Professional Documents
Culture Documents
Piling and Sub-Structure
Piling and Sub-Structure
Piling and Sub-Structure
Introduction
Pre Construction Works
Activities In Pile Foundation
Specification
Milestones
Test on Pile
Specialized Subcontractors
May 21
Pile Foundation 1
Introduction
• Pile foundation
Chartered Utilities
Unchartered Utilities
Function of Utilities( Water ,Sewer,Gas)
Level of Utilities
According to pile cap area
Trail Pits
lf the specific gravity of the drilling mud at the base of the bore exceeds 1.20 g/cc the placing
of concrete shall not proceed.
• Spacing of Piles
• piles founded on a very hard stratum and deriving their capacity mainly from end
bearing - 2.5 times the diameter of the shaft
• In case of piles resting on rock, the spacing of 2 times the diameter may be
adopted.
• Piles deriving their bearing capacity mainly from friction shall not be less than
three times the diameter of the shaft.
CMRL : For piles, the rate quoted shall be for per meter of pile.
May 21 Superstructure 32
May 21 Superstructure 33
May 21 Superstructure 34
May 21 Superstructure 35
May 21 Superstructure 36
May 21 Superstructure 37
Pile Construction
Land Piling Inter tidal Piling Marine Piling
May 21 Superstructure 38
May 21 Superstructure 39
May 21 Superstructure 40
May 21 Superstructure 41
May 21 Superstructure 42
May 21 Superstructure 43
TCS-1 Main Viaduct
May 21 Superstructure 44
TCS-2-Connector
May 21 Superstructure 45
TCS-3 Connector
May 21 Superstructure 46
Toll Plaza- Type 1
May 21 Superstructure 47
Cable Stay Bridge
May 21 Superstructure 52
Cable Stay Bridge
Pylon Foundation Details
Plan Section
May 21 Superstructure 53
Pylon Section from Pile cap to Finished road level
May 21 Superstructure 54
Pylon Section from Finished road level Complete View
May 21 Superstructure 55
Balance Cantilever Bridge
Main Viaduct Line Diagram
No. of Cantilever Bridge Chainage Span in m Total No. of Bridge Builder required
1 2317.6 to 2567.6 250
2 5052.6 to 5302.6 250 8
3 6440.6 to 6690.6 250
May 21 Superstructure 56
Tentative Construction Schedule
Sr. No. Description Start Finish Total
1 Pile -Land 10 18 9
2 Pile -ITL 9 42 34
3 Pile -Marine 8 43 36
4 Pilecap -Land 12 24 13
5 Pilecap -ITL 17 49 33
6 Pilecap -Marine 9 44 36
10 PSC 11 51 41
11 Pylon 17 44 28
12 Bal cantilever 17 53 37
May 21 Superstructure 57
Conditions of Contract
Clause Description
That date which is later of the date on which the Contractor has delivered the Performance Security and the date on
Appointed Date
which the Authority has provided the working front not less than 90% (Ninety per cent) of the total length of Project
Performance Security
5% of CP within 10 days of signing of agreement, valid until 60 days after expiry of DLP.
(PS)
Mobilisation Advance 10% of CP in 2 equal instalments @12% PA, against BG of 110% of advance.
Equipment Advance 5% of CP @12 % PA, for newly purchased equipment against BG of 110% of advance.
Recovery of Advances From 20% of Contract price paid to 80% of Contract price @ 15% from each IPC
Payment After all deductions, 90% within 20 days and complete payment mentioned in IPC within 30 days
5% of CP @ 6% from each IPC & released within 15 days of the date of issue of the Completion Certificate.
Retention (Upon furnishing the BG, the Authority shall refund the retention money in tranches not less than the 1% of the
contract price)
0.05% of the Contract Price for delay of each day reckoned from the date specified in Schedule –J and until such
Delay Damages
Project Milestone is achieved or the Works are completed;
May 21 Superstructure 58
Schedule - H
Weightage in
Sr. No. percentage to the Description Items Payment Procedure
Contract Price
Unit of measurement is linear length. Payment of each stage shall be
Road Work (Rigid Earthwork, Sub-
1 0.05% made on pro rata basis on completion of a stage in full length or 5km
Pavement) Base, DLC, PQC
whichever is less
2 Major Bridge > 60m
Payment shall be made on pro rata basis on completion of each
41.49% Main Vaiduct Foundation
foundation with respect to total number of foundation
Payment shall be made on pro rata basis on completion of each
5.22% Bandra Connector Sub-Sturcture
Pier/Abutment with respect to total number of Pier/Abutment
May 21 Superstructure 59
Schedule - H
Weightage in
percentage to
Sr. No. Description Items Payment Procedure
the Contract
Price
May 21 Superstructure 60
Schedule - J
Sr. Milestones Days Contract Condition
No.
1 Milestone 1 365th day 10% of contract price @ 20% of time period
May 21 Superstructure 61
Sr. Description
Major Materials
Unit Approximate Quantity
No
.
1 Cement MT 317000
2 Fly ash MT 106000
3 Reinforcement – TMT MT 181512
Fe550
4 Aggregates for MT 1242000
Concrete
5 Crushed Sand MT 698770
6 HTS MT 20481
7 Mild steel Liner MT 19461
8 Stay Cable MT 455
May 21 Superstructure 62
Sr. No.
Major Equipment
Description No.s
1 Batching Plant - 60cum/hr 1
2 Batching Plant - 30cum/hr 6
3 Transit Mixer 6 cum 14
4 Transit Mixer skid mounted 6 cum 15
5 Crawler Crane 20T 13
6 Crawler Crane 150T 13
7 Truck Mounted Concrete Pump 6
8 Pile Top Rig 11
9 Tugs 8
10 Self propelled barges 15
11 Gantry Crane 120T 9
12 Gantry Crane 10T 5
May 21 Superstructure 63
Risk Assessment
Likelihood Impact
Specific Project Mitigation High3 High3 Rs. Cr. Amount In
Sr.no. Risk Description
Risk measure Medium2 Medium2 Value lakh
Low1 Low1
6 month
Time over run / Slippage in execution/
1 extended 3 3 31299 2347
Construction schedule
period
10
2 Employment of local people References employeesfor 3 3 360 360
36 months
5% of cost
3 Stone quarry Shortage and bans burden every 3 3 1393 1393
year
Traffic
Transportation of equipment and arrangement
4 Traffic fees 3 3 60 60
construction materials to site Rs 1 Lskh per
month
Items which are required but not 0.25% of
5 3 3 964 964
covered in absence of scope clarity direct cost
Rs 130 per rm /day
6 Handing over delays is neglegible 3 3 128549 643
provision
7 Client obligations 3 3 500 500
Rate difference
8 Utilties fouling with the alignment with owing 0.25% 3 3 385647 386
/executingagency
Difference in inputs
9 Hydraulical studies -deviation 3 3 154259 386
provided by client
Difference in inputs
10 eotechnical studies -deviation 3 3 154259 386
provided by client
May 21 Superstructure 64
Site Visit
Photos
May 21 Superstructure 65
Site Visit
Photos
May 21 Superstructure 66