Professional Documents
Culture Documents
Defects Found With Ammonia Plant Stacks During Plant Overhaul Examination
Defects Found With Ammonia Plant Stacks During Plant Overhaul Examination
During an ammonia plant shutdown, defects and deformations, as well as severe corrosion, were
discovered with several plant stacks. The causes of and solutions to these problems are discussed, as
well as efforts to prevent recurrence.
Duncan E. Anderson
ICI C&P Ltd., Billingham, England
Introduction with a 24-in. (610-mm) tip (Figure 1). The flare stack
and header system were lagged for acoustic reasons.
The stack was scheduled to be examined during the
T
he Ammonia 4 1,450-te/d ammonia plant oper-
ated by ICI C&P Ltd. at Billingham, England overhaul, and the acoustic lagging was removed in
was commissioned in 1977. In January 1997 several places for inspections. On removing the lag-
the plant was shut down for its major quarterly over- ging from the bend at the base of the stack, it was dis-
haul, and in the course of this defects were found with covered that the bend was deformed and flattened at
several of the plant stacks. On removal of the lagging the point of contact with the "duck foot" support
at the base of one stack, it was. found that the 90° bend which had pushed up into the bend (Photos 1 and 2).
was deformed and flattened at the point of contact
with the "duck foot" support. Severe corrosion was Investigation
also found to have taken place under the acoustic lag-
ging of three stacks. An investigation was immediately instigated to deter-
mine the cause of the deformed bend with two theories
Collapse of Bend of Stack considered possible:
(1) Thinning of the pipe due to corrosion or
Background (2) Overheating of the pipe at the bend.
Both lead to loss of strength in the bend metal allow-
The E stack is the main plant front-end blowoff flare ing it to be deformed by the weight of the stack.
stack- It is fed from a header system which can receive Initial indications suggested the latter theory to be
make gas from five locations. It is 47 m (154 ft) tall the most likely:
(1) There wasn't any excessive external corrosion
! Un»lMa.(«H»
Figure 1. E flare stack vent header system. Figure 2. E flare stack drainage lute.
the stack. With a low flow rate and hence small pres- Analysis
sure drop down the stack this can give rise to a nega-
tive pressure of typically around -20 m barg It is most likely that air has been drawn into the vent
(-8 in w.g.) at the stack base. This will suck air in from header via the drainage lute adjacent to the base of the
any holes in the vent header allowing a flammable stack. This is supported by the absence of heat damage
atmosphere to be created. or marking to other sections of the header upstream of
The E stack is fitted with a drainage lute at its base, the lute. Ennis (1997) states that if the mixture in the
approximately l m (3 ft) upstream of the deformed stack becomes flammable then the flame from the
bend. During the investigation into the cause of the pilot at the top of the stack may propagate back down
deformation, it was discovered that the lute had been the stack. It is possible for the mixture to run up to
incorrectly installed and did not provided a water seal detonation under these conditions; however, this is
to the drain point. This effectively gave a hole in the unlikely in a vented straight stack. The maximum
vent header at the base of the stack (Figure 2). With pressure experienced in the stack would be in the
the low steam purge rate and a small quantity of make order of 2.5 barg (36 psig). If the air ingress point had
gas entering the vent header from a passing blowoff been more than a few meters into the header system,
valve, conditions which were known to have occurred then it is likely that the deflagration would have run up
in the past, ideal conditions would be created for air to to a detonation which may have caused damage to
be sucked into the header via the drainage lute. Due to both the vent header and process equipment.
the large flammability range of the hydrogen rich In this case a stable flame appears to have been
make gas, this would easily give rise to a flammable formed immediately downstream of the air ingress
atmosphere. point causing localized heating of the pipework. The
Ineffective sealing of acoustic lagging at the top of Ennis, A., "Ammonia 4 Flare Stack Purging," ICI
vertical sections of stacks has allowed water ingress Internal Report (February 2,1997).
which has drained down and collected above lagging Taylor, G., ICI Internal Memo (February 14,1997).
DISCUSSION
A. J. Gupta, TATA Chemicals: Why are you not Anderson: It was a weakness. Our inspection philoso-
changing over to nitrogen purge for the stacks? phy and regime didn't focus heavily enough on
Anderson: At the moment we don't have enough inspection of stacks and inspection of the headers that
nitrogen on the site to supply all the stacks. entered those stacks.
Gupta: The nitrogen requirement for 24-in. size H. van Praag, Terra Nitrogen: Do your stacks have
stacks, I would guess, would be on the order of 15 to molecular sieves at the top?
20 normal m3/h. I think that's quite a small quantity. Anderson: No. Our stacks are straight through, steam
Then you could also get rid of the insulation as well. purged. They have no molecular sieves.
Anderson: The long-term plan is to move to nitrogen B. Geimard, Grande Paroisse: Does the pilot flame
purging with an oxygen analyzer on the stack to check burn continuously at the top of the flare?
for any ingress of oxygen. Anderson: Yes. Our pilots, which are John Zink SDF
L. Zafar, Fauji Fertilizer Companies, Pakistan: In the pilots, are pretty reliable. They don't have thermocou-
photographs that you have shown it seems that the ple monitoring but we have a visual check every shift
vessel and the stack were severely corroded. The prob- on the stacks.
lem could have been avoided by effective monitoring Guimard: Have you experienced explosive ignition in
and combating of the corrosion in the first place. the past when you flared gases?
Perhaps the vessel and the stack were the problem Anderson: We've never had any explosions at the top
area. Could you comment on that? of the stack.