete for the foundation and footing etc.
1 2.15 202 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 3170.62
Providing, jointing and laying HDP pipes (110 mm/125mm outer diameter) with or without collar etc.
2 7.01 701 complete in place as per specification.
50 m 9686.45
Proving and laying RCC pipes of diameter 600 mm (internal) with or without collars jointed with stiff
3 7.02.01 701 mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
rm 9977.24
Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff
5 7.02.03 701 mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
rm 25137.33
Road way excavating and loading in Hard soil / Gravel / Boulder mixed soil by Excavator (PC 200) as
6 per specification.
m3 48.71
7 Road way excavating and loading in Soft rock by Excavator (PC 200) as per specification. m3 64.79
8 Road way excavating and loading in Hard rock by Excavator (PC 200) as per specification. m3 83.61
Road way excavating and loading in Soft soil by Excavator (PC 200) 95% and Manual 5% as per
6 specification.
m3 71.00
Road way excavating and loading in Hard soil / Gravel / Boulder mixed soil by Excavator (PC 200) 95%
6 and Manual 5% as per specification.
m3 89.39
Road way excavating and loading in Soft rock by Excavator (PC 200) 95% and Manual 5% as per
7 specification.
m3 172.48
Road way excavating and loading in Hard rock by Excavator (PC 200) 95% and Manual 5% as per
8 specification.
m3 525.06
Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as
9 9.01.a 905 per specification.
m3 977.21
Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift
10 9.01.b 905 upto 1.5 m etc. all complete as per specification.
m3 1302.95
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as
11 9.01.c 905 per specification.
m3 3583.11
Road Way excavation including disposal upto 10 m and lift upto 1.5 m etc. all complete(Hard Rock
12 9.01 d 905 without blasting)
m3 15635.40
Earthwork excavation in soft soil for drain and trenches including shoring, struting, bracing, sheeting
13 9.02.a 905 and disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification
m3 1172.66
Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and trenches including shoring,
14 9.02.b 905 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per m3 1954.43
specification
Earthwork excavation in soft rock for drain and trenches including shoring, struting, bracing, sheeting
15 9.02.c 905 and disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification
m3 3908.85
Excavation of foundation through all types of Soil including relevant lift and disposal upto 20 m (depth
16 9.07.01 905 upto 1.50 m)
m3 2605.90
Backfilling in layers in foundation pits,trenches etc including compaction and watering etc complete,lead
17 9.10.a 908 10 m, a) Depth of foundation upto 1.5m
m3 1485.36
18 9.11.a 908 Excavation and disposal of slides manually haulage distance upto 50m a)Soft soil m3 781.77
Subgrade construction and preparation of formation in cutting (other than rock excavation) including
22 10.01 1003 disposal of material upto10m .
m3 200.28
Subgrade construction, preparation and formation of subgrade in rock cutting with regulating course of
23 10.02 1003 natural materials.
m3 237.64
Subgrade construction with loose untreated materials; preparation and formation of subgrade in fill
24 10.03 1003 areas.
m3 237.64
Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm)
25 10.05.a 1003 in common soil.
m2 195.44
Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm)
26 10.05.b 1003 in gravel & boulder mixed soil.
m2 390.89
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading
27 12.01 1201 as per table 12.1 of standard specification lead upto 10m.
m3 3693.70
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading
28 12.02 1201 as per table 12.1 of standard specification lead upto 10m (for manual works).
m3 4901.08
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for subbase
29 12.06 1202 course grading SB2*lead upto 10m. (for manual works)
m3 5398.00
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base
30 12.06 1202 course lead upto 10m.
m3 4456.91
Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base
31 12.07 1201 course lead upto 10m for manual works.
m3 6191.75
Providing, laying, spreading, watering, levelling and compaction of waterbound Macadam base course
32 12.10 1203 class D1* grading 1 or grading 2 lead upto 10m.
m3 4427.27
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing course
33 12.12 1205 class -1 / class -2 lead upto 10m.
m3 3584.44
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing course
34 12.13 1205 class -1/class -2 lead upto 10m for manual works.
m3 5503.39
Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using
35 13.01 1301, 1302 wire, brushes, broom etc. before applying tack coat.
Ltr 201.78
Fabricating, Providing, assembling and erecting Timber superstructure inlcuding necessary hardware
36 13.01.b for beam structure. (Falsework not included).
m3 269186.04
Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using
37 13.02 1301, 1302 wire, brushes, broom etc. before applying tack coat, using manual methods.
Ltr 196.30
Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using
38 13.03 1301, 1302 wire, brushes, broom etc. before applying prime coat.
Ltr 201.78
Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using
39 13.04 1301, 1302 wire, brushes, broom etc. before applying prime coat, using manual methods.
Ltr 176.06
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or
40 13.05.01 1301, 1303 broken stone chips including compaction -- I) Bituminous binder for surface dressing( mass work).
Ltr 161.89
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or
41 13.05.03 1301, 1303 broken stone chips including compaction -- II) Cutter for bitumen grade 80/100.
Ltr 114.60
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or
42 13.05.04 1301, 1303 broken stone chips including compaction -- III) Chipping for surface dressing for 1st coat size or second Mt 3285.01
coat size.
Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or
43 13.05.05 1301, 1303 broken stone chips including compaction -- IV) Production of percorated chipping.
m3 5799.01
44 13.06.01 1301, 1304 Providing and laying semi-grouting with compaction 50mm thickness. m2 1037.54
45 13.06.02 1301, 1304 Providing and laying semi-grouting with compaction 75mm thickness. m2 1381.44
46 13.06.03 1301, 1304 Providing and laying full grouting with compaction 50 mm thicknes. m2 1218.74
47 13.07 1301, 1305 Providing and laying sand seal. m2 133.50
48 13.08.01 1301, 1306 Providing, mixing and laying slurry seal with fine slurry mix. m2 177.62
Summary of rates(Old)
Specification
S.N. Norms No Description Unit Rate ( NRs.)
Clause No.
49 13.08.02 1301, 1306 Providing, mixing and laying slurry seal with normal slurry mix. m2 195.44
50 13.08.03 1301, 1306 Providing, mixing and laying slurry seal with coarse slurry mix. m2 224.57
51 13.09 1307, 1308 Providing, mixing, laying and compaction of premix carpet. m3 19016.30
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate,
52 15.01.a 1501 cement concrete, painting, writing and supporting steel angle nut and bolit etc. complete a) 60cm. Dia. no 3395.27
Circular, 60cm. equilateral traingle and 60cm.x 45cm. rectangular shaped sign (single post).
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate,
53 15.01.b 1501 cement concrete, painting, writing and supporting steel angle nut and bolit etc. complete b) 1.2m.x no 9166.68
0.75m. Size bigger traffic sign with back support and two or more post.
Supplying and applying paint for Road marking including cleaning, watering, brooming etc. all complete
54 15.02.a 1502 (10cm. wide strip) a) Two coats over old painted surface
m 11.42
Supplying and applying paint for Road marking including cleaning, watering, brooming etc. all complete
55 15.02.b 1502 (10cm. wide strip) b) More than two coats over new bitumin surface
m 17.34
Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing etc.
56 15.03.a 1503 all complete as per specification a) Standard KM post placed at each kilometer.
no 3556.96
Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing etc.
57 15.03.b 1503 all complete as per specification b) Bigger kilometer post (placed at each 5 km.)
no 8109.17
Supplying and fixing in place R.C.C. delineator and guard post including excavation, back filling,
58 15.04 1504 painting and erection etc. all complete as per drawing.
no 1497.13
Providing , Preparing and Installing form work including necessary supports and removing after
59 18.01 1804, 1805 completion for foundation and footings using timber ( soft wood) - Class F1 finish.
m2 520.26
Providing , Preparing and Installing form work & removing after completion for Precast elements of
60 18.07 1804, 1805 square / rectangular section using timber (soft wood) -- Class F3 finish.
m2 1267.69
Providing and placing machine mixed M10/40 cement concrete for the foundation and footing etc.
61 20.01.a.01 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 16987.13
Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc.
62 20.01.a.02 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 10307.07
Providing and placing machine mixed M20/40 cement concrete for the foundation and footing etc.
63 20.01.a.03 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 10268.85
Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc.
64 20.01.a.04 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 10273.78
Providing and placing machine mixed M25/20 cement concrete for the foundation and footing etc.
65 20.01.a.05 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 10300.96
Providing and placing manually mixed M10/40 cement concrete for the foundation and footing etc.
66 20.01.b.01 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 11220.00
Providing and placing manually mixed M15/40 cement concrete for the foundation and footing etc.
67 20.01.b.02 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 11110.74
Providing and placing manually mixed M20/40 cement concrete for the foundation and footing etc.
68 20.01.b.03 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 11026.68
Providing and placing manually mixed M20/20 cement concrete for the foundation and footing etc.
69 20.01.b.04 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 11078.76
Providing and placing manually mixed M25/20 cement concrete for the foundation and footing etc.
70 20.01.b.05 2000 including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
m3 11085.35
Providing and placing manually mixed non structural cement concrete [ cement (1): sand (4) :
71 20.06.b.1 2000 aggregate (8) ] including compaction, curing, testing and lead 30m. etc. all complete as per m3 10937.82
specification and drawing.
Providing and placing manually mixed non structural cement concrete [ cement (1): sand (3) :
72 20.06.b.02 2000 aggregate (6) ] including compaction, curing, testing and lead 30m. etc. all complete as per m3 10944.28
specification and drawing.
Providing and placing manually mixed non structural cement concrete [ cement (1): sand (2) :
73 20.06.b.03 2000 aggregate (4) ] including compaction, curing, testing and lead 30m. etc. all complete as per m3 10775.57
specification and drawing.
Providing and laying Reinforcement ( diameter upto 8 mm) including cutting, bending, binding, fixing in
74 20.07.01 2000 position and lead 30m. etc. all complete as per specification and drawing.
mt 171817.79
Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting,
75 20.07.02 2000 bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
mt 162638.50
Providing and laying Reinforcement ( diameter above 16 mm) including cutting, bending, binding,
76 20.07.03 2000 fixing in position and lead 30m. etc. all complete as per specification and drawing.
mt 153605.26
Fabrication of [ 3 x 1 x 1 : (16 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes /
mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg and selvedged wire 7 swg ,
including rolling, cutting and weaving ; assembling Gabion boxes mattresses, palcing in position
77 24.02.01 2401 including stretching, forming compartments; tying with bracing wires and tie wires; tying down the lid
box 17482.23
complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing,
beding, bonding and all transporation as per specification.
Fabrication of [ 2 x 1 x 1 : (11 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes /
mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg and selvedged wire 7 swg ,
including rolling, cutting and weaving ; assembling Gabion boxes mattresses , palcing in position
78 24.02.02 2401 including stretching, forming compartments; tying with bracing wires and tie wires; tying down the lid
box 11881.20
complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing,
beding, bonding and all transporation as per specification.
Fabrication of [ 1.5 x 1 x 1 : (9 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes /
mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg and selvedged wire 7 swg ,
including rolling, cutting and weaving ; assembling Gabion boxes mattresses , palcing in position
79 24.02.03 2401 including stretching, forming compartments; tying with bracing wires and tie wires; tying down the lid
box 11211.52
complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing,
beding, bonding and all transporation as per specification.
Fabrication of [ 1 x 1 x 1 : (6 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes /
mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg and selvedged wire 7 swg ,
including rolling, cutting and weaving ; assembling Gabion boxes mattresses , palcing in position
80 24.02.04 2401 including stretching, forming compartments; tying with bracing wires and tie wires; and tying down the
box 6277.77
lid complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including
dressing, beding, bonding and all transporation as per specification.
Providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding,
81 24.02.05 2401 bonding and all transporation as per specification.
m3 3472.48
Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per
82 24.14.01.a 2406; 2, 4 specification Lead 30m, lift 1.5m , using concrete mixer and vibrator.
m3 8389.78
Summary of rates(Old)
Specification
S.N. Norms No Description Unit Rate ( NRs.)
Clause No.
Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per
83 24.14.01.b 2406; 2, 4 specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator.
m3 8864.12
Providing and placing plum-concrete with 70% M 15/40 concrete and 30% boulders/stones as per
84 24.14.02.a 2406; 2, 4 specification. Lead 30m, lift 1.5m using concrete mixer and vibrator.
m3 8585.01
Providing and placing concrete with 70% M 15/40 concrete and 30% boulders/stones as per
85 24.14.02.b 2406; 2, 4 specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator.
m3 9220.96
2602, 2603, Providing and laying dry stone masonry (coursed rubble) including dressing etc. complete as per
86 26.01 specification, lead 30m.
m3 6943.08
2068
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including
2602, 2603,
87 26.03.a scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10538.25
2607 mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
2602, 2603,
88 26.03.b scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10639.16
2607 mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including
2602, 2603,
89 26.03.c scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (machine m3 10737.89
2607 mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including
90 26.04.a 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual m3 11665.23
mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
91 26.04.b 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual m3 11766.14
mixing), mortar 35%
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including
92 26.04.c 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual m3 11864.87
mixing), mortar 35%
Removal of old paints by sand blasting, cleaning and repairing of metal surfaces for the application of
93 27.07 2713 new paints as per specification.
m2 1024.77
Maintenance of earthen shoulders by making irregularities even to the required level including watering
94 29.02 2903 and compaction etc. all complete lead 10m.
m2 295.56
Maintenance of gravel shoulders and gravel carriageway by repairing pot holes and making
95 29.03 2904 iregularities even to the required level including watering and compaction etc. all complete lead 10m.
m2 741.24
96 2-25-kha Back fill with common material. m3 325.74
Backfilling in layers in foundation ,pits,trenches etc including compaction and watering etc ,complete
97 2 - 26 lead 10 m
m3 2820.95
98 6-5 Supply and place dry stone soling m2 828.57
99 6-5 Supply and place dry stone soling m3 4142.83
13-1-b, 15-
100 Double coat whitewash on new surface including supply of materials all complete m2 64.68
16-b
101 13-2 Single coat whitewash on old surface including supply of materials all complete m2 47.73
102 15-5-a, b Single coat enamel paint/ readymade emulsion paint including supply of materials all complete. m2 280.00
103 31.01.a 3105 Providing and installing Railing including Railing Posts -- 100 mm dia m 11536.30
104 31.01.b 3105 Providing and installing Railing including Railing Posts -- 50 mm dia m 1684.29
105 31.01.c 3105 Providing and installing Railing including Railing Posts -- 38 mm dia m 1371.84
Back fill with graded filter materials in layer with necessary watering and compaction, lead 30m, lift
106 24.11 1.5m
m3 6040.39
107 31.03 3109 Supply and Laying of Geo-textile as per specification Sq.m 135.70
Spec. cl. No: Road way excavation in hard rock by Blasting. Making rubbles of required size including making hole,
108 9.02.d.ii).II m3 4602.86
905 blasting and breaking with chisel or hammer, hauling distance 10m. and stacking.
109 Applying of Antistripping Additive Kg 369.78
Description of
works: Machine Type Machine Capacity Soil type Unit : 1
Road way excavation all complete as per specification.
m3
Spec. cl. No: 905 Excavator Upto 0.35 m3 Soft Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 0.750 600.00 450.00 Tools and plant 3.00% of L.C. 13.50
Sub total of A = 450.00 Sub total of B = 0.00 Sub total of C = 13.50
Unit Rate = 463.50 Percentage 5.00 Manual Component Rate = 23.18
Machine
Diesel lit 0.1304 97 12.64 Hydraylic Excavator hr 0.0163 2500.00 40.75
Sub total of B = 12.64 Sub total of C = 40.75
Unit Rate = 53.39 Percentage 95.00 Machine Component Rate = 50.72
Total Rate (Manual + Machine) 73.90
Contractor's overhead expenses 15% = 11.08
Total Rate (Manual + Machine) with 15% Contractor Overhead 84.98
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.63 m3 Soft Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 0.750 600.00 450.00 Tools and plant 3.00% of L.C. 13.50
Sub total of A = 450.00 Sub total of B = 0.00 Sub total of C = 13.50
Unit Rate = 463.50 Percentage 5.00 Manual Component Rate = 23.18
Machine
Diesel lit 0.1160 97 11.25 Hydraylic Excavator hr 0.0116 2500.00 29.00
Sub total of B = 11.25 Sub total of C = 29.00
Unit Rate = 40.25 Percentage 95.00 Machine Component Rate = 38.24
Total Rate (Manual + Machine) 61.41
Contractor's overhead expenses 15% = 9.21
Total Rate (Manual + Machine) with 15% Contractor Overhead 70.62
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.80 m3 Soft Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 0.750 600.00 450.00 Tools and plant 3.00% of L.C. 13.50
Sub total of A = 450.00 Sub total of B = 0.00 Sub total of C = 13.50
Unit Rate = 463.50 Percentage 5.00 Manual Component Rate = 23.18
Machine
Diesel lit 0.1248 97 12.10 Hydraylic Excavator hr 0.0104 2500.00 26.00
Sub total of B = 12.10 Sub total of C = 26.00
Unit Rate = 38.10 Percentage 95.00 Machine Component Rate = 36.20
Total Rate (Manual + Machine) 59.37
Contractor's overhead expenses 15% = 8.91
Total Rate (Manual + Machine) with 15% Contractor Overhead 68.28
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 1.32 m3 Soft Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 0.750 600.00 450.00 Tools and plant 3.00% of L.C. 13.50
Sub total of A = 450.00 Sub total of B = 0.00 Sub total of C = 13.50
Unit Rate = 463.50 Percentage 5.00 Manual Component Rate = 23.18
Machine
Diesel lit 0.1380 97 13.38 Hydraylic Excavator hr 0.0069 2500.00 17.25
Sub total of B = 13.38 Sub total of C = 17.25
Unit Rate = 30.63 Percentage 95.00 Machine Component Rate = 29.10
Total Rate (Manual + Machine) 52.27
Contractor's overhead expenses 15% = 7.84
Total Rate (Manual + Machine) with 15% Contractor Overhead 60.11
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Average of all Soft Soil
Total Rate (Manual + Machine) 71.00
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.35 m3 Hard Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 1.000 600.00 600.00 Tools and plant 3.00% of L.C. 18.00
Sub total of A = 600.00 Sub total of B = 0.00 Sub total of C = 18.00
Unit Rate = 618.00 Percentage 5.00 Manual Component Rate = 30.90
Machine
Diesel lit 0.1600 97 15.52 Hydraylic Excavator hr 0.0200 2500.00 50.00
Sub total of B = 15.52 Sub total of C = 50.00
Unit Rate = 65.52 Percentage 95.00 Machine Component Rate = 62.24
Total Rate (Manual + Machine) 93.14
Contractor's overhead expenses 15% = 13.97
Total Rate (Manual + Machine) with 15% Contractor Overhead 107.12
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.63 m3 Hard Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 1.000 600.00 600.00 Tools and plant 3.00% of L.C. 18.00
Sub total of A = 600.00 Sub total of B = 0.00 Sub total of C = 18.00
Unit Rate = 618.00 Percentage 5.00 Manual Component Rate = 30.90
Machine
Diesel lit 0.1400 97 13.58 Hydraylic Excavator hr 0.0140 2500.00 35.00
Sub total of B = 13.58 Sub total of C = 35.00
Unit Rate = 48.58 Percentage 95.00 Machine Component Rate = 46.15
Total Rate (Manual + Machine) 77.05
Contractor's overhead expenses 15% = 11.56
Total Rate (Manual + Machine) with 15% Contractor Overhead 88.61
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.80 m3 Hard Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 1.000 600.00 600.00 Tools and plant 3.00% of L.C. 18.00
Sub total of A = 600.00 Sub total of B = 0.00 Sub total of C = 18.00
Unit Rate = 618.00 Percentage 5.00 Manual Component Rate = 30.90
Machine
Diesel lit 0.1500 97 14.55 Hydraylic Excavator hr 0.0125 2500.00 31.25
Sub total of B = 14.55 Sub total of C = 31.25
Unit Rate = 45.80 Percentage 95.00 Machine Component Rate = 43.51
Total Rate (Manual + Machine) 74.41
Contractor's overhead expenses 15% = 11.16
Total Rate (Manual + Machine) with 15% Contractor Overhead 85.57
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 1.32 m3 Hard Soil
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 1.000 600.00 600.00 Tools and plant 3.00% of L.C. 18.00
Sub total of A = 600.00 Sub total of B = 0.00 Sub total of C = 18.00
Unit Rate = 618.00 Percentage 5.00 Manual Component Rate = 30.90
Machine
Diesel lit 0.1680 97 16.29 Hydraylic Excavator hr 0.0084 2500.00 21.00
Sub total of B = 16.29 Sub total of C = 21.00
Unit Rate = 37.29 Percentage 95.00 Machine Component Rate = 35.43
Total Rate (Manual + Machine) 66.33
Contractor's overhead expenses 15% = 9.95
Total Rate (Manual + Machine) with 15% Contractor Overhead 76.27
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Average of all Hard Soil
Total Rate (Manual + Machine) 89.39
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.35 m3 Soft Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 2.750 600.00 1650.00 Tools and plant 3.00% of L.C. 49.50
Sub total of A = 1650.00 Sub total of B = 0.00 Sub total of C = 49.50
Unit Rate = 1699.50 Percentage 5.00 Manual Component Rate = 84.98
Machine
Diesel lit 0.2216 97 21.49 Hydraylic Excavator hr 0.0277 2500.00 69.25
Sub total of B = 21.49 Sub total of C = 69.25
Unit Rate = 90.74 Percentage 95.00 Machine Component Rate = 86.20
Total Rate (Manual + Machine) 171.18
Contractor's overhead expenses 15% = 25.68
Total Rate (Manual + Machine) with 15% Contractor Overhead 196.85
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.63 m3 Soft Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 2.750 600.00 1650.00 Tools and plant 3.00% of L.C. 49.50
Sub total of A = 1650.00 Sub total of B = 0.00 Sub total of C = 49.50
Unit Rate = 1699.50 Percentage 5.00 Manual Component Rate = 84.98
Machine
Diesel lit 0.1960 97 19.01 Hydraylic Excavator hr 0.0196 2500.00 49.00
Sub total of B = 19.01 Sub total of C = 49.00
Unit Rate = 68.01 Percentage 95.00 Machine Component Rate = 64.61
Total Rate (Manual + Machine) 149.58
Contractor's overhead expenses 15% = 22.44
Total Rate (Manual + Machine) with 15% Contractor Overhead 172.02
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.80 m3 Soft Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 2.750 600.00 1650.00 Tools and plant 3.00% of L.C. 49.50
Sub total of A = 1650.00 Sub total of B = 0.00 Sub total of C = 49.50
Unit Rate = 1699.50 Percentage 5.00 Manual Component Rate = 84.98
Machine
Diesel lit 0.2064 97 20.02 Hydraylic Excavator hr 0.0172 2500.00 43.00
Sub total of B = 20.02 Sub total of C = 43.00
Unit Rate = 63.02 Percentage 95.00 Machine Component Rate = 59.87
Total Rate (Manual + Machine) 144.84
Contractor's overhead expenses 15% = 21.73
Total Rate (Manual + Machine) with 15% Contractor Overhead 166.57
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 1.32 m3 Soft Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 2.750 600.00 1650.00 Tools and plant 3.00% of L.C. 49.50
Sub total of A = 1650.00 Sub total of B = 0.00 Sub total of C = 49.50
Unit Rate = 1699.50 Percentage 5.00 Manual Component Rate = 84.98
Machine
Diesel lit 0.2340 97 22.69 Hydraylic Excavator hr 0.0117 2500.00 29.25
Sub total of B = 22.69 Sub total of C = 29.25
Unit Rate = 51.94 Percentage 95.00 Machine Component Rate = 49.34
Total Rate (Manual + Machine) 134.32
Contractor's overhead expenses 15% = 20.15
Total Rate (Manual + Machine) with 15% Contractor Overhead 154.47
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Average of all Soft Rock
Total Rate (Manual + Machine) 172.48
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.35 m3 Hard Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 12.000 600.00 7200.00 Tools and plant 3.00% of L.C. 216.00
Sub total of A = 7200.00 Sub total of B = 0.00 Sub total of C = 216.00
Unit Rate = 7416.00 Percentage 5.00 Manual Component Rate = 370.80
Machine
Diesel lit 0.2960 97 28.71 Hydraylic Excavator hr 0.0370 2500.00 92.50
Sub total of B = 28.71 Sub total of C = 92.50
Unit Rate = 121.21 Percentage 95.00 Machine Component Rate = 115.15
Total Rate (Manual + Machine) 485.95
Contractor's overhead expenses 15% = 72.89
Total Rate (Manual + Machine) with 15% Contractor Overhead 558.84
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.63 m3 Hard Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 12.000 600.00 7200.00 Tools and plant 3.00% of L.C. 216.00
Sub total of A = 7200.00 Sub total of B = 0.00 Sub total of C = 216.00
Unit Rate = 7416.00 Percentage 5.00 Manual Component Rate = 370.80
Machine
Diesel lit 0.2560 97 24.83 Hydraylic Excavator hr 0.0256 2500.00 64.00
Sub total of B = 24.83 Sub total of C = 64.00
Unit Rate = 88.83 Percentage 95.00 Machine Component Rate = 84.39
Total Rate (Manual + Machine) 455.19
Contractor's overhead expenses 15% = 68.28
Total Rate (Manual + Machine) with 15% Contractor Overhead 523.47
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.80 m3 Hard Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 12.000 600.00 7200.00 Tools and plant 3.00% of L.C. 216.00
Sub total of A = 7200.00 Sub total of B = 0.00 Sub total of C = 216.00
Unit Rate = 7416.00 Percentage 5.00 Manual Component Rate = 370.80
Machine
Diesel lit 0.2724 97 26.42 Hydraylic Excavator hr 0.0227 2500.00 56.75
Sub total of B = 26.42 Sub total of C = 56.75
Unit Rate = 83.17 Percentage 95.00 Machine Component Rate = 79.01
Total Rate (Manual + Machine) 449.81
Contractor's overhead expenses 15% = 67.47
Total Rate (Manual + Machine) with 15% Contractor Overhead 517.28
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 1.32 m3 Hard Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 12.000 600.00 7200.00 Tools and plant 3.00% of L.C. 216.00
Sub total of A = 7200.00 Sub total of B = 0.00 Sub total of C = 216.00
Unit Rate = 7416.00 Percentage 5.00 Manual Component Rate = 370.80
Machine
Diesel lit 0.3060 97 29.68 Hydraylic Excavator hr 0.0153 2500.00 38.25
Sub total of B = 29.68 Sub total of C = 38.25
Unit Rate = 67.93 Percentage 95.00 Machine Component Rate = 64.53
Total Rate (Manual + Machine) 435.33
Contractor's overhead expenses 15% = 65.30
Total Rate (Manual + Machine) with 15% Contractor Overhead 500.63
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Average of all Hard Rock
Total Rate (Manual + Machine) 525.06
Description of Road way excavation all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Average of all All
Soil Type Rate % Amount
Soft Soil 71.00 #REF! #REF!
Hard Soil 89.39 #REF! #REF!
Soft Rock 172.48 #REF! #REF!
Hard Rock 525.06 #REF! #REF! Total
Total Rate (Soil) #REF! #REF! #REF!
Description of Excavation of metalled road all complete as per specification. Machine Type Machine Capacity Soil type
works: Unit : 1
m3
Spec. cl. No: 905 Excavator Upto 0.35 m3 Soft Rock
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Manual
9.01.a Unskilled md 2.750 600.00 1650.00 Tools and plant 3.00% of L.C. 49.50
Sub total of A = 1650.00 Sub total of B = 0.00 Sub total of C = 49.50
Unit Rate = 1699.50 Percentage 10.00 Manual Component Rate = 169.95
Machine
Diesel lit 0.2216 97 21.49 Motor Grader hr 0.0126 1200.00 15.12
Sub total of B = 21.49 Sub total of C = 15.12
Unit Rate = 36.61 Percentage 90.00 Machine Component Rate = 32.95
Total Rate (Manual + Machine) 202.90
Contractor's overhead expenses 15% = 30.43
Total Rate (Manual + Machine) with 15% Contractor Overhead 233.33
Province Government
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Gandaki Province
Pokhara, Nepal
0
Transportation Cost
Chap (Mahendra Pul) to Nar Road Project
Description of works: Transportation of materials by truck, including loading, unloading and stacking by manpower lead upto 10m using 5 tonne capacity Truck.
Spec. Clause No. 800 Travel time (T) for truck to be used for this activity shall be determined as follows:
T=2x{d1/v1+d2/v2+d3/v3+………………..dn/vn}, where d1,d2,d3………dn and v1,v2,v3……..vn are the streches of distances to be travelled and corresponding average
speeds on these streches. [ T = 2*(d1/v1+d2/v2+……dn/vn) = ] (T=travel time for truck in
Description of works Unit Activity No d1 v1 d2 v2 d3 v3 d4 v4 …. …. dn vn Travel time T (hrs) Remarks
Excavated earthwork soil material m3 8.04.2.1.a T = 2 1.00 10.00 0.00 25.00 40.00 = 0.20
Excavated earthwork rock material 1.00 10.00 0.00 25.00 40.00
m3 8.04.2.1.b T= 2 = 0.20
Sand, Stone dust m3 8.04.2.2 T= 2 6.00 10.00 7.00 25.00 0.00 40.00 = 1.76 Morang to Project Site
Gravel, river shingle, broken stone, and
40.00
bats m3 8.04.2.3 T= 2 6.00 10.00 7.00 25.00 0.00 = 1.76 Morang to Project Site
Crushed Aggregate (Chips) m3 8.04.2.3 T= 2 6.00 10.00 7.00 25.00 0.00 40.00 = 1.76 Morang to Project Site
Boulder, Cobbles, quarry stone m3 8.04.2.4 T= 2 3.00 10.00 0.00 25.00 40.00 = 0.60
Brick 1000
40.00
nos 8.04.2.6 T= 2 17.00 10.00 11.00 25.00 0.00 4.28 Jikhimti Bazzar to Project Site
Cement t 8.04.2.7 T= 2 17.00 10.00 11.00 25.00 0.00 40.00 = 4.28 Jikhimti Bazzar to Project Site
Reinforcement Steel and gabion wire t 8.04.2.8 T= 2 17.00 10.00 11.00 25.00 0.00 40.00 = 4.28 Jikhimti Bazzar to Project Site
Bitumen 1000
40.00
lit 8.04.2.9 T= 2 17.00 10.00 11.00 25.00 0.00 = 4.28 Jikhimti Bazzar to Project Site
Timber for temporary works m 3
8.04.2.11 T= 2 1.00 10.00 0.00 25.00 40.00 = 0.20 Jikhimti Bazzar to Project Site
RCC hume pipe of 900mm dia m 8.04.2.16.a T= 2 17.00 10.00 11.00 25.00 0.00 40.00 = 4.28 Jikhimti Bazzar to Project Site
RCC hume pipe of 750mm dia m 8.04.2.16.b T= 2 17.00 10.00 11.00 25.00 0.00 40.00 = 4.28 Jikhimti Bazzar to Project Site
RCC hume pipe of 600mm dia m 8.04.2.16.c T= 2 17.00 10.00 11.00 25.00 0.00 40.00 = 4.28 Jikhimti Bazzar to Project Site
Water 1000
40.00
lit 8.04.2.17 T= 2 1.00 10.00 0.00 25.00 = 0.20
Activity No: 8.04.02 F/Y: 075/076
Spec. Clause No. 800
Description of works: Transportation of materials by truck, including loading, unloading and stacking by manpower lead upto 10m using 5 tonne capacity Truck Place:
2) Sand m3 Unskilled md 0.30 600 180.00 Fuel lit 2.2xT= 3.872 97.00 375.58 Truck hr 0.22x(T+0.75)= 0.552 630.00 347.89
Sub total of Labour + Materials + Equipments = 903.47 Contractor's overhead expenses 15% = 135.52 Unit rate = 1038.99
3.1) Crushed aggregate m3 Unskilled md 0.50 600 300.00 Fuel lit 2.6xT= 4.576 97.00 443.87 Truck hr 0.26x(T+0.75)= 0.653 630.00 411.14
Sub total of Labour + Materials + Equipments = 1155.01 Contractor's overhead expenses 15% = 173.25 Unit rate = 1328.26
3.2) Gravel, river shingle, broken stone, m3 Unskilled md 0.50 600 300.00 Fuel lit 2.6xT= 4.576 97.00 443.87 Truck hr 0.26x(T+0.75)= 0.653 630.00 411.14
and bats
Sub total of Labour + Materials + Equipments = 1155.01 Contractor's overhead expenses 15% = 173.25 Unit rate = 1328.26
4) Boulder, Cobbles, quarry stone m3 Unskilled md 0.50 600 300.00 Fuel lit 3.4xT 2.040 97.00 197.88 Truck hr 0.34x(T+0.75)= 0.459 630.00 289.17
Sub total of Labour + Materials + Equipments = 787.05 Contractor's overhead expenses 15% = 118.06 Unit rate = 905.11
6) Brick m3 Unskilled md 0.60 600 360.00 Fuel lit 5xT 21.400 97.00 2075.80 Truck hr 0.5x(T+0.75)= 2.515 630.00 1584.45
Sub total of Labour + Materials + Equipments = 4020.25 Contractor's overhead expenses 15% = 603.04 Unit rate = 4623.29
7) Cement m 3 Unskilled md 0.40 600 240.00 Fuel lit 2xT 97.00 Truck hr 0.2x(T+0.75)= 1.006 630.00 633.78
Sub total of Labour + Materials + Equipments = 873.78 Contractor's overhead expenses 15% = 131.07 Unit rate = 1004.85
8) Reinforcement Steel and gabion wire t Unskilled md 0.60 600 360.00 Fuel lit 2xT 97.00 Truck hr 0.2x(T+0.75)= 1.006 630.00 633.78
Sub total of Labour + Materials + Equipments = 993.78 Contractor's overhead expenses 15% = 149.07 Unit rate = 1142.85
9) Bitumen 1000 Unskilled md 1.00 600 600.00 Fuel lit 3xT 12.840 97.00 1245.48 Truck hr 0.3x(T+0.75)= 1.509 630.00 950.67
lit Sub total of Labour + Materials + Equipments = Contractor's overhead expenses 15% = 419.42 Unit rate =
2796.15 3215.57
11) Timber for temporary works m3 Unskilled md 0.30 600 180.00 Fuel lit 2.4xT 0.480 97.00 46.56 Truck hr 0.3x(T+0.75)= 0.285 630.00 179.55
Sub total of Labour + Materials + Equipments = 406.11 Contractor's overhead expenses 15% = 60.92 Unit rate = 467.03
16) RCC Hume pipe
a) RCC hume pipe of 900mm m Skilled md 0.04 900 36.00 Fuel lit 1.3xT 5.564 97.00 539.71 Truck hr 0.13x(T+1.75)= 0.654 630.00 411.96
Unskilled md 0.40 600 240.00
Sub total of Labour + Materials + Equipments = 1227.67 Contractor's overhead expenses 15% = 184.15 Unit rate = 1411.81
m Skilled md 0.03 900 27.00 Fuel lit 1.1xT 4.708 97.00 456.68 Truck hr 0.11x(T+1.75)= 0.553 630.00 348.58
b) RCC hume pipe of 750mm dia
Unskilled md 0.33 600 198.00
Sub total = 225.00 Sub total = 456.68 Sub total = 348.58
Sub total of Labour + Materials + Equipments = 1030.26 Contractor's overhead expenses 15% = 154.54 Unit rate = 1184.79
c) RCC hume pipe of 600mm m Skilled md 0.02 900 18.00 Fuel lit 0.8xT 3.424 97.00 332.13 Truck hr 0.08x(T+1.75)= 0.402 630.00 253.51
Unskilled md 0.25 600 150.00
Sub total = 168.00 Sub total = 332.13 Sub total = 253.51
Sub total of Labour + Materials + Equipments = 753.64 Contractor's overhead expenses 15% = 113.05 Unit rate = 866.69
17) Water 1000 litSkilled md 0.01 900 9.00 Fuel lit 1.5xT 0.300 97.00 29.10 Truck hr 0.2x(T+0.5)= 0.140 630.00 88.20
Unskilled md 0.10 600 60.00 Pump 10cmdia hr 0.050 170.00 8.50
Sub total = 69.00 Sub total = 29.10 Sub total = 88.20
Sub total of Labour + Materials + Equipments = 186.30 Contractor's overhead expenses 15% = 27.95 Unit rate = 214.25
District Labour, Collection Rate of Materials, Fuel and Equipment Hire Rate (Terhathum District)
1) Labour 4) Material
Rate at Collection Royalty ( Transportation Total Rate
S.N. Description Unit District Rate S.N. Description Unit
Juphal Rate (C) R ) Rate ( Tp ) ( C + R + Tp)
1 Skilled md 900.00 1 Gravel
2 Unskilled (Labour) md 600.00 1.a ( 5 - 70 mm ) m3 1200.00 1155.01 2355.01
3 Driller/Blaster md 900.00 1.b ( 5 - 40 mm) m3 1920.00 1155.01 3075.01
1.c ( 5 - 20 mm) m3 2820.00 1155.01 3975.01
1.d ( 5 - 08 mm) m3 4800.00 1155.01 5955.01
2 Broken Aggregates
2.a ( 70 - 100 mm) m3 3600.00 1155.01 4755.01
2) Fuel and Lubricant 2.b ( 40 - 70 mm) m3 4800.00 1155.01 5955.01
1 Diesel lit. 97.00 2.c ( 20 - 40 mm) m3 7200.00 1155.01 8355.01
2 Kerosene lit. 97.00 2.d ( 10 - 20 mm) m3 10800.00 1155.01 11955.01
3 Petrol lit. 110.00 2.e ( 5 - 10 mm) m3 15000.00 1155.01 16155.01
3 Sand m3 900.00 903.47 1803.47
3.a Quary output less than 33% m3 2400.00 903.47 3303.47
3.b Quary output 33 - 66% m3 1800.00 903.47 2703.47
3) Equipment 3.c Quarry output more than 66% m3 858.00 903.47 1761.47
Operator's DOR Hire Total rate 3.d Sand in hilly areas m3
S.N. Description Unit 900.00 903.47 1803.47
Allowance rate per hour
1 Truck ( 3 tonnes) hr. 460.00 460.00 4 Brick 20000.00 4020.25 24020.25
2 Truck ( 5 tonnes) hr. 630.00 630.00 4.a Chimney made
3 Truck ( 8 tonnes) hr. 800.00 800.00 4.b Machine made
4 Grader ( 90 HP) hr. 1200.00 1200.00 5 Sal Wood
5 Pump 10cm dia hr. 170.00 170.00 5.a Sal wood Local m3 160558.36
6 Vibrator Roller hr. 400.00 400.00 5.b Local Wood m3 38816.31
7 Roller ( 8 - 10 ton) hr. 700.00 700.00 6 Stone dust m3
8 Water bowser hr. 550.00 550.00 7 Rubble m3 840.00 787.05 1627.05
9 Loader (1.9-2.2 cu m) hr. 1200.00 1200.00 8 Cement mt. 20000.00 873.78 20873.78
10 Boiler hr. 180.00 180.00 9 Water lt. 0.19
11 Sprayer (Up to 1 KL) hr. 260.00 260.00 10 Bitumen / Emulsion kg 75.50 2.80 78.30
12 Air compressor hr. 250.00 250.00 11 Crushed Aggregate
13 Hand Sprayer hr. 260.00 260.00 11.a 10 mm ( Small) m3 1900.00 1155.01 3055.01
14 Aggregate Spreader hr. 300.00 300.00 11.b 20 mm ( Intermediate) m3 1900.00 1155.01 3055.01
15 Pneumatic Tyred Roller hr. 1200.00 1200.00 11.c 40 mm (Large) m3 1900.00 1155.01 3055.01
16 mixer hr. 470.00 470.00 12 Round Aggregate
17 Vibrator hr. 100.00 100.00 12.a 10 mm ( Small) m3 1850.00 1155.01 3005.01
18 Blasting machine hr. 0.00 12.b 20 mm ( Intermediate) m3 1850.00 1155.01 3005.01
19 Generator hr. 80.00 80.00 12.c 40 mm (Large) m3 1850.00 1155.01 3005.01
20 Screw Jack hr. 0.00 13 Reinforcement (Tor Steel)
21 Electric Heating Plate hr. 0.00 13.a 4.75 mm mt. 94000.00 993.78 94993.78
22 Bitumen Distributor hr. 1300.00 1300.00 13.b 8 mm mt. 94000.00 993.78 94993.78
23 Chip Spreader hr. 300.00 300.00 13.c 10mm, 12mm, 16mm mt. 94000.00 993.78 94993.78
24 Tractor hr. 300.00 300.00 13.d 20mm, 25mm mt. 94000.00 993.78 94993.78
Excavator 111 to 150 Binding Wire
hr. 14
25 HP 1800.00 2500.00
14.a Binding wire Black kg 126.00 0.99 126.99
14.b Binding wire White kg 156.00 0.99 156.99
15 G.I Wire heavy coated
15.a 8 gauge kg 96.00 0.99 96.99
15.b 10 gauge kg 96.00 0.99 96.99
15.c 12 gauge kg 97.00 0.99 97.99
16 Stone
16.a Crushed stone m3 1000.00 787.05 1787.05
16.b Dressed stone m3 1000.00 787.05 1787.05
17 RCC Hume Pipes
17.a 450mm diameter m 4400.00
17.b 500 mm diameter m 5211.00
17.c 600 mm diameter m 6022.00 753.64 6775.64
17.d 750 mm diameter m 8332.00 1030.26 9362.26
17.e 900 mm diameter m 11825.00 1227.67 13052.67
18 Jute kg 60.00 60.00
19 Nails kg 110.00 110.00
20 Ply wood
plywood 3 mm sq. ft. 225.00 11.51
20.a
plywood 4 mm sq. ft. 300.00
20.b
plywood 6 mm sq. ft. 350.00
20.c
plywood 8 mm sq. ft. 450.00
20.d
plywood 12 mm sq. ft. 510.00
20.e
plywood 19 mm sq. ft. 750.00
20.f
21 Road Paint lit.
22 Enamel Paint lit.
23 Lime kg
24 Gum kg
25 Snow cem kg
26 Primer kg
27 Steel Plate Sq. m
28 Steel tube Rm
29 GI Pipe Medium class with sockets
29.a 38 mm m
29.b 50 mm m
29.c 75 mm m
29.d 100 mm m
30 HDP Pipe NS40 110mm m
base aggregate 3055.01 in m3
subbaseagg 2355.01 in m3
coarse aggregate 3055.01 in m3
key aggregate 3055.01 in m3
Aggregate 3055.01 in m3
chips 1909.38 in ton
Description of works: Excavation of metalled road and removal of all materials including soling and screening, sorting out reusable materials and disposing unusable materials upto 20m. Lead.
(b)Bituminous Materials Unit : m3
Spec. cl. No: 202
Description of works: Providing, jointing and laying HDP pipes (110 mm/125mm outer diameter) with or without collar etc. complete in place as per specification.
Unit : 50 m
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.01 Skilled md 3.0 1476.00 4428 HDP pipe m 50.00 0.00 Generator (<2kva) hr. 8.00 80.00 640.00
Unskilled md 3.0 1100.00 3300 Petrol lit 0.50 110.00 55.00 Screw Jack hr. 8.00 0.00 0.00
electric heating plate hr. 8.00 0.00 0.00
Sub total of A = 7728.00 Sub total of B = 55.00 Sub total of C = 640.00
Sub total of A +B + C = 8423.00 Contractor's overhead expenses 15% = 1263.45 Unit Rate (50 m)= 9686.45
Description of works: Proving and laying RCC pipes of diameter 600 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine
sand ) , lead upto 100m. Unit : 1 rm
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.02.1 Skilled md 0.281 1476.00 414.76 RCC Pipe No 1.0 6775.64 6775.64 Ballies, crow, bars, chain , pulleys ,
3.00% of total cost 252.70
Unskilled md 1.094 1100.00 1203.40 Cement kg 6.813 0.00 0.00 block and ropes etc.
Sand m3 0.009 1803.47 16.23
Jute kg 0.219 60 13.14
Sub total of A = 1618.16 Sub total of B = 6805.01 Sub total of C = 252.70
Sub total of A +B + C = 8675.86 Contractor's overhead expenses 15% = 1301.38 Unit Rate = 9977.24
Description of works: Proving and laying RCC pipes of diameter 750 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine
sand ) , lead upto 100m. Unit : 1 rm
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.02.2 Skilled md 0.308 1476.00 454.61 RCC Pipe m 1.00 9362.26 9362.26 Ballies, crow, bars, chain , pulleys ,
3.00% of total cost 339.46
Unskilled md 1.328 1100.00 1460.80 Cement kg 7.937 0.00 0.00 block and ropes etc.
Sand m3 0.011 1803.47 19.84
Jute kg 0.297 60.00 17.82
Sub total of A = 1915.41 Sub total of B = 9399.91 Sub total of C = 339.46
Sub total of A +B + C = 11654.78 Contractor's overhead expenses 15% = 1748.22 Unit Rate = 13403.00
Description of works: Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine
sand ) , lead upto 100m. Unit : 1 rm
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.02.03 Skilled md 0.344 1476.000 507.744 RCC Pipe No 1.0 18950.00 18950.00 Ballies, crow, bars, chain , pulleys ,
3.00% of total cost 636.66
Unskilled md 1.562 1100.00 1718.20 Cement kg 9.062 0.00 0.00 block and ropes etc.
Sand m3 0.013 1803.47 23.45
Jute kg 0.375 60 22.50
Sub total of A = 2225.94 Sub total of B = 18995.95 Sub total of C = 636.66
Sub total of A +B + C = 21858.55 Contractor's overhead expenses 15% = 3278.78 Unit Rate = 25137.33
Description of works: Road way excavating and loading in Hard soil / Gravel / Boulder mixed soil by Excavator (PC 200) as per specification.
Unit : 1 m3
Reference No: HED, page 33
Labour (A) Material (B) Equipment (C)
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 0.00 1476.00 0.00 diesel lit. 0.15 97.00 14.55 Hydraylic Excavator PC 200 hr 0.01 1800.00 22.50
Unskilled md 0.00469 1100.00 5.16 Lubricant ( 1% of Fuel) 0.15
Description of works: Road way excavating and loading in Hard rock by Excavator (PC 200) as per specification.
Unit : 1 m3
Reference No: HED, page 33
Labour (A) Material (B) Equipment (C)
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled md 0.00 1476.00 0.00 diesel lit. 0.27 97.00 26.42 Hydraylic Excavator PC 200 hr 0.02 1800.00 40.86
Unskilled md 0.00469 1100.00 5.16 Lubricant ( 1% of Fuel) 0.26
Description of works: Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.01.a Unskilled md 0.750 1100.00 825.00 Tools and plant 3.00% of L.C. 24.75
Sub total of A = 825.00 Sub total of B = 0.00 Sub total of C = 24.75
Sub total of A +B + C = 849.75 Contractor's overhead expenses 15% = 127.46 Unit Rate = 977.21
Description of works: Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.01.b Unskilled md 1.000 1100.00 1100.00 Tools and plant 3.00% of L.C. 33.00
Sub total of A = 1100.00 Sub total of B = 0.00 Sub total of C = 33.00
Sub total of A +B + C = 1133.00 Contractor's overhead expenses 15% = 169.95 Unit Rate = 1302.95
Description of works: Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Description of works: Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.01.c Unskilled md 2.750 1100.00 3025.00 Tools and plant 3.00% of L.C. 90.75
Sub total of A = 3025.00 Sub total of B = 0.00 Sub total of C = 90.75
Sub total of A +B + C = 3115.75 Contractor's overhead expenses 15% = 467.36 Unit Rate = 3583.11
Description of works: Road way excavation including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification. (Hardrock without Blasting)
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.01.d Unskilled md 12.000 1100.00 13200.00 Tools and plant 3.00% of L.C. 396.00
Sub total of A = 13200.00 Sub total of B = 0.00 Sub total of C = 396.00
Sub total of A +B + C = 13596.00 Contractor's overhead expenses 15% = 2039.40 Unit Rate = 15635.40
Description of works: Earthwork excavation in soft soil for drain and trenches including shoring, struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per
specification Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.02.a Unskilled md 0.900 1100.00 990.00 Tools and plant 3.0% of L.C. 29.70
Sub total of A = 990.00 Sub total of B = 0.00 Sub total of C = 29.70
Sub total of A +B + C = 1019.70 Contractor's overhead expenses 15% = 152.96 Unit Rate = 1172.66
Description of works: Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and trenches including shoring, struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5
m etc. all complete as per specification Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.02.b Unskilled md 1.500 1100.00 1650.00 Tools and plant 3.00% of L.C. 49.50
Sub total of A = 1650.00 Sub total of B = 0.00 Sub total of C = 49.50
Sub total of A +B + C = 1699.50 Contractor's overhead expenses 15% = 254.93 Unit Rate = 1954.43
Description of works: Earthwork excavation in soft rock for drain and trenches including shoring, struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per
specification Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.02.c Unskilled md 3.000 1100.00 3300.00 Tools and plant 3.00% of L.C. 99.00
Sub total of A = 3300.00 Sub total of B = 0.00 Sub total of C = 99.00
Sub total of A +B + C = 3399.00 Contractor's overhead expenses 15% = 509.85 Unit Rate = 3908.85
Description of works: Excavation for foundation through all types of soil including relevant lift and disposal upto 20 m (Depth upto 1.50 m)
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.07.01 Unskilled md 2.000 1100.00 2200.00 Tools and plant 3.00% of L.C. 66.00
Sub total of A = 2200.00 Sub total of B = 0.00 Sub total of C = 66.00
Sub total of A +B + C = 2266.00 Contractor's overhead expenses 15% = 339.90 Unit Rate = 2605.90
Description of works: Excavation for foundation through Soft Rock including relevant lift and disposal upto 20 m (Depth upto 1.50 m)
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.07.02 Unskilled md 3.000 1100.00 3300.00 Tools and plant 3.00% of L.C. 99.00
Sub total of A = 3300.00 Sub total of B = 0.00 Sub total of C = 99.00
Sub total of A +B + C = 3399.00 Contractor's overhead expenses 15% = 509.85 Unit Rate = 3908.85
Description of works: Backfilling in layers in foundation pits,trenches etc including compaction and watering etc complete,lead 10 m, a) Depth of foundation upto 1.5m
Unit : 1 m3
Spec. cl. No: 908
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.10.a Unskilled md 1.140 1100.00 1254.00 Tools and plant 3.00% of L.C. 37.62
Sub total of A = 1254.00 Sub total of B = 0.00 Sub total of C = 37.62
Sub total of A +B + C = 1291.62 Contractor's overhead expenses 15% = 193.74 Unit Rate = 1485.36
Item no:
Description of works: Excavation and disposal of slides manually haulage distance upto 50m a)Soft soil
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.11.a Unskilled md 0.600 1100.00 660.00 Tools and plant 3.00% of L.C. 19.80
Sub total of A = 660.00 Sub total of B = 0.00 Sub total of C = 19.80
Sub total of A +B + C = 679.80 Contractor's overhead expenses 15% = 101.97 Unit Rate = 781.77
Description of works: Subgrade construction and preparation of formation in cutting (other than rock excavation) including disposal of material upto10m .
Unit : 1 m3
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.01 Skilled md 0.01 1476.00 14.76 diesel lit. 0.122 97.00 11.83 Grader (75 Hp) hr 0.01 1200.00 12.00
Unskilled md 0.10 1100.00 110.00 Roller 8-10t hr 0.017 700.00 11.90
Lab tests 10.0% ot Total .C. 13.66
Sub total of A = 124.76 Sub total of B = 11.83 Sub total of C = 37.56
Sub total of A +B + C = 174.15 Contractor's overhead expenses 15% = 26.12 Unit Rate = 200.28
Description of works: Subgrade construction, preparation and formation of subgrade in rock cutting with regulating course of natural materials.
Unit : 1 m3
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.02 Skilled md 0.01 1476.00 14.76 Sub grade material m3 1.10 0.00 Grader (75 Hp) hr 0.02 1200.00 24.00
Unskilled md 0.10 1100.00 110.00 Diesel lit 0.122 97.00 11.83 Roller 8-10t hr 0.017 700.00 11.90
Water lit 100.00 0.19 18.63 Lab tests 10.0% ot T.C. 15.52
Sub total of A = 124.76 Sub total of B = 30.46 Sub total of C = 51.42
Sub total of A +B + C = 206.65 Contractor's overhead expenses 15% = 31.00 Unit Rate = 237.64
Description of works: Subgrade construction with loose untreated materials; preparation and formation of subgrade in fill areas.
Unit : 1 m3
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.03 Skilled md 0.01 1476.00 14.76 Sub grade material m3 1.10 0.00 Grader (75 Hp) hr 0.02 1200.00 24.00
Unskilled md 0.10 1100.00 110.00 Diesel lit 0.122 97.00 11.83 Roller 8-10t hr 0.017 700.00 11.90
Water lit 100.00 0.19 18.63 Lab tests 10.0% ot T.C. 15.52
Sub total of A = 124.76 Sub total of B = 30.46 Sub total of C = 51.42
Sub total of A +B + C = 206.65 Contractor's overhead expenses 15% = 31.00 Unit Rate = 237.64
Description of works: Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in common soil.
Unit : 1 m2
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.05.a Unskilled md 0.15 1100.00 165.00 Tools and Plant 3% of LC 4.95
Sub total of A = 165.00 Sub total of B = 0.00 Sub total of C = 4.95
Sub total of A +B + C = 169.95 Contractor's overhead expenses 15% = 25.49 Unit Rate = 195.44
Description of works: Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in gravel & boulder mixed soil.
Spec. cl. No: 1003 Unit : 1 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.05.b Unskilled md 0.30 1100.00 330.00 Tools and Plant 3% of LC 9.90
Sub total of A = 330.00 Sub total of B = 0.00 Sub total of C = 9.90
Sub total of A +B + C = 339.90 Contractor's overhead expenses 15% = 50.99 Unit Rate = 390.89
Description of works: Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m.
Spec. cl. No: 1201 Unit : 1 m3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.01 Skilled md 0.0050 1476.00 7.38 Subbase agg. cu.m. 1.2800 2355.01 3014.41 Grader hr 0.0220 1200.00 26.40
Unskilled md 0.0400 1100.00 44.00 Diesel lit 0.7920 97.00 76.82 Vibrator Rolller hr 0.0220 400.00 8.80
Water bowser hr 0.0380 550.00 20.90
Loader hr 0.0110 1200.00 13.20
Sub total of A = 51.38 Sub total of B = 3091.24 Sub total of C = 69.30
Sub total of A +B + C = 3211.92 Contractor's overhead expenses 15% = 481.79 Unit Rate = 3693.70
Description of works: Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m (for
manual works). Unit : 1 m3
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m (for
manual works). Unit : 1 m3
Spec. cl. No: 1201
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.02 Skilled md 0.0050 1476.00 7.38 Subbase agg. m3 1.280 2355.01 3014.41 Road Roller hr. 0.030 700.00 21.00
Unskilled md 1.0500 1100.00 1155.00 Diesel lit 0.660 97.00 64.02
Sub total of A = 1162.38 Sub total of B = 3078.43 Sub total of C = 21.00
Sub total of A +B + C = 4261.81 Contractor's overhead expenses 15% = 639.27 Unit Rate = 4901.08
Description of works: Providing, laying, spreading, watering, levelling and compaction of crusher run materials for subbase course grading SB2*lead upto 10m. (for manual works)
Unit : 1 m3
Spec. cl. No: 1202
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.06 Skilled md 0.0050 1476.00 7.38 Sub base aggregate cu.m. 1.300 2355.01 3061.51 Road Roller hr 0.030 700.00 21.00
Unskilled md 1.4000 1100.00 1540.00 Diesel lit 0.660 97.00 64.02
Sub total of A = 1547.38 Sub total of B = 3125.53 Sub total of C = 21.00
Sub total of A +B + C = 4693.91 Contractor's overhead expenses 15% = 704.09 Unit Rate = 5398.00
Description of works: Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base course lead upto 10m.
Unit : 1 m3
Spec. cl. No: 1202
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.06 Skilled md 0.0050 1476.00 7.38 Base aggregate cu.m. 1.200 3055.01 3666.01 Grader hr 0.033 1200.00 39.60
Unskilled md 0.0200 1100.00 22.00 Diesel lit 0.990 97.00 96.03 Vibrator Rolller hr 0.033 400.00 13.20
Water Bowser hr 0.033 550.00 18.15
Loader hr 0.011 1200.00 13.20
Sub total of A = 29.38 Sub total of B = 3762.04 Sub total of C = 84.15
Sub total of A +B + C = 3875.57 Contractor's overhead expenses 15% = 581.34 Unit Rate = 4456.91
Description of works: Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base course lead upto 10m for manual works.
Unit : 1 m3
Spec. cl. No: 1201
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.07 Skilled md 0.01 1476.00 14.76 Base agg. cu.m. 1.2000 3005.01 3606.01 Road Roller hr 0.0400 700.00 28.00
Unskilled md 1.50 1100.00 1650.00 Diesel lit 0.8800 97.00 85.36
Sub total of A = 1664.76 Sub total of B = 3691.37 Sub total of C = 28.00
Sub total of A +B + C = 5384.13 Contractor's overhead expenses 15% = 807.62 Unit Rate = 6191.75
Description of works: Providing, laying, spreading, watering, levelling and compaction of waterbound Macadam base course class D1* grading 1 or grading 2 lead upto 10m.
Unit : 1 m3
Spec. cl. No: 1203
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.10 Skilled md 0.0050 1476.00 7.38 Base agg. cu.m. 1.2000 3005.01 3606.01 Grader hr 0.0360 1200.00 43.20
Unskilled md 0.0200 1100.00 22.00 Diesel lit 1.1970 97.00 116.11 Vibrator Rolller hr 0.0360 400.00 14.40
Stone dust cu.m. 0.2660 0.00 0.00 Water Bowser hr 0.0500 550.00 27.50
Loader hr 0.0110 1200.00 13.20
Sub total of A = 29.38 Sub total of B = 3722.12 Sub total of C = 98.30
Sub total of A +B + C = 3849.80 Contractor's overhead expenses 15% = 577.47 Unit Rate = 4427.27
Description of works: Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing course class -1 / class -2 lead upto 10m.
Unit : 1 m3
Spec. cl. No: 1205
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.12 Skilled md 0.0050 1476.00 7.38 Aggregate cu.m. 1.2200 2355.01 2873.11 Grader hr 0.0360 1200.00 43.20
Unskilled md 0.0200 1100.00 22.00 Diesel lit 1.1970 97.00 116.11 Vibrator Rolller hr 0.0360 400.00 14.40
Water Bowser hr 0.0500 550.00 27.50
Loader hr 0.0110 1200.00 13.20
Sub total of A = 29.38 Sub total of B = 2989.22 Sub total of C = 98.30
Sub total of A +B + C = 3116.90 Contractor's overhead expenses 15% = 467.54 Unit Rate = 3584.44
Description of works: Providing, laying, spreading, watering, levelling and compaction of natural sand gravel wearing course class -1/class -2 lead upto 10m for manual works.
Unit : 1 m3
Spec. cl. No: 1205
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.13 Skilled md 0.0050 1476.00 7.38 Aggregate cu.m. 1.2200 2355.01 2873.11 Road Roller hr 0.0900 700.00 63.00
Unskilled md 1.5000 1100.00 1650.00 Diesel lit 1.9800 97.00 192.06
Sub total of A = 1657.38 Sub total of B = 3065.17 Sub total of C = 63.00
Sub total of A +B + C = 4785.55 Contractor's overhead expenses 15% = 717.83 Unit Rate = 5503.39
Description of works: Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc. before applying tack coat.
Unit : 1 lit.
Spec. cl. No: 1301,1302
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.01 Skilled md 0.0030 1476.00 4.43 Bitumen MC30/MC70 lit. 1.0500 78.30 82.21 Boiler hr 0.0025 180.00 0.45
Unskilled md 0.0460 1100.00 50.60 kerosene lit 0.1000 97.00 9.70 Sprayer hr 0.0025 260.00 0.65
Diesel lit 0.2750 97.00 26.68 Air compresser hr 0.0030 250.00 0.75
Sub total of A = 55.03 Sub total of B = 118.59 Sub total of C = 1.85
Sub total of A +B + C = 175.46 Contractor's overhead expenses 15% = 26.32 Unit Rate = 201.78
Item no:
Description of works: Fabricating, Providing, assembling and erecting Timber superstructure inlcuding necessary hardware for beam structure. (Falsework not included). Unit : 1 m3
Spec. cl. No:
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Sal wood (seasoned and
Unskilled md 15.00 m3 1.10 160558.36 176614.20 Tools and Plant 3 % of Labour Cost 1159.2
13-1-b 1100.00 16500.00 sawn)
Skilled md 15.00 1476.00 22140.00 Hardware 10% of timber cost 17661.42
Sub total of A = 38640.00 Sub total of B = 194275.62 Sub total of C = 1159.20
Sub total of A +B + C = 234074.82 Contractor's overhead expenses 15% = 35111.22 Unit Rate = 269186.04
Description of works: Providing and spraying bituminous tack coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc. before applying tack coat, using manual
methods. Unit : 1 lit.
Spec. cl. No: 1301,1302
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.02 Skilled md 0.0030 1476.00 4.43 Bitumen MC30/MC70 lit. 1.0500 78.30 82.21 Boiler hr 0.0140 180 2.52
Unskilled md 0.0620 1100.00 68.20 kerosene lit 0.1000 97.00 9.70 Hand Sprayer hr 0.0140 260.00 3.64
Sub total of A = 72.63 Sub total of B = 91.91 Sub total of C = 6.16
Sub total of A +B + C = 170.70 Contractor's overhead expenses 15% = 25.60 Unit Rate = 196.30
Rate per m2(1.16L/m2) 227.71
Description of works: Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc. before applying prime coat.
Unit : 1 lit.
Spec. cl. No: 1301,1302
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.03 Skilled md 0.0030 1476.00 4.43 Bitumen MC30/MC70 lit. 1.0500 78.30 82.21 Boiler hr 0.0025 180 0.45
Unskilled md 0.0460 1100.00 50.60 kerosene lit 0.1000 97.00 9.70 Sprayer hr 0.0025 260.00 0.65
Diesel lit 0.2750 97.00 26.68 Air compresser hr 0.0030 250.00 0.75
Sub total of A = 55.03 Sub total of B = 118.59 Sub total of C = 1.85
Sub total of A +B + C = 175.46 Contractor's overhead expenses 15% = 26.32 Unit Rate = 201.78
Description of works: Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc. before applying prime coat, using manual
methods. Unit : 1 lit.
Spec. cl. No: 1301,1302
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.04 Skilled md 0.0030 1476.00 4.43 Bitumen MC30/MC70 lit. 1.0500 78.30 82.21 Boiler hr 0.0140 180 2.52
Unskilled md 0.0460 1100.00 50.60 kerosene lit 0.1000 97.00 9.70 Hand Sprayer hr 0.0140 260.00 3.64
Sub total of A = 55.03 Sub total of B = 91.91 Sub total of C = 6.16
Sub total of A +B + C = 153.10 Contractor's overhead expenses 15% = 22.96 Unit Rate = 176.06
Rate per m2 ( 0.93 L per m2) 163.74
Description of works: Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or broken stone chips including compaction -- I) Bituminous binder for
surface dressing( mass work). Unit : 1 lit.
Spec. cl. No: 1301,1303
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.05.01 Skilled md 0.0020 1476.00 2.95 Bitumen 80/100open lit 1.0500 78.30 82.21 Boiler hr 0.0025 180 0.45
Unskilled md 0.0140 1100.00 15.40 Kerosene lit 0.1000 97.00 9.70 Distributor hr 0.0025 1300.00 3.25
Diesel lit 0.2700 97.00 26.19 Air compresser hr 0.0025 250.00 0.625
Sub total of A = 18.35 Sub total of B = 118.10 Sub total of C = 4.33
Sub total of A +B + C = 140.78 Contractor's overhead expenses 15% = 21.12 Unit Rate = 161.89
Description of works: Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or broken stone chips including compaction -- II) Cutter for bitumen
grade 80/100. Unit : 1 lit.
Spec. cl. No: 1301,1303
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Cutter (Diesel or
Skilled md 0.0010 1476.00 1.48 lit 1.00 97.00 97.00 Tools and Plants 3.00% Of L.C. 0.07728
13.05.03 kerosene)
Unskilled md 0.0010 1100.00 1.10
Sub total of A = 2.58 Sub total of B = 97.00 Sub total of C = 0.08
Sub total of A +B + C = 99.65 Contractor's overhead expenses 15% = 14.95 Unit Rate = 114.60
Description of works: Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or broken stone chips including compaction -- III) Chipping for surface
dressing for 1st coat size or second coat size. Unit : 1 mt..
Spec. cl. No: 1301,1303
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.05.04 Skilled md 0.0010 1476.00 1.48 Chips t 1.0500 1909.38 2004.85 Chips spreader hr 0.1000 300 30
Unskilled md 0.2100 1100.00 231.00 Diesel lit 3.6000 97 349.20 Tyred Roller hr 0.2000 1200 240
Sub total of A = 232.48 Sub total of B = 2354.05 Sub total of C = 270.00
Sub total of A +B + C = 2856.53 Contractor's overhead expenses 15% = 428.48 Unit Rate = 3285.01
Description of works: Laying of single / double / multiple bituminous coats for surface dressing using river gravels, shingles or broken stone chips including compaction -- IV) Production of
percorated chipping. Unit : 1 m3
Spec. cl. No: 1301,1303
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.05.05 Skilled md 0.0400 1476.00 59.04 Bitumen MC30 lit 14.0000 78.30 1096.15 Wheel Loader hr 0.1000 1200 120
Unskilled md 0.3000 1100.00 330.00 Kerosene lit 0.7000 97 67.90 Tractor hr 0.2000 300 60
Chips t 1.7300 1909.38125 3303.23 Boiler hr 0.0350 180 6.3
Sub total of A = 389.04 Sub total of B = 4467.28 Sub total of C = 186.30
Sub total of A +B + C = 5042.62 Contractor's overhead expenses 15% = 756.39 Unit Rate = 5799.01
Description of works: Providing and laying semi-grouting with compaction 50mm thickness.
Unit : 10 m2.
Spec. cl. No: 1301,1304
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.06.01 Skilled md 0.2100 1476.00 309.96 Bitumen lit 52.0000 78.30 4071.40 Boiler hr 0.0700 180 12.60
Unskilled md 1.8000 1100.00 1980.00 Kerosene lit 0.2500 97.00 24.25 Roller hr 0.0700 700.00 49.00
Diesel lit 2.5200 97.00 244.44 Sprayer hr 0.0700 260.00 18.20
Coarse agg. m3 0.6000 3055.01 1833.01 Agg. Spreader hr 0.0700 300.00 21.00
Key agg. m3 0.1500 3055.01 458.25
Sub total of A = 2289.96 Sub total of B = 6631.35 Sub total of C = 100.80
Sub total of A +B + C = 9022.11 Contractor's overhead expenses 15% = 1353.32 Rate (10m2) = 10375.42
Unit Rate(1 m2) = 1037.54
Description of works: Providing and laying semi-grouting with compaction 75mm thickness.
Unit : 10 m2.
Spec. cl. No: 1301,1304
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.06.02 Skilled md 0.21 1476.00 309.96 Bitumen lit 68.0000 78.30 5324.14 Boiler hr 0.0700 180 12.60
Unskilled md 2.45 1100.00 2695.00 Kerosene lit 0.4000 97.00 38.80 Roller hr 0.0700 700.00 49.00
Diesel lit 2.5200 97.00 244.44 Sprayer hr 0.0700 260.00 18.20
Coarse agg. m3 0.9000 3055.01 2749.51 Agg. Spreader hr 0.0700 300.00 21.00
Key agg. m3 0.1800 3055.01 549.90
Sub total of A = 3004.96 Sub total of B = 8906.79 Sub total of C = 100.80
Sub total of A +B + C = 12012.55 Contractor's overhead expenses 15% = 1801.88 Rate (10m2) = 13814.43
Unit Rate(1 m2) = 1381.44
Description of works: Providing and laying full grouting with compaction 50 mm thicknes.
Unit : 10 m2.
Spec. cl. No: 1301,1304
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.06.03 Skilled md 0.2100 1476.00 309.96 Bitumen lit 72.0000 78.30 5637.32 Boiler hr 0.0700 180 12.60
Unskilled md 1.8000 1100.00 1980.00 Kerosene lit 0.3500 97.00 33.95 Roller hr 0.0700 700.00 49.00
Diesel lit 2.5200 97.00 244.44 Sprayer hr 0.0700 260.00 18.20
Coarse agg. m3 0.6000 3055.01 1833.01 Agg. Spreader hr 0.0700 300.00 21.00
Key agg. m3 0.1500 3055.01 458.25
Sub total of A = 2289.96 Sub total of B = 8206.97 Sub total of C = 100.80
Sub total of A +B + C = 10597.73 Contractor's overhead expenses 15% = 1589.66 Rate (10m2) = 12187.39
Unit Rate(1 m2) = 1218.74
Description of works: Providing, mixing and laying slurry seal with fine slurry mix.
Unit : 100 m2.
Spec. cl. No: 1301,1306
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.08.01 Skilled md 0.20 1476.00 295.20 Aggregate m3 0.49 3055.01 1496.95 Mixer hr 0.07 470.00 32.90
Unskilled md 3.00 1100.00 3300.00 Emulsion lit 122.00 78.30 9552.13
Pneumatic Tyred Roller hr 0.55 1200.00 660.00
Cement Kg 8.30 0.00 0.00
water LS 0.00 Tools & Plant 3% of L.C. 107.856
Diesel lit 8.40 97.00
Sub total of A = 3595.20 Sub total of B = 11049.09 Sub total of C = 800.76
Sub total of A +B + C = 15445.04 Contractor's overhead expenses 15% = 2316.76 Rate (100 m2) = 17761.80
Unit Rate(1 m2) = 177.62
Description of works: Providing, mixing and laying slurry seal with normal slurry mix.
Unit : 100 m2.
Providing, mixing and laying slurry seal with normal slurry mix.
Unit : 100 m2.
Spec. cl. No: 1301,1306
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.08.02 Skilled md 0.20 1476.00 295.20 Aggregate m3 0.56 3055.01 1710.81 Mixer hr 0.080 470 37.60
Unskilled md 3.00 1100.00 3300.00 Emulsion lit 139.00 78.30 10883.16
Pneumatic Tyred Roller hr 0.550 1200.00 660.00
Cement Kg 9.40 0.00 0.00
water LS 0.00 Tools & Plant 3% of L.C. 107.856
Diesel lit 8.40 97.00
Sub total of A = 3595.20 Sub total of B = 12593.97 Sub total of C = 805.46
Sub total of A +B + C = 16994.63 Contractor's overhead expenses 15% = 2549.19 Rate (100 m2) = 19543.82
Unit Rate(1 m2) = 195.44
Description of works: Providing, mixing and laying slurry seal with coarse slurry mix.
Unit : 100 m2.
Spec. cl. No: 1301,1306
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13.08.03 Skilled md 0.20 1476.00 295.20 Aggregate m3 0.67 3055.0100 2046.86 Mixer hr 0.090 470 42.30
Unskilled md 3.00 1100.00 3300.00 Emulsion lit 167.00 78.30 13075.46
Pneumatic Tyred Roller hr 0.550 1200.00 660.00
Cement Kg 11.30 0.00 0.00
water LS 0.00 Tools & Plant 3% of L.C. 107.856
Diesel lit 8.40 97.00
Sub total of A = 3595.20 Sub total of B = 15122.31 Sub total of C = 810.16
Sub total of A +B + C = 19527.67 Contractor's overhead expenses 15% = 2929.15 Rate (100 m2) = 22456.82
Unit Rate(1 m2) = 224.57
Description of works: Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate, cement concrete, painting, writing and supporting steel angle nut and
bolit etc. complete a) 60cm. Dia. Circular, 60cm. equilateral traingle and 60cm.x 45cm. rectangular shaped sign (single post). Unit : 1 no.
Spec. cl. No: 1501
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.01.a Skilled md 0.033 1476.00 47.97 Enamel paint lit 0.100 440.00 44.00
Unskilled md 0.088 1100.00 96.80 M10/40 PCC m3 0.030 14771.41 443.14
Steel plate m2 0.250 1852.00 463.00
Formwork (F1) m2 0.360 0.00 0.00
Steel tube m 2.500 743.00 1857.50
Sub total of A = 144.77 Sub total of B = 2807.64 Sub total of C = 0.00
Sub total of A +B + C = 2952.41 Contractor's overhead expenses 15% = 442.86 Unit Rate = 3395.27
Description of works:
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate, cement concrete, painting, writing and supporting steel angle nut and
bolit etc. complete b) 1.2m.x 0.75m. Size bigger traffic sign with back support and two or more post. Unit : 1 no.
Spec. cl. No: 1501
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.01.b Skilled md 0.085 1476.00 125.46 Enamel paint lit 0.400 440.00 176.00
Unskilled md 0.300 1100.00 330.00 M10/40 PCC m3 0.120 14771.41 1772.57
Steel plate m2 1.00 1852.00 1852.00
Formwork (F1) m2 1.00 0.00 0.00
Steel tube m 5.00 743.00 3715.00
Sub total of A = 455.46 Sub total of B = 7515.57 Sub total of C = 0.00
Sub total of A +B + C = 7971.03 Contractor's overhead expenses 15% = 1195.65 Unit Rate = 9166.68
Description of works: Supplying and applying paint for Road marking including cleaning, watering, brooming etc. all complete (10cm. wide strip) a) Two coats over old painted
surface Unit : 1 m.
Spec. cl. No: 1502
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.02.a Skilled md 0.003 1476.00 4.43 Road Marking paint lit 0.042 0.00 0.00
Unskilled md 0.005 1100.00 5.50
Sub total of A = 9.93 Sub total of B = 0.00 Sub total of C = 0.00
Sub total of A +B + C = 9.93 Contractor's overhead expenses 15% = 1.49 Unit Rate = 11.42
Rate per m2 238.20
Description of works: Supplying and applying paint for Road marking including cleaning, watering, brooming etc. all complete (10cm. wide strip) b) More than two coats over new bitumin
surface Unit : 1 m
Spec. cl. No: 1502
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.02.b Skilled md 0.005 1476.00 7.38 Road Marking paint lit 0.075 0.00 0.00
Unskilled md 0.007 1100.00 7.70
Sub total of A = 15.08 Sub total of B = 0.00 Sub total of C = 0.00
Sub total of A +B + C = 15.08 Contractor's overhead expenses 15% = 2.26 Unit Rate = 17.34
Description of works: Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing etc. all complete as per specification a) Standard KM post placed at
each kilometer. Unit : 1 no.
Spec. cl. No: 1503
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.03.a Skilled md 0.030 1476.00 44.28 M15/40 RCC m3 0.060 4588.00 275.28
Unskilled md 0.116 1100.00 127.60 M10/40 PCC m3 0.090 14771.41 1329.43
Formwork (F3) m2 0.500 1102.34 551.17
Enamel paint lit 0.120 440.00 52.80
Reinforcement bar kg 7.500 94.99 712.45
Sub total of A = 171.88 Sub total of B = 2921.13 Sub total of C = 0.00
Sub total of A +B + C = 3093.01 Contractor's overhead expenses 15% = 463.95 Unit Rate = 3556.96
Description of works: Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing etc. all complete as per specification b) Bigger kilometer post (placed at
each 5 km.) Unit : 1 no.
Spec. cl. No: 1503
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.03.b Skilled md 0.080 1476.00 118.08 M15/40 RCC m3 0.170 4588.00 779.96
Unskilled md 0.300 1100.00 330.00 M10/40 PCC m3 0.230 14771.41 3397.43
Formwork (F3) m2 1.300 1102.34 1433.04
Enamel paint lit 0.400 440.00 176.00
Reinforcement bar kg 8.600 94.99 816.95
Sub total of A = 448.08 Sub total of B = 6603.37 Sub total of C = 0.00
Sub total of A +B + C = 7051.45 Contractor's overhead expenses 15% = 1057.72 Unit Rate = 8109.17
Description of works: Supplying and fixing in place R.C.C. delineator and guard post including excavation, back filling, painting and erection etc. all complete as per drawing.
Unit : 1 no.
Spec. cl. No: 1504
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.04 Skilled md 0.021 1476.00 31.00 M20/20 RCC m3 0.030 8933.72 268.01
Unskilled md 0.055 1100.00 60.50 Formwork (F3) m2 0.540 1102.34 595.26
Enamel paint lit 0.180 440.00 79.20
Reinforcement bar kg 2.82 94.99 267.88
Sub total of A = 91.50 Sub total of B = 1210.36 Sub total of C = 0.00
Sub total of A +B + C = 1301.85 Contractor's overhead expenses 15% = 195.28 Unit Rate = 1497.13
Description of works: Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings using timber ( soft wood) - Class F1
finish. Unit : 10 m2
Spec. cl. No: 1804,1805
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
18.01 Skilled md 1.50 1476.00 2214.00 Planks 38mm thick. m3 0.42 0.00
Unskilled md 2.00 1100.00 2200.00 struts, ballies, etc. m3 0.18 0.00
Nails,spikes,etc. kg 1.00 110.00 110.00
Sub total of A = 4414.00 Sub total of B = 110.00 Sub total of C = 0.00
Sub total of A +B + C = 4524.00 Contractor's overhead expenses 15% = 678.60 Rate (10 m2) = 5202.60
Unit Rate (1 m2) = 520.26
Description of works: Providing , Preparing and Installing form work & removing after completion for Precast elements of square / rectangular section using timber (soft wood) -- Class F3 finish.
Unit : 10 m2
Spec. cl. No: 1804,1805
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
18.07,ia Skilled md 2.50 1476.00 3690.00 Ply wood 9mm. thick m2 11 55.76 613.38
Unskilled md 2.00 1100.00 2200.00 timber m3 0.2 21500.00 4300.00
Nails kg 2 110.00 220.00
Sub total of A = 5890.00 Sub total of B = 5133.38 Sub total of C = 0.00
Sub total of A +B + C = 11023.38 Contractor's overhead expenses 15% = 1653.51 Rate (10 m2) = 12676.89
Unit Rate = 1267.69
Description of works: Providing and placing machine mixed M10/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.1 Skilled md 0.50 1476.00 738.00 cement mt 0.220 19412.36 4270.72 mixer (0.28/ 0.20 m3 ) hr 0.60 1309.73 785.84
Unskilled md 3.50 1100.00 3850.00 aggregate 20-40mm m 3
0.650 3300.00 2145.00 vibrator hr 0.25 800.00 200.00
aggregate 10 -20mm m3 0.250 3300.00 825.00 of Cost of
Mix Design and Quality Control 2.50% 360.28
coarse sand m3 0.480 2700.00 1296.00 concrete
petrol lit 0.100 96.59 9.66
diesel lit 3.000 85.97 257.92
water lit 132.000 0.25 33.00
Sub total of A = 4588.00 Sub total of B = 8837.30 Sub total of C = 1346.12
Sub total of A +B + C = 14771.41 Contractor's overhead expenses 15% = 2215.71 Unit Rate = 16987.13
Description of works: Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.2 Skilled md 0.50 1476.00 738.00 cement mt 0.260 0.00 0.00 mixer (0.28/ 0.20 m3 ) hr 0.60 470 282.00
Unskilled md 3.50 1100.00 3850.00 aggregate 20-40mm m3 0.530 3055.01 1619.16 vibrator hr 0.25 100 25.00
aggregate 10-20mm m3 0.240 3055.01 733.20
of Cost of
Mix Design and Quality Control 2.50% 218.60
aggregate 10mm & down m 3
0.110 concrete
3055.01 336.05
coarse sand m3 0.460 1803.47 829.60
petrol lit 0.100 110.00 11.00
diesel lit 3.000 97.00 291.00
water lit 156.000 0.19 29.06
Sub total of A = 4588.00 Sub total of B = 3849.07 Sub total of C = 525.60
Sub total of A +B + C = 8962.67 Contractor's overhead expenses 15% = 1344.40 Unit Rate = 10307.07
Description of works: Providing and placing machine mixed M20/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.3 Skilled md 0.50 1476.00 738.00 cement mt 0.320 0.00 0.00 mixer (0.28/ 0.20 m3 ) hr 0.60 470 282.00
Unskilled md 3.50 1100.00 3850.00 aggregate 20-40mm m 3
0.520 3055.01 1588.61 vibrator hr 0.25 260 65.00
aggregate 10-20mm m3 0.220 3055.01 672.10
of Cost of
Mix Design and Quality Control 2.50% 217.79
aggregate 10mm & down m3 0.120 3055.01 366.60 concrete
Description of works: Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.4 Skilled md 0.50 1476.00 738.00 cement mt 0.330 0.00 0.00 mixer (0.28/ 0.20 m3 ) hr 0.60 470 282.00
Unskilled md 3.50 1100.00 3850.00 aggregate 20-40mm m3 0.580 3055.01 1771.91 vibrator hr 0.25 100 25.00
aggregate 10 -20mm m3 0.300 3055.01 916.50 of Cost of
Mix Design and Quality Control 2.50% 217.90
coarse sand m3 0.440 1803.47 793.53 concrete
petrol lit 0.100 110.00 11.00
diesel lit 3.000 97.00 291.00
water lit 198.000 0.19 36.89
Sub total of A = 4588.00 Sub total of B = 3820.82 Sub total of C = 524.90
Sub total of A +B + C = 8933.72 Contractor's overhead expenses 15% = 1340.06 Unit Rate = 10273.78
Description of works: Providing and placing machine mixed M25/20 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.5 Skilled md 0.50 1476.00 738.00 cement mt 0.375 0.00 0.00 mixer (0.28/ 0.20 m3 ) hr 0.60 470 282.00
Unskilled md 3.50 1100.00 3850.00 aggregate 20-40mm m 3
0.580 3055.01 1771.91 vibrator hr 0.25 100 25.00
aggregate 10 -20mm m3 0.300 3055.01 916.50 of Cost of
Mix Design and Quality Control 2.50% 218.47
coarse sand m3 0.450 1803.47 811.56 concrete
petrol lit 0.100 110.00 11.00
diesel lit 3.000 97.00 291.00
water lit 225.000 0.19 41.92
Sub total of A = 4588.00 Sub total of B = 3843.89 Sub total of C = 525.47
Sub total of A +B + C = 8957.36 Contractor's overhead expenses 15% = 1343.60 Unit Rate = 10300.96
Description of works: Providing and placing manually mixed M10/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification
and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.b.1 Skilled md 1.00 1476.00 1476.00 cement mt 0.245 0.00 0.00 of Cost of
Mix Design and Quality Control 2.50% 237.9640175
Unskilled md 4.00 1100.00 4400.00 aggregate 20-40mm m3 0.650 3055.01 1985.76 concrete
aggregate 10 -20mm m3 0.250 3055.01 763.75
coarse sand m3 0.480 1803.47 865.67
water lit 147.000 0.19 27.39
Sub total of A = 5876.00 Sub total of B = 3642.56 Sub total of C = 237.96
Sub total of A +B + C = 9756.52 Contractor's overhead expenses 15% = 1463.48 Unit Rate = 11220.00
Description of works: Providing and placing manually mixed M15/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification
and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.b.2 Skilled md 1.00 1476.00 1476.00 cement t 0.285 0.00 0.00 of Cost of
Mix Design and Quality Control 2.50% 235.65
Unskilled md 4.00 1100.00 4400.00 aggregate 20-40mm m3 0.530 3055.01 1619.16 concrete
aggregate 10-20mm m3 0.240 3055.01 733.20
Description of works: Providing and placing manually mixed M20/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification
and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.b.3 Skilled md 1.00 1476.00 1476.00 cement t 0.355 0.00 0.00 of Cost of
Mix Design and Quality Control 2.50% 233.86
Unskilled md 4.00 1100.00 4400.00 aggregate 20-40mm m3 0.520 3055.01 1588.61 concrete
aggregate 10-20mm m 3
0.220 3055.01 672.10
Description of works: Providing and placing manually mixed M25/20 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification
and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.b.5 Skilled md 1.00 1476.00 1476.00 cement mt 0.415 0.00 0.00 of Cost of
Mix Design and Quality Control 2.50% 235.11
Unskilled md 4.00 1100.00 4400.00 aggregate 10-20 mm m3 0.580 3055.01 1771.91 concrete
aggregate 10 mm and
m3 0.300 3055.01 916.50
down
coarse sand m3 0.440 1803.47 793.53
water lit 249.000 0.19 46.39
Sub total of A = 5876.00 Sub total of B = 3528.32 Sub total of C = 235.11
Sub total of A +B + C = 9639.43 Contractor's overhead expenses 15% = 1445.91 Unit Rate = 11085.35
Description of works: Providing and placing manually mixed non structural cement concrete [ cement (1): sand (4) : aggregate (8) ] including compaction, curing, testing and lead 30m. etc. all complete
as per specification and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.06.b.1 Skilled md 1.00 1476.00 1476.00 cement t 0.190 0.00 0.00 of Cost of
Mix Design and Quality Control 0.50% 47.32
Unskilled md 4.00 1100.00 4400.00 aggregate 20-40mm m3 0.650 3055.01 1985.76 concrete
aggregate 10 -20mm m3 0.240 3055.01 733.20
sand m3 0.470 1803.47 847.63
water lit 114.000 0.19 21.24
Sub total of A = 5876.00 Sub total of B = 3587.83 Sub total of C = 47.32
Sub total of A +B + C = 9511.15 Contractor's overhead expenses 15% = 1426.67 Unit Rate = 10937.82
Description of works: Providing and placing manually mixed non structural cement concrete [ cement (1): sand (3) : aggregate (6) ] including compaction, curing, testing and lead 30m. etc. all complete
as per specification and drawing. Unit : 1 m3
Description of works: Providing and placing manually mixed non structural cement concrete [ cement (1): sand (3) : aggregate (6) ] including compaction, curing, testing and lead 30m. etc. all complete
as per specification and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.06.b.2 Skilled md 1.00 1476.00 1476.00 cement t 0.240 0.00 0.00 of Cost of
Mix Design and Quality Control 0.50% 47.35
Unskilled md 4.00 1100.00 4400.00 aggregate 20-40mm m3 0.650 3055.01 1985.76 concrete
aggregate 10 -20mm m3 0.240 3055.01 733.20
sand m3 0.470 1803.47 847.63
water lit 144.000 0.19 26.83
Sub total of A = 5876.00 Sub total of B = 3593.42 Sub total of C = 47.35
Sub total of A +B + C = 9516.76 Contractor's overhead expenses 15% = 1427.51 Unit Rate = 10944.28
Description of works: Providing and placing manually mixed non structural cement concrete [ cement (1): sand (2) : aggregate (4) ] including compaction, curing, testing and lead 30m. etc. all complete
as per specification and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.06.b.3 Skilled md 1.00 1476.00 1476.00 cement t 0.350 0.00 0.00 of Cost of
Mix Design and Quality Control 0.50% 46.62
Unskilled md 4.00 1100.00 4400.00 aggregate 20-40mm m3 0.520 3055.01 1588.61 concrete
aggregate 10 -20mm m3 0.330 3055.01 1008.15
sand m3 0.450 1803.47 811.56
water lit 210.000 0.19 39.12
Sub total of A = 5876.00 Sub total of B = 3447.44 Sub total of C = 46.62
Sub total of A +B + C = 9370.06 Contractor's overhead expenses 15% = 1405.51 Unit Rate = 10775.57
Description of works: Providing and laying Reinforcement ( diameter upto 8 mm) including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Unit : 1 mt.
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.07.1 Skilled md 15.00 1476.00 22140.00 Reinforcement t 1.150 94993.78 109242.85
Unskilled md 15.00 1100.00 16500.00 Binding wire kg 12.000 126.99 1523.93
Sub total of A = 38640.00 Sub total of B = 110766.77 Sub total of C = 0.00
Sub total of A +B + C = 149406.77 Contractor's overhead expenses 15% = 22411.02 Unit Rate = 171817.79
Description of works: Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification
and drawing. Unit : 1 mt.
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.07.2 Skilled md 12.00 1476.00 17712.00 Reinforcement t 1.150 94993.78 109242.85
Unskilled md 12.00 1100.00 13200.00 Binding wire kg 10.000 126.99 1269.94
Sub total of A = 30912.00 Sub total of B = 110512.78 Sub total of C = 0.00
Sub total of A +B + C = 141424.78 Contractor's overhead expenses 15% = 21213.72 Unit Rate = 162638.50
Description of works: Providing and laying Reinforcement ( diameter above 16 mm) including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Unit : 1 mt.
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.07.3 Skilled md 9.00 1476.00 13284.00 Reinforcement t 1.150 94993.78 109242.85
Unskilled md 9.00 1100.00 9900.00 Binding wire kg 9.000 126.99 1142.94
Sub total of A = 23184.00 Sub total of B = 110385.79 Sub total of C = 0.00
Sub total of A +B + C = 133569.79 Contractor's overhead expenses 15% = 20035.47 Unit Rate = 153605.26
Description of works: Fabrication of [ 3 x 1 x 1 : (16 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including rolling,
cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.1 Skilled md 0.50 1476.00 738.00 Mesh wire Kg 35.10 96.99 3404.48
Unskilled md 0.22 1100.00 242.00 selvedge wire Kg 4.51 96.99 437.44
Sub total of A = 980.00 Sub total of B = 3841.92 Sub total of C = 0.00
Sub total of A +B + C = 4821.92 Contractor's overhead expenses 15% = 723.29 Unit Rate = 5545.21
Description of works: Fabrication of [ 2 x 1 x 1 : (11 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including rolling,
cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.2 Skilled md 0.34 1476.00 501.84 Mesh wire Kg 24.15 96.99 2342.40
Unskilled md 0.15 1100.00 165.00 selvedge wire Kg 3.41 96.99 330.75
Sub total of A = 666.84 Sub total of B = 2673.15 Sub total of C = 0.00
Sub total of A +B + C = 3339.99 Contractor's overhead expenses 15% = 501.00 Unit Rate = 3840.99
Description of works: Fabrication of [ 1.5 x 1 x 1 : (9 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.3 Skilled md 0.28 1476.00 413.28 Mesh wire Kg 19.75 96.99 1915.63
Unskilled md 0.12 1100.00 132.00 selvedge wire Kg 3.11 96.99 301.65
Sub total of A = 545.28 Sub total of B = 2217.28 Sub total of C = 0.00
Sub total of A +B + C = 2762.56 Contractor's overhead expenses 15% = 414.38 Unit Rate = 3176.94
Description of works: Fabrication of [ 1 x 1 x 1 : (6 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including rolling,
cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.4 Skilled md 0.19 1476.00 280.44 Mesh wire Kg 13.16 96.99 1276.44
Unskilled md 0.08 1100.00 88.00 selvedge wire Kg 2.32 96.99 225.03
Sub total of A = 368.44 Sub total of B = 1501.46 Sub total of C = 0.00
Sub total of A +B + C = 1869.90 Contractor's overhead expenses 15% = 280.49 Unit Rate = 2150.39
3678.38
Description of works: Fabrication of [ 3 x 1 x 0.75 : (13.5 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.5 Skilled md 0.42 1476.00 619.92 Mesh wire Kg 29.62 96.99 2872.96
Unskilled md 0.19 1100.00 209.00 selvedge wire Kg 4.14 96.99 401.55
Sub total of A = 828.92 Sub total of B = 3274.51 Sub total of C = 0.00
Sub total of A +B + C = 4103.43 Contractor's overhead expenses 15% = 615.51 Unit Rate = 4718.94
Description of works: Fabrication of [ 2 x 1 x 0.75 : (9.25 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.6 Skilled md 0.29 1476.00 428.04 Mesh wire Kg 20.29 96.99 1968.00
Unskilled md 0.13 1100.00 143.00 selvedge wire Kg 3.11 96.99 301.65
Sub total of A = 571.04 Sub total of B = 2269.65 Sub total of C = 0.00
Sub total of A +B + C = 2840.69 Contractor's overhead expenses 15% = 426.10 Unit Rate = 3266.80
Description of works: Fabrication of [ 1 x 1 x 0.75 : (5 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.7 Skilled md 0.16 1476.00 236.16 Mesh wire Kg 10.97 96.99 1064.02
Unskilled md 0.07 1100.00 77.00 selvedge wire Kg 2.07 96.99 200.78
Sub total of A = 313.16 Sub total of B = 1264.80 Sub total of C = 0.00
Sub total of A +B + C = 1577.96 Contractor's overhead expenses 15% = 236.69 Unit Rate = 1814.65
Description of works: Fabrication of [ 3 x 1 x 0.5 : (11 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.8 Skilled md 0.34 1476.00 501.84 Mesh wire Kg 24.15 96.99 2342.40
Unskilled md 0.15 1100.00 165.00 selvedge wire Kg 3.78 96.99 366.64
Sub total of A = 666.84 Sub total of B = 2709.04 Sub total of C = 0.00
Sub total of A +B + C = 3375.88 Contractor's overhead expenses 15% = 506.38 Unit Rate = 3882.26
Description of works: Fabrication of [ 2 x 1 x 0.5 : (7.5 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.9 Skilled md 0.23 1476.00 339.48 Mesh wire Kg 16.45 96.99 1595.55
Unskilled md 0.10 1100.00 110.00 selvedge wire Kg 2.80 96.99 271.58
Sub total of A = 449.48 Sub total of B = 1867.13 Sub total of C = 0.00
Sub total of A +B + C = 2316.61 Contractor's overhead expenses 15% = 347.49 Unit Rate = 2664.10
Description of works: Fabrication of [ 1 x 1 x 0.5 : (4 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.10 Skilled md 0.12 1476.00 177.12 Mesh wire Kg 8.78 96.99 851.61
Unskilled md 0.06 1100.00 66.00 selvedge wire Kg 1.83 96.99 177.50
Sub total of A = 243.12 Sub total of B = 1029.10 Sub total of C = 0.00
Sub total of A +B + C = 1272.22 Contractor's overhead expenses 15% = 190.83 Unit Rate = 1463.06
Description of works: Fabrication of [ 3 x 1 x 0.3 : (9 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.11 Skilled md 0.28 1476.00 413.28 Mesh wire Kg 19.75 96.99 1915.63
Unskilled md 0.12 1100.00 132.00 selvedge wire Kg 3.49 96.99 338.51
Sub total of A = 545.28 Sub total of B = 2254.14 Sub total of C = 0.00
Sub total of A +B + C = 2799.42 Contractor's overhead expenses 15% = 419.91 Unit Rate = 3219.33
Description of works: Fabrication of [ 2 x 1 x 0.3 : (6.1 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.12 Skilled md 0.19 1476.00 280.44 Mesh wire Kg 13.40 96.99 1299.72
Unskilled md 0.08 1100.00 88.00 selvedge wire Kg 2.56 96.99 248.30
Sub total of A = 368.44 Sub total of B = 1548.02 Sub total of C = 0.00
Sub total of A +B + C = 1916.46 Contractor's overhead expenses 15% = 287.47 Unit Rate = 2203.93
Description of works: Fabrication of [ 1 x 1 x 0.3 : ( 2.2 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with mesh wire 10 swg and selvedged wire 7 swg , including
rolling, cutting and weaving as per specification. Unit : 1 box
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.01.02.13 Skilled md 0.07 1476.00 103.32 Mesh wire Kg 4.83 96.99 468.48
Unskilled md 0.03 1100.00 33.00 selvedge wire Kg 1.63 96.99 158.10
Sub total of A = 136.32 Sub total of B = 626.58 Sub total of C = 0.00
Sub total of A +B + C = 762.90 Contractor's overhead expenses 15% = 114.43 Unit Rate = 877.33
Description of works:
Fabrication of [ 3 x 1 x 1 : (16 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with binding wire 12 swg, mesh wire 10
swg and selvedged wire 7 swg , including rolling, cutting and weaving ; assembling Gabion boxes mattresses, palcing in position including stretching, forming
compartments; tying with bracing wires and tie wires; tying down the lid complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including Unit : 1 box
dressing, beding, bonding and all transporation as per specification.
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.02.01 Unskilled md 1.04 1100.00 1144.00 GI wire 12 swg Kg 1.81 97.99 177.37
Fabrication of box ( Item
box 1.00 4821.92 4821.92
no. 24.01.02.1)
Filing Stone (Item no
m3 3.00 3019.55 9058.65
24.02.04 )
Sub total of A = 1144.00 Sub total of B = 14057.94 Sub total of C = 0.00
Sub total of A +B + C = 15201.94 Contractor's overhead expenses 15% = 2280.29 Unit Rate = 17482.23
Description of works:
Fabrication of [ 2 x 1 x 1 : (11 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with binding wire 12 swg, mesh wire 10
swg and selvedged wire 7 swg , including rolling, cutting and weaving ; assembling Gabion boxes mattresses , palcing in position including stretching, forming
compartments; tying with bracing wires and tie wires; tying down the lid complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including Unit : 1 box
Spec. cl. No: 2401 dressing, beding, bonding and all transporation as per specification.
Description of works:
Fabrication of [ 1 x 1 x 1 : (6 sq. m)] hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg
and selvedged wire 7 swg , including rolling, cutting and weaving ; assembling Gabion boxes mattresses , palcing in position including stretching, forming compartments;
tying with bracing wires and tie wires; and tying down the lid complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, Unit : 1 box
Spec. cl. No: 2401 beding, bonding and all transporation as per specification.
Description of works: Providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all transporation as per specification.
Unit : 1 m3
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.02.05 Skilled md 0.25 1476.00 369.00 Block Stone m3 1.00 1627.05 1627.05 Quality Control 2% of M.C. 35.80
Unskilled md 0.75 1100.00 825.00 Bond Stone m3 0.1 1627.05 162.71
Sub total of A = 1194.00 Sub total of B = 1789.76 Sub total of C = 35.80
Sub total of A +B + C = 3019.55 Contractor's overhead expenses 15% = 452.93 Unit Rate = 3472.48
Description of works: Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification Lead 30m, lift 1.5m , using concrete mixer and vibrator.
Unit : 1 m3
Description of works: Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification Lead 30m, lift 1.5m , using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.14.01.a Skilled md 0.30 1476.00 442.80 cement t 0.169 0.00 0.00 Concrete mixer ( 0.28 / 0.20 m3 ) hr. 0.50 470 235.00
Unskilled md 3.00 1100.00 3300.00 Aggregates 20-40(mm) m3 0.345 3055.01 1053.98 Concrete vibrator hr. 0.10 100 10.00
Aggregates 10-20 (mm) m3 0.156 3055.01 476.58
Aggregates 5-10(mm) m3 0.072 3055.01 219.96
sand m 3
0.299 1803.47 539.24
petrol lit 0.100 110.00 11.00
diesel lit 3.000 97.00 291.00
Boulder/Stone m3 0.440 1627.05 715.90
Sub total of A = 3742.80 Sub total of B = 3307.66 Sub total of C = 245.00
Sub total of A +B + C = 7295.46 Contractor's overhead expenses 15% = 1094.32 Unit Rate = 8389.78
Description of works: Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.14.01.b Skilled md 0.30 1476.00 442.80 cement t 0.185 0.00 0.00
Unskilled md 4.00 1100.00 4400.00 Aggregates 20-40(mm) m3 0.156 3055.01 476.58
Aggregates 10-20 (mm) m3 0.072 3055.01 219.96
Aggregates 5-10(mm) m3 0.299 3055.01 913.45
sand m3 0.299 1803.47 539.24
Boulder/Stone m 3
0.440 1627.05 715.90
Sub total of A = 4842.80 Sub total of B = 2865.13 Sub total of C = 0.00
Sub total of A +B + C = 7707.93 Contractor's overhead expenses 15% = 1156.19 Unit Rate = 8864.12
Description of works: Providing and placing plum-concrete with 70% M 15/40 concrete and 30% boulders/stones as per specification. Lead 30m, lift 1.5m using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.14.02.a Skilled md 0.30 1476.00 442.80 cement t 0.195 0.00 0.00 Concrete mixer ( 0.28 / 0.20 m3 ) hr. 0.50 470 235.00
Unskilled md 3.00 1100.00 3300.00 Aggregates 20-40(mm) m3 0.398 3055.01 1215.89 Concrete vibrator hr. 0.10 100 10.00
Aggregates 10-20 (mm) m3 0.180 3055.01 549.90
Aggregates 5-10(mm) m3 0.082 3055.01 250.51
sand m3 0.345 1803.47 622.20
petrol lit 0.100 110.00 11.00
diesel lit 3.000 97.00 291.00
Boulder/Stone m3 0.330 1627.05 536.93
Sub total of A = 3742.80 Sub total of B = 3477.43 Sub total of C = 245.00
Sub total of A +B + C = 7465.23 Contractor's overhead expenses 15% = 1119.78 Unit Rate = 8585.01
Description of works: Providing and placing concrete with 70% M 15/40 concrete and 30% boulders/stones as per specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.14.02.b Skilled md 0.30 1476.00 442.80 cement t 0.214 0.00 0.00
Unskilled md 4.00 1100.00 4400.00 Aggregates 20-40(mm) m3 0.398 3055.01 1215.89
Aggregates 10-20 (mm) m3 0.180 3055.01 549.90
Aggregates 5-10(mm) m3 0.082 3055.01 250.51
sand m3 0.345 1803.47 622.20
Boulder/Stone m3 0.330 1627.05 536.93
Sub total of A = 4842.80 Sub total of B = 3175.43 Sub total of C = 0.00
Sub total of A +B + C = 8018.23 Contractor's overhead expenses 15% = 1202.73 Unit Rate = 9220.96
Description of works: Providing and laying dry stone masonry (coursed rubble) including dressing etc. complete as per specification, lead 30m.
Spec. cl. No: Unit : 1 m3
2602,2603,2608
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.01 Skilled md 1.25 1476.00 1845.00 Stone m3 1.15 1627.05 1871.11 Tools & Plant 3% of L.C. 121.35
Unskilled md 2.00 1100.00 2200.00
Sub total of A = 4045.00 Sub total of B = 1871.11 Sub total of C = 121.35
Sub total of A +B + C = 6037.46 Contractor's overhead expenses 15% = 905.62 Unit Rate = 6943.08
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc. complete, masoned
height 0-5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No:
2602,2603,2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.03.a Skilled md 1.50 1476.00 2214.00 Diesel lit 1.000 97.00 97.00 Concrete mixer (0.28/0.2 m3) hr. 0.15 470 70.50
Unskilled md 3.50 1100.00 3850.00 Cement t 0.190 0 0.00 Tools & Plant 3% of L.C. 181.92
Sand m3 0.400 1803.47 721.39 Quality Control 1.50% of T.C. 135.42
Stone m3 1.150 1627.05 1871.11
water lit 120.000 0.1863 22.36
Sub total of A = 6064.00 Sub total of B = 2711.85 Sub total of C = 387.84
Sub total of A +B + C = 9163.70 Contractor's overhead expenses 15% = 1374.55 Unit Rate = 10538.25
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc. complete, masoned
height 0-5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No:
2602,2603,2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.03.b Skilled md 1.50 1476.00 2214.00 Cement t 0.155 0.00 0.00 Concrete mixer (0.28/0.2 m3) hr. 0.15 470 70.50
Unskilled md 3.50 1100.00 3850.00 Sand m3 0.450 1803.47 811.56 Tools & Plant 3% of L.C. 181.92
Stone m3 1.150 1627.05 1871.11 Quality Control 1.50% of T.C. 136.72
Diesel lit 1.000 97 97.00
water lit 100.00 0.1863 18.63
Sub total of A = 6064.00 Sub total of B = 2798.30 Sub total of C = 389.14
Sub total of A +B + C = 9251.44 Contractor's overhead expenses 15% = 1387.72 Unit Rate = 10639.16
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc. complete, masoned
height 0-5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No:
2602,2603,2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.03.c Skilled md 1.50 1476.00 2214.00 Cement t 0.105 0.00 0.00 Concrete mixer (0.28/0.2 m3) hr. 0.15 470 70.50
Unskilled md 3.50 1100.00 3850.00 Sand m3 0.500 1803.47 901.74 Tools & Plant 3% of L.C. 181.92
Stone m3 1.150 1627.05 1871.11 Quality Control 1.50% of T.C. 137.9895525
Diesel lit 1.000 97 97.00
water lit 70.000 0.1863 13.04
Sub total of A = 6064.00 Sub total of B = 2882.88 Sub total of C = 390.41
Sub total of A +B + C = 9337.29 Contractor's overhead expenses 15% = 1400.59 Unit Rate = 10737.89
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation of mortar etc. complete, masoned
height 0-5m, lead 30m (manual mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.04.a Skilled md 1.50 1476.00 2214.00 Cement t 0.190 0.00 0.00 Tools & Plant 3% of L.C. 214.92
Unskilled md 4.50 1100.00 4950.00 Sand m3 0.400 1803.47 721.39 Quality Control 1.50% of T.C. 149.91
Stone m3 1.150 1627.05 1871.11
water lit 120.000 0.1863 22.36
Sub total of A = 7164.00 Sub total of B = 2614.85 Sub total of C = 364.83
Sub total of A +B + C = 10143.68 Contractor's overhead expenses 15% = 1521.55 Unit Rate = 11665.23
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc. complete, masoned
height 0-5m, lead 30m (manual mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.04.b Skilled md 1.50 1476.00 2214.00 Cement t 0.155 0.00 0.00 Tools & Plant 3% of L.C. 214.92
Unskilled md 4.50 1100.00 4950.00 Sand m3 0.450 1803.47 811.56 Quality Control 1.50% of T.C. 151.20
Stone m3 1.150 1627.05 1871.11
water lit 100.000 0.1863 18.63
Sub total of A = 7164.00 Sub total of B = 2701.30 Sub total of C = 366.12
Sub total of A +B + C = 10231.42 Contractor's overhead expenses 15% = 1534.71 Unit Rate = 11766.14
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(6)] including scaffolding, curing, preparation of mortar etc. complete, masoned
height 0-5m, lead 30m (manual mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2607
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.04.c Skilled md 1.50 1476.00 2214.00 Cement t 0.105 0.00 0.00 Tools & Plant 3% of L.C. 214.92
Unskilled md 4.50 1100.00 4950.00 Sand m3 0.500 1803.47 901.74 Quality Control 1.50% of T.C. 152.47
Stone m3 1.150 1627.05 1871.11
water lit 70.000 0.1863 13.04
Sub total of A = 7164.00 Sub total of B = 2785.88 Sub total of C = 367.39
Sub total of A +B + C = 10317.28 Contractor's overhead expenses 15% = 1547.59 Unit Rate = 11864.87
Description of works: Removal of old paints by sand blasting, cleaning and repairing of metal surfaces for the application of new paints as per specification.
Unit : 1 m2
Spec. cl. No: 2713
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
27.07 Skilled md 0.12 1476.00 177.12 Diesel lit 4.0 97.00 388.00 Air compressor hr. 0.32 250 84.8384
Sand (1.6 mm to 600 m3
Unskilled md 0.08 1100.00 88.00 0.04 1803.47 72.14 Blasting machine hr. 0.32 0 0
micro mm)
Scaffolding 10.00% of T.C. 81.01
Sub total of A = 265.12 Sub total of B = 460.14 Sub total of C = 165.85
Sub total of A +B + C = 891.11 Contractor's overhead expenses 15% = 133.67 Unit Rate = 1024.77
Description of works: Maintenance of earthen shoulders by making irregularities even to the required level including watering and compaction etc. all complete lead 10m.
Unit : 1 m2
Spec. cl. No: 2903
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
29.02 Skilled md 0.02 1476.00 29.52 Tools 3.00% of L.C. 7.49
Unskilled md 0.20 1100.00 220.00
Sub total of A = 249.52 Sub total of B = 0.00 Sub total of C = 7.49
Sub total of A +B + C = 257.01 Contractor's overhead expenses 15% = 38.55 Unit Rate = 295.56
Description of works: Maintenance of gravel shoulders and gravel carriageway by repairing pot holes and making iregularities even to the required level including watering and compaction etc.
all complete lead 10m. Unit : 1 m2
Spec. cl. No: 2904
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
29.03 Skilled md 0.03 1476.00 44.28 Gravel m3 0.11 2355.01 259.05 Tools 3.00% of L.C. 11.23
Unskilled md 0.30 1100.00 330.00
Sub total of A = 374.28 Sub total of B = 259.05 Sub total of C = 11.23
Sub total of A +B + C = 644.56 Contractor's overhead expenses 15% = 96.68 Unit Rate = 741.24
Description of works: Double coat whitewash on new surface including supply of materials all complete
Spec. cl. No:
Unit : 100 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13-1-b Unskilled md 1.10 1100.00 1210.00 lime kg 22.000 0.00 0.00
Skilled md 1.50 1476.00 2214.00 Gum kg 0.880 0.00 0.00
15-16-b Unskilled md 2.00 1100.00 2200.00
Sub total of A = 5624.00 Sub total of B = 0.00 Sub total of C = 0.00
Sub total of A +B + C = 5624.00 Contractor's overhead expenses 15% = 843.60 Rate = 6467.60
Unit Rate (1 m2) 64.68
Description of works: Single coat whitewash on old surface including supply of materials all complete
Spec. cl. No:
Unit : 100 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
13-2 Unskilled md 0.70 1100.00 770.00 Lime kg 10.000 0.00 0.00
Skilled md 0.80 1476.00 1180.80 Gum kg 0.400 0.00 0.00
Cleaning Unskilled md 2.00 1100.00 2200.00
Sub total of A = 4150.80 Sub total of B = 0.00 Sub total of C = 0.00
Sub total of A +B + C = 4150.80 Contractor's overhead expenses 15% = 622.62 Rate = 4773.42
Unit Rate (1 m2) 47.73
Description of works: Single coat enamel paint/ readymade emulsion paint including supply of materials all complete.
Spec. cl. No:
Unit : 100 m2
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15-5-b Unskilled md 2.00 1100.00 2200.00 Enamel paint kg 16.00 440.00 7040.00
Skilled md 5.00 1476.00 7380.00 Primer kg 8.10 0.00 0.00
15-5-a Unskilled md 3.00 1100.00 3300.00
Skilled md 3.00 1476.00 4428.00
Sub total of A = 17308.00 Sub total of B = 7040.00 Sub total of C = 0.00
Sub total of A +B + C = 24348.00 Contractor's overhead expenses 15% = 3652.20 Rate = 28000.20
Unit Rate (1 m2) 280.00
Item no:
Description of works: Backfilling in layers in foundation ,pits,trenches etc including compaction and watering etc ,complete lead 10 m
Spec. cl. No:
Unit : 1m3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
2-26(old norms)
Unskilled md 1.00 1100.00 1100.00 Riverbed gravel m3 1.100 1200.00 1320.00 Tools and Plants 3% of L.C. 33
Sub total of A = 1100.00 Sub total of B = 1320.00 Sub total of C = 33.00
Sub total of A +B + C = 2453.00 Contractor's overhead expenses 15% = 367.95 Unit Rate = 2820.95
Item no:
Description of works: Providing and installing Railing including Railing Posts -- 100 mm dia
Unit : m
Spec. cl. No: 3105
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
31.01.a Skilled md 0.15 1476.00 221.40 GI Pipe m 1.10 1918.33 2110.16
Unskilled md 7.00 1100.00 7700.00
Sub total of A = 7921.40 Sub total of B = 2110.16 Sub total of C = 0.00
Sub total of A +B + C = 10031.56 Contractor's overhead expenses 15% = 1504.73 Unit Rate = 11536.30
Item no:
Description of works: Providing and installing Railing including Railing Posts -- 50 mm dia
Unit : m
Spec. cl. No: 3105
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
31.01.b Skilled md 0.25 1476.00 369.00 GI Pipe m 1.10 496.00 545.60
Unskilled md 0.50 1100.00 550.00
Item no:
Description of works: Providing and installing Railing including Railing Posts --38 mm dia
Unit : m
Spec. cl. No: 3105
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
31.01.c Skilled md 0.25 1476.00 369.00 GI Pipe m 1.10 249.00 273.90
Unskilled md 0.50 1100.00 550.00
Sub total of A = 919.00 Sub total of B = 273.90 Sub total of C = 0.00
Sub total of A +B + C = 1192.90 Contractor's overhead expenses 15% = 178.94 Unit Rate = 1371.84
Item no:
Description of works: Letter Writing and painting on KM Post ( On Prepared Surface)
Unit : 100 m2
Spec. cl. No:
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
from old norms Skilled md 18.00 1476.00 26568.00 Enamel Paint Lit 7.00 440.00 3080.00
Unskilled md 7.00 1100.00 7700.00
Sub total of A = 34268.00 Sub total of B = 3080.00 Sub total of C = 0.00
Sub total of A +B + C = 37348.00 Contractor's overhead expenses 15% = 5602.20 Unit Rate = 42950.20
Unit Rate (Per m2)= 429.502
Item no:
Description of works: White washing on old surface (Lime washing)
Unit : 100 m2
Spec. cl. No:
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
from old norms Skilled md 0.80 1476.00 1180.80 White Lime kg 10.00 0.00 0.00
Unskilled md 0.70 1100.00 770.00 Febicol kg 0.40 0.00 0.00
Sub total of A = 1950.80 Sub total of B = 0.00 Sub total of C = 0.00
Sub total of A +B + C = 1950.80 Contractor's overhead expenses 15% = 292.62 Unit Rate = 2243.42
Unit Rate (Per m2)= 22.43
Item no:
Description of works: Maintenance of Pot holes and damaged bituminouns surface including cleaning rolling and brooming etc all complete lead 10 m b) 20 mm shallow patching using hot
Unit : 100 m2
Spec. cl. No:
premix material.
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
from old norms Skilled md 0.15 1476.00 221.40 MC cutback 30 biutmen Lit 110.00 0.00 0.00 Asphalt mixing plant hr 0.10
Unskilled md 7.00 1100.00 7700.00 Bitumen Lit 250.00 0.00 0.00 Wheel loader hr 0.15
Mineral filler t 0.05 Steel Roller hr 1.20
Aggregate m3 2.80
Diesel Lit 20.00
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 0.120 1100.00 132.00 V. Roller hr 0.0025 1080.00 2.70
Motor Grader hr 0.004 1500.00 6.00
15 - 4 (Ka) Sub Total (A) 132.00 Sub Total (B) 0.000 Sub Total ( C ) 8.70
Direct Cost (A+B+C) = NRs 140.70
Contractor Overhead @ 15% of (A+B+C) = NRs 21.11
Total Item Rate = NRs 161.81
Description of Work:- Supply and laying sub-base couse material including required compaction and level as specified
Unit: 1.00 Cu.m.
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 1.267 1100.00 1393.70 5-63 mm agg Cu.m 1.280 3055.01 3910.413 V. Roller hr 0.09 1080.00 97.20
Unskilled md 0.120 1100.00 132.00 Motor Grader hr 0.03 1500.00 45.00
15 - 19(ga) Water Tanker hr 0.005 550.00 2.75
15 - 8 Sub Total (A) 1525.70 Sub Total (B) 3910.413 Sub Total ( C ) 144.95
Direct Cost (A+B+C) = NRs 5581.06
Contractor Overhead @ 15% of (A+B+C) = NRs 837.16
Total Item Rate = NRs 6418.22
Description of Work:- Supply and laying graded crushed stone base material including required compaction and level as specified
Unit: 1.00 Cu.m.
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 1.200 1100.00 1320.00 5-40 mm agg Cu.m 1.000 3055.01 3055.010 V. Roller hr 0.03 1080.00 32.40
Unskilled md 0.080 1100.00 88.00 Motor Grader hr 0.01 1500.00 15.00
15 - 13 Water Tanker hr 0.005 550.00 2.75
(kha) 15 - 8 Sub Total (A) 1408.00 Sub Total (B) 3055.010 Sub Total ( C ) 50.15
Direct Cost (A+B+C) = NRs 4513.16
Contractor Overhead @ 15% of (A+B+C) = NRs 676.97
Total Item Rate = NRs 5190.13
Description of Work:- Supply and application of prime coat with cut back bitumen as specified
Unit: 1.00 lit
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.015 1476.00 22.14 MC 30/70 kg 1.000 78.30 78.296 B. Distributor hr 0.004 1280.00 5.12
Unskilled md 0.005 1100.00 5.50 Kerosene lit 0.050 97.00 B. pre heater hr 0.004 550.00 2.20
15 - 18
(kha) 15 - Air Compressor hr 0.004 990.00 3.96
16 (ka) Sub Total (A) 27.64 Sub Total (B) 78.296 Sub Total ( C ) 11.28
Direct Cost (A+B+C) = NRs 117.22
Contractor Overhead @ 15% of (A+B+C) = NRs 17.58
Total Item Rate = NRs 134.80
Description of Work:- Supply and application of bitumenous binder, bitumen grade 80/100 pen as specified for first coat
Unit: 1.00 lit
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.015 1476.00 22.14 Bitumen kg 1.200 78.30 93.955 B. Distributor hr 0.004 1280.00 5.12
Unskilled md 0.005 1100.00 5.50 Kerosene lit 0.050 97.00 4.850 B. pre heater hr 0.004 550.00 2.20
15 - 19 Sub Total (A) 27.64 Sub Total (B) 98.805 Sub Total ( C ) 7.32
Direct Cost (A+B+C) = NRs 133.77
Contractor Overhead @ 15% of (A+B+C) = NRs 20.06
Total Item Rate = NRs 153.83
Description of Work:- Supply and application of bitumenous binder, bitumen grade 80/100 pen as specified for Second coat
Unit: 1.00 lit
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.015 1476.00 22.14 Bitumen kg 1.000 78.30 78.296 B. Distributor hr 0.004 1280.00 5.12
Unskilled md 0.005 1100.00 5.50 Kerosene lit 0.050 97.00 4.850 B. pre heater hr 0.004 550.00 2.20
15 - 20 Sub Total (A) 27.64 Sub Total (B) 83.146 Sub Total ( C ) 7.32
Direct Cost (A+B+C) = NRs 118.11
Contractor Overhead @ 15% of (A+B+C) = NRs 17.72
Total Item Rate = NRs 135.82
Description of Work:- Supply, spread and compact 14 mm to 20 mm normal size aggregate for surface dressing over prime coat as specified
Unit: 1.00 Sq. m
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 1476.00
0.006 8.86 40/20 and 14/20 Agg Cu.m 0.020 3055.01 61.100 Chip spreader hr 0.004 450.00 1.80
Unskilled md 0.058 1100.00 63.80 P Roller hr 0.004 990.00 3.96
Foreman md 0.006 600.00 3.60 Tipper hr 0.004 460.00 1.84
15 - 19 a Sub Total (A) 76.26 Sub Total (B) 61.100 Sub Total ( C ) 7.60
Direct Cost (A+B+C) = NRs 144.96
Contractor Overhead @ 15% of (A+B+C) = NRs 21.74
Total Item Rate = NRs 166.70
Description of Work:- Supply, spread and compact 10 mm to 14 mm normal size aggregate for surface dressing over prime coat as specified
Unit: 1.00 Sq. m
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 1476.00
0.006 8.86 10 / 14 Agg Cu.m 0.014 3055.01 42.770 Chip spreader hr 0.004 450.00 1.80
Unskilled md 0.058 1100.00 63.80 P Roller hr 0.004 990.00 3.96
Foreman md 0.006 600.00 3.60 Tipper hr 0.004 460.00 1.84
15 - 19. Sub Total (A) 76.26 Sub Total (B) 42.770 Sub Total ( C ) 7.60
Direct Cost (A+B+C) = NRs 126.63
Contractor Overhead @ 15% of (A+B+C) = NRs 18.99
Total Item Rate = NRs 145.62
Description of Work:- Preparation of site by felling, cutting and carrying away tree dia. 12-30 cm including 15 m lead for disposal
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 0.130 1100.00 143.00
1-1 Sub Total (A) 143.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 143.00
Contractor Overhead @ 15% of (A+B+C) = NRs 21.45
Total Item Rate = NRs 164.45
Description of Work:- Preparation of site by felling, cutting and carrying away tree dia. 31-60 cm including 15 m lead for disposal
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 0.390 1100.00 429.00
1-1 Sub Total (A) 429.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 429.00
Contractor Overhead @ 15% of (A+B+C) = NRs 64.35
Total Item Rate = NRs 493.35
Description of Work:- Preparation of site by felling, cutting and carrying away tree dia. 61-90 cm including 15 m lead for disposal
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 0.520 1100.00 572.00
1-1 Sub Total (A) 572.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 572.00
Contractor Overhead @ 15% of (A+B+C) = NRs 85.80
Total Item Rate = NRs 657.80
Description of Work:- Preparation of site by felling, cutting and carrying away tree dia. 19-120 cm including 15 m lead for disposal
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 1.560 1100.00 1716.00
1-1 Sub Total (A) 1716.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 1716.00
Contractor Overhead @ 15% of (A+B+C) = NRs 257.40
Total Item Rate = NRs 1973.40
Description of Work:- Preparation of site by felling, cutting and carrying away tree dia. 121-180 cm including 15 m lead for disposal
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 2.500 1100.00 2750.00
1-1 Sub Total (A) 2750.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 2750.00
Contractor Overhead @ 15% of (A+B+C) = NRs 412.50
Total Item Rate = NRs 3162.50
Description of Work:- Preparation of site by felling, cutting and carrying away tree dia. 181-240 cm including 15 m lead for disposal
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 4.000 1100.00 4400.00
1-1 Sub Total (A) 4400.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 4400.00
Contractor Overhead @ 15% of (A+B+C) = NRs 660.00
Total Item Rate = NRs 5060.00
Description of Work:- thin bush cutting and uprooting bushes including 25 m lead dial upto 30 cm an d15 plant per 100 sq.m
Unit: 1.00 no
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 0.041 1100.00 45.10
1-2 Sub Total (A) 45.10 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 45.10
Contractor Overhead @ 15% of (A+B+C) = NRs 6.77
Total Item Rate = NRs 51.87
Description of Work:- Back fill with graded filter materials in layer with necessary watering and compaction, lead 30m, lift 1.5m
Unit: 1 no.
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Unskilled md 0.800 1100.00 880.00 Graded filter materials Cu.m 1.100 3975.01 4372.51
1-2 Sub Total (A) 880.00 Sub Total (B) 4372.511 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 5252.51
Contractor Overhead @ 15% of (A+B+C) = NRs 787.88
Total Item Rate = NRs 6040.39
Description of Work:- Providing and planting containerised tree and shrub seedling, including pitting, transplanting, composing and mulching, on slopes > 40deg. Pit size 10cm diameter x 30cm depth. Mix compost
with soil and back fill into pit to 1/4 of pit volume.
Unit: 10 No
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.000 1476.00 0.00 Seedling No 10.000 7.00 70.000 0.00
15 - 18 Unskilled md 0.400 1100.00 440.00 Compost Cum 0.050 1000.00 50.000 0.00
(kha) 15 - Green mulch Cum 0.040 200.00 8.000 0.00
16 (ka) Sub Total (A) 440.00 Sub Total (B) 128.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 568.00
Contractor Overhead @ 15% of (A+B+C) = NRs 85.20
Total Item Rate = NRs 653.20
Per Unit Rate = NRs 65.32
Description of Work:- Providing and planting rooted tree stump cutting bare root seedling, including pitting, transplanting, composing and mulching, on slopes > 45deg. Pit size 10cm diameter x 20cm depth. Compost
volume 1/4 of volume of the pit mix with original soil.
Unit: 10 No
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.000 1476.00 0.00 Seedling kg 10.000 12.00 120.000 0.00
15 - 18 Unskilled md 0.330 1100.00 363.00 Compost lit 0.030 1000.00 30.000 0.00
(kha) 15 - Green mulch 0.040 200.00 8.000 0.00
16 (ka) Sub Total (A) 363.00 Sub Total (B) 158.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 521.00
Contractor Overhead @ 15% of (A+B+C) = NRs 78.15
Total Item Rate = NRs 599.15
Per Unit Rate = NRs 59.92
Description of Work:- Grass sodding works including sod cutting, transporting, placing in position and water sprinkling ( Lead upto 10m)
Unit: 1-Sqm
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.000 1476.00 0.00 0.000 0.00
15 - 18 Unskilled md 0.050 1100.00 55.00 0.00
(kha) 15 - 0.00
16 (ka) Sub Total (A) 55.00 Sub Total (B) 0.000 Sub Total ( C ) 0.00
Direct Cost (A+B+C) = NRs 55.00
Contractor Overhead @ 15% of (A+B+C) = NRs 8.25
Total Item Rate = NRs 63.25
Description of Work:- Hydraulic Excavator Up to 0.80 m3 Capacity Excavator including fuel, operator cost all complete.
Unit: 1 Hour
Resources
Norms labour (A) Material (B) Equipment ( C )
Activity Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.143 1476.00 210.86 Diesel Lit 12.000 97.00 1164.000 Hydraylic Excavator 111 to 150 HP Hour 1 1800.00 1800.00
Unskilled md 1100.00 0.00 0.00
2.01.01, Sub Total (A) 210.86 Sub Total (B) 1164.000 Sub Total ( C ) 1800.00
Direct Cost (A+B+C) = NRs 3174.86
Contractor Overhead @ 15% of (A+B+C) = NRs 476.23
Total Item Rate = NRs 3651.09
Per Unit Rate = NRs 3651.09
Description of works: Road way excavation in hard rock by Blasting. Making rubbles of required size including making hole, blasting and breaking with chisel or hammer, hauling distance 10m. and stacking.
Unit : 1 m3
Spec. cl. No: 905
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.02.d.ii).II Unskilled md 1.750 1100.00 1925.00 Gelatine Kg 0.25 331.55 82.8875 Compressor & Rock Drill hr 0.4 1401.00 560.40
Blaster md 0.120 900.00 108.00 Detonator Nos 2 331.55 663.1
Fuse Wire m 2 331.55 663.1
Sub total of A = 2033.00 Sub total of B = 1409.09 Sub total of C = 560.40
Sub total of A +B + C = 4002.49 Contractor's overhead expenses 15% = 600.37 Unit Rate = 4602.86
Description of works: Applying of Antistripping Additive
Unit : 1 m3
Spec. cl. No:
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 1100.00 0.00 Antistripping Additive Kg 1 321.55 321.55 0.00
Blaster md 900.00 0.00 0
0
Sub total of A = 0.00 Sub total of B = 321.55 Sub total of C = 0.00
Sub total of A +B + C = 321.55 Contractor's overhead expenses 15% = 48.23 Unit Rate = 369.78
Province Government
Ministry of Physical Infrastructure Development
Transport Infrastructure Directorate
Gandaki Province
Pokhara, Nepal
Rate Analysis
Sub TotalB
C) Equipment Cost
T&P 3 % of labour cost 1053.79
Hydraulic excavator hr 5.40 3,089.60 16683.84
Sub Total C 17737.63
D) Other Cost
3.2 907
Excavation of foundation of structures, including construction of shoring
and bracing, removal of stumps and other deleterious matter as per drawing
and technical specifications. (10 % manually, 90 % mechanically)
Ordinary Soil and ordinary rock
Manually Norms Reference: 9.4 I, A, (i)+ II, A,(i)
Unit = 10 cum
NRs. NRs.
a) Labour Cost
Unskilled Labour md 9.00 1100.00 9900.00
Skilled Labour md 1.00 1476.00 1476.00
Sub Total 1 11376.00
b) Material Cost
Sub Total 2
c) Equipment Cost
T&P 3 % of labour cost 341.28
Sub Total 3
Sub Total (A+B+C) 11717.28
Contractor's Overhead t (15%) 1757.59
Total per cum 1347.49 ok
3.2 Foundation excavation on all type of soil (manually 10% machine 90%) 319.07 ok
Sub Total 4
Sub Total (A+B+C+D) 187.98
Contractor's Overhead (15%) 28.20
Total (E+F) 216.17 per cum
Rate per cum 216.17
Sub Total 4
Sub Total (A+B+C+D) 241.87
Contractor's Overhead and (15%) 36.28
Total (E+F) 278.15
Rate per sqm 278.15
Dry Brick on edge soling including sand sealing / bedding & compaction.
Unit = cum [For 10 m2]
a) Labour
Skilled day 1.00 550.00 550.00
Unskilled day 3.25 335.00 1,088.75
b) Material
Brick No. 750.00 16.00 12,000.00
Sand cum 0.71 2,700.00 1,917.00
Total (A+B) 15,555.75
Overhead 15% 2,333.36
Total 17,889.11
Rate per Sq. m 1,788.91 ok
5.2 2600 Providing and laying Stone Masonry work in cement mortar 1:4 in structure complete
as per Drawing and Technical Specifications
2607 Random Rubble Masonry
A ( coursed/uncoursed )
Unit = cum (For 5 cum)
a) Labour
Skilled day 7.00 1,476.00 10,332.00
Unskilled day 20.00 1,100.00 22,000.00
Sub total a 32,332.00
b) Material
Stone cum 5.75 1,800.00 10,350.00
Cement tonne 0.66 19,412.36 12,812.15
Sand cum 1.85 2,700.00 4,995.00
Cost of water KL 1.00 250.00 250.00
-
Add 5 per cent of cost of Labour and material for scaffolding 1,616.60
Sub total b 30,023.75
Sub total (a+b) 62,355.75
Overhead 15% 9,353.36
Total 71,709.12
Rate per cum 14,341.82 ok
Supply and assembling mechanical woven Gabion boxes /mattresses, placing in position including
stretching; forming compartments; tying the sides and diaphragms with binding wire in each mesh; tying
with bracing wires and tie wires; and tying down the lid of machine made mechanically salvaged gabion
and mattresses from double twisted heavy coated GI wire, of hexagonal mesh size 100 mm x 120 mm, with
mesh size 3 mm, selvaged wire 3.9 mm, lacing wire 2.4 mm and stone filling in gabions including transport
and fixing of gabions in position, all complete
5.5 2404 Laying and fixing of Geo-Textile all complete as per specification.
Providing and laying of a geotextile filter between pitching and embankment slopes
as per Drawing and Technical Specifications.
Unit = sqm (For 300 sqm)
a) Labour
Skilled day 1 1,476.00 1,476.00
Unskilled day 2 1,100.00 2,200.00
Sub total a 3,676.00
b) Material
Geotextile sqm 360 75.00 27,000.00
27,000.00
Sub Total (a+b) 30,676.00
Overhead 15% 4,601.40
Total 35,277.40
Rate per sqm 117.59 ok
5.8 2000 Providing and laying of Plain/Reinforced Cement Concrete in Foundation complete as
per Drawing and Technical Specifications.
A PCC Grade M 15/40
Unit = cum (For 15 cum)
a) Labour
Skilled day 3 1,476.00 4,428.00
Unskilled day 30 1,100.00 33,000.00
Sub Total a 37,428.00
b) Material
Cement tonne 4.13 19,412.36 80,173.03
Coarse sand cum 6.75 2,700.00 18,225.00
40 mm Aggregate cum 8.1 3,300.00 26,730.00
20 mm Aggregate cum 4.05 3,300.00 13,365.00
10 mm Aggregate cum 1.35 3,300.00 4,455.00
Cost of water KL 2 250.00 500.00
Sub Total b 143,448.03
c) Equipment
Concrete mixer hour 6 1,309.73 7,858.38
Generator hour 6 579.86 3,479.16
Sub Total c 11,337.54
d) Other Cost
Formwork @ 10 % on cost of concrete 19,221.36
Sub Total d 19,221.36
Total (a+b+c+d) 211,434.92
Overhead 15% 31,715.24
Total 243,150.16
Rate per cum 16,210.01 ok
B a) Labour
Skilled day 1.00 1,476.00 1,476.00
Unskilled day 6.00 1,100.00 6,600.00
Sub-total (A) 8,076.00
b) Material
Sand cum 0.09 2,700.00 243.00
Cement tonne 0.07 19,412.36 1,358.86
RCC pipe meter 12.50 5,702.95 71,286.88
Sub-total (B) 72,888.74
c) Equipment
Add 3 % of Labour cost
for bellies, crow bars,
chain pulley and other
T&P
Sub-total (C) 242.28
Total (A+B+C) 81,207.02
Overhead 15% 12,181.05
Total 93,388.07
Rate per m 7,471.05
Roadway Excavation in
ordinary rock by
Mechanical Means .
Roadway Excavation in
ordinary rock as per
Drawing and Technical
specification, including all
lift and lead as per Drawing
and instruction of the
Engineer.
Ordinary soil
Manual Means
Unit = cum (For 10 cum)
Depth upto 3 m
a) Labour
Skilled day 1.00 1,476.00 1,476.00
Unskilled day 8.00 1,100.00 8,800.00
Sub-total (A) 10,276.00
Total (A) 10,276.00
Overhead 15% 1,541.40
Total 11,817.40 1,181.74
Mechanical Means
Depth upto 3 m
6.2 a Providing and fixing RCC M 15 grade kilometer post including painting and printing as per standard drawing -
2070 and technical specifications. Position.
One Kilometer post
1506 Unit:14 no DoR Norms Reference: 15.11 ii
a) Labour Cost
Unskilled Labour md 7.00 1100.00 7700.00
Skilled Labour md 2.00 1476.00 2952.00
Sub Total A 10652.00
b) Material Cost
Concrete M15/40 m3 1.40 14095.66 19733.93
Concrete M10/40 m3 2.38 11448.24 27246.82
Reinforcement kg 82.88 86.63 7180.09
Excavation in soil for foundation m3 2.38 282.37 672.03
Painting two coats m2 11.90 747.03 8889.67
lettering on km post Cm-letter 1680.00 0.25 420.00
Sub Total B 64142.53
c) Equipment Cost
Tractor-trolley hr 3.00 697.92 2093.76
Sub Total C 2093.76
d) Other Cost
Sub Total D
Sub Total (A+B+C+D) 76888.29
Contractor's Overhead (15%) 11533.24
Total 88421.54
Rate per no 6315.82
6.04) Supplying and erecting one sided double steel guard rail, including posts, spacer posts, and nutbolts as
per specifications all complete.
a) steel guard rail
Unit: 12m
A Labour Cost
Installation @ 5% of material 4170.85
Sub Total A 4170.85
B Material Cost
GI W section beam each 4.318m
long 2.8mm thick double
layered each side nos 6 7360 44160.00
7.1 2807 Planting rooted grass slips on the slopes <45o including preparation of slips on site. a
max of 5 cm depth with metal rod or Operation includes digging planting hole to hard-
wood peg, depending on the nature of the soil. The planting drills should be space
7.3 C Planting containerized tree and shrub seedlings, including pitting, transplanting,
composting and mulching, on slopes 30o . - 400 Pit size 30 cm diameter x depth mix
Compost with soil and back fill into pit to 1/4 of the pit volume
Insurance 1 % of 4.37
Labour
cost
First aid 0.3 % of 1.31
Labour
cost
Item No.
909,910 Providing and filling with graded previous (filter material) in layer with necessary watering and
compaction as per specification and instruction of Engineer
Unit:10 m3 Norms Reference: 9.12
A Labour Cost
Unskilled Labour md 10.000 1100.00 11,000.00
Skilled Labour md 1.000 1476.00 1,476.00
Sub Total 1 12,476.00
Tubuler Steel Railing on precast RCC post. Providing, fencing and errecting 50 mm dia painted steel pipe
raling in 3 rows on precast M20 grade RCC vertical post 1.8 m high (1.2 m above GL) wth 3 holes 50 mm
dia for pipe , fixed 2 m cener to ,complete as per drawing and technical specification
Unit:100 m Specification Clause No: 3105 DoR Norms Reference: 31.7
Rate Amount
S.N. Description Unit Quantity Remarks
NRs. NRs.
i) Excavation for foundation Cum 12.960 319.073 4135.185
ii) Foundation concrete M-15 Cum 6.480 16210.011 105040.870
iii) RCC M20 Cum 3.200 17906.77 57301.68
iv) Painting of Pipe Sqm 47.100 747.031 35185.156
A Labour Cost
Skilled day 1.00 1476.00 1476.00
Unskilled day 6.00 1100.00 6600.00
Sub Total A 8076.00
B Material
Steel Pipe 50 mm dia as per IS 1 m 300.00 473.00 141900.00
Sub Total B 141900.00
C Equipment
Tractor Trolley hr 6.00 697.920 4,187.52
E Total (A+B+C+D) 355,826.41
F Contractors overhead and Profit Cost (15 %) 53373.96138617
G Total (E+F) 409,200.37 per 100 m
4092.00 Per m
Item No. 7.05
Providing required material and painting lines,dashes,arrows etc on roads in two coats on new work with
ready mixed road marking paint conforming to NS 408/IS 164 on bituminious surface , including cleaning
the surface of all dirt , dust and other foreign matter ,demarcation at site and traffic control as per
Drawing and Technical Specifications
Unit:10 m2 Specification Clause No: 1503 DoR Norms Reference: 15.7
Rate Amount
S.N. Description Unit Quantity Remarks
NRs. NRs.
A Labour Cost
Unskilled Labour md 2.000 1248.00 2,496.00
Skilled Labour md 1.000 1476.00 1,476.00
Sub Total 3
D Other Cost
Sub Total 4
E Sub Total (A+B+C+D) 4,828.92
F Contractor's Overhead and Profit Cost (15%) 724.34
G Total (E+F) 5,553.26 per 10 m2
555.33 per m2
Bridge
S.N. Chainage Span (m) Remark
1 1+200.00 15 River
2 1+220.00 15 River