1 Jasa Inspeksi Turbine, Generator & Balance Of Plant PLTP Dieng Unit 1 14 days Mon 05/04/21 08:00 Sun 18/04/21 20:00 0%
2 Shutdown And Cooling Down Finish 0 days Mon 05/04/21 08:00 Mon 05/04/21 08:00 05/04
3 Turbine 9 days Mon 05/04/21 08:00 Tue 13/04/21 17:00 0%
4 Disassembly 4 days Mon 05/04/21 08:00 Thu 08/04/21 17:00 0%
5 Remove Turbine Isolation 4 hrs Mon 05/04/21 08:00 Mon 05/04/21 12:00 0%
6 Removing the spool pipes steam inlet and spray water 2 hrs Mon 05/04/21 13:00 Mon 05/04/21 15:00 0%
7 Open Manhole and Flip 2 hrs Mon 05/04/21 15:00 Mon 05/04/21 17:00 0%
8 Take off Bolt & Nut Turbine Casing 8 hrs Tue 06/04/21 08:00 Tue 06/04/21 17:00 0%
9 Disassembly Trimming Valve 3 hrs Wed 07/04/21 08:00 Wed 07/04/21 11:00 0%
10 Lifting Up Casing Turbine 7 hrs Wed 07/04/21 11:00 Thu 08/04/21 10:00 0%
11 Uninstall Instrument & Control Equipment Part 1 hr Thu 08/04/21 10:00 Thu 08/04/21 11:00 0%
12 Disassembly Turning Gear 2 hrs Tue 06/04/21 08:00 Tue 06/04/21 10:00 0%
13 Disassembly Front Standard 2 hrs Thu 08/04/21 10:00 Thu 08/04/21 12:00 0%
14 Disassembly Turbine Bearing 1 & 2 (Casing + Journal) 4 hrs Thu 08/04/21 13:00 Thu 08/04/21 17:00 0%
15 Execution 4,13 days Wed 07/04/21 11:00 Sun 11/04/21 12:00 0%
16 Cleaning Trimming Valve 4 hrs Wed 07/04/21 11:00 Wed 07/04/21 16:00 0%
17 Cleaning Casing Turbine & Bolt Nut 16 hrs Thu 08/04/21 10:00 Sat 10/04/21 10:00 0%
18 Perform measuring initial Data (Clearence Bearing etc, Alignment and Run Out Rotor) 10 hrs Fri 09/04/21 08:00 Sat 10/04/21 10:00 0%
19 Check/Replace Turbine Bearing 1 & 2 if Required + NDT* 10 hrs Fri 09/04/21 13:00 Sat 10/04/21 15:00 0%
20 Boroscope Turbine 16 hrs Fri 09/04/21 08:00 Sat 10/04/21 17:00 0%
21 Perform Life Assesment MOP + Replace Bearing if Required + NDT 4 hrs Fri 09/04/21 13:00 Fri 09/04/21 17:00 0%
22 Clearance Check Labyrinth Diaphragm 8 hrs Fri 09/04/21 13:00 Sat 10/04/21 12:00 0%
23 Check of Rotor Turbine 8 hrs Sat 10/04/21 13:00 Sun 11/04/21 12:00 0%
24 Thrust & Eccentricity Instrument Calibration 4 hrs Thu 08/04/21 11:00 Thu 08/04/21 16:00 0%
25 Turbine Instrumentation Calibration 4 hrs Thu 08/04/21 16:00 Fri 09/04/21 11:00 0%
26 Cleaning Servo CV 1 & CV 2 8 hrs Wed 07/04/21 16:00 Thu 08/04/21 16:00 0%
27 Assembly 2,5 days Sun 11/04/21 13:00 Tue 13/04/21 17:00 0%
28 Assembly Casing Turbine & Trimming Valve 6 hrs Sun 11/04/21 13:00 Mon 12/04/21 10:00 0%
29 Assembly Turbine Bearing 1 & 2 4 hrs Sun 11/04/21 13:00 Sun 11/04/21 17:00 0%
30 Assembly Front Standard 2 hrs Mon 12/04/21 10:00 Mon 12/04/21 12:00 0%
31 Assembly Turning Gear 2 hrs Mon 12/04/21 13:00 Mon 12/04/21 15:00 0%
32 Install and Tightening Bolt & Nut Turbine Casing 8 hrs Mon 12/04/21 15:00 Tue 13/04/21 15:00 0%
33 Assembly Spool Pipe Steam Inlet Turbine 2 hrs Tue 13/04/21 15:00 Tue 13/04/21 17:00 0%
34 Generator 9 days Mon 05/04/21 08:00 Tue 13/04/21 17:00 0%
35 Disassembly 2,5 days Mon 05/04/21 08:00 Wed 07/04/21 12:00 0%
36 Disconnect Generator Output Terminal cable and star connection 4 hrs Mon 05/04/21 08:00 Mon 05/04/21 12:00 0%
37 Remove the Exciter Cover and remove the Carbon Brush. 4 hrs Mon 05/04/21 13:00 Mon 05/04/21 17:00 0%
38 Disassembly Bearing 3 & 4 Generator 8 hrs Tue 06/04/21 08:00 Tue 06/04/21 17:00 0%
39 Remove Generator Cover 4 hrs Wed 07/04/21 08:00 Wed 07/04/21 12:00 0%
40 Disassembly Generator Cover Water Cooler 4 hrs Tue 06/04/21 08:00 Tue 06/04/21 12:00 0%
41 Execution 3,5 days Wed 07/04/21 08:00 Sat 10/04/21 12:00 0%
42 Cleareance Measurement & Check Cover Generator 4 hrs Wed 07/04/21 13:00 Wed 07/04/21 17:00 0%
43 Check/Replace Generator Bearing 3 & 4 if Required + NDT* 10 hrs Thu 08/04/21 08:00 Fri 09/04/21 10:00 0%
44 Check Slip Ring Generator/Replace if Required. 8 hrs Wed 07/04/21 08:00 Wed 07/04/21 17:00 0%

Page 1
WBS Update PLTP Dieng.mpp
ID Task Name Duration Start Finish
04 Apr '21 11 Apr '21 18 Apr '21
S M T W T F S S M T W T F S S M T
45 Isolation Stator test:Insulation Resistance 4 hrs Thu 08/04/21 08:00 Thu 08/04/21 12:00 0%
46 Isolation Rotor test:Insulation Resistance 4 hrs Thu 08/04/21 13:00 Thu 08/04/21 17:00 0%
47 Isolation Stator test: Ohm test, Partial Discharge, Tangen Delta, Insulation Resistance 12 hrs Fri 09/04/21 08:00 Sat 10/04/21 12:00 0%
48 Assembly 3,5 days Sat 10/04/21 13:00 Tue 13/04/21 17:00 0%
49 Assembly Generator Bearing 3 & 4 8 hrs Sat 10/04/21 13:00 Sun 11/04/21 12:00 0%
50 Install the Exciter Cover and Carbon Brush 4 hrs Sun 11/04/21 13:00 Sun 11/04/21 17:00 0%
51 Reinstall the Terminal Output Generator cable connection and the star connection 4 hrs Mon 12/04/21 08:00 Mon 12/04/21 12:00 0%
52 Install generator cover both side 4 hrs Mon 12/04/21 13:00 Mon 12/04/21 17:00 0%
53 Perform Clearance Check After Installation (Bearing, cover, oil guard) 8 hrs Mon 12/04/21 13:00 Tue 13/04/21 12:00 0%
54 Install and tightening Bolt Generator Cover 4 hrs Tue 13/04/21 13:00 Tue 13/04/21 17:00 0%
55 Balance Of Plant 8,75 days Mon 05/04/21 08:00 Tue 13/04/21 15:00 0%
56 Penggantian Drain Line System Scrubber 12 hrs Mon 05/04/21 08:00 Tue 06/04/21 12:00 0%
57 Pembuatan drine line ejector (Steam trap baru) 12 hrs Tue 06/04/21 13:00 Wed 07/04/21 17:00 0%
58 Inspection and Cleaning Motor Auxilary Pump MP-103 AB 6 hrs Mon 05/04/21 08:00 Mon 05/04/21 15:00 0%
59 Inspection and Cleaning Pump Auxilary Pump MP-103 AB 6 hrs Sat 10/04/21 08:00 Sat 10/04/21 15:00 0%
60 Inspection and Cleaning Motor Vacuum Pump MP-104 AB 6 hrs Mon 05/04/21 15:00 Tue 06/04/21 12:00 0%
61 Inspection and Cleaning Pump Vacuum Pump MP-104 AB 6 hrs Sat 10/04/21 15:00 Sun 11/04/21 12:00 0%
62 Inspection and Cleaning Motor Jockey CHO Pump MP-122 AB 6 hrs Tue 06/04/21 13:00 Wed 07/04/21 10:00 0%
63 Inspection and Cleaning Pump Jockey CHO Pump MP-122 AB 6 hrs Sun 11/04/21 13:00 Mon 12/04/21 10:00 0%
64 Inspection and Cleaning Motor Main EHC MP-128 AB 6 hrs Wed 07/04/21 10:00 Wed 07/04/21 17:00 0%
65 Inspection and Cleaning Pump Main EHC MP-128 AB 6 hrs Mon 12/04/21 10:00 Mon 12/04/21 17:00 0%
66 Inspection and Cleaning Motor Lifting Pump AB 6 hrs Thu 08/04/21 08:00 Thu 08/04/21 15:00 0%
67 Inspection and Cleaning Pump Lifting Pump AB 6 hrs Tue 13/04/21 08:00 Tue 13/04/21 15:00 0%
68 Tightening Check of Cooling Tower Structure using Torque Tool 6 hrs Tue 13/04/21 08:00 Tue 13/04/21 15:00 0%
69 Install The New Strainer Ejector 16 hrs Thu 08/04/21 08:00 Fri 09/04/21 17:00 0%
70 Pengukuran Ration CT & PT All, Arester 40 hrs Thu 08/04/21 08:00 Mon 12/04/21 17:00 0%
71 Additional Pengujian dan Service Transformer 6,75 days Mon 05/04/21 18:00 Mon 12/04/21 15:00 0%
72 Pengujian dan Service Transformer EE‐TX‐1A (15KV‐6KV) 2 days Mon 05/04/21 18:00 Wed 07/04/21 17:00 0%
73 Cleaning Isolator 1 au 2 hrs Mon 05/04/21 18:00 Mon 05/04/21 20:00 0%
74 Cleaning Bushing 1 au 2 hrs Tue 06/04/21 08:00 Tue 06/04/21 10:00 0%
75 Jasa Purifying Minyak Trafo (2717 Liter) 10 hrs Tue 06/04/21 10:00 Wed 07/04/21 10:00 0%
76 Pengujian Tegangan Tembus Minyak 2 hrs Tue 06/04/21 15:00 Tue 06/04/21 17:00 0%
77 Pengujian Karakteristik Minyak Trafo 4 hrs Tue 06/04/21 15:00 Tue 06/04/21 20:00 0%
78 Pengujian DGA 2 hrs Wed 07/04/21 08:00 Wed 07/04/21 10:00 0%
79 Pengecekan Spare Part Instrumentasi dan rekomendasi 6 hrs Wed 07/04/21 10:00 Wed 07/04/21 17:00 0%
80 Pengujian dan Service Transformer EE‐TX‐1B (15KV‐380V) 2 days Wed 07/04/21 10:00 Fri 09/04/21 10:00 0%
81 Cleaning Isolator 1 au 2 hrs Wed 07/04/21 10:00 Wed 07/04/21 12:00 0%
82 Cleaning Bushing 1 au 2 hrs Wed 07/04/21 13:00 Wed 07/04/21 15:00 0%
83 Jasa Purifying Minyak Trafo (1520 Liter) 10 hrs Wed 07/04/21 15:00 Thu 08/04/21 15:00 0%
84 Pengujian Tegangan Tembus Minyak 2 hrs Thu 08/04/21 10:00 Thu 08/04/21 12:00 0%
85 Pengujian Karakteristik Minyak Trafo 4 hrs Thu 08/04/21 10:00 Thu 08/04/21 15:00 0%
86 Pengujian DGA 2 hrs Thu 08/04/21 15:00 Thu 08/04/21 17:00 0%
87 Pengecekan Spare Part Instrumentasi dan rekomendasi 6 hrs Thu 08/04/21 15:00 Fri 09/04/21 10:00 0%
88 Pengujian dan Service Transformer EE‐TX‐1C (15KV‐380V) 2 days Thu 08/04/21 18:00 Sat 10/04/21 17:00 0%

Page 2
WBS Update PLTP Dieng.mpp
ID Task Name Duration Start Finish
04 Apr '21 11 Apr '21 18 Apr '21
S M T W T F S S M T W T F S S M T
89 Cleaning Isolator 1 au 2 hrs Thu 08/04/21 18:00 Thu 08/04/21 20:00 0%
90 Cleaning Bushing 1 au 2 hrs Fri 09/04/21 08:00 Fri 09/04/21 10:00 0%
91 Jasa Purifying Minyak Trafo (1520 Liter) 10 hrs Fri 09/04/21 10:00 Sat 10/04/21 10:00 0%
92 Pengujian Tegangan Tembus Minyak 2 hrs Fri 09/04/21 15:00 Fri 09/04/21 17:00 0%
93 Pengujian Karakteristik Minyak Trafo 4 hrs Fri 09/04/21 15:00 Fri 09/04/21 20:00 0%
94 Pengujian DGA 2 hrs Sat 10/04/21 08:00 Sat 10/04/21 10:00 0%
95 Pengecekan Spare Part Instrumentasi dan rekomendasi 6 hrs Sat 10/04/21 10:00 Sat 10/04/21 17:00 0%
96 Pengujian dan Service Transformer 6KV‐250V (EE‐TX‐1E) 1,75 days Sat 10/04/21 10:00 Sun 11/04/21 17:00 0%
97 Pengujian Insulation Resistance 1 au 2 hrs Sat 10/04/21 10:00 Sat 10/04/21 12:00 0%
98 Pengujian TAN DeLTa 1 au 2 hrs Sat 10/04/21 13:00 Sat 10/04/21 15:00 0%
99 Pengujian Turn Ratio 1 au 2 hrs Sat 10/04/21 15:00 Sat 10/04/21 17:00 0%
100 Pengujian SFRA 1 au 4 hrs Sat 10/04/21 18:00 Sun 11/04/21 10:00 0%
101 Pengujian DC Resistance 1 au 2 hrs Sun 11/04/21 10:00 Sun 11/04/21 12:00 0%
102 Pengujian Contact Resistance 1 au 2 hrs Sun 11/04/21 10:00 Sun 11/04/21 12:00 0%
103 Cleaning Isolator 1 au 2 hrs Sun 11/04/21 13:00 Sun 11/04/21 15:00 0%
104 Cleaning Bushing 1 au 2 hrs Sun 11/04/21 15:00 Sun 11/04/21 17:00 0%
105 Finishing Pekerjaan Trafo 8 hrs Sun 11/04/21 18:00 Mon 12/04/21 15:00 0%
106 Turning Gear On 1 hr Wed 14/04/21 08:00 Wed 14/04/21 09:00 0%
107 Machining Slip Ring 36 hrs Wed 14/04/21 08:00 Thu 15/04/21 20:00 0%
108 Assembly Exciter 8 hrs Thu 15/04/21 20:00 Fri 16/04/21 04:00 0%
109 Start Up 64 hrs Fri 16/04/21 04:00 Sun 18/04/21 20:00 0%