CHECK LIST FOR FIRE PUMP - NFPA 20 SYSTEMS GENERAL SUBMITTAL

REQUIREMENTS

Nb:
1 This checklist must be completed/answered by consultant(s) by ticking [√] appropriate boxes
2 Submit a separate sheet containing explanatory notes against all negated answers
3 It is axiomatic that the submission has been made by the consultants only upon having read and clearly understood all the relevant provisions of
the current Fire Protection, Fire Prevention and Fire/Emergency Control(FP, FP&FF) Regulations

FIRE PUMP INFORMATION [ horizontal or vertical]


1 Manufacturer specification sheet(s) provided YES NO
2 Model number details provided YES NO
3 Manufacturer specification sheet(s) provided YES NO
4 Proof that all equipment components are listed YES NO
5 GPM rating provided on the plans YES NO
6 Head rating provided on the plans YES NO
7 RPM's provided on the plans YES NO
8 Piping size and type is detailed YES NO
9 OS & Y valve in suction pipe is correctly detailed in the plans YES NO
10 Size of suction pipe and type is detailed YES NO
11 Check valve in pump discharge assembly YES NO
12 Eccentric taper reducer for suction is detailed (taper at bottom) YES NO
13 Vortex plate is provided when stored water is used YES NO
14 Indicating valve on the system side of the check valve YES NO
15 Pressure relief valve located between pump and pump discharge YES NO

FIRE PUMP INFORMATION [horizontal or vertical]


1 Emergency lighting provided in pump room YES NO
2 Automatic sprinkler protection provided in the pump room YES NO
3 Pump room floor drain provided YES NO
4 Pump room wiring in rigid or liquid tight flexible metal conduit YES NO
5 Double backflow preventer valve is detailed YES NO

ADDITIONAL INFORMATION VERTICAL PUMPS


1 Submergence level of pump impellers YES NO
2 Well screen and suction and strainer details YES NO
3 Dimensions of well YES NO
4 Air relief valves, water level detectors, pressure gauges, etc YES NO

DRIVER INFORMATION
1 Manufacturer and specification information provided YES NO
2 Model number provided YES NO
3 Rated horsepower provided YES NO
4 RPM's provided YES NO
5 Electric or diesel information provided YES NO
6 Hours of fuel supply given YES NO

ELECTRIC DRIVERS
1 Electrical circuit schematic provided YES NO
2 Schematic for secondary power circuit and transfer equipment YES NO
3 Controller near motors(more than 12" above floor and 3½' clearance YES NO
to the rear)
4 Controller listed for electric motor drivers YES NO
5 Alarm signal provided to an attended location YES NO
6 Transfer switch specification and listing provided YES NO
7 One transfer switch provided for each individual pump YES NO
CHECK LIST FOR FIRE PUMP - NFPA 20 SYSTEMS GENERAL SUBMITTAL
REQUIREMENTS
DIESEL DRIVERS
1 Listed fire pump used YES NO
2 Closed circuit and liquid cooling details provided in the plans YES NO
3 Equipped with over speed shutdown device YES NO
4 Instrument panel with tachometer, oil pressure, and temperature gauges YES NO
5 Two batteries provided for each engine- rack supported YES NO
6 Batteries have two means for recharging shown YES NO
7 Pump room & engine has adequate ventilation provided YES NO
8 Fuel tank is at least 1 gallon per horsepower plus a 5% cushion YES NO
9 The controller is listed for diesel pump use YES NO
10 Controller near motors(more than 12" above floor and 3½' clearance to the YES NO
rear)
11 Alarm signal provided to an attended location YES NO

JOCKEY PUMP INFORMATION


1 Jockey pump location and piping is detailed YES NO
2 Jockey pump specification sheet(s) provided with the plans YES NO
3 Jockey pump check valve is detailed on the discharge pipe YES NO

WATER SUPPLY INFORMATION


1 Minimum supply provided YES NO
2 Connection to water supply YES NO
3 FDC location is acceptable (within 50' of a public fire hydrant) YES NO

OTHER DETAILS
1 Dedicated ATS for individual Fire pumps sets provided for electric YES NO
driven pumps
2 Dedicated and direct Power supply for the fire pumps 2 sets provided YES NO
from the main distributin board of the source (DEWA Transformer)
3 Minimum 1m from all sides provided for easy access/maintenance of fire YES NO
protection system maintained inside the room
4 Controllers are placed inside the pump room with easy accessiblity YES NO
5 Control logic/pressure switch setting details provided YES NO
6 Adequate and appropriate ventilations for pump YES NO
7 Factory test curve & related test documents provided YES NO

Dilakukan Oleh, Disetujui Oleh,

PT. Anugerah PT. Adhi Karya, Tbk.


PT. Talya Teknindo PT. Pertamina (Persero)
Kamila Utama (Persero)

Signature

Name
Sign Date
Job Tittle