EXHIBIT-C (1) Attachment (2)

EXHIBIT-C Work Description, Supply Condition and Method of Measurement


Civil and Building Work

Attachment (2) Method of Measurement

04 Ex-C_Method Of Meas
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

Method of Measurement (Civil & Building Works)

Definition
This Method of Measurement provides a uniform basis for measuring the quantities of the PERMANENT
WORKS, which shall be referred to as the Bill of Quantities (BOQ) hereinafter, and which shall be used for basis
of the calculation of the DIRECT WORK PRICE.

A. General Note

1. BOQ shall be measured as the net volume in accordance with the design drawings (hereinafter referred
to as the Drawings) issued later on at the job-stage and rules referred to hereinafter regardless of actual
volume of the work, volume of waste or loss, etc.
However this rule shall not apply to the measurement for the CONTRACTOR's temporary facility (e.g.
camp, site office building, temporary warehouse, utility service, net work and the like).

2. BOQ of earth work items shall be calculated based on the dimensions on Drawings regardless of
bulking after excavation.

3. As for any new work item which is not specified in this exhibit, the CONTRACTOR shall submit the
proposed method of measurement to TIC for approval.

4. Weight of steel structures, metal and reinforcing bar, etc. shall be calculated as per unit weight referred
in the Code applied for materials and/or net based on the volume and specific gravity (the specific
gravity of steel is 7.85).

5. Unit of measurement shall conform to the metric system.

04 Ex-C_Method Of Meas - 1 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

6. Definitions of Sub-structure and Super-structure are as follows.

6-1 Sub-structure

Beam
Column
≦2m ≦2m ≦2m
GL
Pedestal Footing Sump Pit

FOUNDATION PIT FRAMING STRUCTURE

6-2 Super-structure (hatched portion)

Beam
Column
>2m >2m >2m
GL
Pedestal Footing Sump Pit

FOUNDATION PIT RC FRAMING STRUCTURE

04 Ex-C_Method Of Meas - 2 -
EXHIBIT-C (1) Attachment (2)

B. Method of Measurement for Civil & Building Works

Introduction

PI : Pile Work PL : Plaster Work


SH : Shoring & Dewatering Work LN : Coating & Lining Work
EA : Earth Work WP : Waterproofing Work
BC : Base Course Work ML : Metal & Plastic Work
RE : Reinforcing Bar Work RO : Roofing & Siding Work
AN : Anchoring & Embedding Work AL : ALC Board Work
JT : Joint Work JN : Joinery Work
FM : Form Work GL : Glazing Work
CO : Concrete Work IN : Interior Finishing Work
AS : Asphalt Work TL : Ceramic Tile Work
SS : Steel Structure Work ME : Mechanical Equipment Work
PA : Painting Work SI : Soil Improvement Work
FP : Fire Proofing Work GR : Green Work
PP : Underground Pipe Work RM : Removal Work
PC : Pre-Cast Concrete Unit Work SU : Survey Work
MA : Masonry Work

04 Ex-C_Method Of Meas - 3 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

PI: PILE WORK

PI -1 (RC, PC, Steel, etc.) Pile m This item shall be measured as net length of pile from ground level (cut level = GL) for pile machine working in
accordance with the Drawings.
-2 Projection of the pile to be cut off shall not be measured in the BOQ.
-3
-4
-5
-6
-7
GL PIER SLAB

Damaged Pile shall


not be measured. Reinforcement
L S.W.L.
L
SEA BED

GL: Ground Level


L : Length of Pile

Even if the pile should be stopped before being driven to its full length, the length of remaining portion shall be
disregarded for measurement and not taken as the matter of price adjustment.
Further no additional payment shall be made for the pile driving with attachment.

PI-8 Pile Head Treatment nos This item shall be measured as the number of piles treated in accordance with the Drawings.

PI-9 Pile Loading Test nos This item shall be measured as the number of piles tested in accordance with the Drawings.

04 Ex-C_Method Of Meas - 4 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

SH: SHORING & DEWATERING WORK

SH-1A Steel Sheet Pile m2 This item shall be measured as the net area shored in accordance with the Drawings.

A=HxL

A: Area of shoring
H: Depth of excavation from finished grade
L: Perimeter length

Any excavation that may be required while driving the sheet piles, or for the removal of piling frame or
for any other reasons associated with sheet piling work shall be deemed to be a part of this work item and
shall not be measured separately.

SH-2A Well Point m This item shall be measured as the net length of header pipes.

04 Ex-C_Method Of Meas - 5 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

EA: EARTH WORK

EA -1A Excavation m3 This item shall be measured as the net volume of excavated soil in accordance with the Drawings and the rules
described below.
-1B The width of excavation shall include 300 mm of working space from the edge of the structure, where the depth of
excavation is up to 2000 mm, and 1000 mm of working space from the edge of the structure where the depth is over
2000 mm.

SUB STR.(FDN,ETC.)
EA-1A

< 2000
=
3000

300 300

EA-1B (HATCHED AREA)


1000 1000

In case that the excavation depth is more than 3,000 mm, the soil volume below 3,000 mm depth shall be
measured in work item EA-1B and the volume from finish ground level to 3,000 mm depth shall be measured in
work item EA-1A.

EA-1D Scraping (D≦300 mm) m2 This item shall be measured as the net area of the land that has been scraped in accordance with the Drawings.

04 Ex-C_Method Of Meas - 6 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

EA -2A Back Filling m3 This item shall be calculated as follows;


-2B
VB = VE - (VC + VL +VV)

VB: Backfilling Volume (Excavated Soil) (m3)


VE: Excavation Volume (m3)
VC: Structure Volume of U/G Portion (m3)
VL: Leveling Concrete Volume if necessary (m3)
VV: Voids of the Structure of U/G Portion (m3)

If a part or whole of the excavated pit is not backfilled, such volume shall be deducted from VB.

EA -3A Disposal of Surplus Soil m3 This item shall be measured as follows;


-3B
VD = VE - VB

VD: Surplus Soil Volume (m3)


VE: See EA-2A
VB: See EA-2A

If a part of backfilling is done with purchased soil and the excavated soil is not used, such volume shall
be added to VD.

EA -4A Sand Filling m3 This item shall be measured as the net volume of the filled sand without bulking in accordance with the Drawings.
-4B
-4C

EA-4D Crushed Stone Filling m3 Same as EA-4A, but “sand” shall be read as “crushed stone”.

EA-5A Earth Dike m3 This item shall be measured as the net volume of earth banking in accordance with the Drawings.
-5B

04 Ex-C_Method Of Meas - 7 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

EA -5C Filling for Slab-on-grade m3 This item shall be measured as the net volume of fill in accordance with the Drawings.
-5D

EA-6A Final Grading m2 This item shall be measured as the net area of the land where the final grading is made, in accordance with the
Drawings.

EA-7A Stripping for Site Preparation m3 This item shall be measured as the net volume of the land where the stripping is made in accordance with the Drawings.

EA-7B Cutting for Site Preparation m3 This item shall be measured as the net volume of the cut based on the cut depth and area in accordance with the
Drawings.

EA-7C-1 Filling for Site Preparation m3 This item shall be measured as the net volume of the fill based on the fill depth and area in accordance with the
Drawings.
-2

EA-7D Grading for Site Preparation m2 This item shall be measured as the net area of the land where the grading is made in accordance with the Drawings.

04 Ex-C_Method Of Meas - 8 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

BC: BASE COURSE WORK

BC -1A Base Course m3 This item shall be measured as the net volume of the base course based on its area and thickness in accordance with the
Drawings.
-2A
-3A
-3B

BC -4A Sub-grade m3 This item shall be measured as the net volume of the sub-grade based on its area and thickness in accordance with the
Drawings.
-4B

BC-5A Crushed Stone m3 This item shall be measured as net volume of the crushed stone based on its area and thickness in accordance with the
Drawings.

04 Ex-C_Method Of Meas - 9 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

RE: REINFORCEMENT (RE-BAR) WORK

RE -1A Re-Bar for Sub-structure ton This item shall be measured as the net weight of reinforcing bars, using length and unit weight.
-1B Unit weight per length shall be based on the Drawings.
Scrap and waste reinforcing bar shall not be counted in the work volume nor shall utilization of a temporary nature
such as, but not limited to, tie-bars, chairs, form ties, binding wire and like, be counted.
Opening in walls, slabs and like exceeding 0.5 m2 shall be deducted.
Measurements for lap length and development length shall be considered in accordance with TIC's Standard
Drawings for compression or tension reinforcement.

RE -2A Re-Bar for Super-structure ton Same as RE-1A


-2B

RE-3A Welded Wire Fabric ton This item shall be measured as the net weight of welded wire fabric, using projected area where the welded wire fabric
is provided and unit weight in accordance with the Drawings.

- Lap length shall be disregarded.


- Wastage, circular cutting, etc. less than 0.5 m2 shall not be deducted.
- Spacer Blocks, chairs, Binding wire, etc. shall not be measured.

04 Ex-C_Method Of Meas - 10 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

AN: ANCHORING & EMBEDDING WORK

AN-1A Anchor Box nos This item shall be measured as the number of anchor boxes regardless of its dimensions in accordance with the
Drawings.

AN-2A Anchor Bolt with Template ton This item shall be measured as the net weight of bolt sets and templates in accordance with the Drawings, which
shall be supplied by TIC.
Any temporary support required for setting anchor bolts, nuts, washers and templates shall be deemed to be a part
of this work item and shall not be measured in BOQ.

AN-2B Anchor Bolt without Template ton Same as AN-2A, but templates shall not be supplied by TIC nor measured in BOQ.

AN-2C Anchor Bolt Supply & Setting ton Same as AN-2B, but anchor bolt sets and all other necessary materials shall be supplied by CONTRACTOR.

AN-3A Embedded Steel Setting ton Same as AN-2A, but “bolt sets and templates” shall be read as “embedded steel”.

AN-3B-1 Embedded Steel Supply & Setting ton Same as AN-2C, but “bolt sets and templates” shall be read as “embedded steel”.
-2

AN-4A Expansion Anchor (Hole-in-Anchor) nos This item shall be measured as the number of expansion anchor sets in accordance with the Drawings.

AN-4B Chemical Anchor nos Same as AN-4A, but “expansion anchor sets” shall be read as “chemical anchor”.

AN-5A Plastic Pipe m This item shall be measured as the net length of plastic pipe in accordance with the Drawings.

04 Ex-C_Method Of Meas - 11 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

JT: JOINT WORK

JT -1A Expansion Joint m This item shall be measured as the net length of expansion joint regardless of its depth and width in
accordance with the Drawings.
-2A
-3A

JT -4A Water Stop Plate m This item shall be measured as the net length of water stop plate regardless of its width and thickness in
accordance with the Drawings.
Scrap, waste materials or lap length shall not be measured.

04 Ex-C_Method Of Meas - 12 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

FM: FORM WORK

FM-1A Form for Sub-structure m2 This item shall be measured as the vertical surfaces of the finished structure in accordance with the Drawings.
No allowance shall be made for overlaps and no deduction shall be made for openings not exceeding 0.5 M2.
The bottom surface of the finished structure where fresh concrete shall be poured against surface of leveling
concrete or ground and top surface where form work is not used for concreting shall not be measured in BOQ.

FM-1B Curved Form for Sub-structure m2 Same as FM-1A

FM-2A Form for Super-structure m2 Same as FM-1A

FM-2B Curved Form for Super-structure m2 Same as FM-1A

FM-2C Form for Exposed Concrete Finish m2 Same as FM-1A

FM-3A Sliding Form m2 Same as FM-1A

04 Ex-C_Method Of Meas - 13 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

CO: CONCRETE WORK

(General)

Volume or area occupied by reinforcement steel bars and insert steel shall not be
deducted from the net volume of concrete.

CO-1A-1 Leveling Concrete m2 This item shall be measured as the net area of concrete to be poured based on dimensions on the Drawings.
1A-2

CO-1B-1 Lean Concrete m2 Same as CO-1A


1B-2

CO-2A Concrete for Sub-structure m3 This item shall be measured as the net volume of concrete to be poured based on dimensions on the Drawings.

CO-3A Concrete for Super-structure m3 Same as CO-2A

CO-4A Concrete for Slab-on-grade m3 Same as CO-2A

CO-5A-1 Concrete for Road/Paving m3 Same as CO-2A


to 5A-6

CO-6A-1 Covering Concrete for Waterproofing m2 Same as CO-1A


to 6A-3

CO-8A Pre-cast Concrete m3 Same as CO-2A


-8B

04 Ex-C_Method Of Meas - 14 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

AS: ASPHALT WORK

AS-1A-1 Asphalt Concrete for Road/Paving m2 This item shall be measured as the net area of asphalt concrete based on the area and thickness shown on the Drawings.
-2
-3
-4

AS -2A Asphalt Concrete Mortal m2 Same as AS-1A-1


-3A

AS-4A Oil/Asphalt Spray m2 This item shall be measured as the net area where oil/asphalt spray is applied in accordance with the Drawings.

04 Ex-C_Method Of Meas - 15 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

SS: STEEL STRUCTURE WORK

SS -1A,B,C Structural Steel ton This item shall be measured as the net weight of structural steel including joists, fasteners, gusset plate, etc. in
accordance with the Drawings.
-2A Gusset plates shall be measured to the actual geometrical shapes to the maximum extent possible.
-3A,B,C In case, it is not possible to measure the basis of geometrical shapes, then, the nearest possible geometrical shape
-4A,B,C shall be considered to calculate the weight.

SS-5A-1 Checkered Plate m2 This item shall be measured as the net area of checkered plate in accordance with the Drawings.
5A-2 Each opening in the plate exceeding 0.5 m2 in area, shall be deducted from the net measured area of the checkered
plate.
Supporting members of the plates such as joist, etc. shall not be measured.

SS-5B-1 Grating m2 Same as SS-5A, but “checkered plate” shall be read as “grating”.
5B-2

SS-5C-1 Deck Plate m2 Same as SS-5A, but “checkered plate” shall be read as “deck plate”.
5C-2
5C-3

SS-5D-1 Expanded Metal m2 Same as SS-5A, but “checkered plate shall be read as “expanded metal”.
5D-2

SS-5E-1 Punching Metal m2 Same as SS-5A, but “checkered plate” shall be read as “punching metal”.
5E-2

04 Ex-C_Method Of Meas - 16 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

SS-6A Steel Handrail m This item shall be measured as the net length of steel handrail consisting of top rail, middle rail, toe plate and post
including fasteners, gusset plates, chain and accessories for pedestrian access way, in accordance with the
Drawings.

SS-6B Steel Ladder m This item shall be measured as the net length of steel ladder including fasteners, gusset plates and cage if required
in accordance with the Drawings.

SS-6C Steel Stair Case m This item shall be measured as the net length of steel stair case including string, gusset plates, fasteners and braces
as required in accordance with the Drawings.
Treads and handrail are not measured in this BQ/Item Code.

SS-7A Crane Rail m This item shall be measured as the net weight of crane rail including fasteners and accessories but excluding the
girders on which the crane rail is to be installed, in accordance with the Drawings. “ I ” beam which is used as a
rail for hoist crane shall not be measured in this BQ Item Code but shall be included in the work item SS-1A.

04 Ex-C_Method Of Meas - 17 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

PA: PAINTING WORK

PA-1A Paint on Wood m2 This item shall be measured as the net area to be painted in accordance with the Drawings.
Regardless of the required number of coats, the area to be paint-finished shall be measured only once.

PA-2A Paint on Metal m2 Same as PA-1A

PA-3A Paint on Steel Structure m2 Same as PA-1A

PA-4A Paint on Board/Mortar m2 Same as PA-1A

PA-5A-1 Paint on Concrete m2 Same as PA-1A


5A-2

04 Ex-C_Method Of Meas - 18 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

FP: FIRE PROOFING WORK

FP-1A Fireproof Calcium Silicate Board m2 This item shall be measured as the net area covered by fireproofing with the following formula according to the
Drawings, regardless of material and shape of fireproofing.

A=Lxl

A: Area of fireproofing
L : Perimeter length
l : Length of structure steel member covered by fireproofing

b b b b

a a a a
L=2x(a+b) L=2x(a+b) L=2x(a+b) L=2xb+a

FP-2A Fireproof ALC Board m2 Same as FP-1A

FP-3A Fireproof Rock Wool m2 Same as FP-1A

FP-4A Fireproof Mortar m2 Same as FP-1A

FP-5A Fireproof Concrete m2 Same as FP-1A

FP-6A Fireproof Brick m2 Same as FP-1A

04 Ex-C_Method Of Meas - 19 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

PP: UNDERGROUND PIPE WORK

PP-1 Concrete Pipe m This item shall be measured as the net length of pipelines in accordance with the Drawings.
Fittings and accessories are deemed to be included in this BQ Item Code, and shall not be measured separately.

PP-2 Plastic Pipe m Same as PP-1

PP-3 Clay Pipe m Same as PP-1

PP-4 Asbestos Cement Pipe m Same as PP-1

PP-5 Cast-Iron Pipe m Same as PP-1

PP-6 Steel Pipe m Same as PP-1

04 Ex-C_Method Of Meas - 20 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

PC: PRE-CAST CONCRETE UNIT WORK

PC-1A Pre-Cast Curbstone m This item shall be measured as the net length of pre-cast curbstone in accordance the Drawings.
Gaps or voids shall not be measured but be deducted from the BOQ.

PC-2A Pre-Cast Concrete Plate m2 This item shall be measured as the net area of pre-cast concrete plate in accordance with the Drawings.
Gaps or voids shall not be measured but be deducted from BOQ.

PC-3A Pre-Cast L-Gutter m This item shall be measured as the net length of pre-cast L-Gutter in accordance with the Drawings.
Gaps or voids shall not be measured but be deducted from BOQ.

PC-4A Pre-Cast Catch Basin nos This item shall be measured as the number of pre-cast catch basin in accordance with the Drawings.

PC-4B Pre-Cast Manhole nos Same as PC-4A, but “catch basin “ shall be read as “manhole”.

04 Ex-C_Method Of Meas - 21 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

MA: MASONRY WORK

MA-1A Brick m2 This item shall be measured as the net area of brickwork in accordance with the Drawings,
-1B irrespective of its inclination.
-1C Opening shall not be measured as particular work volume and all opening exceeding 0.5 m2 shall be
deducted from the gross area.
No wastage shall be included for breakage, loss and damage in the work volume.

MA-2A Concrete Block m2 Same as MA-1A, but “brick” shall be read as “block”.
-2B
-2C
-2D

MA-3A Fire Brick m2 Same as MA-1A, but “brick” shall be read as “fire brick”.

MA-4A Stone Riprap m2 Same as MA-1A, but “brick” shall be read as “stone riprap”.

MA-4B Concrete Block Riprap m2 Same as MA-1A, but “brick” shall be read as “block riprap”.

04 Ex-C_Method Of Meas - 22 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

PL: PLASTER WORK

PL-1A Metal Trowel Finish for Floor m2 This item shall be measured as the net area finished with metal trowel in accordance with the Drawings.

PL-1B Surface Finish for Road/Paving/ m2 This item shall be measured as the net area of concrete road/paving/slab on grade, where the surface
finish is made in accordance with the Drawings.
Concrete Slab on grade

PL-2A Mortar Finish for Floor m2 This item shall be measured as the net area of floor, where mortar finish is provided in accordance with the Drawings.

PL-2B Mortar Skirting m2 This item shall be measured as the net area of skirting made of mortar in accordance with the Drawings.

PL-2C Mortar Finish for Wall/Ceiling m2 This item shall be measured as the net area of wall/ceiling, where mortar finish is provided in accordance with the
Drawings.

PL-2D Mortar Finish for Foundation m2 Same as PL-1A, but “metal trowel” shall be read as “mortar”.

PL-3A Mortar Grouting for Equipment m3 This item shall be measured as the net volume of filled mortar in accordance with the Drawings.

PL-4A Lithin Coat Finish m2 Same as PL-1A, but “metal trowel” shall be read as “lithin coat”.

PL-4B Resin Coat Finish m2 Same as PL-1A, but “metal trowel” shall be read as “resin coat”.

PL-5A Gypsum Plaster for Wall/Ceiling m2 Same as PL-1A, but “metal trowel” shall be read as “gypsum plaster”.

PL-5B Field Terrazzo m2 Same as PL-1A, but “metal trowel” shall be read as “field terrazzo”.

04 Ex-C_Method Of Meas - 23 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

LN: LINING WORK

LN-1A Asphalt Coating m2 This item shall be measured as the net area in accordance with the Drawings.
Surface area to be finished shall be measured only once, regardless of the required number of coats or lining.

LN-2A Stainless Steel Lining m2 Same as LN-1A

LN-3A Sheet Lining for Earth Pond m2 Same as LN-1A

LN-4A Floor Hardener m2 Same as LN-1A

LN-5A Chemical Resistant Brick m2 Same as LN-1A

LN-5B Chemical Resistant Tile m2 Same as LN-1A

LN-5C-1 Chemical Resistant Resin Mortar m2 Same as LN-1A


-2

LN-5D Chemical Resistant Resin Coating m2 Same as LN-1A

LN-5E-1 Chemical Resistant Resin Lining m2 Same as LN-1A


-2

04 Ex-C_Method Of Meas - 24 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

WP: WATER PROOFING WORK

WP-1A Membrane Waterproofing m2 This item shall be measured as the net area to be waterproofed in accordance with the Drawings.
-2A Measurement shall be made only once, irrespective of the required number of layers.
-3A Upstanding portion at parapets and corners shall also be measured as part of the net area.
Openings shall not be measured as particular work volume and all openings exceeding 0.5 m2 shall be
deducted from the gross area.

WP-4A Waterproof Coating m2 Same as WP-1A

WP-5A Waterproof Mortar m2 Same as WP-1A

WP-6A Moisture Protection m2 Same as WP-1A, but shall be applied to “moisture protection” in lieu of “waterproofing”.

04 Ex-C_Method Of Meas - 25 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

ML: METAL & PLASTIC WORK

ML-1A Floor Drain nos This item shall be measured as the net number of floor drain in accordance with the Drawings.

ML-1B Roof Drain nos Same as ML-1A, but “floor drain” shall be read as “roof drain”.

ML-2A Down Pipe m This item shall be measured as net length of down pipe in accordance with the Drawings.
Accessories shall not be measured as particular work volume.

ML-2B Eaves Gutter m Same as ML-2A, but “down pipe “ shall be read as “ eaves gutter”.

ML-2C Valley Gutter m Same as ML-2A, but “down pipe” shall be read as “valley gutter”.

ML-2D Metal Coping m Same as ML-2A, but “down pipe “ shall be read as “ metal coping”.

ML-3A Metal Lathing m2 This item shall be measured as net area where metal lathing is provided in accordance with the Drawings.
Overlapping shall not be taken into account in the BOQ.

ML-4A Steel Frame Backing for Ceiling m2 Same as ML-3A, but “metal lathing” shall be read as “steel frame backing”.

ML-4B Steel Frame Backing for Wall m2 Same as ML-4A

ML-4C Wooden Frame Backing for Wall m2 Same as ML-4A, but “steel frame backing” shall be read as “wooden frame backing”.

ML-5A Manhole Cover (Cast Iron) nos Same as ML-1A, but “floor drain “ shall be read as “manhole cover”.
Frame and accessories shall not be measured in a particular item.

ML-5B Grating Cover m2 This item shall be measured as net projection area of grating cover in accordance with the Drawings.
Accessories, fittings and frame shall not be measured in a particular item.

ML-5C Checkered Plate Cover m2 Same as ML-5B, but “grating” shall be read as “checkered plate”.

04 Ex-C_Method Of Meas - 26 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

ML-6A Net Fence m2 This item shall be measured as net area of fence (height of net fence x length of net fence) in accordance with the
Drawings. Foundation and earth work are included in this BQ Item Code, but shall not be measured particularly in
BOQ.

ML-6B Barbed Wire Fence m2 Same as ML-6A, but “net fence” shall be read as “ barbed wire fence”.

ML-6C Steel Gate m2 Same as ML-6A, but “net fence” shall be read as “ steel gate”.

ML-7A Guardrail m This item shall be measured as net length of guardrail in accordance with the Drawings.
Foundation and earth work are included in this BQ Item Code but shall not be measured particularly in BOQ.

ML-8A Roof Ventilator nos Same as ML-1A, but “floor drain” shall be read as “roof ventilator”.
(Natural & Spot Type)

ML-8B Roof Ventilator m Same as ML-2A, but “down pipe” shall be read as “roof ventilator”.
(Continuous Type)

ML-9A Bird/Insect Screen m2 Same as ML-3A, but “metal lathing” shall be read as “bird/insect screen”.

04 Ex-C_Method Of Meas - 27 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

RO: ROOFING & SIDING WORK

RO-1A Cement Sheet (Roof) m2 This item shall be measured as the net area of finished surface of the roof and/or wall in accordance with
the Drawings.
Overlapping of each sheet shall be disregarded in BOQ and projection area shall be measured only once in BOQ.
Valley, ridge and corner shall not be measured as particular work volume, but shall be measured in square meters
comprehensively together with the finished surface.
Openings shall not be measured as particular work volume and all opening exceeding 0.5 m2 shall be deducted
from BOQ.
Accessories (e.g. fixing bolts, clips, tacks, joint sealer and the like) shall not be measured as particular work
volume, but shall be included in this BQ Item Code.

RO-1B Iron Sheet (Roof) m2 Same as RO-1A

RO-1C Aluminum Sheet (Roof) m2 Same as RO-1A

RO-1D F.R.P. Sheet (Roof) m2 Same as RO-1A

RO-1E Sandwich Panel (Roof) m2 Same as RO-1A

RO-2A Cement Sheet (Wall) m2 Same as RO-1A

04 Ex-C_Method Of Meas - 28 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

RO-2B Iron Sheet (Wall) m2 Same as RO-1A

RO-2C Aluminum Sheet (Wall) m2 Same as RO-1A

RO-2D F.R.P. Sheet (Wall) m2 Same as RO-1A

RO-2E Sandwich Panel (Wall) m2 Same as RO-1A

RO-3A Glass/Rock Wool Insulation m2 Same as RO-1A

RO-3B Foamed Plastic Insulation m2 Same as RO-1A

RO-4A Excelsior Board m2 Same as RO-1A

04 Ex-C_Method Of Meas - 29 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

AL: ALC BOARD WORK

AL -1A ALC Board m2 This item shall be measured as the net area of finished surface of the roof, wall and/or floor
-1B in accordance with Drawings.
-1C Opening shall not be measured as particular work volume and all opening exceeding 0.5 m2
-2A shall be deducted from the BOQ.
-2B Accessories shall not be measured separately, but shall be deemed to be included in the BOQ.
-2C
-3A
-3B
-3C

04 Ex-C_Method Of Meas - 30 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

JN: JOINERY WORK

JN-1A Wooden Door m2 This item shall be measured as net area of the joineries in accordance with Drawings.
Frame, hardware and accessories shall not be measured as particular work volume.

JN-1B Steel Door m2 Same as JN-1A

JN-1C Steel Hanger Door m2 Same as JN-1A

JN-1D Aluminum Door m2 Same as JN-1A

JN-1E Fire Resistant Door m2 Same as JN-1A

JN-1F Blast Resistant Door m2 Same as JN-1A

JN -2A Rolling Shutter m2 Same as JN-1A


-2B

JN-3A Wooden Window m2 Same as JN-1A

JN-3B Steel Window m2 Same as JN-1A

JN-3C Aluminum Window m2 Same as JN-1A

JN-4A Wooden Louver m2 Same as JN-1A

JN-4B Steel Louver m2 Same as JN-1A

JN-4C Aluminum Louver m2 Same as JN-1A

04 Ex-C_Method Of Meas - 31 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

GL: GLAZING WORK

GL-1A Clear Glass m2 This item shall be measured as the net area of finished surface of the glass (for windows, etc.) in accordance with
the Drawings.

GL-1B Figured Glass m Same as GL-1A

GL-1C Wired Glass m2 Same as GL-1A

04 Ex-C_Method Of Meas - 32 -
EXHIBIT-C (1) Attachment (2)

BQ/Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

IN: INTERIOR FINISHING WORK

IN-1A Plastic Flooring m2 This item shall be measured as net area of finished surface of the floor in accordance with Drawings.
Opening shall not be measured as particular work volume and all opening exceeding 0.5 m2 be deducted
from the BOQ.

IN-1B Wooden Flooring m2 Same as IN-1A

IN-1C Terrazzo Tile m2 Same as IN-1A

IN-1D Free Access Floor m2 Same as IN-1A

IN-1E Carpet m2 Same as IN-1A

IN-2A Cement Board (Wall) m2 Same as IN-1A, but “floor” shall be read as “wall”.

IN-2B Gypsum Plaster Board (Wall) m2 Same as IN-2A

IN-2C Calcium Silicate Board (Wall) m2 Same as IN-2A

IN-2D Plywood Board (Wall) m2 Same as IN-2A

IN-3A Wooden Fiber Board (Ceiling) m2 Same as IN-1A, but “floor” shall be read as “ceiling”.

04 Ex-C_Method Of Meas - 33 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

IN-3B Cement Board (Ceiling) m2 Same as IN-3A

IN-3C Gypsum Plaster Board (Ceiling) m2 Same as IN-3A

IN-3D Rock Wool Board (Ceiling) m2 Same as IN-3A

IN-4A Plastic/Wood Skirting m This item shall be measured as net length of the skirt in accordance with Drawings.

IN-5A Movable Partition m2 This item shall be measured as net area of the partition.
Fitting and accessories shall not be measured as particular work volume.

IN-5B Toilet Partition m2 Same as IN-5A

IN-5C Accordion Door/Partition m2 Same as IN-5A

IN-6A Curtain m2 Same as IN-5A, but “partition” shall be read as “curtain”.

IN-6B Venetian Blind m2 Same as IN-5A, but “partition” shall be read as “venetian blind”.

04 Ex-C_Method Of Meas - 34 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

TL: CERAMIC TILE WORK

TL-1A Ceramic Floor Tile m2 This item shall be measured as net area of finished surface of the floor in accordance with the Drawing.
Opening shall not be measured as particular work volume and all opening exceeding 0.5 m2 shall be deducted
from the BOQ.

TL-2A Ceramic Exterior Wall Tile m2 Same as TL-1A, but “floor” shall be read as “exterior wall”.

TL-3A Ceramic Interior Wall Tile m2 Same as TL-1A, but “floor shall be read as “interior wall”.

04 Ex-C_Method Of Meas - 35 -
EXHIBIT-C (1) Attachment (2)

BQ item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

ME: MECHANICAL EQUIPMENT WORK

ME-1A Overhead Crane lot This item shall be measured as the number of the crane sets including girders and accessories in accordance with
Drawings. Power supply including distribution panel and thereafter and control system shall be included in this
WORK ITEM but shall not be measured as particular BOQ.

ME-2A Hoist nos Same as ME-1A, but “crane sets” shall be read as “hoist sets”.

ME-3A Elevator lot Same as ME-1A, but “crane sets” shall be read as “elevator sets”.

04 Ex-C_Method Of Meas - 36 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

SI: SOIL IMPROVEMENT WORK

SI-1A Soil Replacement m3 This item shall be measured as net volume of replaced soil in accordance with Drawings.

No bulking nor wastage shall be added to the BOQ.

SI-2A Cement/Chemical Stabilization m3 This item shall be measured as net volume of the soil improved in accordance with Drawings.

No bulking of soil nor wastage of cement/chemical shall be added to the BOQ.

SI-3A Pre-Loading m3 This item shall be measured as net volume of the materials piled up for surcharge in accordance with Drawings.

No wastage of the surcharge materials shall be added to the BOQ.

SI-4A Vertical Drain m This item shall be measured as net length of the vertical drain in accordance with Drawings.

SI-5A Sand Compaction Pile m Same as SI-4A, but “vertical drain” shall be read as “sand compaction pile”.

SI-6A Dynamic Consolidation m2 This item shall be measured as net surface area of land improved in accordance with Drawings.

SI-7A Soil Improvement Pile m2 Same as SI-6A

04 Ex-C_Method Of Meas - 37 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

GR: GREEN WORK

GR-1A Turfing m2 This item shall be measured as net area of finished surface of the turfing in accordance with Drawings.

GR-2A Landscaping m2 Same as GR-1A

04 Ex-C_Method Of Meas - 38 -
EXHIBIT-C (1) Attachment (2)

BQ Item
WORK ITEM UNIT MEASUREMENT OF WORK
Code

RM: REMOVAL WORK

RM-1A Removal of Building m2 This item shall be measured as net floor area of the buildings in accordance with Drawings.
-1B
-1C

RM-2A Removal of Joineries/Sheets m2 This item shall be measured as net area of the joineries/sheets in accordance with Drawings.

RM-2B Removal of Block/Brick Wall m2 Same as RM-2A, but “joineries/sheets” shall be read as “block/brick wall”.

RM-3A Removal of Underground Pipe ton This item shall be measured as net weight of the pipes in accordance with Drawings, regardless of size and
materials of the pipes.

RM-3B Removal of RC Sub-Structure m3 This item shall be measured as net volume of the removed RC Sub-structure before removal in accordance
with Drawings.

RM-3C Removal of RC Super-Structure m3 Same as RM-3B

RM-3D Removal of RC Paving/Floor m3 Same as RM-3B

RM-3E Removal of Asphalt Paving/Floor m2 This item shall be measured as net area of the removed paving/floor in accordance with Drawings.

RM-4A Removal of Steel Structure ton This item shall be measured as net weight of the removed steel structure in accordance with Drawings.

04 Ex-C_Method Of Meas - 39 -