Daily Drilling Report

DANAN OILFIELD DEVELOPMENT


General Data
Country/ Province Iran / Ilam Well Type Deevelopment W.S.S. Day/ Night H.Parvizi / M.Onagh Report No. 263
Field/ Well No. DANAN-DA-13 Spud Date/ Time 09/15/2020(99/06/25)/02:00 Operations / Area Manager M.Amini / M.Aliabadi Report Date 06/04/2021 (00/03/14)
Rig Name NOOR 1 Est. Rig Days 139 Geologist Hoseini Actual Rig Days 262 Days + 22 Hrs.
EPD Contractor MAPNA Hole Section 6" ICOFC Rep K.Ghodsi / A.Valizadeh
Act Rig Days less NPT 114 Days + 11 Hrs.
Client ICOFC Section Start Date (1400.01.06) / 13:30 Senior/ Night Toolpusher A.Mortazavian / A.Sohrabi

Well Data Bit Data Mud Data


N (m) 1,182,043.48 Bit No. Mud Type S.S. Polymer
Location (UTM):
E (m) 1,736,309.47 Bit Size TCI/ MT/ PDC MW Min / Max (pcf) 80
Project TD (m): 3536.5 Bit Manufacture Flow Line Temp. (deg F) P.CH
R.T.E (m) G.L.E (m) 294.7 284.2 Bit Type Funnel Vis (sec/qrt) 39
Morning Depth (m) 3514 Bit Serial No. Fann 600 44
Mid Night Depth (m) 3514 IADC Code Fann 300 29
Previous Depth (m) 3514 Nozzle Number * Size ( /32 in) Fann 200/ 100 22 / 16
Drilled Interval (m) 0.0 W.O.B (klb) Fann 6/ 3 3/2
Drilling Time (hr) RPM / Total bit RPM PV (cp) 15
Average ROP (m/hr) #DIV/0! Torque (klb.ft) YP (lb/100ft^2) 14
Cum. DRLG Time (hr) 1438.5 Pump Type GEL 10 s/ 10 min/ 30 min 2/3/
Estimated / Actual Rig Days 139 262 Days + 22 Hrs. Pump Liner Size (in) API Fluid Loss (cc/30 min) 3.5
KOP (m) 2595 Flow Rate (gpm) Mud Cake Thickness (1/32") 1
Last Formation MD TVD (m) Sarvak 3414 Standpipe Pressure (psi) Oil %
Lithology Lst TFA (in2) Water % 84
Last casing/ liner shoe 5" @ 3417.5 m Jet Velocity (ft/s) Solid/ Sand Content (%) 16 /
Last liner lap (m) 5"@2551 Bit Daily Drilled (m) Salinity(ppm)/Chlorides (mg/l) / 160000
Last FIT TVD (m) EMW (pcf) 2460 85 Bit On BTM Hours PH / MBT 9.9 /
Costs Today Well's Total Cum Drill Out CMT/ Ream (m) Total Hardness/Calcium (mg/l) 1280 / 1200
Day rate Cum Drill Out CMT/ Ream (hr) KCl (%WT)/ Glycol (%Vol) -
Mud & Cement Bit Cum. Drilled (m) Vol. in Hole (bbl) 638
Bit Bit Cum. Hours Vol. in Pits (bbl) 574
Cas/Tub W/H Bit In / Bit Out(m) Mud Sys./ Daily Made (bbl) 762 / 0
Service Bit Dull Condition Form. Loss/ Mud Pump Repair 0/0
Total Weight Below Jar in mud (klb) Evap./ Shaker / Pit Cleaning 4/0/0
Mud Materials & Chemicals BHA #98 Dump/ Trip/ Centrifuge/ Other 0/0/0/0
Material Type Unit Rec/ Sent Used STK Item Description Length (m) OD (in) ID (in) Cum. L. (m) Total Loss 4
BARITE 1.5 MT 0 POB
BENTONITE 1 MT 0 MDCO 5
SODA ASH 50 Kg / 25 kg 18 / 36 ICOFC 5
SALT (NaCl) 1 MT 43 Services Catering 20 13
CaCO3 (Weight agent) 1 MT 24 Rig crew Guests 38 4
CAUSTIC SODA 25 kg 48 Casual labors 10
Corrosion inhibitor 55 Gal 4 Drivers 9
Xanthan Gum 25 kg 7 Security 7
Starch,Potato 25 kg 128 Total 111
KCL 1 MT 0 HSE
Wallnut Shell F 25 kg 69 HSE Cases Daily Cum
CaCO3 (F/M/C) 25 kg / 25 kg 40 / 80 / 0 LTI free days 1 390
MICA M/ C 25 kg 80 / 0 Man-hours 1248 306552
MICA M 1MT 1 BHA # 97 LTI Accidents 0 0
MICA F 25 kg 70 Description length(m) OD (in) ID (in) Cum. L. (m) Non LTI Accidents 3 946
Shell Fish F/C 25 kg 0/0 BOP Drill 00/02/20 7
Shell Fish C 1 MT 2 H2S Drill 00/01/15 1
Shell Fish M 25 kg 172 Fire Drill 0 1
Shell Fish M 1 MT 0 Medevac Drill 0 1
PAC-LV/R 25 kg 0/0 Stop Card 3 1123
Fiber Lock 25 kg 45 PJSM 3 702
SODIUM BICARB 25 kg 2 Toolbox Meeting 2 672
PIPELAX DR 4
Defoamer 55 gal 4
PHPA 25 kg 15 BOP Test
Cement & Cement Additive LAST BOP TEST Date 1400.02.27
Mat. Type Unit Rec/ Sent Used STK Days Since Last BOP Test 18
CMT "G" Kerman sxs 160 Pumps Data
CMT "G" delijan sxs 1200 Pump # 1 Pump # 2 Pump # 3
NaCl-Salt (1ton) bb Make BOMCO BOMCO BOMCO

Antifaom Agent AA-01 can DP, HWDP & DC Data Type KLF1600 KLF1600 KLF1600

Dispersant FR-02 sxs Size (in) Grade Nominal Weight (ppf) Power (hp) 1600 1600 1600

GMC-01 dr DP 5" / 5" 3 1/2" - 2 7/8" G/S G - G/S 19.5/19.5 13.3 - 10.4 Liner Size (in) 6 6 6

FLC 03/02 dr/sxs HWDP 3 1/2" 25.3 23.2 Stroke (in) 12 12 12

chemical wash, CW-01 can DC 4 3/4" 3 1/8" 47 19 Max Press (psi) 3200 3200 3200

Mutual solvent SLV-01 sxs Down Hole Equipment


Magneset thinner sxs Equipment (Quantity, OD and Description) ID (in) Serial Number Cum Drlg (hr) Cum W&R/ D/O (hr)
1771150011-1771150007-17110002-1771150008-1771150023-1771100019-06-?-?-?-?-
Cement Equipment 3 1/8" DCs 1 1/2" 1771150015-?-1771100021-?-?-1711100030-1771150003-1771100004-1771150006-?-
1771100024-1771150017-?
39.5 / 85.5
Equipment Unit Rec Send STK 4 3/4" D.Jar 2" 5060040 0.0 68.5 / 87.5
Cement Unit no
Solution Tank no
CMT Silo no 5 Solid Control Equipment
Hook Load Data
Air Compressor no Equipment Working Time (hr) Remarks
Surfactant drum Shakers 1 / 2 / 3 Mesh Size: 4*140/2*170+2*140/2*170+2*140 H.L (Klb) Pump On Pump Off
Fuel & Water Desilter / Desander / Degasser Pick Up
Fluid Type Unit Rec. Used STK Mud Cleaner Mesh Size: 4*320 Slack-Off
DIESEL Liter 22,000 2,000 83300 Centrifuge #1 / #2 Rotation
Drill Water bbl 1700 Super Clone TDS & Block Weight 58
KOP : Survey Casing Data
No. MD (m) INC (deg) AZ (deg) TVD (m) NS EW DLS Remark Shoe Depth Liner Lap
Casing Size (in) Grade Weight (ppf) Thread Length (m)
1 2675.0 8.7 253.0 2672.25 -32.13 -87.73 0.320 m) (m)
2 2684.9 8.0 253.0 2682.04 -32.55 -89.11 2.120 20 K-55 106.5 WSP-BIG 57.5 57.5
3 2694.5 6.4 250.0 2691.57 -32.93 -90.25 5.140 13 3/8 N-80 68.0 BTC 1415.5 1415.5
4 2704.1 4.2 249.0 2701.13 -33.24 -91.08 6.881 9 5/8 HC95SS & T-95 53.50 WSP-3T 2455.5 2455.5
5 2713.5 2.1 249.0 2701.51 -33.42 -91.56 6.702 7 L-80 29 PJE 1045.0 2595.0 2375
6 2723.1 1.3 250.0 2720.11 -33.52 -91.83 2.502 5 L-80 18 WSP-4T 864 3418 2551.0
7 2731.5 1.1 249.0 2728.51 -33.58 -91.99 0.718
8 B.P 2744.5 0.8 245.0 2741.50 -33.67 -92.19 0.709
Daily Drilling Report

DANAN OILFIELD DEVELOPMENT

Formation Data Well Control (SCR)

Forecasted Top MW (pcf)/ FV


Formation Name Actual Top (m) Lithology Pump # SPM# 1 SPP 1 (psi) SPM# 2 SPP 2 (psi) Depth (m) Time
(m) (s/qrt)

Aghajari Surface Rd. Ml + Gy.Ml + S.st 1

Gachsaran 7- 5 1600 1385.0 Anhy + Rd. Ml + Gy.Ml+ Salt 2

Gachsaran 4 - 2 1990.5 1874.0 Anhy + Rd. Ml + Gy.Ml+ Salt 3

Gachsaran 1 (Cap Rock) 2482.5 2426.5 Anhy + Salt + Shale Wellhead BOP Test Record
Asmari 2556.5 2491.0 Lst + Anhy Component Top FLG (Size/ WP) BTM FLG (Size/ WP) Component Type and Size Test Pressure

Kalhur 2626.8 2566.0 Lst+ Anhy+ Shale+ Cyst+Salt Xmas Tree Annular 13 5/8"-5K 2500

Pabdeh 2860.6 2837.0 Lst+Marl THS 11" 5K 13 5/8" 3K Top Rams 13 5/8"-10K 4500

Gurpi 3311 3295.0 Lst DSA Pack off - - - - Blind Rams 13 5/8"-10K 4500

Ilam 3356.5 3334.0 CHS 13 5/8" 3K 21 1/4" 2K Bottom Rams 13 5/8"-10K 4500

Sarvak 3440.5 3414.0 Lst CHH 21 1/4" 2K - - Choke Manif. 5k 4500

Well TD 3536.5 3514 L.St Wear Bushing Size: 11" IN/ OUT: IN Accumulator 3k Function test

Received

Sent

Request

7 1/16" Golp. Flange


Outstanding

Detail of Operations within Last 24 hours


Code /Activity Hrs From To Hrs Code Remarks
1. Rigging and Moving 00:00 01:30 1.5 10B Run#1 as DLL/SONIC/CDR/GR logging tools (Length: 23m, Max OD:3") to 3512 (Logger depth TD) while F/U the well with NL-NG.
2. Drilling 01:30 04:00 2.5 10C Log up with DLL/SONIC/CDR/GR tools from 3512 to 3417m. Continue log up with CDR/GR tools f/3417 to 2500m while F/U the well
3. Hole Conditioning 04:00 05:00 1.0 10B POOH Run#1 logging tools to Surface While F/U the Well with NL-NG.
4. Coring 05:00 06:00 1.0 10A L/D Run#1 logging tools. R/U Run#2 logging tools while F/U the Well W/NL-NG.
5. Mud Condition & Circ. 06:00 10B Run#2 as ZDL/CNT/NGT logging tools (Length: 12m, Max OD:3") to 3512m while F/U the well with NL-NG.
6. Trips Log up with ZDL/CNT/NGT tools from 3512 to 3330m & repeat log.
7. Rig Services 11:30 5.5 10B POOH Run#2 logging tools to Surface While F/U the Well with NL-NG. L/D Run#2 logging tools.
8. Slip and Cut DRLG Line 11:30 Run#3 as CBL/VDL/CCL/GR logging tools (Length: 11m, Max OD:3") to 2500m. Due to detecting high temperature at IDW (depth enc
9. Deviation Survey resulting depth difference up to 25m in RIH, POOH from 2500 to 2300m, observe cable armour damaged. Cancel the logging opera
10. Logging 11.5 16:30 5.0 22C from 2300m to surface. L/D Run#3 logging tools While F/U the Well with NL-NG.
11. Running Casing/ Liner 16:30 While wait on receive new logging truck, change top rams from 7" fix to 4 1/2" x 7" VBR. Retrieve wear bushing and install plug tes
12. Cementing Perform BOP test as NIOC policy: P/T Annular preventer with 2500 psi, Ok. P/T top, bottom, blind rams and related valve and also
13. Nipple up/ down 24:00 7.5 22C manifold with 4500 psi, OK.
14. BOP Test

15. Formation Testing

16. Directional Drilling

17. Well Completion

18. Perforation Note: Consider 12.5 Hrs. waiting for Asmari Logging Co. due to logging truck problem and wait on change truck.
19. Stimulation Note: Mud box is not sealing properly (sealing rubber damaged).
20. Production & Well Testing Note : 4" valve of rig pump(#3) is out of service.
21. Suspension/Abandonment

22. NPT 12.5


23. Other

Time 8:00 13:00 19:00


Pool Level (m) 0.3 0.25 0.2
Rig Shortage: ###
1- Some caravans facilities are not completed.
24.0 24.0
From To Hrs Code Morning Report
00:00 04:30 4.5 22C While wait on receive new logging truck, P/T burning line with 1000 psi, Ok. Work on koomy unit & perform koomey unit function test, Ok.
While wait on receive new logging truck, RIH with used 8 3/8" B.Bit#11RR5 (537, 3*18/32 Nzl) followed by 5" DPs from surface to 513m. Slow circulate
04:30
mud with
06:00 1.5 22C NL-NG.

Total (Hrs) 6.0


Operations Summary

Perform logging: Run#1 as DLL/SONIC/CDR/GR to 3512m (Logger depth TD). Run#2 as ZDL/CNT/NGT. Run#3 as CBL/VDL/CCL/GR logging tools to 2500m, Due to damaged cable armour, cancel
the logging operation & POOH to surface. While wait on receive new logging truck, perform BOP test.

Next Operations
Perform CBL/VDL/CCL/GR logging. RIH with 7" casing scraper to scrap completion packer setting depth.
Operations Reference Code
MAPNA Drilling Co.
Code/
Main Activity Details
Subcode
1 Rigging & Moving
2 Drilling
2A Drilling Vertical Drilling using rotary BHA
2B Performance Drilling Vertical Drilling using PDM
3 Hole Conditioning
4 Coring
5 Mud Conditiong & Circulation
6 Trips
7 Rig Services
8 Slip & Cut Drilling Line
9 Deviation Survey
10 Wireline Logging
11 Running Casing/ Liner
12 Cementing
13 Nipple up/ down
14 BOP Test
15 Formation Testing
16 Directional Drilling
17 Well Completion
18 Perforation
19 Stimulation
20 Production & Well Testing
21 Suspension/ Abandonment
22 NPT
22A Waiting on Client
22B Waiting on EPD Contractor
22C Waiting on Service Company
22D Waiting on Rig Contractor
22E Stuck
22F Fishing and milling All preparing, assembling of fishing equipment to recover of junks or fish from a wellbore
22G Side-Tracking All operations related to Sidetracking Original Hole to Bypass a Fish (using cement plug or whipstock)
22H Well Control Issue
22I Washout Including trip out and trip in until reaching previous depth
22J String Plug Including trip out and trip in until reaching previous depth
22K Rig Repair
22L Wait On Weather
22M Force Majeure Other Force Majeures out of Client and Operator's Control
22N Other Down Hole Problem NPTs which is not within the above mentioned Categories
23 Others