Professional Documents
Culture Documents
Suria Engineering.: Test Pack For Tt307B Piping
Suria Engineering.: Test Pack For Tt307B Piping
Suria Engineering.: Test Pack For Tt307B Piping
TT307B PIPING
SURIA ENGINEERING.
SERVICE
Cooling water return line
AREA
S-400
PIPING TEST PACK FOR
TT307B PIPING
TABLE OF CONTENT
STATUS
Sr.No CONTENTS
Yes NO N/A
7 Punch List ü
8 Pre-Hydro / Pneumatic Test piping checklist ü
9 Release for Hydro / Pneumatic / Leak Test ü
10 Piping Hydrotest/ Pneumatic Test Certificate ü
11 Gauge Calibration Certificate for hydro test ü
12 System Flushing Report ü
13 Temporary Removed Items List ü
14 Post Test Inspection Report ( Reinstatement) ü
15 Temporary Blinds and Spool List ü
16 Test Package Drawing / Line index ü
17 Line List ü
18 P & I Diagram ü
19 Piping Isometric Drawing/Weld Map ü
20 Pipe Supports list ü
PIPING TEST PACK FOR
TT307B PIPING
Sign: Sign:
Date: Date:
Sign: Sign:
Date: Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Sign:
Date:
Reinstatement
(SURIA+EPCL)
Sign:
Date:
PIPING TEST PACK FOR
TT307B PIPING
LEGENDS
7 Removed
R 8 Temp. Spool
TEST MEDIA
Description of Category: A= Should be completed before hydro test. B=Should be completed before commissioning. C=should be completed before handing over.
Signature:
Date:
SURIA ENGINEERING.
TT307B PIPING
PRE-HYDRO / PNEUMATIC TEST PIPING CHECK LIST
Yes N/A No
1 Check Isometrics Against P&ID's q q q
2 Check that all NDT / Stress relieving Requirements are as specified q q q
have been met and recorded
3 Check that the correct bolts and gaskets are installed at all Mechanical Joints q q q
4 Check that All Vents and Drains are Installed (Add temporary Vents q q q
and Drains for Testing as required
5 Check Piping for Correct Schedule and Type q q q
6 Check valve Materials as per Piping Material Spec. q q q
7 Check the rating of forged Steel Fittings q q q
8 Check that branch reinforcement is Correct q q q
9 Check that all Pressure Connections are Installed Correctly as per Spec. q q q
10 Check for Correct Flow direction of arrow through Filters and q q q
Strainers, Traps, Check valves, Globe Valves and Control Valves.
11 Check that all Non Return valve Flappers are Removed q q q
12 Check all In line Instruments are Removed q q q
13 Check All Instruments Impulse Line are Disconnected q q q
14 Check orifice valve Tap Orientation q q q
15 Check that orifice Flanges have Required upstream and Down Stream Clearance q q q
16 Check that the bases of all orifices Flanges have been Ground q q q
17 Check that all Pipe Supports are Completely Installed as per Drgs and q q q
Schedules- Additional Supports may be Required Refer to Standard Drg.
18 Check that any Temporary Pipe Supports required have been Installed q q q
19 Check that Gags on Springs Supports are in Position q q q
20 Check that all Chain Wheels Required for Specified Valve have been Installed q q q
21 Check that all Pipe Seals have been Installed q q q
22 Check that all Orifice Taps have been Seal Welded and unused tapped holes
have been plugged and seal welded q q q
23 Check test Medium for conformity to requirements q q q
24 Check Pressure gauge Calibration q q q
PREPARED BY SURIA QA/QC EPCL QA/QC
TT307B PIPING
RELEASE FOR
HYDRO / PNEUMATIC / LEAK TEST
Signature
Activity Clear Not Clear
SURIA EPCL
Temperature
S.No. Time Pressure (PSIG)
( C)
TT307B PIPING
TEST TYPE:-
Not Accepted
NOTE:
TT307B PIPING
Document Title: SYSTEM FLUSHING & AIR BLOWING REPORT
Date: Rev.: 00 Sheet 1 of 1
EQUIPMENT NO.
ISOMETRIC NUMBER REV. LINE NO. REMARKS
FROM TO
22023-ISO-01 5 14"-CS-1H-33-3501-CWR-5627
Signatre:
Date:
SURIA ENGINEERING.
TT307B PIPING
TEMPORARY REMOVED ITEM LIST
PROJECT: TT307B
YES N/A NO
1 Check all instruments removed as per item list before testing
Remarks:-
NAME:
SIGNATURE:
DATE:
SURIA ENGINEERING.
TT307B PIPING
Document POST TEST INSPECTION REPORT
Title: (REINSTATEMENT)
Flow poistion.
installed.
correctly installed.
installed.
Remarks:
Name:
Signature:
Date:
SURIA ENGINEERING.
TT307B PIPING
TEMPORARY BLIND AND SPOOL LIST
PROJECT: TT307B
Remarks:-
NAME:
SIGNATURE:
DATE:
TEST PACKAGE DRAWING / LINE INDEX
1 22023-ISO-01 1 of 1 5 14"-CS-1H-33-3501-CWR-5627
P & ID
Note:
Note: