Diagram Barchat

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Mode Task Name Duration Start Finish Predecessors

W T F
1 DIVISI 1. UMUM 26 days Fri 11/23/18 Tue 12/18/18
2 Mobilisasi 1 day Fri 11/23/18 Fri 11/23/18
3 Manajemen dan Keselamatan Lalu Lintas 26 days Fri 11/23/18 Tue 12/18/18
4 DIVISI 7. PEKERJAAN STRUKTUR 25 days Sat 11/24/18 Tue 12/18/18
5 Beton mutu sedang fc' 20 Mpa ( Rigid Jalan ) 7 days Mon 12/10/18 Sun 12/16/18 6
6 Beton mutu rendah fc' 10 Mpa 6 days Tue 12/4/18 Sun 12/9/18 7
7 Baja Tulangan 10 days Sat 11/24/18 Mon 12/3/18 2
8 Joint Sealent 2 days Mon 12/17/18 Tue 12/18/18 5

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Tue 11/13/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
Nov 25, '18 Dec 2, '18 Dec 9, '18 Dec 16, '18
F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Tue 11/13/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2