Professional Documents
Culture Documents
Lesson Learned 2020 SD Updaed 28 Nov 2020
Lesson Learned 2020 SD Updaed 28 Nov 2020
Lesson Learned 2020 SD Updaed 28 Nov 2020
Item Observation
3 Scaffolding
Many insulation works requested from different departements
after freezing Scope and some of them requested during SD
4
shortage in bolts and gasket and valves
5
the expander CMS overhauling in W/S takes long time and many
problems were faced during overhauling in addition delay in
supply chain of T/E material needed for unit A
6
repeated interruption of national grid power supply
7
enough spare bolts and gasket should be revised and flange management experit to
availed as stock before any major activities. review the stored materials
condition and fittness for
work and preservation
CMS overhauling to be at vendor W/S abroad and FAT
tested to be ready at site any time as a contingency
spare, and all critical material to be secured with
vendors/supplier before enough time period from SD's
Maint.
End of 2020
End of 2020
Mar-21
Planning/Operation/PMT
Eng./WH TL's
Item
Observation
1
Surplus material requirments during SD
2
long shift
3
Lack of LCP
5
one contractor for construction not proper in contengy cases
6
Lack of manual valves spares / repair kits
6
Repeated leakage from methanol injection point
7
lack of drain plugs / caps
12
16
Maint.
communications traffic
remark improved than before
it is important to find more channels and distribute and additional channels is
departement over radios channels security autherity not UGDC
autherity
recommended to have enough spaces /offices enough for
manapower New building hurry up and
using TCF for S/D manpower
facility
recommended to avail manpower with enough time and
to be familiar with UGDC rules , and to wear same UGDC
coverall Need to discuss
2020
2020
info
2020 Shut Down Lesson Learned (Closing and Start up Ph
Item
Observation
2
all lesson learned not well communicated
3
Close out PMR's related to SD activities