Professional Documents
Culture Documents
Benin 330kV Layout
Benin 330kV Layout
A A
Symbol Description
CB
-SR Shunt reactor C
-ET Earthing transformer
DS
DS CT CB CT DS
Busbar 1
DS
D DS
Note: This layout drawing is for bidding purposes only.
Busbar 2
330kV
Sapele 1 OHL Sapele 2 OHL Sapele 3 OHL Delta OHL Onitsha 1 OHL Onitsha 2 OHL Ajaokuta 1 OHL Ajaokuta 2 OHL
E 150MVA 150MVA
TR
TR
To Be Replaced To Be Replaced
With 300MVA With 300MVA Date:............................. Signature/Stamp:....................................................
Project Consultant
SR
75MVAR
T2 SR
75MVAR
T1
ET2 ET1
To 132kV To 132kV E
Switchyard Switchyard TRANSMISSION COMPANY OF NIGERIA
Project Management Unit (PMU)
Drawing Detail
Name: Date:
Technical Feasibility & Identification of
Scope of Work for Substation Upgrading &
Prepared: Arjun Sabat 01/11/2016
Transmission Line Re-Conducting in Nigeria
G Drawn: Khemissi Hartem 01/11/2016
NETAP
Title:
Checked: Zdravko Dolencic 01/11/2016
Benin 330kV G
Sandeep Bhowmick
Approved: 01/11/2016
Substation Layout
Revisions
H H
No. Name Date
H
Scale: NTS Rev.:
Drawing No.
1 2 3 4 5 6 7 8 9