Professional Documents
Culture Documents
ASurveyof Construction Claimsand Claim Management Processin Thailand
ASurveyof Construction Claimsand Claim Management Processin Thailand
net/publication/233400972
CITATIONS READS
0 3,745
2 authors, including:
Kongkoon Tochaiwat
Thammasat University
174 PUBLICATIONS 60 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Kongkoon Tochaiwat on 01 June 2014.
Both employer and contractor should establish efficient claim management within
their organizations to deal with claims, by them against the other and vice versa. This
management staff members from employers’ organizations, both public and private
the questionnaire survey. It was found that, on average, the frequency, severity and
impacts of the events entitling the contractor’s rights to claim are higher than the
employer’s while the employer has higher ability to manage his claims. The
incomplete contract documents while there were three contractor’s issues indicated:
incomplete contract documents, higher employer’s bargaining ability, and the delay of
the engineer’s responses. The outcome of the study can be used to improve the claim
INTRODUCTION
involved in the construction process (Arditi and Patel, 1989). Construction claims
have significant effect on the project cost and time. A survey done by Semple (1994)
in Western Canada found that a large proportion of claims involved some delays and
in many cases the delay exceeded the original contract duration by over 100%. As to
the project cost, more than half of the claims resulted in an additional cost of at least
30% of their original contract value. Other research works done in the United States
(Callahan, 1998) and in Thailand (Khanchitvorakul, 2000) revealed the same results:
the average cost escalation caused by claims is approximately about 7% of the original
contract value.
Even though construction claims have a high level of impact on the project success,
there have been few studies about construction claims and construction claim
construction claims, such as their frequency rates and their severity levels, will be
the existing claim management processes such as their efficiencies, problems, and
guidelines for improving, can help both parties realize their strong points, weak
This research aimed at finding the necessary information related to the employers’ and
frequency rate, severity level and impact level, the contract management efficiency,
LITERATURE REVIEW
There are a number of ways to classify construction claims. Classified by the party
filing the claim, claims are of two types: the employer’s claims and the contractor’s
claims. Based on the relevant legal bases, construction claims can be further
classified several ways. For example, Chappell et al (2005) classified claims into
contractual claims, common law claims, quantum meruit claims and ex gratia claims
while some works such as those of Hughes and Barber (1992) and Alkass and Harris
(1991) classified claims into contractual claims, extra-contractual claims (or ex-
contractual claims or common law claims) and ex gratia claims. This research
In order to deal with or control the claims in an effective way, all parties should
detection of a change. It is the first and critically important ingredient of the claim
This sub-process involves alerting the claimed party of a potential problem in a non-
adversarial manner. Time limit requirements are very crucial and critical (Kululanga
et al., 2001). Normally, the contract specifies such duties to the claimant.
construction claims. The daily events and details of the jobs must be documented to
substantiate claim entitlements and prove damages. With a carefully prepared claim
package of facts and figures, the claimant can support his position and propel
The objective of this sub-process is to determine the impact of the change that occurs.
The analyst shall perform schedule analysis to calculate the time impact while
breaking down the cost into various cost components to assess the cost impact. There
are various methods used for calculating time and cost impacts. Each method has its
own pros and cons (Adrian, 1988). In monetary claim pricing process, there are two
types of claim pricing methods: forward pricing and post pricing (Levin, 1998). This
detailed cost description is necessary for negotiating, and justifying extra contract
costs.
5. Claim preparation
The claim documents should be logically built up, well organized, and factually
convincing. It can be divided into two sections: claim entitlement and claim quantum.
The former section should form the legal and factual bases that the contract or legal
requirement was breached while the latter should provide the estimated recovery of
This sub-process concerns the process of presenting the claim to the claimed party,
and mutual settlement of such claim. If an agreement cannot be reached and any party
Construction Claim Management
believed his position is correct, he should request to begin the dispute resolution
process.
There are several approaches to settle construction disputes. There are a variety of
techniques available to help the parties come to some form of settlement without
private enquiry, adjudication, and mini-trial (Murdoch and Hughes, 1996). However,
if this fails, the remaining choice is to implement the more formal dispute resolution
insufficiency of the claim processes. Lots of the insufficiencies were caused by the
Vidogah and Ndekugri (1998) concluded several deficiencies found in the consultant’s
the basic good management practice (diaries, timesheets, and programmes), and (4)
impossibility to quantify claims with precision. They also discussed the claim
not treated as a management function and is always poorly resourced and performed
As to claim management in Thailand, where this research was done, Thai public
For larger projects, the public authority may employ a private consulting firm to act as
a construction supervisor. In such case, the private construction supervisor will have
the same rights and responsibilities as the public construction supervisor. Regarding
claim management, the committee also has power to determine the entitlement and the
amount of compensation the contractor deserves, in case of the contractor’s claim, and
make decision to file claims against the contractor, by using the reports and
On the other hand, the components of the private construction project organization,
staff, rights and responsibilities differ from one project to the other because of
project manager, and 3) various disciplines of project engineers. The project director
is generally responsible for overlooking several projects in the big picture while the
time, within the budget, and with acceptable quality. The types and number of the
project engineer crews differ depending on the sizes and details of the projects. In
The power to make decision over claims in private projects generally belongs to
project manager.
From literature, there are several topics left for studying in the claim management
field such as the characteristics of the events which entitle the employer and the
contractor to the rights to file claims against the other party, the performance,
TERMINOLOGY
or the contractor can refer to in substantiating his right to the claim entitlement.
specific event entitling the employer (both private and public) or the contractor to the
rights to claim in one construction project, no matter whether the entitled party finally
of a specific event entitling the employer or the contractor to the rights to claim in one
construction project.
effects occurring from all occurrences of a specific event entitling the employer or the
5. “Impact Score” is the index used for indicating the level of impact of a
specific event entitling the employers or the contractors to the rights to claim in one
construction project.
the ability of the employer or the contractor to perform the related construction claim
7. “Efficiency Index” is the index used for indicating the level of efficiency of
This research aimed at finding necessary information related to employers’ and the
questionnaire survey was then the selected method. There were two sets of
questionnaires: the questionnaires for the employers and the questionnaires for the
contractors. Both of them had four parts of questions. The first part contained the
questions related to the respondents’ data such as their positions, their working
experiences, and their experienced maximum contract values. These data were used
in identifying and screening out. The contract value of 20 million baht, which was
from the medium and the big-sized projects (Booen, 1999), was used as a screening
criterion. The second part contained thirty questions for the contractors or twenty
questions for the employers, which were relevant to the frequency and severity of the
each event entitling them the rights to claim. Each respondent was asked to
approximate the number of occurrences per project for each event in each question.
On the other hand, the severity of each event was assessed by using five-leveled
Likert-Scaled questions (McIver and Carmines, 1981) The third part contained nine
abilities to manage their claims, acquired by deliberately grouping each party’s tasks
for each sub-process considering their numbers and their similarities: (1) recognition
and identification of the change, (2) notification of the change, (3) performing
Construction Claim Management
systematic and accurate documentation of the change, (4) performing analysis of time
and cost and then pricing the change, (5) negotiation about the claim, (6) recognition
and identification of the other party’s change, (7) performing systematic and accurate
documentation of the other party’s change, (8) performing analysis of time and cost
and pricing the other party’s change, and (9) negotiation about the other party’s claim.
Finally, the fourth part was an open-ended question asking the respondents to identify
processes.
staff members were then selected by using the stratified sampling technique, taking
account of their locations (Bangkok, Bangkok Vicinity, Central Part, Northern Part,
North Eastern Part, and Southern Part) for the contractors, and their type of
organizations (Private, or Public) for the employers. From statistical data, there were
452 government organizations, 213 private consultant companies, and 1,018 contractor
companies in the year 2002 (Energy Policy and Planning Office, 2005; AECasia,
2002). The criterion used in classifying the contractors’ locations was adopted from
that of the National Statistical Office, which groups the Eastern Part and the Western
Part of Thailand with the Central Part (National Statistical Office, 2004).
3. The data acquired from the returned questionnaires were then analyzed. The
data acquired from the employers’ organizations were analyzed both by considering
them as a whole and as the separated private employers and public employers.
However, the contractors’ data were analyzed only by considering them entirely
because there was no significant influence from the location to the characteristics of
the contractors and the number of the each sample group will be too small. In
addition, the majority of the contractors had projects nationwide or in more than one
Chovichien and Tochaiwat
region of the country. Each claim’s frequency and severity were calculated from
arithmetic mean of all respondents’ answers. Then, the impact of each claim-leading
event was determined by using its “Impact Score” calculated by its frequency and
severity.
Because both the frequency and the severity of a claim have high levels of effect on
the project, the Impact Score, which takes account of both frequency and severity,
should be used in determining the impact of the claim on a construction project. The
Impact Score for each claim-leading event for the employers and the contractors (as
case may be) can be calculated by multiplying its frequency by its severity, which the
denominator had been changed from 4 to 10 by multiplying with 10/4, as shown in the
following formula:
Next, the efficiency of each claim management sub-process was calculated by finding
the arithmetic mean of all respondents’ answers for each question in Part 3. Finally,
the process problems and improvement guidelines acquired from questionnaires were
analyzed.
4. After the analysis process, all results acquired were then discussed and the
From Table 1, it can be seen that the compositions of the responsive respondents both
from the employers and the contractors had the proximate compositions of the
returned from the contractors in Bangkok Vicinity, Central Part, Northern Part, and
North Eastern were close to that of the contractors nationwide (NSO, 2004).
However, the composition of the Bangkok and the Southern Part were clearly
claims, the respondents’ average maximum contract values and the average number of
Table 2 Average maximum contract values and number of years managing claims
No. Description Experience Max. Contract Value
(Year) Million Baht Million Dollar*
1. Employer
1.1 Private 14.55 2,765.45 70.62
1.2 Public 12.90 733.52 18.73
Overall 13.46 1,432.00 36.57
2. Contractor
Overall 12.94 1,147.65 29.31
Remark: * converted by 39.16, the rate at the time conducting the survey (Bank of Thailand, 2004).
Chovichien and Tochaiwat
The average maximum contract values and the average years managing claims
showed that the respondents, in average, had high experiences and qualifications. The
results of statistical tests showed that respondents who work in the employers’ and the
of years managing claims but were different in the maximum experienced contract
values. The average maximum experienced contract value of the private employers
was significantly higher than those of the public employers and the contractors.
Details of these statistical analyses are shown in Table 3. Note that non-parametric
statistical tests were selected because of their advantage in being free from the
had high levels of reliability, as seen from their Cronbach’s Alpha in Table 4. Note
that the Cronbach’s Alpha of close to 1 shows the questionnaires are highly reliable.
Construction Claim Management
LEADING EVENTS
From Table 5, the average frequency of each claim-leading event assessed by the
respondents is shown. The contractors were found to have more chances to claim
against their employers while both types of employers seem to have equal chances, as
seen from the numbers of overall claims (40.06, 36.46, and 94.19). This trend also
applied to contractual claims and ex gratia claims. All parties seemed to have equal
chances to claim against the other party under common law claim basis. Finally, the
rights to claim under quantum meruit basis occurred to contractors more often than
both types of employers. The contractor had the rights to claim under quantum meruit
basis more frequently by the common law basis while both types of the employers had
As to the severity of each claim-leading event, Table 6 shows that the claims filed by
the contractor and the employers have different trends. For both types of employers,
common law claim had the highest effect, followed by contractual claim, quantum
meruit claim, and ex gratia claim, respectively. The contractor were effected by ex
gratia claim the most, followed by contractual claim, common law claim and quantum
meruit claim, respectively (common law claim and quantum meruit claim had the
same rank). It should be noted that severity of overall claim was calculated by their
According to Table 7, the impact of each type of claim can be calculated from its
frequency and its severity, according to equation (1). For example, the impact score
of the event entitling the contractor to the rights to claim for the contractual claim is
equaled to (10 / 4) x 2.91 x 69.08 = 502.56. The impact of claim on the project has
the similar trend to the claim frequency. The contractor’s claim-leading events had
higher impact than those of both types of employers for almost all types of claims.
However, their impacts were lower than those of private employers’ and public
It can be clearly seen that contractors in the construction projects have to cope with
events impacting his performance more often and with higher average severity than
employers. For this reason, the Impact Scores of contractors are much higher than
those of private and public employers. There are no significant differences in the
frequencies, and the severities of private and public employers’ rights to claim, as
seen from the significance values from Mann-Whitney tests of 0.357 and 0.204
respectively.
Contractual Claim
Compared with other types of claims, the events justifying the rights to claim on
contractual claim basis got the highest frequency and impact. This emphasizes the
of the project. The well-prepared construction contract documents can help both the
project employer and the contractor settle the changes that occur before they become
claims or disputes, which consume much more time and costs from both parties to.
On the other hand, the common law claims also have high level of effects on the
projects, which can be seen from their frequencies and impacts. This implied that
both parties need not only the deliberate scrutiny of contract documents, but also the
Chovichien and Tochaiwat
familiarity with related laws, regulations, and other standards of works. This helps
them avoid or more efficiently settle the changes that have occurred.
Quantum meruit claims have important effects on the project performance, especially
from the contractor’s point of view. This implied that the contractors always have to
perform the works not clearly specified in the contract documents. An appropriate
Ex gratia Claim
The ex gratia claims are the least frequent claims among all four types. They seem to
have low impact to the employers but they play important roles to the contractors.
The highest severity rank among all types of claims assessed by respondents from
contractors’ organizations showed that even though ex gratia claims occur not very
often in the projects, the contractors felt that they have a high level of impact to their
performances. This finding was supported by the fact that there were some
respondents who notified that their project employers sometimes asked them to do
some work out of the original scope of the contracts. These contractors also informed
that they have to follow these requests because of their expectation for prospective
The Efficiency Indexes of both employers’ and contractors’ claim management sub-
processes and of the overall process are shown in Table 8. The Efficiency Indexes of
averaging all relevant sub-processes. To find the efficiency index of overall process,
Construction Claim Management
the index of overall active sub-processes and the index of overall defensive sub-
processes were averaged, using the overall frequency rates of the private employer’s,
public employer’s, and contractor’s claim-leading events from Table 5. Moreover, the
frequency of the events leading the overall employer to the rights to claim can be
assessed by using the ratio of 32.27: 67.73, which is the ratio of Gross Domestic
Product (GDP) originating from construction of private sector and public sector in
2000, respectively (NESDB, 2004). Thus, the frequency of overall employer’s claim-
leading events was (40.06 x 32.27 + 36.46 x 67.73) / 100 = 37.62 and the Efficiency
Index of the contractor’s overall processes was (2.78 x 94.19 + 2.56 x 37.62) / (94.19
+ 37.62) = 2.72
Since there is no clear activity that both the employer and the contractor have to
Among all parties, public employers have the highest Efficiency Index while the
contractors have the lowest. Thai employers, especially public employers, normally
have an advantage over the contractors. The government standard contract gives the
employers dominating power and is silent on the contractors’ rights to claim against
addition, the expectation of the future work is also an important reason that makes
The public employers and the contractors can well identify changes occurring to their
works, which entitle them to the rights to claim against the other contracting party.
The reason of these contractors’ abilities is that they are so close to project progress
that they can notice the changes happening, while public employers have more power
to access the information of their contractors than private employers. The contractors
also have high ability to analyze and price the changes that occur to them, signified by
the higher relevant Efficiency Indexes than those of the overall active and defensive
documentation of the contractors’ changes, they are not good at analyzing and pricing
the changes because they have less experience with claims and employing claim
consulting services in the public works is uncommon. On the other hand, private
employers have lower ability to collect data, analyze, and price the contractors’
From Table 8, the active tasks that all parties can perform well (better than the overall
Efficiency Index) comprise (1) notification of change, and (2) systematic and accurate
efficiency than their overall average. The probable reason of this finding is that
contractors are able to become aware of active claims sooner and easier to access the
data required in managing these active claims. However, the respondents rated their
abilities to negotiate the employers’ claims against them better than those against the
employers. This was in accordance with the problem notified by some respondents in
Part 3 of the questionnaire which was about their low bargaining abilities to negotiate
The activities that all parties can not perform well (worse than their overall average)
and should be improved are: (1) claim negotiation (both active and defensive), and
(2) defensive identification of the change happening to the other party. Moreover,
private employers should develop their abilities to identify, analyze and price the
changes entitling them to the rights to claim against their contractors and public
employers should improve their skills of analyzing and pricing the changes that cause
claim liabilities.
RECOMMENDATIONS
The problems informed by the respondents can be divided into three main categories,
e.g. problems arising from: contracts, employers and employers’ personnel, and
contractors.
Chovichien and Tochaiwat
The contracts are sometimes incomplete, unclear in specifying each party’s rights and
duties, and lead to different interpretations by different parties. Some contracts allow
too much bureaucratic procedure, lack of necessary data, and lack of clear regulations.
Some respondents revealed that they decided to quit claim filing process because of
projects.
Not only the employers, but also their personnel can cause problems to the project.
Sometimes designers issue impractical designs which can cause delay or cost overrun
in the construction phase. The engineers may issue an incomplete or oral variation
contract specifying the rights and duties only of the contracting parties: the employer
and contractor, there is no clear engineer’s rights and responsibilities specified in such
contract. Thus, the engineers in Thai public contracts presumably act as employers’
personnel.
The last group of problems is from contractors. They sometimes cause problems to
incompetence, lack of management skills, refusal to comply with the defects liability
The recommendations collected from the respondents were related to the improvement
professional ethics.
1. Management
Good contracts and contract management also have great roles in the improvement.
method and technique, which he will be adopted in executing works, before allowing
contractors to begin works. Before issuing variation orders, the employers or the
engineers should analyze their consequences. Variation orders should be clear and
3. Project Procurement
project parties: contractors and engineers. This strategy will help reducing several
Construction Claim Management
consequential problems to the projects. The reference price, especially which used in
4. Professional Ethics
Finally, every party involved in the project should maintain professional ethics. The
employer and the contractor should be fair to each other. In addition, the engineers
determination.
From analyzing the collected problems, it was found that there are three important
(Jervis, 1988). The problem of the engineer’s partiality always occurs when the
engineer’s impartial performance will damage his employer, who pays the
remuneration to him. Engineers have the power to make determination and to issue
if they are incorrect or unfair, because of their concern regarding future contract
acquisition. Employers who lack the construction knowledge or possess too much
disputes. Some contracts can not fairly allocate risks between employers and the
contractors. In addition, some contractors accepted that they do not have enough
4. Recommendation
scrutinizing the contract provisions, enhancing the cooperative atmosphere among all
issuing prompt notification to employers to the events that change contractors’ status,
and signing another contract whenever the variation orders contains high value items.
Some contractors suggest that the government help them by improving relevant laws,
CONCLUSION
The highest frequency and impact of events justifying the rights to claim on
construction contract at the beginning of the project. Common law claim also has
high level of effects on the project, which can be seen from its frequency and impact.
This implied that both parties need not only the deliberate scrutiny of contract
documents, but also the familiarity with laws, regulations, and other standards of
works related to the work. Ex gratia claims seem to have low impact on the
employers but they play important role to contractors. Even though ex gratia claims
occurred not very often in the project, contractors felt that it has a high level of impact
to their performances. Among all parties, public employers have the highest ability to
manage claims while contractors have the lowest ability. Three main groups of the
The frequency, severity, and impact of each type of claims can help both employers
and contractors realize the priorities of claims they should pay attention to. The
Chovichien and Tochaiwat
contractors which sub-processes are their strong points, which should be maintained,
and weak points, which should be improved. Employers and contractors can use the
REFERENCES
AECasia (2002) Thai Design & Construction Directory 2002. Bangkok: AECasia.
Alkass, S and Harris, F (1991) Expert Systems Construction Contractor’s Claims Analysis:
Arditi, D and Patel, B K (1989) Expert System for Claim Management in Construction
Booen, P L (1999) FIDIC’s Conditions of Contract for the Next Century: 1998 Test Editions.
Chappell D et al (2005) Building Contract Claim 4ed. Great Britain: Blackwell Publishing.
The First National Transport Conference: NTC-1, 15 October 2003, Bangkok, 30-35.
Construction Claim Management
Energy Policy and Planning Office [EPPO] (2005). Complete Royal Thai Government
December 2005.
Hughes, G A and Barber, J N (1992) Building and Civil Engineering Claims in Perspective
Jervis, B M and Levin, P (1988) Construction Law: Principle and Practice. New York:
McGraw-Hill.
Thonburi.
Levin, P (1998) Construction Contract Claims, Changes & Dispute Resolution. 2ed. Boston:
ASCE Press.
Murdoch, J and Hughes, W (1996) Construction Contract : Law and management. 2ed.
National Economic & Social Development Board [NESDB] (2004). Gross Domestic Product
National Statistical Office [NSO] (2004). Important Details of the Thai Contractors Classified
Semple C et al. (1994) Construction Claims and Disputes: Clauses and Cost/ Time Overruns.
363-372.