Professional Documents
Culture Documents
Unit-V
Unit-V
UNIT-V
PROJECT SCHEDULING
Prepared by
G Narender M.tech
Assistant professor
Anurag Engineering College
Ananthagiri, Kodada
Syllabus
Project scheduling – PERT – CPM, Resource
levelling, Construction claims, Dispute and Project
closure – Source of claim – Claim management –
Dispute resolution – Arbitration – Construction
closure – Contract closure – Documentation.
Introduction
The main objective of construction management is to
complete a prescribed quantum of work within specified
time at a previously estimated cost.
In order to achieve this objective, planning is necessary.
In the process of planning, one method and sequence of work
is selected from various possible ways in which a project can
be executed.
This requires a clear definition of all activities that have to be
carried out in order to complete the job
Project Scheduling
Scheduling is the determination of the time required for the
execution of each activity and the sequence in which the
activities have to be carried out.
Scheduling is required not only for construction activities but
also for the resources like men, material, machinery and
money.....
Controlling is the process in which differences between the
planned and the actual performance are reviewed after the
project has begun.
Controlling is required both for the physical progress of work
and the project cost.
Continue.......,
Although bar charts are used in a number of projects for
planning, scheduling and controlling the work, their utility is
limited due to the following reasons:
The bar chart does not show clearly the inter-relationships of
all activities.
When a delay occurs in a large project, many activities tend
to be crashed unnecessarily as it is almost impossible to
remember which activities in the bar chart are
interdependent.
Bar charts do not indicate critical areas of work.
Network Techniques
Network Techniques are effective tools for planning,
scheduling and controlling construction jobs.
The PCGI, BPE, IRC and many other professional
organisations have been advocating the use of network
techniques for project management.
These techniques provide a rational approach to the planning
and controlling of construction works.
The application of such techniques is inevitable when there is
a constraint on resources.
Different Types of Network Techniques
The two commonly used network techniques are PERT and
CPM.
CPM- Critical Path Method
PERT- Programme Evaluation and Review Technique.
While essentially both are identical, there are some minor
differences between the two techniques.
Comparison of PERT and CPM
PERT CPM
PERT is event oriented CPM is activity oriented
The time estimates for
Single time estimates are
activities are probabilistic.
The three types of time used for the various
estimates are used for each activities i.e. the time
activity: (i) estimates are deterministic
Optimistic time (to) (ii)
Pessimistic time (tp) (iii)
Likely time (tl) or most
likely time (tm)
Comparison of PERT and CPM
PERT CPM
PERT is used for pioneering CPM is used for repetitive
type of projects i.e. projects types of projects where the
which are the first of their time estimates for various
own kind and where prior activities are either known or
data about activity times is can be determined fairly or
not available. accurately
PERT lays emphasis on CPM places emphasis upon
reducing project completion optimising allocation of
time without cost resources and minimising
constraint. overall project cost.
PERT
Programme Evaluation and Review
Technique (PERT)
PERT was developed by engineers of the United States Navy
while working on the Polaris Missile Programme during 1957-
58.
Since then, PERT has been in use for various research and
development projects which are non-repititive in nature.
Such projects are characterised by an extreme degree of
uncertainty both in the development of the system and in the
time of duration of various activities.
Three time estimates are used to determine the expected or
average time of each activity.
The expected time forms the basis of PERT networks.
Computation of Expected Time
The three time estimates used in PERT are described below:
Optimistic Time Estimate(to) is the shortest possible time
for completing an activity if everything proceeds as planned
without any problem i.e. the activity is performed under
ideal conditions.
Most Likely Time Estimate (tm or tl) is the time for
completing an activity under normal conditions. In this case,
conditions are not ideal and minor mishaps may occur.
Computation of Expected Time
Pessimistic Time Estimate (tp) is the maximum time
required to complete an activity under abnormal or
extremely adverse conditions in which everything goes
wrong. The estimate, however, does not include catastrophes
such as fires, earthquakes, floods etc.
Computation of Expected Time
The average or expected time, te, is calculated as a weighted average of the three
estimates,
𝑆t = (𝑡p − 𝑡o) /6
𝑉t = (𝑆t)2
NUMERICAL PROBLEMS
Advantages of PERT
PERT are very useful in large, complex studies where
overlooking details may create unresolvable problems.
PERT fecilitates identification of the critical path and makes
this visible.
It incorporates risk analysis in project network.
PERT determines critical activities in the project.
PERT determines the most economical schedule for a fixed
project duration.
CPM
Critical Path Method (CPM)