♦ what is the maximum allowable over pull while POOH in vertical and horizontal well ?
20klbs
♦ we can use separator while drilling instead of vacum degassed, Why?
a- true b-false
False …..seperator can only be used while killing a well
♦ How to use top drive function to make a connection
Set slips,break out top drive from drill string ,plup new stand make up near stand in drill
string
1/2
♦ What is the most important steps in blowout prevention once awarning sign has been
detected ?
Start circulation with per circulated rate and kill the well barite-
Shut the blow out preventer-
Pull to the shoe quickly-
Call the tool pusher and company man-
Close the well in properly-
♦ If the formation pressure gradient increase from 0.60 psi/ft at 1200 ft to 0.62 psi/ft at
12700 ft mud weight is 12 ppg through the interval the -overbalance increase by about
288 psi
-overbalance increase constant since mud weight not changed
-overbalance is reduced by 51 psi
-overbalance is reduced by 237 psi