PMT OPRNS

NMK
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MAA

5.3.1.1.3 Remove existing pipe guard rail.


ENGG CERT

HAK

5.3.2 New Work: Refer to Drawing No. HA-004774 sheet 005 index M, HA-
MMA

004774 sheet 006, index Q, Revision 00.

5.3.2.1 Valve Boxes

5.3.2.1.1 Install new CMU valve box wall.


ISSUED FOR CONSTRUCTION

5.3.2.1.2 Construct new reinforced concrete beam on top of the


CMU valve box wall.
DESCRIPTION

5.3.2.1.3 Install new structural steel beams and angle bar


complete with fixing parts to support valve box cover.

5.3.2.1.4 Install new 20mm thick galvanized steel plate cover


with manhole.

5.3.2.1.5 Apply sand cement plaster on the existing and new


JO/EWO
12-27-2020 20U033

CMU interior wall surface.

5.3.2.1.6 Prepare and apply epoxy paint finish to steel plate


DATE

cover and manhole cover including top of concrete.


NO.
REV

00

5.3.2.1.7 Re-paint steel plate cover of the existing adjacent


DISCIPLINE
ENGINEER
valve box.
BOS
12-22-2020
DATE: 5.3.2.1.8 Restore affected areas back to its original shape.
PROJECT
ENGINEER
MMA 5.3.2.2 Parking Sunshade
DATE:12-23-2020
CERTIFIED 5.3.2.2.1 Construct new single and double parking sunshades
HAK
complete with reinforced concrete footing and
12-23-2020
DATE: pedestal, steel framing system and fabric membrane.
CONSTRUCTION
AGENCY
MAA 5.4 Mechanical - Plumbing (Non-Electrical Utilities)
12-27-2020
DATE:
OPERATIONS 5.4.1 General
NMK
12-27-2020 5.4.1.1 All works shall be done in accordance to SAES-S-030, SAES-L-
DATE:
CONTROL NUMBER

105, SAES-S-060 and other applicable Saudi ARAMCO


VERIFICATION

Standard.
EDSD

5.4.1.2 Shut-off isolation valves serving the area prior to start of any
DATE:
BY:

piping work. CONTRACTOR to verify exact location. Padlock the


REVISIONCERTIFICATION

valve handle to protect against accidental opening of the valve.


APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


00

Coordinate with SAUDI ARAMCO Project Engineer and Utilities


Department.
(DCC) NO. _____________________
20U033-033

SCOPE OF WORK DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

SURFACE PARKING AT MUNIRAH COMPLEX DOC


21
1S61 A HE-004776
COMMUNITY SERVICES FACILITIES DH. of 00
DHAHRAN SAUDI ARABIA JO/EWO 20U033 221
PMT OPRNS

NMK
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MAA

5.4.1.3 Any work, which involves fire protection system, fire hydrant
should be coordinated professionally with Fire Protection
ENGG CERT

HAK

Inspection & Maintenance Unit (FPI & MU ,U&FSD, underground


MMA

utilities staff and Fire Protection Department (FrPD) staff.

5.4.1.4 All new plumbing installation shall be protected from


contamination during installation in accordance with SAES-S-
060, Chapter 6 Section 613.0 and shall be disinfected in
ISSUED FOR CONSTRUCTION

accordance with the requirements of Saudi Aramco Sanitary


Code (SASC), GI-0151.006
DESCRIPTION

5.4.1.5 All isolation valves shall be in compliance to SAES L-108.

5.4.1.6 For trust block wrap with neoprene material at the edges where
non metallic pipes shall be protected from contact with concrete
and fitting touches the metal support. Use 9COM Material number
for tape wrap 1000199982 / 1000199986 / 1000200030 or
equivalent.or to refer to SAES S-070.

5.4.1.7 CONTRACTOR shall submit a detailed Tie-in and shutdown


JO/EWO

procedures for SAUDI ARAMCO’s approval at least FOUR


12-27-2020 20U033

WEEKS before a Tie-in is scheduled.


DATE

5.4.1.8 Project Engineer shall coordinate with the CONTRACTOR to


submit as-built drawing to Operations Maintenance Support
NO.
REV

00

Group (OMSG) indicating name plate valve box numbers and


DISCIPLINE
ENGINEER
SAP number for each valve boxes, valve box cover to update the
BOS system.
12-22-2020
DATE:
PROJECT
ENGINEER 5.4.2 Demolition/Removal (Refer to Drawing No. HA-004773 Sheet No. 001,
MMA Rev. 00).
DATE:12-23-2020
CERTIFIED 5.4.2.1 Demolish existing valve boxes VB# 0646, VB# 0648, VB# 0649,
HAK
VB# 0650, VB# 0651, VB# 0652, and VB# 0659,
DATE:
12-23-2020
CONSTRUCTION
AGENCY 5.4.2.2 Demolish existing sewer manhole, DH No. 950, DH No. 965, DH
MAA No. 966 DH No. 967 DH No. and 968 DH No. 969
12-27-2020
DATE:
OPERATIONS 5.4.2.3 Remove existing fire hydrants No. DH No. 333, DH No. 334,and
NMK
DH No. 335. Provide blind flange underground.
12-27-2020
DATE:
CONTROL NUMBER

5.4.2.4 Cut and remove portion of existing gas line to be provided with
VERIFICATION

flanged at above ground.


EDSD

5.4.2.5 Remove existing pressure gauges for raw and sweet water from
DATE:
BY:

valve box No. DH 0657 to be relocated from outside side to inside


REVISIONCERTIFICATION

the valve box.


APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


00

(DCC) NO. _____________________


20U033-033

SCOPE OF WORK DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

SURFACE PARKING AT MUNIRAH COMPLEX DOC


22
1S61 A HE-004776
COMMUNITY SERVICES FACILITIES DH. of 00
DHAHRAN SAUDI ARABIA JO/EWO 20U033 221
PMT OPRNS

NMK
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MAA

5.4.2.6 Purge the existing gas line with nitrogen and cut the pipe with cold
cutting machine to prevent fire or explosion. Contractor shall
ENGG CERT

HAK

prepare & submit the cold cutting/tie-in procedure to U&FSD


MMA

further review and approval.

5.4.2.7 Cut and remove portion of existing above ground raw and sweet
water lines to be diverted to underground.
ISSUED FOR CONSTRUCTION

5.4.3 Water Supply System (Refer to Drawing No. HA-004773 Sheet No. 002
&, 003 Rev. 00).
DESCRIPTION

CONTRACTOR shall:

5.4.3.1 Excavate to required depth and length to accommodate the


installation of new valve boxes.and other modification works.

5.4.3.2 Construct reinforced concrete valve boxes complete with 6 mm


aluminum checkered plate cover and lifting handle. Apply
bituminous paint coatings to all concrete exposed surfaces.
JO/EWO
12-27-2020 20U033

5.4.3.3 Layout and install new raw water and drinking water piping shall
be laid and diverted underground in such a manner that new
piping and appurtenances shall be prepared and installed prior to
DATE

shut-down. Connecting the new lines for the tie-in shall be the
task to be done simultaneously for the existing 16ӯ raw water
NO.
REV

00

and 8ӯ drinking water lines which shall be cut from the main line
DISCIPLINE
ENGINEER
during the shutdown.
BOS
12-22-2020
DATE: 5.4.3.4 Install pipe support take –off above ground apply paint all pipe
PROJECT
ENGINEER supports with corrosion resistant coating.
MMA

DATE:12-23-2020 5.4.3.5 Pipes that pass thru concrete or Valve box wall shall be provided
CERTIFIED with wall entry sleeves and sealant/or equivalent.
HAK
12-23-2020
DATE: 5.4.3.6 Install new pipes,with check valve and gate valve tie in and
CONSTRUCTION
AGENCY connect to the existing raw and water supply means to the
MAA proposed valve boxes and stub-out with capped for future
12-27-2020
DATE: connection.
OPERATIONS
NMK
5.4.3.7 Install blind flange, all water supply force main pipe ends and
12-27-2020 provide capped to all drainage pipe, fill with concrete that need
DATE:
CONTROL NUMBER

to be abandoned.
VERIFICATION
EDSD

5.4.3.8 Reinstall existing pressure gauges for raw and sweet water from
valve box No. DH 0657 to be placed inside the valve box.
DATE:
BY:
REVISIONCERTIFICATION

5.4.3.9 Install new PVC pipe sleeves in a road crossing with capped at
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


00

both ends for future connection.


(DCC) NO. _____________________
20U033-033

SCOPE OF WORK DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

SURFACE PARKING AT MUNIRAH COMPLEX DOC


23
1S61 A HE-004776
COMMUNITY SERVICES FACILITIES DH. of 00
DHAHRAN SAUDI ARABIA JO/EWO 20U033 221
PMT OPRNS

NMK
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MAA

5.4.3.10 Backfill trench to existing ground surface level with selected sweet
sand bedding and marl fill compacted to not less than 95% density
ENGG CERT

HAK

determine by ASTM 1557, restore ground surface affected by the


MMA

work to match existing surfaces.

5.4.4 Testing ,Commissioning Procedures & Requirement

5.4.4.1 All equipment and materials including water required to perform


ISSUED FOR CONSTRUCTION

Raw and drinking water lines testing shall be furnished by the


Contractor.
DESCRIPTION

5.4.4.2 Flushing: Before backfilling and pressure testing and with all
valves in place, completely flush the drinking water system and
repairs all leaks. Flushing procedure shall be in accordance with
section 10.10.2 of NFPA-24 as applicable

5.4.4.3 All piping installed for the purpose of conveying raw water &
drinking water shall be tested after installation in accordance
with SAES-S- 070 Section 18. Piping shall not be pressurized
until it has cured in accordance with the manufacturer's
JO/EWO
12-27-2020 20U033

instructions. Comply with the requirements of SAES-A-004


during the hydro-test. Fresh water satisfying the requirements
of Section 18.2.b, SAES-S-070 (as defined in SAES-S-040
DATE

Section 6.3) shall be used for hydro testing. During hydro-test


all exposed pipes, joints and valves shall be carefully examined
NO.
REV

00

for leakage. Only permanent repair methods according to


DISCIPLINE
ENGINEER
SAES-S-070 Section 20 shall be acceptable for repair work.
BOS
12-22-2020
DATE: 5.4.4.4 The gauge used for pressure test shall be certified and
PROJECT
ENGINEER
approved by SAUDI ARAMCO representative.
MMA
5.4.4.5 A hydrostatic test pressure of 150 psi shall be used. The piping
DATE:12-23-2020
CERTIFIED shall be tested for a duration of four (4) hours with the line
HAK partially backfilled and with all joints exposed. If the line is
12-23-2020
DATE:
completely backfilled including all joints the test duration shall
CONSTRUCTION be 24 hours with pressure limit of 150 psi.
AGENCY
MAA
12-27-2020 5.4.4.6 All piping systems while being tested shall be protected from
DATE:
OPERATIONS
overpressure by calibrated relief valve (s) of adequate capacity
NMK set to relieve at 5 percent above the test pressure. The relief
12-27-2020 valve (s) shall be tested, dated, and tagged within one week
DATE:
prior to the test.
CONTROL NUMBER
VERIFICATION

5.4.4.7 Visible leaks of exposed joints shall be made tight welded. Pipe
EDSD

fittings and other materials found to be defective under test shall


DATE:

be repaired and restored as necessary until test requirements


BY:

are met satisfactorily. Repair of all leaking joints shall be at the


REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,

Contractor’s expense.
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


00

(DCC) NO. _____________________

5.4.4.8 The hydrostatic test shall be repeated after the repair of any
20U033-033

defect until the system is proved satisfactory.


SCOPE OF WORK DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

SURFACE PARKING AT MUNIRAH COMPLEX DOC


24
1S61 A HE-004776
COMMUNITY SERVICES FACILITIES DH. of 00
DHAHRAN SAUDI ARABIA JO/EWO 20U033 221
PMT OPRNS

NMK
SAUDI ARABIAN OIL COMPANY

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
MAA

5.4.4.9 The piping will be considered satisfactory if there is no evidence


of leakage or pressure loss observed during the specified test
ENGG CERT

HAK

period.
MMA

5.4.4.10 The CONTRACTOR is responsible for disposal of the water


discharged from the new water pipe after hydrostatic pressure
test.
ISSUED FOR CONSTRUCTION

5.4.4.11 The CONTRACTOR should strictly abide by the Engineering


Standards, rules and procedures for performing the hydro-test.
DESCRIPTION

5.4.4.12 Test and commission drain system and prove watertight in


accordance with SAES-S-060.

5.4.5 Completion

5.4.5.1 Upon satisfactory completion of testing and commissioning


operations, the systems shall be handed over to the SAUDI
ARAMCO Project Engineer and a completion certificate shall be
provided by the CONTRACTOR.
JO/EWO
12-27-2020 20U033

5.4.5.2 The area of the installation shall be cleaned and then signed over
to the Saudi Aramco Project Engineer.
DATE

5.5 Electrical
NO.
REV

00

DISCIPLINE
ENGINEER
5.5.1 General
BOS
12-22-2020
DATE: 5.5.1.1 CONTRACTOR shall conduct site survey to verify the existing
PROJECT
ENGINEER 13.8 kV Primary U/G cable, transformers and roadway lighting
MMA locations prior to the excavation works also to determine final
DATE:12-23-2020 arrangement of the duct banks and roadway lightings.
CERTIFIED
HAK
5.5.1.2 CONTRACTOR shall coordinate properly with other discipline
12-23-2020
DATE: prior to start the construction and avoid clashing of utilities.
CONSTRUCTION
AGENCY Any discrepancies that arise, CONTRACTOR may suggest a
MAA better routing & installation but subject for approval by
12-27-2020
DATE: Concerned Discipline & SAUDI ARAMCO Project Engineer
OPERATIONS prior to implementation of WORK.
NMK
12-27-2020 5.5.1.3 WORK shall be in accordance with the latest edition of NFPA
DATE:
CONTROL NUMBER

70 and SAUDI ARAMCO Engineering Codes and Standards


VERIFICATION

performed by qualified Electrical personnel approved by


EDSD

SAUDI ARAMCO Project Engineer. Only hand excavation


were allowed at the vicinity of existing primary & secondary
DATE:
BY:

U/G cables and around transformer location.


REVISIONCERTIFICATION

APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE

OF THIS DRAWING IS COVERED, FOR ALL

BY DRAWING COMPLETION CERTIFICATE


00

5.5.1.4 CONTRACTOR shall be responsible for the complete supply,


installation, testing and commissioning as deemed
(DCC) NO. _____________________

appropriate for the identified WORK items.


20U033-033

SCOPE OF WORK DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION

SURFACE PARKING AT MUNIRAH COMPLEX DOC


25
1S61 A HE-004776
COMMUNITY SERVICES FACILITIES DH. of 00
DHAHRAN SAUDI ARABIA JO/EWO 20U033 221