Professional Documents
Culture Documents
Civil Technical Specification
Civil Technical Specification
Civil Technical Specification
BS British Standard
10.0 STEELWORK.............................................................................................................96
10.1 Materials Standard and Workmanship.......................................................................96
10.2 Workshop Drawing.....................................................................................................96
10.3 Erection Process.........................................................................................................96
10.4 Welding.......................................................................................................................96
10.5 Making Holes..............................................................................................................96
10.6 Cutting Metal Plate.....................................................................................................96
10.7 Barbed Wire................................................................................................................96
10.8 Nuts & Bolts................................................................................................................96
10.9 Stainless Steel............................................................................................................97
10.10 Aluminium...................................................................................................................97
10.11 Galvanizing.................................................................................................................97
10.12 Shop Painting.............................................................................................................97
10.13 Measurement..............................................................................................................97
The Contractor shall carry out the works so that there is the minimum of interruption in the supply
through the existing water mains and services. The Contractor shall comply with the requirements of
the Water, Gas, Telephone, Electricity and other Authorities. Where such interruption is
unavoidable, it shall only be carried out with the permission of and during such times as are agreed
in writing by the Engineer.
If it should become necessary for the proper execution of the work, to remove or divert temporarily
any existing pipe, field-drain or other service, the Contractor shall obtain permission from the
Competent Authority or Owner and shall carry out the work at his own cost in a manner and at times
to be approved by such Authority or Owner and shall subsequently reinstate the work to the
satisfaction of such Authority or Owner.
In addition to the office space required for his own use, the Contractor shall provide a furnished field
office for the use of the Engineer and his staff.
The Contractor shall submit for the approval of the Engineer before construction, plans and
drawings showing proposed details and location for the field office, including foundations, access
roads, shades, layout of electrical and water supplies and hard standings thereto. The Engineer
may require revision of the plans prior to giving approval for construction. The Contractor shall also
submit details of proposed furniture and fittings to the Engineer for approval. These items shall
generally be of the best quality obtainable locally.
The office, complete with furnishings, fittings, access roads and hard standings shall be ready for
occupation by the Engineer within four weeks of the date when the Contractor first occupies the site.
The Contractor shall arrange for the field office to be regularly and properly cleaned and for access
roads and hard standings to be maintained in a well drained and trafficable condition. All furnishings
and fittings in the field office shall also be maintained by the Contractor in working condition and to
the approval of the Engineer.
All materials recovered from dismantling the office and removing access roads, hard standings etc.,
should be stockpiled on site as approved by the Engineer and along with all furniture and fittings will
be the property of the Employer.
Except where otherwise specified, the Contractor shall execute any temporary drains, water courses
and other works that may be required to keep the works free from water and he shall supply and
work such pumping capacity as may necessary for the purpose.
Sanitary conveniences for the use of persons employed on the works shall be provided and
maintained by the Contractor to the extent and in such manner and at such places as shall be
approved by the Engineer and the Authority concerned, and all persons connected with the works
shall be obliged to use them. The Contractor shall make all temporary arrangements for the proper
discharge of sewage and drainage from or in connection with the Works and shall maintain the
same to the satisfaction of the Engineer and the Authority concerned as long as they may be
required.
The Contractor shall adopt such measures as the Engineer may consider reasonable and
necessary to minimize nuisance to others from noise, dust and other causes.
The Contractor is to proceed with the implementation of the works in accordance with the works
schedule for commencement and completion of the various sections. He shall submit to the
Engineer for his approval a statement with drawings and diagrams showing how he proposes to
carry out the Works. The statement shall describe the methods to be employed, the constructional
plant which the Contractor intends to supply or use together with the estimated dates on which the
various sections of the works will commence and the estimated rate of construction to ensure the
whole of the works are completed within the Contractor Period.
It shall be the Contractor’s responsibility before commencing the Contract to obtain from the
Engineer in writing the location and level of the benchmark to be used. All temporary benchmarks
shall be referred thereto.
(a) The levels of the ground and the levels and dimensions of existing features are believed but are
not guaranteed to be correct. Wherever dimensions or levels are marked on the drawings, such
dimensions or levels shall take precedence over dimensions scaled from the drawings and scaled
dimensions shall be used only in the absence of other more precise information. Large scale
drawings shall be used only in the absence of other more precise information. Large scale drawings
shall be taken in preference to drawings of a smaller scale.
(b) The drawings give dimensions and levels relating to the works, but these dimensions may be
modified by the Engineer if so required.
(c) The Contractor shall set in the ground on the Sites steel temporary benchmarks which shall be
securely concreted in. He shall establish the levels of these benchmarks and obtain the agreement
of the Engineer. All levels used in the construction of the works shall be referred to these
benchmarks.
Where any benchmark is situated within the working area, the Contractor shall, on written
agreement from the Engineer, locate and establish new benchmarks outside the working areas.
Each month on a date to be agreed with the Engineer, the Contractor shall arrange to take a series
of not less than 20 and not more than 40 color photographs which record the progress of the Works.
Two complete sets of prints of approximate size 175 mm x 125 mm plus the negatives shall be
supplied to the Engineer by the Contractor within one week of each series of photographs being
taken. A list shall accompany the photographs, indicating the date when the photographs were
taken and a short description of the photographs, against the negative numbers.
The Engineer will give the Contractor due notice of his intention to carry out any inspections during
the Defects Notice Period and the Contractor shall upon receipt of such notice arrange for a
responsible representative to be present at the times and dates named by the Engineer. This
representative shall render all necessary assistance and take note of all matters and things to which
his attention is directed by the Engineer.
Before incorporating in the finished work any materials or articles which he must supply under the
terms of the Contract, the Contractor shall submit to the Engineer for his approval a sample of each
respective material or article and such samples shall be delivered to and kept at his office for
reference. All the respective kinds of materials and articles used in and upon the works shall be at
least equal quality to the approved samples. Each and every sample shall be a fair average of the
bulk material or of the article which it represents. The Engineer may decide the method by which
each sample to be taken from bulk.
The responsibility shall rest upon the Contractor for ordering and delivering materials and
manufactured articles and samples that they may be tested sufficiently far in advance of the work so
as not to delay it. He shall not be entitled to any time credit for delays occasioned by his neglect to
order sufficiently well in advance or to payment of any costs he may incur as the result thereof. Any
tests carried out will be at the expense of the Contractor.
The materials and workmanship shall be of the best of their respective kinds and shall be to the
approval of the Engineer. In the reading of these Specifications, the words “to the approval of the
Engineer” shall be deemed to be included in the description of all materials incorporated in the
works whether manufactured or natural and in the description of the description of all operations for
the due execution of the works.
1. 16 Soil Dumps
The Contractor shall not deposit excavated materials on public or private land except where directed
by the Engineer in writing and with consent in writing of the Local Authority of the owner or reusable
representative of the owner of such land and only then in those places and under such conditions as
the Local Authority, owner or responsible representative may prescribe.
All soil, gravel, store or other material obtained in the excavation, clearing and earth stripping of the
sites of the works shall belong to the Employer except where otherwise described and must not be
removed from the works Site without the consent of the Engineer. The Contractor, however, shall
use for the construction or installation of the works any of the materials excavated which the
Engineer may determine to be fit for such use.
1. 18 Unsuitable Materials
Where in the opinion of the Engineer, existing materials are unsuitable for use in the installation or
construction, the Contractor shall remove such unsuitable material and replace it with filling
approved by the Engineer and such work shall be covered by the Conditions of Contractor.
1. 19 Notice Boards
Notice Boards in Bengali and English are to be displayed in suitable positions on the Sites on the
day work commences. This is to show the Employer’s name together with name of the Project and
the names of the Consulting Engineer and the Contractor. The exact sign dimensions and layout
and the exact positions of the signs on the Site are to be agreed with the Engineer.
The Contractor shall provide, erect and maintain on the Sites at such positions and for such duration
as may be required by the Engineer all protective barriers, traffic signs and traffic control signals
necessary for the direction and control of all traffic and clear away when the work involved in the
diversions has been completed.
The signs and barriers shall be adequately illuminated at night and kept clean and legible at all
times. The Contractor shall reposition the barriers, signs and signals as necessary as the work
progresses.
Where single file traffic is necessary, the Contractor shall, where directed by the Engineer, provide
and maintain temporary lighting, barriers and traffic direction signs required.
The Contractor shall at all times conform to the provisions of any ordinance and of any order,
proclamation, rule or notice made under any ordinance relating to the works, employment of labor,
etc. and to any water or electricity company within whose area and jurisdiction the works are to be
executed.
The Contractor is to allow for the provision, maintenance and removal at the end of the Contract of
all offices, stores, covered workshops, canteens, toilet facilities etc. for his own use, required to
execute the Works in accordance with the Contract Documents. In addition, the Contractor is to
allow for complying with his obligations for safety, security and protection of the environment
described in the Contract Documents.
This item is for the provision by the Contractor of the Performance Security, the requirements of
which are stated in Contract document.
This item is for the provision of insurances as required in accordance with Clauses in contract
document. The minimum amount of third party insurance shall be as stated in the contract
document. Failure to provide insurance will result in no interim payment.
The Contractor shall furnish sets of as-built Drawings of the Works to the Engineer, showing the
permanent works as actually constructed, within one month of completion of the Works. Included in
the sets of as-built Drawings will be revisions of Tender Drawings and Drawings supplied to the
Contractor during the Contract as well as revisions of drawings supplied by the Contractor during
the Contract. The As-built drawings Submitted by the Contractor will be subject to the approval of
the Engineer. For specific requirements for the As-built Drawings refer to Particular Specifications.
1. 23 Price Escalation
During the project period, the market price of the construction or manufacturing materials may be
higher or lower than the estimated cost / quoted rate or analyzed rate submitted by the contractor
for manufacturing of the equipment and ancillary works. The appointed contractor would not be
allowed to claim extra money for escalation of price of materials. The contractor will be paid for
satisfactory completion of works only as per BOQ of the tender document.
2.1.1 Description
This work shall consist of excavation in any material for the foundation of structures, other than pipe
trench, not otherwise provided for in the Specifications; constructing and removing cofferdams,
sheeting; pumping, dewatering and bailing; backfilling of completed structures with suitable material
and disposal of excavated material.
2.1.2 Materials
2.1.3.1 Clearing
Prior to starting excavation operations in any area, all necessary clearing and grubbing shall have
been performed accordingly.
2.1.3.2 Excavation
(A) General
The Contractor shall notify the Engineer sufficiently in advance of the beginning of any excavation
so that cross section elevations and measurements may be taken of the undisturbed ground. The
natural ground adjacent to the structure shall not be disturbed without permission of’ the Engineer.
Trenches and foundation pits for structures and structure footings shall be excavated to the lines,
grades and elevations shown on the Drawings or as directed by the Engineer, The elevations of the
bottoms of footings shown on the Drawings are approximate only and the Engineer may order in
writing such changes in the dimensions or elevations of footings as may be deemed necessary to
secure a satisfactory foundation.
Boulders, logs and other objectionable material encountered in excavation shall be removed After
each excavation is complete the Contractor shall notify the Engineer to that effect and no footings,
bedding material or structure shall be placed until the Engineer has approved the depth of
excavation and the character of the foundation material.
The foundation material shall be cleared of all loose material and cut to a firm surface, either level or
stepped or serrated, as specified or shown on the Drawings or directed by the Engineer.
If the bottom form is achieved by such strengthening of the ground, the Contractor shall, if
requested, submit calculations showing that the pile cap will not be harmed during hardening due to
differential settlements between the piles and the strengthened ground
Excavated material shall be deposited in such places and in such a manner as not to cause damage
to roads, services or property either within or outside the right-of-way and so as to cause no
impediment to the drainage of the site or surrounding area The location of spoil heaps shall be
subject to the approval of the Engineer who may require that the reference lines and the traverse
lines of any part of the structure be kept free of obstruction.
2.1.3.4 Cofferdams
(a) The term “cofferdam” denotes any temporary or removable structure, constructed to hold
the surrounding earth, water or both, out of the excavation, whether such structure is
constructed of earth, timber, steel, concrete or any combination of these. The term includes
earth dikes, timber cribs, sheet piling, removable steel shells and all bracing— and it shall
be understood to include excavation enclosed by pumping wells and well points.
The cost of cofferdams is always to be included in the tender rates/prices for the permanent
work.
(b) The term “caisson” denotes a permanent part of the substructure so constructed as to sink
gradually into place as material is excavated within the area protected by its side walls.
Where the term “well is used it shall be taken to have the same meaning as caisson”.
(c) When no provision for caissons is shown on the Drawings, it shall be the intent of the
Contract that suitable cofferdams shall be provided for all excavations where cofferdams
may be necessary in order to control water to preclude sliding and caving of the walls of the
excavation.
(d) The Contractor shall submit upon request, drawings showing his proposed method of
cofferdam and caisson construction. Approval of the drawings by the Engineer will not in
any way relieve the Contractor of the responsibility for the adequacy of the design for
strength and stability or for the safety of the people working therein.
(e) The interior dimensions of cofferdams shall be such as to give sufficient clearance for the
construction and removal of any required forms and the inspection of the interior and to
permit pumping.
(f) If possible, cofferdams shall be so designed that no cross bracing shall be left in place. If
this is not possible bracings left in place shall be of structural steel. The end of such
structural members that would be exposed when the structure is completed shall be boxed
back at least 50 mm behind the concrete face. The resulting holes shall be completely filled
with concrete.
(g) In general, sheet piling cofferdams shall extend well below the bottom of the footing and
shall be well braced and as watertight as possible.
(h) When foundation piles are to be driven inside a cofferdam and it is judged impossible to de-
water the cofferdam before placing a concrete seal, the excavation may be extended below
the designed level to a depth sufficient to allow for swell of the material during pile driving
operations. Any material that rises to a level above the design level shall be removed.
(i) Where it is possible to dc-water the cofferdam, the foundation material shall be removed to
exact grade after the foundation piles are driven) Backfilling in a foundation to
PW3-Sec-7 (Tech. Spec.) 9
compensate for excavation, which has been extended below the required grade, shall be at
the expense of the Contractor. Backfilling shall be with concrete or foundation fill material as
indicated on the Drawings, or as directed by the Engineer.
If no material is indicated, backfilling shall be concrete of the same kind as required for the
structure to be constructed in the excavation. Unless otherwise permitted no excavation
shall be made outside of caissons or cribs or cofferdams or sheet piling and the natural
streambed adjacent to the structure shall not be disturbed without permission from the
Engineer.
If any excavation or dredging is made at the site of the structure before caissons, cribs, or
cofferdams are in place, the Contractor shall after the foundation is in place, backfill all such
excavation to the original ground surface or stream bed with material satisfactory to the
Engineer.
Material deposited within the stream area from foundations or other excavations or from the
filling of cofferdams shall be removed and the stream area freed from obstruction.
(j) Caissons and cofferdams, which have tilted or moved laterally during construction, shall be
corrected as necessary at the expense of the Contractor.
(k) Unless otherwise provided cofferdams shall be removed, after the completion of the sub-
structure. The removal shall be effected in such a manner as not to disturb or mar the
finished work. The Engineer may order the Contractor to leave any part or the whole to the
cofferdam in place.
(l) When conditions which, in the Opinion of the Engineer, render it impossible to dc-water the
foundation before placing the footing are encountered, the Engineer may require the
construction of a concrete foundation or seal of such dimensions as he may consider
necessary, and of such thickness as to resist any possible uplift. The concrete for such seal
shall be placed as shown on the Drawings or required by the Engineer. The foundation shall
then be de-watered and the footing placed. When weighted cribs are used and the weight is
used to overcome partially the hydrostatic pressure acting against the bottom of the
foundation seal, special anchorages such as dowels or keys shall be provided to transfer
the entire weight of the crib to the foundation seal. When a foundation seal is placed under
water the cofferdam shall be vented at low water as directed.
Cofferdams shall be constructed so as to protect newly cast concrete from sudden rising of
the water and to prevent damage to the foundation by erosion.
Excavation shall be as- dry as possible prior to and during placing concrete. Placing concrete under
water will only be permitted if indicated on the Drawings or approved by the Engineer.
2.1.3.6 Backfilling
All spaces excavated under these Specifications and not occupied by the permanent structure shall
be backfilled. Backfilled material shall fully comply with this Specification and adequate provision
shall be made for drainage. No backfilling shall commence until permission has been given by the
Engineer.
Backfill under top level of pile caps shall always be made with compacted sand fill free from
chemical contamination. Over top level of the pile cap but outside embankment and road areas, the
backfill shall be excavated material if suitable and free from chemical contamination, and approved
by the Engineer. If the excavated material is not suitable, the Engineer may order sand filling.
PW3-Sec-7 (Tech. Spec.) 10
Special care shall be taken to prevent any unduly high pressure against the structures. In placing
backfill and embankment, the material shall be placed insofar as possible to approximately the
same height on both sides of the structure at the same time. If conditions require backfilling
appreciably higher on one side, the additional material on the higher side shall not be placed until
permission is given by the Engineer that the structure has enough strength to withstand any
pressure created.
Jetting of fill or other hydraulic methods involving, or likely to involve, liquid or semi-liquid pressure is
prohibited. Backfill and embankment fill shall not be placed behind the walls of bridges or box
culverts until the top slab has been placed for at least three days.
The placing of embankment and the benching of slopes shall continue in such a manner that at all
times there will be a horizontal beam of thoroughly compacted material for a distance at least equal
to the height of the abutment or wall to be backfilled.
2.1.4 Measurement
The volume of excavation and backfill shall be measured in cubic meters of excavated undisturbed
material.
The quantity of excavation for structures to be measured for payment shall include excavation for all
structures except pipe culverts, which will be in accordance with Section 6.2. The measured volume
shall be the excavation plan outline, bounded on the bottom by the plane of the underside of the
brick flat soling to the blinding concrete under the reinforced concrete footing and on the top by the
surface of the existing ground and on the sides by vertical planes of the footings.
Backfilling with previously excavated material shall not be measured or paid for separately but shall
be deemed included in the rate for excavation.
Backfill with concrete or sand where directed by the Engineer including concrete seals shall be
measured separately as the volume within the- plan outline and top and bottom surfaces. Concrete
or sand placed to backfill excavation beyond the excavation required will not be measured for
payment. The plan outline referred to is the excavation plan outline as defined above. If sand fill is
ordered over top level of pile cap, the fill shall be the specified filling volume measured on the
Drawings up to profiles agreed upon in writing by the Engineer. In the case of structures for which a
lump sum price is called for, the volume of excavation as stated above for the work as shown on the
Contract Drawings, shall be subtracted from the volume measured as above, and the price to be
paid or deducted shall be based on the measured increase or reduction of the excavation shown on
the Drawings.
Removal of slides, cave-ins, silting or filling shall not be measured nor paid for.
Notwithstanding any relevant information furnished by the Employer or Engineer, the Contractor
shall be responsible for ascertaining from his own inspection of the Site and from the respective
supply authorities and other public bodies the position of all mains, pipes and pipe, whether
underground or overhead, within or near the site.
2.2.2 Excavation
Trial holes or pit shall be excavated well ahead of the trench excavation to such depths as are
necessary to determine the alignment for the trench. Trial holes may also be required by the
PW3-Sec-7 (Tech. Spec.) 11
Contractor to determine the position of underground services, subsoil drains or for any other reason.
Trial holes shall be excavated and reinstated at the Contractor’s expense and the Contractor rates
for pipe line installation shall be deemed to provide for all trial holes.
Excavations shall be done in all kinds of soils for pipe trench up to required depth of 1.1m plus pipe
diameter from the road surface and width equal to outer diameter of pipes plus 0.3m as per drawing
and direction of the Engineer. While excavating, at least 150 mm of the depth shall initially be left
unexcavated which shall dug out carefully in the final dressing after checking of the levels. If any
portion of the trench is excavated to a greater depth than specified, the excess depth shall be filled
up with compacted khoa and sand in the ratio of 2:1 at the contractor’s own cost. If foundation bed
is wet due to rains or due to slow seepage of water, care shall be taken to dry it up before the
foundation is laid. Dry sand is to be laid to the required thickness for this purpose at contractor’s
cost. The excavated earth shall be kept sufficiently away from the side walls to avoid collapse of the
excavations due to the pressure of the surcharged earth and also in such a manner that it does not
interfere with traffic or approach to private or public properties.
When excavation is made on metal, tarred, concrete or brick paved roads, the Contractor shall
remove the salvageable cut materials, stack them away from the trenches and preserve them
separately from excavated earth. Any excavated earth shall be removed from site within 24 hours of
excavation.
The line level of trenches shall be as shown in the Drawings or as may be directed by the Engineer.
Before starting trench excavation, the route of the trench shall be pegged out accurately and the
natural ground levels and chainages shall be measured and agreed with the Engineer. Strong sights
rails shall then be fixed and maintained at each change of gradient, and as many intermediate point
as may be necessary. On these rails shall be marked the centre line and the level at which the
excavation is to be carried out, such rails being not more than 50m apart.
The sides of trench excavation shall be vertical unless the Engineer permits otherwise.
The Contractor shall support the sides of trench excavation to prevent any fall or run from any
portion of the ground outside the excavation and to prevent settlement of or damage to structures
adjacent to the excavation. The Contractor shall be deemed to have made his own allowance for
any excess excavation necessary to provide space for such support and for any other working
space. If for any reason any portion of trench excavation shall give way, the Contractor shall at his
own expense take all necessary remedial measures including the excavation and removal of all the
ground thereby disturbed and extra excavation shall be held to be excess excavation.
Where the contractor elects, and is permitted by the Engineer, to execute trench excavations with
battered sides instead of providing support as aforesaid they shall be excavated to stable slopes
and heights and the resulting extra excavation shall be held to be excess excavation.
Where land drains, culverts or field drains are served by trench excavation, they shall be kept in
effective temporary operation during construction of structure / pipe line. At the appropriate stage of
refilling the trench excavation, the drains shall be permanently restored to their original capacity to
the satisfaction of the Engineer.
Where trench excavation or other work is carried out close to or across existing drains, pipes, pipe,
or other services etc. the Contractor shall obtain all necessary consents from the relevant parties
and execute the work in agreement with regulations etc. in force. Due care for the existing
installations, structure, construction, etc. shall be taken in aligning the pipes and the contractor shall
take all necessary precautions to prevent damage to the said objects. Any expenses caused by
damages etc. in this connection are the total responsibility of the contractor.
Where the trench excavation crosses barriers such as fences and walls, the Contractor, as
temporary measure during construction of the pipe lines, shall provide temporary fencing for any
parts of such barriers as have had to be removed. After trench Excavation has been reinstated, the
Contractor shall carry out the permanent restoration of such barriers.
Design of the shoring or boxing shall be determined by the site conditions and shall be subject to
the approval of the Engineer. The process of boxing and shoring shall be continued until the
excavation reaches the required depth of cutting. All boxing and shoring materials such as planks,
runners and struts shall be withdrawn from the excavations prior to completion of backfilling.
Where gravity drainage is not possible or practical, the Contractor shall provide adequate pumping
facilities to maintain the excavation in a safe and workmanlike condition so that any water dose not
interferes with the progress and quality of the works. Unless specifically provided for by a separate
item in the contract, any costs of pumping shall be deemed to be included in the contract rates, and
no extra payment will be made on this account.
The Engineer shall normally direct that trench excavation along roads be located in footpaths or
verges adjacent to the road rather than in the carriage way itself. Trench excavation shall wherever
practicable be carried out in such a way that every part of the excavation is at least 0.9 m clear of
existing edges of the carriage way. In any event the Contractor shall take special precautions, which
shall include the continuous support of the sides of the excavation, from the time when excavation is
begun until the refilling of the trench is placed, to ensure that there is no disturbance of the adjacent
road or road foundation.
Where trench excavation or any other part of the works obstructs any footpath or right-of-way, the
Contractor shall provide, at his own cost, a temporary footpath around the obstruction of the
Engineer. Where applicable, this temporary footpath shall include stout bridges of wooden planks or
other approved construction across any open trenches.
Where excavated material has temporarily been deposited on a grass margin or verge, the margin
If the bottom of any trench excavation acceptable by the Engineer at the time of his inspection
subsequently become unacceptable due to exposure to weather conditions or due to flooding or
have become puddle, soft or loose during the progress of the works the Contractor shall remove
such damaged, softened or loosened material and excavate further by hand. Such further
excavation shall be held to be excess excavation without any cost to the employer.
The Contractor, when working along carriage ways where it is not possible to stack excavated
materials along the trench, shall be required to remove such materials required for backfill to
temporary sites to be provided by the Contractor and to return these materials on completion of the
installation of pipe laying
For back filling over the pipe zone in open areas / non traffic pathways and traffic ways excavated
materials from the trench shall be placed in 150mm layers and compacted to the original condition
to the satisfaction of the Engineer.
Back filling in the road crossing shall immediately be executed for restoration of movement of
vehicular traffic in easy manner. Until the pavement is restored, the Contractor shall be responsible
to maintain the road in a manner which will allow easy traffic movement.
To permit the proper consolidation of back fill into the voids behind trench sheeting and supports,
trench sheeting shall be withdrawn gradually as back fill progresses in depth and along the trench.
On no account shall any excavated material be dozed back when refilling trenches in roads and no
back filling shall be carried out unless, in the opinion of the Engineer, sufficient mechanical rammers
are in operation on that portion of the work.
Compaction of sand, local fill sand and excavated trench materials shall be done by watering and
compacting with pneumatic or petrol driven tamper not exceeding in 150 mm layers. Prior to
acceptance of the work, the Contractor shall re-grade the area up to the level of the surrounding
ground.
Any approved refilling material become unacceptable to the engineer due to exposure to weather
conditions or due to flooding or have become soft or segregated during the progress of work, the
Contractor shall at his own expense remove such damaged, softened or segregated material and
replace it with fresh approved material.
Volumes of back fill which fail to meet the specified compaction, as tested by the Engineer, shall be
reworked and re-compacted as directed by the Engineer
3.1.1 Description
This work comprises the construction of bored cast in place piles for bridges, including the provision
of all materials and structures in accordance with these Specifications and in conformity with the
requirements of the Drawings or other parts of the Contract Documents.
Piles through water and soft upper soil layers shall be provided with permanent steel casting if
shown on the Drawings.
The pile boring shall be carried out using a temporary steel casing bored to the pile toe or to a level
approved by the Engineer. The temporary casing shall be withdrawn.
Under certain circumstances the Contractor may be permitted to bore all or part of the pile without
casing under water or use drilling fluid to stabilize the borehole as referred to in Section 3.1.2.4.
The piles shall be concreted and reinforced to resist pile loads and horizontal forces on the pile caps
according to the Drawings and these Specifications.
3.1.2 Materials
When permanent steel casing is shown on the drawings, the steel shall conform to the AASI-ITO
Standard Specification M 183-79 (ASTM A36) or equivalent.
The minimum thickness of the permanent steel casing shall be 10 mm. The minimum length shall be
from 100 mm above the bottom of the pile cap to 5 metre under the riverbed or into firm strata. If the
permanent casing is used in the boring operation or if the handling and transport require a greater
thickness to avoid deformation or buckling, the increase in thickness shall be provided by the
Contractor at his own expense.
The steel casing shall be furnished in appropriate lengths and the joints shall be approved by the
Engineer.
The casing shall be handled and stored in a manner that shall prevent buckling and other
deformation as well as accumulation of dirt, oil and paint. When placed in the work it shall be free
from dirt, oil, grease, paint, mill scale and loose or thick rust.
The outside surface of the permanent casing of piles to river piers, for the depth indicated on the
Drawings from the underside of the pile cap shall receive two coats of anticorrosion tar type paint.
The paint shall be approved by the Engineer and its application shall follow the manufacturer’s
instructions.
3 1.2.2 Concrete
The concrete shall conform to Section 3.1 of these Specifications. Concrete class 21 with type 2
cement shall be used.
Concrete placed under-water or drilling mud by tremie shall have a cement content of not less than
350 kg/m3.
The density and consistency of the concrete shall conform to the tremie casting method and the
maintenance of sufficient workability (slump) of all the concrete during the casting and casing
handling period, including reasonably calculated delays, shall be secured by a design mix,
(including the necessary retarders and plasticisers), tested by trial mixes prior to the pile
construction.
(A)Supply
The Contractor shall obtain a certificate from the manufacturer of the bentonite powder, showing the
properties of the consignment delivered to the site. This certificate shall be made available to the
Engineer on request. The Properties to be given by toe manufacturer are the apparent viscosity
range (in centipoises) and the gel strength range for solids in water.
Any other material proposed by the Contractor for the drilling fluid shall be approved by the
Engineer.
(B)Mixing
Bentonite and any other material shall be mixed thoroughly with clean water to suspension which
shall maintain the stability of the pile excavation br the period necessary to place concrete and
complete construction.
Where saline or chemically contaminated groundwater occurs, special precautions shall be taken to
modify the bentonite in fresh water so as to render it suitable in all respects for the construction of
piles.
(C)Tests
The frequency of testing drilling fluid and the method and procedure of sampling shall be proposed
by the Contractor and approved by the Engineer prior to the commencement of the work, The
frequency may subsequently he varied as required depending on the consistency of the results
obtained. The control tests shall cover the determination of density, viscosity, gel strength and pH
values.
The Contractor shall supply all equipment and experienced operators required to carry out tests on
the drilling mud. No additional payment shall he made for these tests which shall be considered. as
an essential part of the drilling operations.
3.1.3.1 General
The Contractor shall demonstrate to the satisfaction of the Engineer that his proposed construction
methods for the piles do not result in the pile shafts being weakened by contamination of the
concrete, by sectional reduction, by washing out of cement. by breaking during pulling of temporary
casings or in any other way, including the construction of neighboring piles.
The following construction procedure has been assumed in the tender design. The final construction
procedure shall be as approved by the Engineer prior to commencing piling operations.
I. Place permanent steel casing, if required, in position and embed casing toe into river
bed or firm strata. If no permanent steel casing is specified a sufficient length of
temporary steel casing shall be used to stabilize the upper part of the borehole.
2. Bore and excavate inside the steel casing down to casing toe level, or to a level
approved, and continue excavation to final pile tip level using either temporary casing
under water, or using drilling mud. The fluid level inside casings shall at all times be at
least 2 metres higher than outside the casings.
6. Withdraw the temporary boring casing concurrently with concreting to the instructed
level.
7. After hardening, break out the top section of the concrete pile to reach sound concrete.
In the tender, the Contractor shall describe the construction method he proposes, including name of
proposed Sub-contractor (if any), information on boring equipment, materials, methods of work and
control of quality. The Contractor shall submit references from similar jobs carried out by him and/or
his proposed Sub-contractor.
During contract negotiations, the Contractor shall submit all requested supplementary detailed
information in writing.
After the Contract has been awarded, the Contractor shall prepare a detailed programme and
establish a procedure for the pile construction. The detailed programme shall contain all required
information on materials. equipment, methods of work etc. and be approved in writing by the
Engineer. Such approval shall not, however, relieve the Contractor of his responsibilities for pile
construction.
The import of ajiy boring equipment or materials by the Contractor, before he has received the
Engineer’s approval of proposed construction methods, shall he at the Contractor’s risk.
3.1.3.4 Tolerances
The centre of Ike 6ornptcted pile at the cut off level shall not deviate more than 100 mm from the
theoretically correct position shown on the Drawings. The inclination of the pile shall not deviate
more than 1:100 from vertical. The Contractor shall provide suitable equipment, such as an inverted
pendulum, to check the verticality of the boreholes at intervals during drilling and prior to concreting.
3.1.3.5 Boring
(A) Methods
Method of excavation shall be proposed by the Contractor and approved by the Engineer. Water or
air jetting for boring of the piles shall not be allowed.
Temporary casings shall be free from significant distortion. They shall be of uniform cross-section
throughout each continuous length. During concreting they shall be free from internal projections
and encrusted concrete which prevent the proper formation of piles.
PW3-Sec-7 (Tech. Spec.) 19
(D) Stability of Pile Excavation Using Drilling Fluid
Where a borehole is formed without casing under water or using drilling fluid for maintaining the
stability of a boring, the level of the water or fluid in the excavation shall be maintained so that the
water or fluid pressure always exceeds the pressure exerted by the soils and external ground water.
The water or fluid level shall be maintained at a level not less than 2 metres above the level of the
river water level or any artesian pressure level.
In the event of a rapid loss of water or bentonite suspension from the pile excavation, the excavation
shall be backfilled without delay and the instructions of the Engineer shall be obtained before
excavation at that location is resumed.
(G) Obstructions
Where boulders or other obstructions render it impossible to bore the pile, excavation operations
inside pile casing as directed by the Engineer shall he carried out to remove obstructions and the
Contractor shall he reimbursed for such operations only when the largest dimension of the
obstruction exceeds 200 mm and the obstruction is found more than 2 metres below river bed.
The Contractor shall allow for carrying out sampling and tests to check soil strengths as required by
the Engineer.
The final toe level of other piles may subsequently be altered according to the results of the test
loadings detailed in Section 3.4.
On completion of the drilling an interval is required, to allow the fine materials to settle (15 minutes
unless otherwise approved by the Engineer). Thereafter the bottom of the excavation shall be
PW3-Sec-7 (Tech. Spec.) 20
carefully cleaned of mud, sedimentation and other soft material by an approved method. The
Contractor shall show, to the satisfaction of the Engineer, that the bottom of the excavation is clean.
Sedimentation tests shall be carried out by the Contractor in the presence of the Engineer.
If boring without casing, the diameter of the boring hole for a representative number of piles shall be
measured by caliper prior to the placing of concrete. The verticality of boreholes will be checked as
directed by the Engineer. These measurements shall be done by the Contractor using approved
equipment and no reimbursement shall be made.
Joints in longitudinal steel bars shall be permitted unless otherwise specified. Joints in
reinforcement shall be such that the full strength of the bar is effective across the joint and shall be
made so that there is no relative displacement of the reinforcement during the construction of the
pile.
Joints in longitudinal bars in piles with tension (for instance for test loading) shall be carried out by
welding unless another method has been approved by the Engineer.
(A) Approval
No concreting shall take place before the bottom of the excavation has been cleaned, the borehole
inspected and approval obtained in writing from the Engineer.
The method for placing concrete requires to be approved and conform with the following:
The method of placing and the workability of the concrete shall be such that a
continuous monolithic concrete shaft of the full cross section is formed.
The concrete shall be placed continuously, and without such interruption as would allow
the previously placed batch to have hardened in this respect the Contractor shall submit
details of his contingency plans, standby plant etc to be utilized in the event of an
equipment failure.
The use of pumped concrete and the methods in its use shall be approved.
The Contractor shall take all precautions in the design of the mix and placing of the
concrete to avoid arching of the concrete in a casing. No spoil, liquid or other foreign
matter shall be allowed to contaminate the concrete
13) Workability of Concrete
Slump measured at the time of discharge into the pile boring shall be in accordance with Table
4.1.1.
Stump
Pilling
Minimum Range Typical Conditions of Use
Workability
(mm) (mm)
A 75 75-150 Placed into water-free unlined or permanently lined bore of
600 mm diameter or over or where casting level lines below.
Temporary casing: reinforcement widely spaced, leaving
ample room for free movement of concrete between bars.
B 100 100-200 Where reinforcement is not spaced widely: where cut-off level of
concrete is within temporary casting: where pile bore is water-
free is water-free and the diameter is less than 600 mm.
Before placing concrete, the Contractor shall ensure that there is no accumulation of silt, other
material, or heavily contaminated bentonite suspension at the base of the boring, which could impair
the free flow of’ concrete from the pipe of the tremie. A sample of the bentonite suspension shall be
taken from the base of the boring using an approved sampling device. If the specific gravity of the
suspension exceeds 1.2, the placing of concrete shall not proceed. In this event the Contractor shall
modify the mud quality.
The concrete shall he a rich coherent mix of high workability in accordance with Section 3.1.2.2 and
shall be placed in such a manner that segregation does not occur.
During and after concreting, care shall be taken to avoid damage to the concrete from pumping and
dewatering operations.
The hopper and Pipe of the tremie shall be clean and watertight throughout. The pipe shall extend
to the base of the boring and a sliding plug or barrier shall be placed in the pipe to Prevent direct
contact between the first charge of concrete in the pipe of the tremie and the water or drilling fluid.
The pipe shall at all times penetrate the concrete, which has previously been placed and shall not
be withdrawn from the concrete until completion of concreting. The bottom of the tremie pipe shall
be kept at least 1.5 meters under the surface of concrete once that amount of concrete has been
placed. At all times a sufficient quantity of concrete shall be maintained within the pipe to ensure
that the pressure from it exceeds that from the water or drilling fluid. The internal diameter of the
pipe of the tremie shall he not less than 150 mm I’or concrete made with 20 mm aggregate and not
less than 200 mm for concrete made with 40 mm aggregate. It shall he so designed that external
projections are minimized, allowing the tremie to liass through reinforcing cages without causing
damage. the internal face of the pipe of the tremie shall be free from projections.
The Contractor shall maintain a continuous record of’ the volume of concrete used and the level of
the concrete in the pile. Any deviations from the theoretical, or expected, volume level relationship
shall be immediately reported to the Engineer.
No concrete shall he place in the boring once the bottom of the casing has been lifted above the top
of the concrete: it shall be placed continuously as the casing is extracted until the desired head of
concrete is obtained.
Adequate precautions shall be taken in all cases where excess heads of water or drilling fluid could
be caused as the easing is withdrawn because of the displacement of water or fluid by the concrete
as it flows into its final position against the walls of the shaft.
The pile shall be concreted with certain over height to allow for chiseling off the top concrete down
to sound hard concrete.
(E) Supervision
The execution of the pile concreting shall be supervised by a qualified person of the Contractor’s
staff, who will keep records on the relation between quantity of concrete used, level of concrete and
withdrawal of casing.
3.1.3.10 Records
The Contractor shall keep records as indicated below for the installation of each pile and shall
submit two signed copies of these records to the Engineer not later than noon of the next working
day after the pile was installed. The signed records shall form a record of the work. The following
data are required:
a) Pile location
b) Pile reference number
c) Pile type
d) Nominal cross-sectional dimensions or diameter
e) Date and time of boring
f) Date and time of concreting
g) River bed level at commencement of installation of pile
h) Working level
i) Pile toe level
j) River water levels
k) Pile head level
1) Length of temporary casing
m) Length of permanent casing
n) Soils samples taken and in situ tests carried out
o) Standing water level
p) Length and details of reinforcement
q) Concrete mix
r) Volume of concrete supplied to pile and corresponding levels of concrete and casings
s) All information regarding obstructions, delays and other interruptions to the sequence
of work.
The pile shall be replaced as directed by the Engineer. All extra expenses shall be borne by the
Contractor and payment shall be made on the basis that no replacement pile had to be provided for
the unsatisfactory pile.
When the safe bearing value of any pile is found by test to he less than the design load, longer piles
or additional piles shall be installed as ordered in writing by the Engineer.
3.1.4 Measurement
The unit of measurement for bored cast in place piling shall be the linear meter of pile constructed
PW3-Sec-7 (Tech. Spec.) 23
and accepted in the structure the payable lengths of the satisfactory bored piles shall be measured
from the toe level to cutoff 100 mm above the bottom level of pile cap. Pile permanent steel casing
shall be measured separately in linear meters of the installed and accepted length of casing.
Reinforcement steel shall be measured in accordance with Specifications Section 5.2.4.
3.1 .5 Payment
Bored piles shall be paid for at the Contract unit price per linear meter. The rate shall constitute full
compensation for all materials including temporary casings and concrete, but excluding
reinforcement steel and Permanent Steel Casing, which items will he paid for separately. The rate
shall also include
boring equipment, standard penetration testing, split spoon sampling, boring, excavation,
concreting, inspection and control, cutting off, welding, coupling and all related tools, rigs, cranes,
jets, frames, leads, labor, and other incidental equipment and work necessary to complete the work.
Payment for reinforcement steel shall be at the Contractor’s rates per tone for mild steel and high
yield deformed steel bars.
Payment for Pile Permanent Steel Casing shall be at the Contract unit price per linear meter. The
rate shall constitute full compensation for all materials, labor and plant necessary for providing and
installing the casing, including all jointing, testing and coatings.
No payment shall he make for unauthorized. Defective, unsound or un-satisfaction piles, or for any
costs incurred by the Contractor for such piles.
3.2.1 Descriptions
3.2.1.1 General
This Section deals with the testing of a pile by the application of an axial load or force. It covers
vertical piles tested in compression.
3.2.1.2 Definitations
(C) Kentledge
The dead weight used in a loading test.
3.2.2 Supervision
All tests shall be carried out only under the direction of an experienced and competent supervisor
conversant with the test equipment and test procedure. All personnel operating the test equipment
shall have been trained in its use.
3.2.3.1 General
When preparing for, conducting and dismantling a pile test the Contractor shall carry out the
requirement of’ the various regulations and other statutory instruments that are applicable to the
work for the provision and maintenance of safe working conditions, and shall. in addition make such
other provision as may be necessary to safeguard against any hazards that are involved in the
testing or preparations for testing.
3.2.3.2 Kentledge
Where kentledge is used the Contractor shall construct the foundations for the kentledge and any
cribwork beams or other supporting structure in such a manner that there will not be differential
sctt1enent, bending or deflection of’ an amount that constitutes a hazard to safety or impairs the
efficiency of the operation. The kentledge shall he adequately bonded, tied or otherwise held
together to prevent it filling apart. or becoming unstable because of’ deflection of’ the supports.
The weight of kentledge shall be greater than the maximum test load and if the weight is estimated
from the density and volume of the constituent materials an adequate factor of safety against error
shall be allowed.
The hydraulic jack, pump, hoses, pipes, couplings and other, apparatus to he operated under
PW3-Sec-7 (Tech. Spec.) 25
hydraulic pressure shall be capable of withstanding a test pressure of 1 .5 times the maximum
working pressure without leaking.
The maximum test load or test pressure expressed as a reading on the gauge in use shall be
displayed and all operators shall be made aware of this limit.
3.2.4 Construction of a Pilot Pile to be Test Loaded
3.2.6.3 Spacing
Where kentledge is used for loading vertical piles in compression, the distance from the edge of the
test pile to the nearest part of the crib supporting the kentledge stack in contact with (lie ground shall
be not less than 1 .3 meters.
The centre to centre spacing of vertical reaction pits, including working piles used as reaction piles,
from a test pile shall he not less than three times the diameter of (lie test pile or the reaction piles or
In addition, large diameter (i.e. exceeding 1 .2 metre) test piles shall he instrumented at 5 different
depths to measure the load distribution along the piles. 1’lic instrumentation shall consist of both a
mechanical system and strain gauges for measuring the pile deformation, The mechanical system
shall consist of 6 mm steel rods or high ensile steel wires gauge No. 23, placed in steel tubes down
to the various depths, and connected to dial gauges at the top. The strain gauges shall be of a
stable type, wholly protected by a steel capsule. They shall be welded to the steel reinforcement, 2
gauges at each depth. The Engineer shall approve the type of gauges to be used and other details
on the instrumentation.
3.2.10.1 General
In a maintained load test movement of the pile head shall be measured by two of the methods as
described below. One method for settlement measurements, the other method for control.
31 .2 Prevention of Disturbance
Construction equipment and persons who are not involved in the testing process shall be kept at a
sufficient distance from the test to avoid disturbance to the measurement apparatus.
3.2.12 Supervision
3.2.12.2 Records
During the progress of a test, the testing equipment and all records of (lie test as required in
Section)
Each stage of unloading shall proceed after the expiry of (lie period shown in Table 3.2.1.
For any period when the load is constant, time and settlement shall be recorded immediately on
reaching the load and at approximately 15 minute intervals between 1 hour at 30 minute intervals
between 1 hour and 4 hours, and at 1 hour intervals between 4 hours and 12 hours after the
application of the increment of load.
The Engineer may require that the full loading, or any portion of the loading, be maintained on the
pile for periods longer than shown in Table 3.2.1.
Loading Sequence
Load as Percentage of Working Load Minimum Time of
Holding Load
Bored Piles Driven Piles
25 50 1 hour
50 100 1 hour
75 125 1 hour
100. 150 1 hour
75 125 10 minutes
50 100 10 minutes
25 50 10 minutes
0 0 1 hour
100 150 6 hours
125 200 1 hour
150 250 6 hours
175 275 1 hour
200 300 24 hours Proof Load
175 275 10 minutes
150 250 10 minutes
125 225 10 minutes
100 200 10 minutes
75 150 10 minutes
50 100 10 minutes
25 50 10 minutes
0 0 1 hour
The Contractor shall provide information about the tested pile in accordance with the following
schedule where applicable.
(A) General
1) Site location
2) Contract identification
3) Proposed structure
4) Date of test
C) Installation Details
1) Dates and times of boring, driving and concreting of test pile and adjacent piles
2) Date and time of casting concrete
3) Driven length of pile or temporary casing at final set
4) 1 hammer type, size or weight
5) Dolly and packing, type and condition before and after driving
6) Driving log (depth, blows per 250 mm, interruptions or breaks in driving)
7) At final set and at redrive set, for drop or single acting hammers, the length of (lie drop
or stroke, for diesel hammers the length of the stroke and the blows per minutes, for
double-acting hammers the number of blows per minute
8) Condition of pile head or temporary casing after driving
1) Weight of kentlege
2) Tension pile, ground anchor or compression pile details of kentledge supports, rafts,
3) Plan of test arrangement showing Position and distances tension or compression piles
and reference frame to test pile
4) Jack capacity
5) Method of Load measurement
6) Method(s) of penetration measurement
7) Relevant dates and times
E) Test Results
1) In tabular form
2) In graphical form: loads Plotted against movements and time
3.2.15.2 Kentiedge
Kentledge and its supporting structure shall be removed from the test pile and stored so that they
are available for use in further tests or removed from the Site.
3.2.15.3Temporary Piles
On completion of a preliminary test, temporary tension piles shall be cut off below ground level,
removed from the Site and the ground made good with approved material as specified.
Load tests on working cast in place piles, less than 1 .2 metre diameter, shall normally be carried
out using temporary anchor piles or kentledge. Separate payment shall not be made for anchor
piles. Separate payments will be made for carrying out each load test and individual rates shall be
provided for different proof loads, which are specified in the Bill of Quantities. Payment for load tests
on pilot piles shall include provision of anchor piles or kentledge, provision of all test equipment,
carrying out of the tests, dismantling of equipment and removal from site, cutting off below level of
temporary anchor piles, preparation of all reports etc.
4.2 Materials
Well burnt first class coal or natural gas fired clay bricks of uniform color, shape, and size having
sharpened square sides and edges as well as parallel faces shall be used. Bricks shall be sound,
hard, homogenous in texture, free from cracks, chips, flows etc. Bricks shall emit a clear metallic
sound when struck.
The mean compressive strength of twelve halved bricks shall be 175 kg/cm 2. The minimum
compressive strength for an individual brick shall be 140 kg/cm2.
The minimum water absorption of the bricks shall be 14% by weight. Slight efflorescence shall be
permitted with the approval of the Engineer.
The standard dimensions of first class bricks shall be 238 mm x 112 mm x 70 mm. The allowable
variation shall not be more than 6 mm in length, 3 mm in breadth, and 1 mm in height. Banana
shaped bricks shall be rejected and shall not be used in the works.
The minimum unit weight of first class bricks shall be 1100 kg/m 3. The minimum weight of first class
picked jhama bricks shall be 1300 kg/m3.
The Engineer reserves the right to inspect the place where the bricks are manufactured and select
bricks for load testing as he may direct. The cost of such testing shall be borne by the Contractor.
Unless otherwise specified or directed all brickwork shall be with first class bricks in cement mortar
of required proportions. The sand use in this work shall have minimum fineness modules of 1.5.
Water for mixing the mortar shall conform to the requirements
4.2.2 Mortars
(1) Unless otherwise specified in the Drawings, cement mortar for brick masonry shall consist by
volume in proportion as specified in the Schedule of Rates. In each mortar just enough water shall
be added and the components mixed and thoroughly incorporated together to give work ability
appropriate to its use. Mortar shall be used whilst freshly mixed and no softening or re-tampering
will be allowed.
(2) Mortar shall be mixed in an approved method unless hand-mixing is specifically permitted by the
Engineer and in a manner as to accurately determine and control the quantity of each ingredient in
the mortar. The cement and sand shall be first mixed dry until thoroughly mixed before adding
mixing water. If hand-mixing is permitted, the operation shall be carried out on a clean watertight
platform, and cement and sand shall be first mixed dry in the required proportion to obtain a uniform
colour and then the mortar shall be mixed for at least two minutes after addition of water.
(3) Only a sufficient quantity of sand and cement shall be mixed with water as can be used within 30
minutes after the addition of water. The adding of additional water to, and re-tempering, cement
mortar that stiffened because of evaporation of water, shall be permitted only within thirty minutes
from the time of addition of water at the time of initial mixing.
(4) Mixing troughs and pans shall be washed clean at the end of each day’s work.
PW3-Sec-7 (Tech. Spec.) 33
4.2.3 Brick Masonry Construction
(1) The method and equipment used for transporting and placing the bricks and mortar shall be
such as will not damage the brick or delay the use of mixed mortar. All equipments and tools used
for mixing and transporting mortar and bricks shall be clean and free from set mortar, dirt or other
injurious foreign substances.
(2) All brickwork shall be placed only after the foundation surfaces have been prepared satisfactorily
in accordance with the specifications and the Engineer’s instructions.
(3) The bricks shall not be placed rain sufficiently heavy or prolonged to wash the mortar from the
bricks. Mortar already spread which becomes diluted by the rain shall be removed and replaced
before continuing the work at the expense of the Contractor.
(4) All bricks to be used in brickwork with mortar joints shall be completely soaked in water for a
minimum period of 6 hours before they are used. The bricks shall be used within two hours of taking
out of water. All bricks shall be free from water adhering to their surface when they are placed in the
brickwork.
(5) Before laying bricks in foundation, a layer of not less than 10mm of mortar shall be spread to
make the surface on which the brick work will be laid even. Immediately therefore, the first course of
bricks shall be laid.
(6) Bricks shall be laid on English bond unless otherwise directed by the Engineer and shall be set
with both bed and vertical joints filled with mortar and shall be bedded in by firmly tapped with the
handle of the trowel. The face with the frog mark shall be placed upward to ensure that the frog
mark is filled with mortar. Bricks shall be skillfully laid with the level courses, uniform joints, square
corners, plumb vertical and true surfaces, except when otherwise shown on the Drawings or
directed by the Engineer.
(7) The bricks used on face shall be selected hole or uniform size and with true rectangular face.
Only full bricks shall be used in the brickwork unless absolutely necessary for breaking joints or
maintaining bond.
(8) Bricks shall be laid on full bed of mortar and shall be slightly pressed so that mortar gets into all
the surface pores of bricks to ensure proper adhesion. Bricks shall be laid where possible from one
face only and each brick shall be set with both horizontal and vertical joints filled with mortar and the
bricks shall be bedded in by firmly tapping with the handle of the trowel. Mortar joints shall be
checked and any hollow or defective joints shall be racked and filled with mortar immediately.
(9) Each course shall break the joints with the course below. All horizontal joints shall be parallel
and all vertical joints in alternate courses shall be directly over one another. In thick wall or
foundations, not only the face of the joints but the joints inside also shall break course.
(10) The thickness of mortar in any joint shall not be less than 6mm and not more than 10mm and
the height of four courses as laid shall not exceed more than 25mm the height of four dry bricks
staked one upon other.
(11) All brickwork shall be truly plumb and shall always be carried up regularly along their entire
length throughout the structure. When the entire work cannot be carried out in even courses, the
break shall be made at regular steps each of a length of at least 1-1/2 times its height. Unless
otherwise directed no overhead work shall be allowed. Toothing may be done where future
extension is contemplated but shall be used as an alternative to raking back.
(12) Where specified, fabric reinforcement shall be embedded completely in mortar. During
construction of well staining members, bars shall be placed accurately in accordance with the
Drawings.
(13) The surface of each course shall be thoroughly cleaned from all dirt before another course is
laid on top of it. If the mortar in any course begun to set, the joints shall be racked out to a depth of
PW3-Sec-7 (Tech. Spec.) 34
25mm before any subsequent course in laid. When the top course has been exposed for more than
two weeks, it shall be removed and the surface below thoroughly cleaned before any more courses
are added.
(14) When fresh masonry is to be placed against the existing surface of structures, these surfaces
shall be cleaned of all loose materials, roughened and wetted as directed by the Engineer so as to
affect a good bond with the new work.
4.2.5 Scaffolding
The scaffolding shall be sound and strong to withstand all loads likely to come upon it and subject to
the Engineer’s approval. Pole going into the masonry is at place which can be filled with a header
brick. The holes which provide resting place for horizontal members shall not be left in masonry
under one meter in width or immediately near the skew backs of arches. The holes left in the
masonry work for supporting the scaffolding shall be filled and made good.
(2) All brickwork requiring mortar shall be cured as it is constructed for not less than seven days
after completion of the last course by being kept continuously wet with water or by covering with
water saturated material or other curing methods approved by the Engineer.
(3) At the completion of the works all visible surfaces shall be free of damage or debris and shall
look clean. Cure shall be taken that bricks are not stained of coated as the work proceeds. No
rubbing of the faces to remove coating shall be allowed.
General
(1) The surface shall be finished by “Jointing” or “Pointing”. The surfaces which shall remain
exposed shall be pointed, and those which shall be buried under ground shall be jointed. The mortar
or finishing shall be prepared as per Clause 7.7.4.
Jointing
(2) In jointing, the face joints of the mortar shall be worked out while still green to give a finished
surface flush with the face of the brickwork. The faces of brickwork shall be cleaned to remove any
splashes of mortar during the course of raising the brickwork.
Pointing
(3) For pointing, the joints shall be squarely raked out to a depth of 15mm while the mortar is steel
green. The raked joint shall be well brushed to remove dust and loose particles and surface shall be
thoroughly washed with water, cleaned and wetted. The mortar shall be filled and pressed into the
raked out joints, before giving the finish. The pointing shall then be finished to proper type given on
the Drawings.
(4) If type of pointing is not mentioned on the Drawing or Schedule of Works, flushing pointing shall
be used. For ruled pointing after the mortar has been filled and pressed into the joints and finished
off level with the edge of the bricks, it shall while still green be ruled along the center with a half
round tool of such width as may be specified by the Engineer. The superfluous mortar shall then be
cut off from the edges of the lines and the surface of the masonry shall also be cleaned of all mortar.
PW3-Sec-7 (Tech. Spec.) 35
4.2.8 Repairing of Brickwork
After the completion of any brickwork, if any brick is out of alignment or level or does not conform to
the lines and grades shown on the Drawings, or shows a defective surface, it shall be removed and
replaced by the Contractor at his expense unless the Engineer’s grants written permission to patch
or replace the defective area.
5.1.1 Description
This work shall consist of the construction of all or portions of structures of Portland cement
concrete, of the required grades and types, with or without reinforcement, pre-stressed
reinforcement and with or without admixture, in accordance with these Specifications and to the
lines, levels, grades and dimensions shown on the Drawings and required by the Engineer. Portland
cement concrete shall consist of a mixture of Portland cement, water and coarse and fine aggregate
with or without admixture.
5.1.2 Materials
(A) Cement
Cement shall be sampled and tested in accordance with bagged or bulk cement which has partially
set or which contains lumps of caked cement shall be rejected. The use of cement reclaimed from
discarded or used bags shall not be permitted.
(B) Water
The water used in mixing-and curing concrete shall be tested by methods described in AASHTO
Test Method T 26. All water shall be clean and free from salt, oil, acid, vegetable or other substance
injurious to the finished product. The use of river water will be subject to the approval of the
Engineer. Such approvals may be withdrawn from time to time depending on the condition of the
river.
(C) Admixtures
Admixtures shall be used as specified or permitted, shall fully conform to the requirements of ASTM
C-494 Type-F of approved brand/origin/manufacturer.
Coarse aggregate for all types of concrete of hard durable crushed or broken rock and generally
conform to the requirements of AASIITO Standard Specification M80. Coarse aggregate shall be
clean, free from dust and other deleterious material.
The amounts of deleterious substances shall not exceed the following limits:
1) Soft fragments; 2% by mass
2) Clay lumps; 0.25% by mass.
3) Material Passing the 0.075 mm sieve; 0.50% by mass if clay, 1.50% by mass if
infrastructure dust.
Table 5.1.1
In heavily reinforced structures with difficult casting conditions smaller size aggregates may he used
ii approved by the Engineer.
Fine aggregate shall consist of natural sand and fine aggregates from different sources of supply
shall not he mixed or stored in the same pile.
The amounts of deleterious substance when tested in accordance with STP 3.4 shall not exceed the
following limits:
The grading shall normally be in accordance with Table 5.1.2. In the event that it is not possible to
obtain regular supplies of sand conforming to this grading, (lie Engineer May approve the adoption
of a grading conforming to the requirements of table 4 with additional limits of either C or M of BS
882:1992. However, any additional costs resulting from changes in aggregate proportions or
additional cement contents required to achieve the specified strengths, when using these alternative
grading, shall be borne by the Contractor and shall not be reimbursed.
Table 5.1.2
(A) Cement
Cement shall he in accordance with AASIITO M 85. The Contractor must provide the Engineer with
manufacturer’s certificates indicating compliance.
Cement shall be sampled and tested for fineness, setting time and strength in accordance with STP
8.1, STP 8.2 and STP 8.3, respectively, at the Contractor’s own expense. The Contractor shall
notify the Engineer of delivery dates so that there will be sufficient time for sampling the cement,
either at the mill or upon delivery. If this is not done, the Contractor may be required to re-handle the
cement in the store for the purpose of obtaining the required samples.
Sampling shall normally be instructed by the Engineer for every batch of cement prior to this cement
being incorporated in the Works.
(B) Water
The, water proposed by the-Contractor to he used in mixing or curing concrete shall be tested by
methods described in AASHTO Test Method T 26.
In sampling water for testing, care shall be taken that the containers arc clean and that samples are
representative.
When comparative tests are made with a water of known satisfactory quality, any indication of
unsoundness, marked change in time of setting, or a reduction of more than 10 percent in mortar
strength, shall be sufficient cause for rejection of the water tinder test.
The water shall be tested at a recognized laboratory approved by the Engineer. The test result shall
be signed by the laboratory. The water shall be tested before commencement of work or if the
source is changed or at any time required by the Engineer. All testing shall be carried out at the
Contractor’s expense.
(C) Admixtures
The Contractor shall submit specifications and samples of any admixtures or additives that he
proposes to use to the Engineer at least 28 days before the commencement of construction or
manufacture of the particular structure on which he intends to use such admixtures.
Any tests (the Engineer may require on concrete mixes on account of the Contractors proposal to
use additives shall) be carried out at the expense of the Contractor.
(D) Aggregates
From the aggregate materials proposed by the Contractor, samples shall be selected according to
STP Section 2.4 and in the presence of the Engineer. The samples shall he tested at the site
laboratory or at an approved testing laboratory for conformance with Section 5.1.2.1 of these
Specifications.
The quality control of the aggregate shall be as directed by Engineer. Grading shall normally be
checked daily.
Moisture contents of fine aggregate shall be determined daily and at any time when a change in
moisture content is expected.
Contractor proposes to change the source of aggregate; the Engineer shall be informed in advance
and in no case less than 3 weeks before the new aggregate shall be used.
PW3-Sec-7 (Tech. Spec.) 40
5.1.2.3 Composition of Concrete
Concrete with cement type I for incorporation in the Works shall be of the classes indicated on the
Drawings and shall comply with Table 5.1.3.
Table 5.1.3
(B) Proportioning
When designing the concrete mix, the Contractor shall consider the following conditions:
1) Strength
The class is the specified characteristic cylinder strength at 28 days and a crushing strength
24 N/mm2. Concrete mixes shall be designed to comply with Specifications Section 5.1.2.4.
2) Water/Cement Ratio
The ratio of free water to cement when using saturated surface dry aggregate shall be as
low as possible and not exceed 0.50 by weight for all concrete, except for blinding concrete
where it shall not exceed 0.6, unless approved by the Engineer.
For concrete in barriers, edge beams and bridge decks directly exposed to traffic or
concrete in pile caps or abutments in contact with the ground, the water cement ratio shall
not exceed 0.45, unless approved by the Engineer,
6) Fine Aggregate
The grading and quality is to comply with the requirements of Section 5.1 .2.1.
7) Workability
The concrete shall be of suitable workability to obtain full compaction. Slump measured in
accordance with STP 9.1 shall not exceed 60 mm unless otherwise indicated on the
Drawings or approved by the Engineer.
After the Contractor has received approval for the cement and aggregate to be used, he shall
prepare trial mixes with concrete of designed proportions to prove and establish workability,
strength, water cement/ratio, surface criteria etc. Methods of transporting fresh concrete and the
compaction equipment shall be considered. The trial mixes shall be made and compacted in the
presence of the Engineer, using the same type of plant and equipment as will be used for the
Works.
From each trial mix, cylinders or cubes shall be made and tested in accordance with Section 5.1 .
2.4.
From the same mix as that from which the test specimens are made, the workability of the concrete
shall he determined by the slump test in accordance with STP 9.1. The remainder of the mix shall
be cast in a wooden mould and compacted. After 24 hours the sides of the mould shall be struck
and the surface examined iii order to satisfy the Engineer that an acceptable surface can be
obtained with the mix.
The trial mix proportions should be approved if the required strength is obtained from tests carried
out in accordance with Section 5.1.2.4 and the consistency amid surface is to the satisfaction of the
Engineer.
When a flux has been approved, no variations shall be made in the mix proportions, or in the type,
size, grading zone or source, of any of the constituents without the consent of the Engineer, who
may require further trial mixes to he made before any such variations are approved.
Until the results of trial mixes for a particular class have been approved by the Engineer, no
concrete of the relevant class shall be placed in the Works.
When the Contractor intends to purchase factory-made precast concrete units, trial mixes may be
dispensed with provided that evidence is given to satisfy the Engineer that the factory regularly
produces concrete which complies with the Specifications. The evidence shall include details of mix
proportions, water/cement ratios, slump tests and strengths obtained at 28 days.
(A) General
The Contractor shall assume the full responsibility for the quality of the concrete conforming to these
specifications and this responsibility shall not be relieved by the testing carried out and approved by
the Engineer.
The Contractor shall thus at his own discretion establish additional testing procedures as necessary.
I) Materials
Batching plants will be tested by the Contractor in a procedure approved by the Engineer before any
major concrete casting and at any other time requested by the Engineer.
3) Fresh Concrete
The frequency of slump tests shall be as directed by the Engineer, with at least one test per 25 m 3 of
concrete.
The Contractor shall take samples of the concrete for testing. The number, frequency and location
shall be decided by the Engineer. A minimum of 3 concrete cubes/cylinders; should be taken for
each day’s casting, or for every 15 M3 of concrete cast in large pours. The slump of concrete
samples shall be measured.
The procedures for sampling and making cubes/cylinders and testing them shall be as described in
STP 9.2.
2) Strength Requirement
The results of the testing shall conform to the strength requirements according to British standard
BS5400:
(D) General
The characteristic strength of concrete is the 28 days strength below which not more than 5% of the
test results may be expected to fall.
1) 1.64 times the standard deviation of tests on at least 100 separate batches of concrete of
nominally similar proportions of similar materials and produced over a period not exceeding
12 months by the same plant tinder similar supervision.
2) 1.64 times the standard deviation of tests on at least 40 separate batches of concrete of
nominally similar proportions of similar materials and produced over a period exceeding 5
days but not exceeding 6 months by the same plant under similar supervision.Where there
are insufficient data to satisfy (1) or (2) above, the margin for the initial mix design should he
taken as two-thirds of the characteristic strength for concrete. This margin should be used as
the current margin only until sufficient data are available to satisfy (I) or (2) above.However,
when the required characteristic strength approaches the maximum possible strength of
concrete made with a particular aggregate, a smaller margin may he permitted by (lie
Engineer for the initial mix design.
PW3-Sec-7 (Tech. Spec.) 43
(F) Testing Plan
Each cube shall be made from a single sample taken from randomly selected batches of concrete.
I) The average strength determined from any group of four consecutive test cubes
exceeds the specified characteristic strength by not less than 0.5 times the current
margin, and
2) Each individual test result is greater than 85% of the specified characteristic strength.
The current margin should be taken to be two-thirds of the specified characteristic strength for
concrete, unless as mentioned above a smaller margin has been established to the satisfaction of
the Engineer.
If only one cube result fails to meet the second requirement then that result may be considered to
represent only the particular batch of concrete from which that cube was taken provided the average
strength of he group satisfies the first requirement.
If more than one cube in a group fails to meet the second requirement or if the average strength of
any group of four consecutive test cubes fails to meet the first requirement then all the concrete in
all the hatches represented by all such cubes shall be deemed not to comply with the strength
requirements. For the purposes of this sub-Section, the batches of concrete represented by a group
of four consecutive test cubes shall include the batches from which samples were taken to make the
first and last cubes in the group of four, together with all the intervening batches.
(G) Action to be taken in the Event of Non-Compliance with the testing Plan
W hen the average strength of four consecutive test cubes fails to meet the first’ requirement in (F),
above, the mix proportions of subsequent batches of concrete should be modified to increase the
strength.
The action to be taken in respect of the concrete which is represented by the test-cubes which fail to
meet either of the requirements (or not by correct statistical proof can be verified to have the
required strength) shall be determined by the Engineer. This may range from qualified acceptance
in less severe cases, to rejection and removal in the most severe cases.
The Engineer may also require the Contractor at his own expensed to prove statistically the
strength, by boring out cores and testing them according to a program approved by the Engineer.
The age of the concrete and degree of hardening at the time of the new testing shall he consider.
The equivalent cylinder/cube strength shall comply the minimum characteristic strength or as
decided by the Engineer.
If the Contractor wants to remove forms and scaffolding earlier than specified herein, extra test
specimens shall be cast by the Contractor in accordance with the instruction of the Engineer. These
specimens shall be tested the day before removal of the form. On the basis of the test results the
Engineer shall take the final decision on the time for the removal of forms. For pre-stressed
concrete, extra test specimens shall be cast by the Contractor in accordance with the instructions of
the Engineer, to determine the time for tensioning the tendons. On the basis of the test results, the
Engineer shall decide upon the time for pre-stressing the concrete.
5.1.3.1 General
The Contractor shall maintain an adequate number of trained amid experienced supervisors and
foremen at the Site to supervise and control the work.
All construction, other than concrete, shall conform to the requirements prescribed in other Sections
of the Specifications, for the particular items of work comprising the complete structure.
Details, plans and structural calculations for scaffolding shall be submitted by the Contractor to the
Engineer for approval, but in no case shall (lie Engineer’s approval relieve the Contractor of his
Contract responsibilities. All scaffolding shall he designed and constructed by (lie Contractor to
provide the necessary rigidity and to support dead and live loads without deflection or deformation.
The Engineer may require the Contractor to employ screw jacks or hardwood wedges to take up
any settlement in scaffolding and formwork, either before or during the placing of concrete.
Tests may be required by the Engineer of materials proposed by the Contractor for scaffolding. Test
loadings of the completed scaffolding may also be required fur (lie determination of flexibility and
strength. All expenses associated with testing shall be borne by the Contractor.
Scaffolding which cannot be founded on a satisfactory footing shall be Supported on piles, which
shall he spaced, driven and removed in a manner approved by the Engineer. When the Contractor
wishes to support scaffolding on existing structures, lie shall submit his proposals in due time to (lie
Engineer, in writing, including loads from the scaffolding, The Engineer will consider the proposals
and respond in writing.
Scaffolding shall be set to give the finished structure a camber, if indicated on the Drawings or
specified by the Engineer.
Scaffolding shall remain in place for periods which shall be determined by the Engineer.
(B) Formwork
Formwork shall include all temporary or permanent moulds for forming the concrete. Formwork shall
be of wood, metal or other approved materials and shall be built mortar light amid rigid enough to
maintain the concrete in position during placing, compacting, setting and hardening.
Formwork for exposed surfaces (“wrought form”) shall he made of dressed lumber of uniform
thickness with or without a form liner of an approved type or shall he of metal sufficiently rigid in
itself with no surface blemishes that will impair (lie quality of the concrete surface finish. No rusty or
bent metal forms shall be used. Exposed concrete arises shall be provide with formed chamfers, as
indicated on the Drawings or instructed by the Engineer.
Rough lumber may be used for surfaces that will not be exposed in the finished structure (“rough
form”).
All lumber shall be sound, free from warps and twists, sap, shakes, large or loose knots wavy edge
or other defects affecting the strength or appearance of the finished structure.
All forms shall be set and maintained true to the line designated until (lie concrete is sufficiently
hardened. Forms shall remain in place for periods, which shall be determined by the Engineer.
When forms appear to be unsatisfactory in any way, either before or during (lie placing of concrete,
the Engineer may order the work stopped until (lie defects are corrected.
The shape, strength, rigidity, water tightness and surface smoothness of reused formwork shall be
maintained at all times. Any warped or bulged lumber must be re-sized before being reused.
Formwork that is unsatisfactory in any respect shall not be reused.
Metal ties or anchorages within the form shall be so constructed as to permit their removal to a
depth of at least 50 mm from the face without injury to the concrete. All fittings for metal ties shall be
of such design that, upon their removal, the cavities which are left will be of the smallest possible
size. The cavities shall be filled with cement mortar and the surface left sound, smooth, even and
uniform in color.
Formwork shall be so constructed that easy cleaning out of any extraneous material inside the
formwork can he achieved without disturbing formwork already checked and approved by the
Engineer.
Formwork shall be treated with approved non-staining oil or saturated with water, to facilitate
formwork removal. The Engineer may require trials to be carried out before approval is given for the
use of a particular type of oil, to ascertain that the oil proposed by the Contractor does not discolour
or injure the finished concrete face in any way.
Before placing any concrete, all shavings, loose binding wires, soil, rubbish and all foreign matter
shall be removed from the formwork amid the formwork shall be carefully and thoroughly washed
with water. if not indicated otherwise, the following tolerances of the finished concrete structures
shall apply:
The cross sectional areas of the superstructure of bridges shall in no place deviate more than 3%
from the theoretically correct cross sectional areas.
Anchors for bearings, expansion joints, railings, etc. shall he placed within the tolerances indicated
on the Drawings or specified by the Engineer.
A leveling layer of blinding concrete shall he provided as the permanent bottom form for all concrete
structures that will directly bear on prepared soil, whether this blinding concrete is shown on the
Drawings or not. The leveling layer of blinding concrete shall be of thickness not less than 75 mm
and shall be constructing on single layer brick flat soling.
If plans and calculations of scaffolding and formwork are requested by the Engineer, no construction
of such scaffolding and formwork shall take place before approval by the Engineer, in writing. Such
approval shall not relieve the Contractor of his responsibilities under the Contract for the adequacy
of scaffolding and formwork.
The Engineer shall have reasonable time for his examination of the Contractor’s plans and
calculations, especially if scaffolding is introducing temporary loading on new structures. The
Contractor shall not be allowed extensions of Contract time due to awaiting such approval.
The Engineer shall inspect all formwork and scaffolding and no concrete shall be placed until the
Engineer’s approval has been given. Such approval shall not relieve the Contractor of any of his
responsibilities under the Contract for the successful completion of the structure.
All cement shall be stored in suitable weatherproof buildings or silos which will protect the cement
from dampness. These buildings or silos shall he placed in locations approved by the Engineer.
Provisions for storage shall he ample, amid the shipments of cement as received shall be separately
stored in such manner as to provide easy access for the identification and inspection of each
shipment. Storage buildings shall have capacity for the storage of a sufficient quantity of cement to
allow sampling at least 14 days before the cement is to be used. Cement shall meet the test
requirements at any time and any cement stored for an elongated time shall be checked amid tested
before use regardless of whether it has previously been tested.
Aggregates shall be so stored as to prevent the inclusion of foreign material. Aggregates shall not
be placed upon the finished roadbed. Aggregates of different sizes and kinds shall be placed in
different stockpiles. Stockpiles of blended coarse aggregates shall be built up in successive
horizontal layers not more than I meter thick. Each layer shall be completed before the next is
started. Should segregation occur, the aggregates shall be recombined to conform to the grading
requirements.
Washed aggregates and aggregates produced or manipulated by methods which involve the use of
water shall he allowed draining at least 12 hours before use.
Before any major casting, the Contractor shall prepare a complete “casting programme” describing
staff and labor, consumption of materials, plant, tools and equipment, reserves of materials, standby
plant and equipment, proposed means of handling and placing the concrete, quality controls etc.
No concrete shall he mixed and placed until the Contractor’s casting programme has been
approved in writing by the Engineer.
Equipment and tools necessary for handling materials and performing the work, and satisfactory to
the Engineer as to design, capacity, and mechanical condition, shall be at the site of the work before
casting is started.
If any equipment is not maintained in full working order, or if the equipment as used by the
Contractor proves inadequate to obtain the result prescribed, such equipment shall be repaired or
other suitable equipment substituted or added at the discretion of the Engineer.
All material in the mix shall be proportioned by weight or volume, subject to the approval of the
Engineer.
When volume batching is proposed by the Contractor, the exact proportions must be converted from
trial mix weights to volumes, from bulk densities determined in the laboratory. Written approval from
the Engineer is required.
(A) General
All concrete shall be mixed in batch mixers, either at the site of construction or at a central plant.
Each mixer shall have attached to it in a prominent place, a manufacturer’s plate showing the
capacity of the drum in terms of mixed concrete and the speed of rotation of the mixing drum.
Mixers at local sites shall be approved drum-type capable of combining the aggregate, cement, and
water into a thoroughly mixed and uniform mass within the specified mixing period and of
discharging the mixture without segregation. The mixer shall be equipped with a suitable charging
hopper, water storage and a water measuring device, accurate within 1%. Controls shall he so
arranged that the water can be applied only while the mixer is being charged. Suitable equipment
for discharging the concrete shall he provided. The mixer shall he cleaned at suitable intervals. The
pickup and throw-over blades in the drum shall be replaced when they have lost 10% of their depth.
The mixer shall be operated at a drum speed of between 15 and 20 revolutions per minute. The
batched materials shall be so charged into the drum that a portion of the water shall enter in
advance of the cement and aggregates and the water shall continue to flow into the drum for a
minimum time of 5 seconds after all the cement and aggregates are in the drum. Mixing time shall
he measured from the time all materials except water are in the drum and shall, in the case of
mixers having a capacity of I cubic metre or less, not be less than 50 seconds nor more than 70
seconds. In the case of dual drum mixers, the mixing time shall not include transfer time. The
contents of an individual mixer drum shall he removed before a succeeding batch is emptied
therein. Any concrete mixed less than the specified minimum time shall be discarded and disposed
of by the Contractor at his own expense.
The volume of concrete mixed per batch shall not exceed the mixer’s nominal capacity in cubic feet
or cubic meters as shown on the manufacture’s guaranteed capacity standard rating plate on the
mixer; except that an overload up to 20% of the mixers nominal capacity may be permitted provided
concrete test data for strength, segregation and uniform consistency are satisfactory, and provided
no spillage of concrete takes place.
Retempering concrete by adding water or by other means shall not be permitted. Concrete which is
not of the required consistency at the time of placement shall not be used and shall be discarded
and disposed of by the Contractor at his own expense.
These mixers shall be of approved drum type capable of combining the aggregate, cement and
water into a thoroughly mixed and uniform mass within the specified mixing period amid of
discharging the mixture without segregation. Central plant mixers shall be equipped with an
acceptable timing device that will not permit the batch to be discharged until the specified mixing
time-has elapsed. The water system for a central mixer shall be either a calibrated measuring tank
or a meter and shall not necessarily be an integral part of the mixer.
The mixers shall be cleaned at suitable intervals. They shall be examined daily for changes in
interior condition. The pick up and throw-over blades in the drum shall be replaced when they have
lost 10016 of their depth.
In addition to the requirements for mixers at local sites detailed above, central plant mixers which
have a capacity of between 2 and 5 cubic meters, or greater than 5 cubic meters, should have a
minimum mixing time of 90 and 120 seconds respectively, provided tests indicate that the concrete
produced is equivalent in strength and uniformity to attained as stated in the preceding paragraphs.
Mixed concrete shall be transported from the central mixing plant to the site of work in agitator
trucks or upon written permission of the Engineer in non-agitator trucks. Delivery of concrete shall
be so regulated that placing is at a continuous rate unless delayed by the placing operations. The
intervals between deliveries of batches shall not he so great as to allow the concrete in place o
harden partially, and in no case shall such an interval exceed 30 minutes.
Unless otherwise permitted in writing by the Engineer, agitator trucks shall have watertight revolving
PW3-Sec-7 (Tech. Spec.) 48
drums suitably mounted and shall be capable of transporting and discharging the concrete without
segregation. The agitating speed of the drum shall not be less than two or more than six revolutions
per minute. The volume of mixed concrete permitted in the drum shall not exceed the
manufacturer’s rating nor exceed 80% (lie gross volume of the drum.
Upon approval by the Engineer, open-top, revolving-blade truck mixers maybe used in lieu of
agitating trucks for transportation of central plant mixed concrete.
Gross volume of agitator bodies expressed in cubic feet or cubic meters shall be supplied by the
mixer manufacturer. The interval between introduction of water into the mixer drum and final
discharge of the concrete from the agitator shall not exceed 45 minutes. During this interval the mix
shall be agitated continuously.
Bodies of non-agitating equipment shall be smooth, water-tight metal containers equipped with
gates that will permit control of the discharge of the concrete. Covers shall be provided when
needed for protection against the weather. The non-agitating equipment shall permit delivery of the
concrete to the site of the work in a thoroughly mixed and uniform mass with a satisfactory degree
of discharge.
Uniformity shall he satisfactory if samples from the one-quarter and three quarter points of the load
do not differ by more than 30 mm in slump. Discharge of concrete shall he completed within 30
minutes after the introduction of the mixing water to the cement and aggregate.
These shall be equipped with electrically actuated counters by which the number of revolutions of
the drum or blades may readily he verified and the counters shall be actuated at the
commencement of fluxing operations at designated mixing speeds. The mixer when loaded shall not
he filled to more than 60% of the drum gross volume. The mixer shall be capable of combining the
ingredients of the concrete into a thoroughly mixed and uniform mass and of’ discharging the
concrete with a satisfactory degree of uniformity.
Except when intended for use exclusively as agitators, truck mixers shall be provided with a water
measuring device to measure accurately the quantity of water for each batch. The delivered amount
of water shall be within plus or minus 1% of the indicated amount.
Truck mixer may be used for complete mixing at the batch plant and as truck agitators for delivery of
concrete to job sites, or they may be used for complete mixing of the concrete at the job site. They
shall either be a closed watertight revolving drum or an open top revolving blade or paddle type.
The amount of mixing shall be designated in number of revolutions of the mixer drum. When a truck
mixer is used for complete mixing, each batch of concrete shall he mixed for between 70 and 100
revolutions of the drum or blades at the rate of rotation designated by the manufacturer of the
equipment as the “mixing speed”. Such designation shall appear on a metal plate attached to the
mixer. If the hatch is at least 0.5 cubic meres less than guaranteed capacity, the number of
revolutions at mixing speed may he reduced to not less than 50. Mixing in excess of 100 revolutions
shall he at the agitating speed. All materials, including the mixing water, shall be in the mixer drum
before actuating the revolution counter which will indicate the number of revolutions of the drum or
blades.
When wash water (flush water) is used as a portion of the mixing water for the succeeding batch, it
shall be accurately measured and taken into account in determining he amount of additional mixing
water required. When wash water is carried on the truck mixer, it shall be carried in a compartment
separate from the one used for carrying or measuring the mixing water. The Engineer will specify
the amount of wash or flush water, when permitted; any may specify a “dry” drum if wash water is
used without measurement or without supervision.
The temperature of concrete at the time of placing shall not exceed 35 0C.
In preparation for the placing of concrete all sawdust, chips and other construction debris and
extraneous matter shall be removed from the interior of forms. Struts, stays and braces, serving
temporarily to hold the forms in correct shape and alignment, pending the placing of concrete at
their locations, shall he removed when the concrete placing has reached an elevation rendering
their service unnecessary. These temporary members shall be entirely removed from the forms and
not buried in the concrete.
Concrete must reach its final position in the forms within 20 minutes of the completion of mixing, or
as directed by the Engineer.
Concrete shall be placed so as to avoid segregation of the materials and the displacement of the
reinforcement. The use of long troughs, chutes and pipes for conveying concrete from the mixer to
the forms shall be permitted only on written authorization of the Engineer. In case an inferior quality
of concrete is produced by the use of such conveyors, the Engineer may order discontinuance of
their use amid the institution of a satisfactory method of placing.
Open troughs and chutes shall be of metal or metal lined. Where long steep slopes are required, the
chutes shall be equipped with baffles or he in short lengths that reverse the direction of movement.
All chutes, troughs and pipes shall be kept clean amid free from coatings of hardened concrete by
thoroughly flushing with water after each run. Water used for flushing shall be discharged clear of
the structure.
When placing operations would involve dropping the concrete more than 1.5 m, it shall be deposited
through sheet metal or other approved pipes. As far as practicable, the pipes shall be kept full of
concrete during placing and their lower ends shall he kept buried in the newly placed concrete. After
initial set of the concrete, the forms shall not he jarred and no strain shall he placed on the ends of
reinforcement bars which project.
Concrete, during and immediately after depositing, shall be thoroughly compacted. The compaction
shall be done by mechanical vibration subject of the following provisions:
Application of vibrators shall be at points uniformly spaced and not further apart than twice the
radius over which the vibration is visibly effective.
6) Vibration shall not be applied directly or through (lie reinforcement to sections or layers
of concrete which have hardened to the degree that the concrete ceases to he plastic
under vibration. It shall not be used to make concrete flow in the forms over distances
so great as to cause segregation, and vibrators shall not he used to transport concrete
in the forms.
8) The provisions of this Section shall also apply to precast piling, concrete cribbing and
other precast members except that, if approved by the Engineer, the manufacturer’s
methods of vibration may he used.
Concrete shall he placed in horizontal layers not more than 600 mm thick except as hereinafter
provided. When less than a complete layer is placed in one operation, it shall be terminated in a
vertical bulkhead. Each layer shall be placed and compacted before the preceding batch has taken
initial set to prevent injury to the green concrete amid avoid surfaces of separation between the
batches. Each layer shall be compacted so as to avoid the formation of a construction joint with a
preceding layer which has not taken initial set.
When the placing of concrete is temporarily discontinued, the concrete, after becoming firm enough
to retain its form, shall be cleaned of laitance and other objectionable material to a sufficient depth
to expose sound concrete. To avoid visible joints as far as possible upon exposed faces, the top
surface of the concrete adjacent to the forms shall be smoothed with a trowel. Where a “feather
edge” might be produced at a construction joint, as in the sloped top surface of a wing wall, an inset
form shall be used to produce a blocked out portion in the preceding layer which shall produce an
edge thickness of not less than 150 mm in the succeeding layer. Work shall not he discontinued
within 450 mm of the top of any face unless provision has been made for a coping less then 450
mm thick, in which case, if permitted by the Engineer, a construction joint may be made at the under
side of the coping.
Immediately following the discontinuance of placing concrete all accumulations of mortar splashed
upon the reinforcement steel and the surfaces of forms shall be removed. Dried mortar chips and
dust shall not be puddle into the unset concrete. If the accumulations are not removed prior to the
concrete becoming set, care shall be exercised not o injure or break the concrete-steel bond at and
near the surface of the concrete, while cleaning the reinforcement steel.
For simple spans, concrete shall preferably be deposited by beginning at the centre of the span and
working from the centre toward the ends. Concrete in girders shall be deposited uniformly for the full
length of the girder and brought up evenly in horizontal layers. For continuous spans, the concrete
placing sequence shall be as shown on the plans or agreed on by the Engineer.
Concrete in slab and girder haunches less than 1 .0 meter in height shall be placed at (lie same time
as that in the girder stem.
Concrete in slab spans shall be placed in one continuous operation for each span unless otherwise
provided Concrete in T-beam or deck girder spans may be placed in one continuous operation if
permitted by the Engineer.
Unless otherwise permitted by the Engineer, no concrete shall be placed in the superstructure until
the column forms have been stripped sufficiently to determine the character of the concrete in the
columns. The load of the superstructure shall not be applied to the supporting structures until they
have been in place at least 14 days, unless otherwise permitted by the Engineer.
Pneumatic placing of concrete shall be permitted only if authorized by the Engineer, The equipment
shall be so arranged that vibration does not damage freshly Placed concrete.
Where concrete is conveyed and placed by pneumatic means the equipment shall he suitable in
kind and adequate in capacity for the work. The machine shall be located as close as practicable to
the place of deposit. The position of the discharge end of the line shall not be more than 3 metres
from the point of deposit. The discharge lines shall be horizontal or inclined upwards from the
machine. At (lie conclusion of placement the entire equipment shall he thoroughly cleaned.
Placement of concrete by pumping shall be permitted only if authorized by the Engineer. The
equipment shall be so arranged that vibrations do not damage freshly placed concrete. Where
concrete is conveyed and placed by mechanically applied pressure, the equipment shall be suitable
in kind and adequate in capacity for the work. The operation of the pump shall be such that a
continuous stream of concrete without air pockets is produced. When pumping is completed, (lie
concrete remaining in (lie pipeline, if it is to be used, shall be ejected in such a manner that (here is
not contamination of the concrete or separation of the ingredients. After this operation, the entire
equipment shall be thoroughly cleaned.
The Contractor is responsible for determining in advance of making any concrete pours, all
requirements for perforation of Concrete sections or embedment therein of special devices of other
trades, such as conduits, pipes, weep holes, drainage pipes, fastenings, etc. Any concrete poured
without prior provision having been made, shall be subject to correction at the Contractor’s expense.
After the final rubbing has been completed and the surface has dried, burlap shall he used to
remove loose powder. The final surface shall be free from unsound patches, paste, powder and
objectionable marks.
Type-E-Bushhammer Finish
Bussammering shall be carried out by treating (lie surface with an approved heavy duty power
hammer fitted with a multi-point tool which shall be operated over the surface (o remove 5 to 6 mm
of concrete paste and expose maximum areas of coarse aggregate.
Aggregate hell embedded shall not he fractured or loose. 25 mm wide hands at all corners and
arises shall be left as cast. The finish surface shall be even and of uniform appearance and shall be
washed with water upon completion.
(A) General
Construction joints shall be made only where located on the plans or shown in the pouring schedule,
unless otherwise approved by the Engineer.
It not detailed on the plans, or in the case of emergency, construction joints shall be placed as
directed by the Engineer. Shear keys or inclined reinforcement shall be used where necessary to
transmit shear or bond the two sections together.
(B) Bonding
Before depositing new concrete on or against concrete which has hardened, the forms shall be re-
tightened. The surface of the hardened concrete shall he roughened as required by the Engineer, in
a manner that does not leave loosened particles of aggregate or damaged concrete at the surface.
It shall be thoroughly cleaned of foreign matter and laitance, and saturated with water. To ensure an
excess of mortar at the juncture of the hardened and the newly deposited concrete, the cleaned and
saturated surfaces, including vertical and inclined surfaces, shall first be thoroughly covered with a
thin coating of mortar or neat cement grout against which the new concrete shall be placed before
the grout has attained its initial set.
The placing of concrete shall be carried continuously from joint to joint. The face edges of all joints
which are exposed to view shall be carefully finished true to line and elevation.
All concrete surfaces shall be kept thoroughly wet for at least 7 days after placing. Bridge deck and
sidewalk slabs shall be covered with wet hessian immediately after final finishing of the surface.
This material shall remain in place for the full curing period or may be removed and replaced with
sand when the concrete has hardened sufficiently to prevent marking. In both cases the materials
shall he kept thoroughly wet for the entire curing period. All other surfaces if not protected by forms,
shall be kept thoroughly wet, either by sprinkling or by the use of wet burlap until the end of the
curing period. The wood forms are allowed to remain in place during the curing period, but they shall
be kept moist at all times to prevent openings at joints.
After a period of 7 days, the concrete shall he watered daily at certain intervals approved by the
Engineer to avoid drying out of the surface. This shall take place during the following 2 weeks. The
water used shall be the same as used in concrete mixes unless otherwise approved by the
Engineer.
Any proposal from the Contractor for the use of liquid membrane curing compound shall be subject
to the approval of the Engineer.
Forms and scaffolding shall not be removed without the approval of the Engineer. The Engineer’s
approval shall not relieve the Contractor of his Contract responsibilities. Any kentledge blocks and
bracing shall be removed at the same time as the forms and in no case shall any portion of the
wood forms be left in the concrete.
Forms used on exposed vertical faces shall remain in place for periods which shall be determined
by the Engineer and normally not less than 3 days.
Supporting scaffolding and forms under slabs, beams and girders shall normally remain in place
until the full required strength of the concrete has been obtained. If a shorter period is requested,
this may be permitted by the Engineer. In such case, special test specimens (see Section 5.1.2.4)
shall be cast to monitor the hardening.
All structures shall be fully stripped before adjacent structures are cast.
As soon as the form has been stripped, the Contractor shall advise the Engineer who shall inspect
the concrete before any improvement of the surface takes place.
All wire or metal devices used for securing the formwork which project from or appear on the
surface of the finished concrete shall be removed or cut back to at least a depth equal to the
required reinforcement cover. All holes and pockets so formed shall be filled with cement mortar
mixed in (lie same proportions as the fine aggregate to cement of the concrete mix used for that
particular section of the structure, after the surface to be patched has been thoroughly cleaned and
wetted to receive the patch.
Excessive honeycombing shall be sufficient to cause rejection of portions of the structure containing
this honeycombing. The Contractor, on receipt of written orders from the Engineer, shall remove
and rebuild such portions of the structure at his own expense.
Smaller honeycombing and other defects can be repaired if permitted by the Engineer. Structural,
maintenance and aesthetical points of view shall he taken into consideration before such approval, if
any, may be given. The method of repair shall be approved by the Engineer and an extension of
period for a certain part of the performance bond may be required.
Concrete shall not he deposited in water except with the approval of the Engineer and under his
immediate supervision; and in-this case the method of placing shall be as defined in this Section.
Any supplier of precast concrete elements shall be approved in writing by the Engineer. Such
approval can be withdrawn at any time.Concrete work in precast concrete elements shall fully
conform with all relevant Sections of these Specifications. The supplier shall maintain laboratory
facilities of the same standard as the site laboratory. Unless otherwise approved by the Engineer,
precast concrete members shall not be moved from the casting position until the concrete has
attained a compressive strength of 80% of the specified 28 day strength, nor transported until it has
developed strength of 90% of the specified 28 day strength.
Extreme care shall be exercised in handling and moving precast concrete members. Precast girders
and slabs shall be transported in an upright position. Shock shall be avoided and the points of
support and directions of the reactions with respect to the member shall be approximately the same
during transportation and storage as when the member is in its final position. If the Contractor
deems it expedient to transport or store precast units in other than this position, this shall be at the
Contractor’s risk, after notifying the Engineer of his intention to do so. Any rejected unit shall be
replaced at the Contractor’s expense by an acceptable unit.
Proposed details on the handling and transportation of precast concrete members shall be
submitted in writing by the Contractor, to the Engineer, for his approval.
Each precast member is to he uniquely and permanently marked so as to show its type, date of
casting and any other information required by the Engineer.
In structures of major dimensions i.e., pile caps, etc. the heat deriving from the hardening of the
concrete shall be controlled by the Contractor. Temperature gradients introducing risk of cracking
shall not occur and the temperature shall not exceed 70 0C.
The Contractor shall submit timely proposals for avoiding excessive heat generation, such as the
cooling of aggregates bef6rc mixing, to the Engineer for approval.
All spaces which have been excavated and the volumes of which are not occupied by the concrete
structure shall be backfilled and compacted with acceptable material in accordance with the
provisions of Section 2.5 as directed by the Engineer.
5.1.3.18 Cleaning Up
Upon completion of a structure and before final acceptance, the Contractor shall remove all forms
and scaffolding etc. down to 0.5 meters below the finished ground line. Excavated, or useless
5.1.19 Measurement
Concrete shall be measured by the number of cubic meters of class and maximum coarse
aggregate size indicated on the Drawings complete in place and accepted by the Engineer. In
computing quantities, the dimensions used shall be those shown on the Drawings. No deduction
from the measured quantity shall be made for drainage. pipes less than 300’-mrn in diameter,
conduits, chamfers, reinforcement bars, stressing tendons, expansion joints water slops or pile
heads embedded in concrete.
Reinforcing and pre-stressing steel shall be measured for payment as described in Specifications
Sections 6.2 and 6.3.
Formwork, scaffolding (false work), construction joints and surface finishes shall not be measured
separately but shall be deemed to be an integral part of the concrete items.
Single layer brick flat soling under blinding concrete for concrete structures bearing directly on
prepared soil shall be measured in M2 as that of the base area of the concrete structure. . The
measured area will be the same.
5.1.5 Payment
Concrete of the classes and maximum coarse aggregate sizes shown on the Drawings and
measured as provided in Section 5.1.4 shall be paid for at the Contract unit prices per cubic meter.
The contractor’s rates shall include all trial mixes (as specified in Section 5.1.2.3), mixing,
transporting, placing and compacting the concrete. The rates shall also include all concrete
finishing, the supply, placing and building in of weep pipes.
The Contractor’s rates shall be fully inclusive of the cost of all labor and materials in providing and
erecting all formwork, falsework and centering and for their subsequent removal.
Payment for single layer brick flat soling shall include the supply of all required Materials and all
labor, equipment, tools and incidentals necessary to complete the work.
(6) Weight tolerance: The different between calculated weight and actual
shall be within +/-3.5%.
The physical properties of the reinforcement shall be analyzed in a reputed laboratory as per
direction of the Engineer in Charge and test report to be submitted to the Engineer.
Reinforcement steel shall be deformed or ribbed twisted. All reinforcement bars shall be mild steel,
made from billet and shall conform to followings specifications:
(a) Deformations shall be spaced along the bar at substantially uniform distances. The
deformation on opposite sides of the bar shall be similar in size and shape.
(b) The deformations shall be placed with respect to the axis of the bar so that the included
angles is not less than 45° where the line of deformation forms and included angle with the
axis of the bar of form 45° to 70° inclusive, the deformations shall alternately reversed in
direction from those on the opposite side. Where the line of deformation is over 70° a
reversed in direction is not required.
(c) The average center to center or distance between deformation on each side of the bar shall
not exceed seventeenth of the nominal diameter of the bar.
(d) The overall length of deformation shall be such that the gap between the extreme ends of the
deformations on opposite sides of the bar shall not shall not exceed 12.5% of the nominal
perimeter of the bar where the where the extreme ends terminate in a longitudinal ribs are
involved the total width of all longitudinal ribs shall not exceed 25% of the nominal perimeter
of the bar, further more the summation of gaps shall not exceed 25% of the nominal diameter
of the bar. The nominal perimeter of the bar shall be 3.14 (π=3.14) times the nominal
diameter.
(e) The minimum height of deformations shall be not less than the following percentage of the
nominal diameter of the bar.
(f) The spacing, height and gap of deformations shall conform to the requirements prescribed
below:
Bar Size Max. average Min. average Max. gap in chord
spacing in mm height in mm 12.5% nominal
perimeter
10mm dia 6.7 0.38 3.5
12mm dia 8.9 0.51 4.9
16mm dia 11.1 0.71 6.1
20mm dia 13.3 0.96 7.3
22mm dia 15.5 1.11 8.5
25mm dia 17.8 1.27 9.7
28mm dia 20.1 1.42 10.9
ii. Code or Standard Ribbed Twisted Bars shall conform to Indian Standard: IS 1986-
1979, or British Standard: BS 1144 & BS 4461 (1969) or
equivalent.
iii. Chemical Ribbed Twisted Bar shall made from soft Mild Steel with
Composition maximum limit (percent) of:
Carbon Sulphur Phosphoro
us
0.25% 0.055% 0.055%
iv. Physical Properties Yield Stress 414 N/mm2
Tensile Stress 621 N/mm2
Elongation (Gauge length 5d) 14.50%
Bend Test Around a mandrel of 3d through
180 degree.
Rebend Test Around a mandrel of 5d,
through 45 degree and reverse
bend through 23 degree.
v. Rib Requirement Pitot length of any Rib 8 to 12 bar dia (after twisting)
Width of all longitudinal 25% (Max.) of nominal
perimeter
Longitudinal Rib A uniform continuous rib
parallel to the axis of the bar
before twisting.
Traverse Rib or Lug Any rib on the surface of a bar
other than a longitudinal rib.
vi. Standard Dimension Dia in mm Weight in kg/m
and Weight 6 0.222
8 0.395
10 0.617
12 0.888
16 1.578
20 2.466
22 2.980
25 3.854
28 4.830
32 6.313
vii. Dimensional and As in plain and Deformed Bar mentioned previously.
Weight Tolerances
(2) Bending ratio shall be as specified on the Drawings with bends made round a former having a
diameter of at least three times the diameter of the bar. If the ratio are not shown on the Drawings,
ACI standard shall be followed.
(3) Where splices or overlapping in reinforcement are required the bars shall, unless otherwise
shown on the Drawings, have an overlap of not less than thirty times the diameter where a U-hook
is employed on each of the overlapping bars and forty-five times the diameter for bars without
hooks.
(2) All intersections of bars shall be secured with No. 22 to 18 gauge galvanized iron wire, the ends
being turned into the body of the concrete. The reinforcement shall be held securely in place to the
lines and grades shown on the Drawings by approved concrete supports, spacers or ties with
particular care being taken during placing of the concrete.
(3) The specified concrete cover to reinforcement shall be maintained with the aid of approved
supports and spacer pieces. Top reinforcement in slabs shall be maintained in position by means
chairs made out of mild steel, the diameter and quantity being sufficient to ensure security of the
reinforcement shall be used to support access ways, working platforms, or the placing equipment for
the conducting of an electric current. Reinforcement supports and spacers shall be sufficient to
maintain reinforcement in place throughout the concreting operation and shall be shall be not
exposed in the concrete face or discolour the finished concrete.
(4) Before any steel reinforcement is embedded in the concrete any loose mill scale, loose rust and
any oil, grease or other deleterious matter shall be removed. Particularly set concrete which may
adhere to the exposed bars during concreting operations shall be removed.
(1) Unless specified on the Drawings, the clear concrete cover to reinforcement shall be as
tabulated below:
(2) Cover shall be maintained by the use of the minimum practical number of purpose made
concrete blocks, approved spacers and concrete and reinforcement chairs. Concrete spacer blocks
shall be made from cement, sand and small aggregate to match the mix proportions of the
surrounding concrete as far as practical to ensure comparable strength, durability and appearance.
(2) Welds in positions other than those shown on the Drawings shall not be permitted.
6.9 Splicing
Reinforcement shall he furnished in the lengths indicated on the Drawings. When the Contractor
wishes to use more splices than are indicated and/or necessary, the Contractor shall furnish
Working Drawings to the Engineer for approval in accordance with the guidelines provided on the
Contract Drawings. If such additional splices are approved, the extra weight occasioned by such
splices shall not be included in the measurement of reinforcement for payment.
All splices for high yield deformed steel bars and mild steel plain steel bars shall have lap lengths as
shown on the Drawings. Lap splices shall generally he located at points of minimum tension in bars.
Except where otherwise shown on the Drawings lap splices shall be made with the bars placed in
contact and securely wired together.
Welding of reinforcing steel shall he done only if detailed on the Drawings or approved in writing by
the Engineer. Before the Engineer may approve of such welding, the Contractor shall submit and
test any samples as the Engineer may require and make due allowance for the time elapsing before
results are available.
6.10 Substitutions
Substitutions of bars shall be permitted only with specific authorization by the Engineer and at the
expense of the Contractor. If bars are substituted they shall have a cross sectional area equivalent
to the design area, or larger. If substitutions of bars are permitted, the Contractor shall produce
working drawings and reinforcing detailing at his own expense and to the approval of the Engineer.
6.11.01 Measurement
The quantity of reinforcement to be measured under this Section shall be the computed weight in
tones of material used and accepted as shown on the Drawings provided that the quantity shall not
include the reinforcement in any item of work for which the basis of payment includes the
reinforcement.
Computing the weight to be measured, the theoretical weights of bars of the cross section shown on
the Drawings or authorized shall be used. The weight shall be calculated based on a constant mass
of 0.00785 kg/mm2 per meter run. The computed weight shall not include the extra material incurred
when bars larger than those specified are used, or the extra material necessary for splices when
bars shorter than those specified are used with the permission of the Engineer, or the weight of any
devices used to support or fasten the reinforcement in the correct position including any necessary
chairs.
However, payment shall he allowed for lap splices not shown when the bars are longer than 12
meters. Only one lap splice per every started 12 meters will he paid for.
6.11.02 Payment
This work measured as provided above, shall he paid for at the Contract unit price per metric tone of
reinforcement of the particular type. The payment shall be full compensation for furnishing and
placing reinforcement of any size and for all labor, binding wire, equipment, tools and incidentals
necessary to complete the work prescribed in this Section.
The whole system shall not contain any matter or chemicals which could impart taste, odor or
toxicity or otherwise be harmful to public health or adversely affect the water conveyed. The
designed working pressure shall be 6 bar. The test pressure shall be of 10 bar.
All other pipes work and fitting on pipes other than DI shall be flanged unless otherwise stated. The
flange shall comply with the relevant requirements of BS 4504 and be drilled according to class PN
10. Each flange shall be complete, with jointing materials, such as gaskets, bolts, nuts, washers,
glands etc. Where steel and cast flanges are mated together, the steel flange shall be machined
over its full face after welding to its respective pipe.
Flexible joints shall be provided to facilitate easy removal and reinstallation of a section after any
repair or maintenance.
The pipe work shall be laid out and designed to facilitate its erection, painting at sites, dismantling of
any section for maintenance and to give a constant and uniform flow of working fluid with a
minimum head loss. Position of flanges shall take into account any necessary pipe support or thrust
blocks.
Facilities shall be provided for drainage and de-aerating the pipe system
Pipes which are required to be cut to form closing pieces in any portion of the pipeline or to
terminate in chambers or other parts of the Works shall not be cut until after all adjacent pipes have
been installed and joined.
The Contractor shall determine the length of each closing piece and the required angle and shape
of the cut. The cut shall be neatly performed and the end of the pipe shaped up and trimmed so as
to ensure an accurate joint or termination as the case may be. Any damage to sheathing, coating or
lining shall be made good.
All pipes shall be cut on site and prepared for jointing in accordance with the supplier's instructions.
The Engineer may, and without thereby relieving the Contractor of any of his obligations, inspect
and test the pipes, fittings and valves by any means he considers appropriate and such tests shall
be performed by the Contractor as aforesaid. The Contractor shall remove from the Site and shall
provide a replacement for any pipe, fitting or valve which in the opinion of the Engineer is so badly
damaged as to be unfit for repair on the Site.
7.6 Laying
Unless specified otherwise, pipes shall be set in place singly and shall not be joined until after they
have been so positioned.
No pipe shall be laid which is damaged, cracked, checked, or spalled or has any other defect
deemed by the Engineer to make it unacceptable, and all such sections shall be permanently
removed from the Works.
Each heavy pipe shall be carefully lowered onto its prepared bed by means of necessary slings and
tackle. PVC pipes may be lowered by hand. A recess shall be left in the prepared bed to permit the
sling to be withdrawn. If the prepared bed is damaged, the pipe shall be raised and the bed made
good before pipe laying is continued. Pipe shall be laid upgrade. Any pipe which is not in true
alignment, both vertical and horizontal, or shows any undue settlement after laying, shall be taken
up and re-laid correctly by the Contractor at his own expense, when so ordered by the Engineer.
The pipe shall rest on solid and even foundation bedding for the full length of the pipe barrel.
Suitable excavation shall be made to receive the socket or collar. Except where directed or shown
otherwise, the minimum cover to the laid pipes, measured at the highest point at the barrel shall be
as shown in the Drawings.
The Contractor shall keep the interior of pipes clean and free from water, dirt, stones or other
foreign matter as installation proceeds, and at the end of the day's work, or at other times when
installation work is not proceeding, the open ends of pipes shall be sealed off by a wooden plug or
other approved stopper. If foreign matter enters the pipe which, in opinion of the Engineer, will not
be removed by the flushing operation, the interior of the pipe shall be cleaned by approved
mechanical means. Potable water pipes shall also be swabbed with a 1% hypo-chlorite disinfecting
solution as directed by the Engineer. Cleaning with any other means shall be undertaken only when
the Engineer has determined that such operation will not force mud or debris into pipe joint spaces.
The pipe trench shall be kept free from water at all times. The Contractor shall take all necessary
precautions to prevent the pipe from floating due to water entering the trench from any source, and
shall assume full responsibility for any damage due to this cause. It shall be at the Contractor's
expense to restore and replace the pipe to its specified condition and grade if it is displaced due to
floating.
Where pipes pass through water - bearing walls, care shall be exercised to ensure joints being
watertight. The pipe exterior shall be free of all dirt and grease to secure a tight bond with the
concrete. No pipe joint will be allowed to occur in the walls.
Installation of PVC pipe in open air is not permitted.
If any damage should occur to any pipes through failure of the Contractor to comply with these
conditions, the damage shall be made good at the Contractor's expense.
Flanged faces shall be thoroughly cleaned of all foreign substances before flanges are connected.
Flanges shall be aligned and faces shall be parallel before the joint is made. Extra care shall be
taken to load the bolts evenly so as to eliminate unnecessary stresses. A torque wrench shall be
used on all PVC to PVC flanged pipe joints and on all PVC to metal flanged pipe joints. The
following torque load shall be applied to produce the required 70 MPa stress in the corrosion
resisting steel bolts of flanged connections.
All PVC pipe connections to cast iron and steel valves and fittings shall socket and spigot or flanged
connections made in accordance with the Bills of Quantities and materials supplied.
All cast iron and steel fittings and valve assemblies in PVC pipe runs shall be supported
independently of the PVC pipe so that their weight will not be supported by or transmitted of the
PVC pipe.
The spigot will be centered in the socket and maintained in this position by resting it on two mounds
of tamped soil, or preferably gravel. The spigot with then be pushed into the socket, checking that
everything is correctly aligned.
Supports for unburied horizontal lines of PVC pipe shall be spaced as indicated in the following
table, unless it is otherwise shown on the drawings:
Where clamping of the pipe for the purpose of anchoring is required, the clamps shall be fitted with
rubber or PVC taper liners. Supports shall be provided at all poits of directional change especially
from horizontal to vertical, regardless that these supports are called for on the drawings or not.
Valves and other devices in the line shall be supported so that the weight or torque applied to the
device does not place undue stress on the pipe. Expansion joints shall be used at other locations
recommended by the pipe manufacturer. All PVC pipe shall be installed and supported to permit
contraction and expansion from temperature changes. Several Standard specifications, such as
British Standard (BS) or ISO that are followed widely in the world for uPVC pipes are given below.
The Contractor shall follow GOST or ISO Standard. .
General
Specific gravity : 1.35 to 1.45
Water absorption in 24 hours : Less than 4 mg/cm (0.10%)
Flammability : Will not support combustion,
Self extinguishing
Physical
The most important properties of this versatile and economical material are given in the following
table and contractor shall be meet the requirements as listed in the Tables:
Properties of polyvinylchloride unplasticised (uPVC), average values.
Chemical
uPVC pipes shall be an excellent resistance to acids, alkalis, salts in all concentration and can
handle water with a PH value of 2 to 12. It shall resist all kinds of acids used for well regeneration if
any.
Heat Reversion
When tested in accordance with the requirements of method 1102 A or 1102 B of BC 2782 using a
temperature 150°C and appropriate immersion times specified in the table below, the change in
length after the conditioning process shall not be more than 5%.
In addition, each test specimen the pipe shall show no faults, cracks, cavities or no blisters when
visually examined after cutting the test specimen longitudinally.
Resistance to Acetone
When tested by the method described as per BS 509 the sample will show no delimitation or
disintegration. Flattening and/or swelling of the pipe will not be deemed to constitute failure.
Capacity
When tested by any method as per BS 3505, the wall of the pipe shall not transmit more than 0.2%
of the visible light falling on to it.
PW3-Sec-7 (Tech. Spec.) 68
Mechanical
IImpact Strength
uPVC pipes shall be tested for impact strength after the specified temperature, length, mass of
striker and its height of free fall are followed as per BS 3505 or GOST.
Electrical
Dielectric Strength : 40 kv/mm: Non-conductor
Volume Resistivity : 105 Ohm/cm
Thermal
Softening Point (Vicat) : 176 F (80C.)
Heat distortion temperature at : 75C. (at 18.5 kg/cm)
Specific heat : 0.25 cal/C.
Coefficient of heat conductivity : 0.14 K cal/kg/C.
Thermal conductivity : 4 X 104 cal/hr/cm2/C/cm
Coefficient of Liner expansion : 5 to 8.5 X 105 mm/C.
Expansion 6 meters length (approx) : 3.2 mm/10C.
Flow Characteristics
Hazen Williams’s coefficient : 135-150
Coole-brook coefficient : 0.00001
Assembly of Joints
The joints of DI/GI pipe to pipe to DI/GI fitting, shall be of the non-self anchoring socket-spigot type
with flexible rubber rings. All joints and preparation thereof shall be in accordance with the
manufacturers printed instructions and as hereinafter specified.
Socket chamber and pipe spigot should be cleaned carefully. Particular attention will be paid to the
gasket seat (i.e. all soil, sand, etc.. should be eliminated). The spigot of the jointing pipe, as well as
the gasket will also be cleaned. Spigot should be chamfered and in good condition. In case of a cut
pipe the chamfer will be remade.
The gasket will be inserted at the trench side. Condition of the gasket will be checked. The gasket
will be introduced into the socket. Radial pressure will be applied to the gasket to force it into place.
It should be ensured that the gasket fits snugly around its circumference.
If the pipe spigot is not already marked, the spigot of the pipe being laid will be market at a distance
from the end equivalent to the socket depth P, minus 10 mm. Lubricating paste will be applied to the
exposed surface of the gasket and to the spigot end and chamfer. The lubricating paste will be
brush applied in reasonable amounts.
The spigot will be centered in the socket and maintained in this position by resting it on two mounds
of tamped soil, or preferably gravel. The spigot with then be pushed into the socket, checking that
everything is correctly aligned.
PW3-Sec-7 (Tech. Spec.) 69
If the pipe is marked singly on site, the spigot will be pushed until the mark is in line with the socket
face. It should not be penetrated beyond this. If the pipe is marked doubly at works, the spigot will
be pushed until the first mark disappears inside the socket. The second marks must still be visible
after assembly. Finally the gasket will be checked to ensure that it is correctly seated by inserting
the end of a metal rule through the annular spigot and socket gap until it touches the gasket. The
rule must penetrate to the same depth around the whole circumference.
As pipe laying equipment, for insertion of the spigot into the socket, mechanical winches shall be
used of specification and with methods prescribe by the manufacturer.
Flanged Joints
Connections between DI pipes and cast iron, steel and PVC pipes, valves and fittings shall be either
with Flange Adapters or with flanges welded to the DI pipe end.
Flanges should be clean and of good appearance. Items being assembled should be aligned
properly. A small gap for gasket insertion should be left between the two flanges being joined. The
gasket will be centered between the bosses on both flanges.
Pipe Cutting
Slitting disc type cutters shall be used. Before cutting the pipes it is essential to measure the
external diameter at the cutting point with a circumference tape or compass callipers, to check that it
is compatible with the intended socket or gland dimension.
After making the cut, and before assembly, it is essential to fettle and remake the chamfer, to avoid
gasket damage during assembly. The chamfer dimensions must be as indicated by the
manufacturer.
Repair of Coatings
External Coating
For slight damage (small areas, zinc not detached) no repair is necessary. Larger damage can be
repaired with bituminous paint. Application method will be by brush, roller or spray gun (air or
airless).
Dirt will be removed by brushing lightly. The area being coated will be dried by the most appropriate
means. The coating should be applied in criss-cross passes, until the coating is up to the level of the
undamaged coating, overlapping the later.
Internal Lining
Any cement mortal damage caused accidentally or by rough handling can be repaired on site,
provided it is not longer than a quarter of tlie pipe circumference and with no localized pipe
deformation. Otherwise the damaged section must be cut off.
Brush, trowel, palette knife, or sleeker will be used for mortar application. The pipe will be rotated to
bring the area to be repaired as close to the bottom as -, possible. The damaged area and 1 or 2 cm
of surrounding sound mortar should be removed with hammer and cold chisel. The edge of the
cleared zone must be vertical to the iron surface. Non-adherent material will be cleaned with a wire
brush. The repair area will be moistened.
The water emulsion mixture in brush applied a few minutes before making the repair so that the
original mortar is wetted over a width of about 20 cm around edges of the repair zone.
The mortar will be trowelled on to compact it adequately to restore the thickness. The repaired
surface will be smoothened with palette knife or sleeker.
It should be checked that there is no gap between the fresh and the original material. A protective
coat of water and emulsion is applied, not more than 30 minutes after final smoothing, to prevent the
patch from drying too quickly and to give good strength (to be covered with damp cloth until sun
PW3-Sec-7 (Tech. Spec.) 70
set).
7.9 Definition
Fittings
Shall mean bends, junctions, reducers, tapers, couplings, adapters and similar items which are not
water flow control equipment.
Valves
A device to control flow of water.
Specials
Shall mean any fittings which are not normally manufactured, rather these are made locally
depending on the requirements to connect pipes and accessories
General
The pipes shall be accurately installed to the line, levels, grades and positions specified in the
drawings.
Pipes shall be laid in accordance with CP312 for pipes specified. The programme for pipe laying
shall be submitted to and approved by the Engineer before the commencement of the works. Any
subsequent change in programme shall also be approved by the Engineer.
Externally coated pipe shall be handled at all times with non-abrasive canvas, rubber or length belts
or other equipment designed to prevent damage to the coating. The planks may be used to support
the coated pipe prior to lowering into the trench and shall be properly padded for the purpose of
protecting the coating.
Any injury to the protective coating from any cause must be repaired before the pipes are used.
Every precaution shall be taken to prevent foreign material from entering the pipes or fittings. Pipes
and fittings lowered into the trench shall be carefully cleaned before jointing.
Piping shall be adequately supported with hangers, clamps supports, or other devices of appropriate
design, and as specified herein. Where details are shown on the drawings or specified herein, the
supports shall conform thereto and shall be placed as indicated. System shall be adequately
supported where details are not provided.
The Contractor shall keep the interior of pipes clean and free from waste dirt, stones or other foreign
matter as installation proceeds, and at the end of the day's work, or at other times when installation
work is not proceeding, the open ends of pipes shall be sealed off by a wooden plug or other
approved stopper.
All piping which will pass through walls shall be provided with specified pipe with annular space
sealed or with wall casting. The contractor shall provide the wall sleeves for insertion in the walls.
No pipe joint will be allowed to occur in the sleeve. The seal on both ends of the sleeve shall be
flush with the wall surfaces on completion of work. Drying of standard sealing and scaling of wall
sleeves shall conform to the following requirements.
The annular space between the pipe and sleeve be cleaned of all loose particles and contamination,
and shall be dry prior to sealing. Tape or other recommended protection shall be applied on the
structure surfaces to preclude contamination by the sealant, and any contamination which occurs
shall be removed immediately, followed by a through washing of the surfaces with solvent. Prepared
compound not used during the application time limits designated by the manufacturer of such
compound shall be discarded.
The sealing shall be performed after any required has been applied and backup material placed.
The application shall be made in clean, straight lines free of wrinkles, be touched as required and
finished with a convex furnace just sufficient to provide the required flush surface upon drying.
The annular space shall be packed and ends shall be caulked as required for bell and joints in
PW3-Sec-7 (Tech. Spec.) 71
AWWA standard C600.
Pipes shall be laid or placed accurately to the lines and levels as shown on the drawings, within a
tolerance of ±5mm. The jointing of pipes shall be made in accordance with the manufacture's
recommendations and as the Engineer may order. The Contractor shall obtain from the
manufacturer all special information regarding the handling of their pipes and the formation of the
joints and submit the same to the Engineer.
When pipe lying is not in progress, including overnight, the open ends of the pipe line shall be
blocked with a temporary watertight fitting approved by the Engineer.
Trenching
Before cutting trenches, the alignment of pipelines should be thoroughly inspected and seen that the
proposed trenches may not ordinarily encounter with electric or telephone poles, underground
sewer, gas and drainage pipes and may offer least troubles to pedestrians and vehicular traffic.
After fixing the alignment, the right-of-way should be cleared off all obstructions including roots of
trees etc. The width of the trench shall be adequate (pipe dia + 150mm both sides) to permit
working space for making joints conveniently. The maximum depth shall be such that the pipe will
have at least 1.0 meter coverage on top. Trenches should always be straight except at road corners
and other possible obstructions. Curves and bends used should not be beyond the permissible
deflection of the type of joints used. The side of trenches will be vertical as far as the soil conditions
permits and if necessary side protection should be made against collapsing of adjacent structures
with the help of planks or trench supports.
Laying of Pipes
The pipes shall be laid on a bed of soil so prepared that the barrel of pipe is supported over it's
entire length. Before lying, the bed should be properly rammed and leveled and so that there is no
sagging or settlement of any part of the trench anywhere. When sand bedding is required in case of
PVC pipes, trench is made 100 mm deeper than the required level and filled up to required level
with sand. After laying and fitting fixing the pipe, the same is covered by at least 150mm sand on top
and 150 mm each side. However, the minimum trench width shall not be less than 500 mm.
When laying pipes the trench shall be kept dry and if required a de-watering pump should be
engaged. Extra excavation should be made below each joint to facilitate the making of the joint
properly. Special arrangement should be made when pipe line crosses a canal or a culvert in
suspension. The suspended pipe should be supported at each joint, concrete thrust blocks shall be
installed at each bend, deflected position of pipe and at dead ends. Where loose solid or gorges in
the trenches are encountered, the loose soil should be replaced by sand or sand and khoa mixer.
Compacting of back fill material shall be done by watering and compacting with pneumatic or petrol
driven tamper not exceeding 150 mm layers. Prior to acceptance of the work, the Contractor shall
develop the area up to the level of the surrounding ground.
PW3-Sec-7 (Tech. Spec.) 72
Volumes of back fill which fail to meet the specified compaction, as tested by the Engineer, shall be
reworked and re-compacted until they conform to the specified compaction.
Should the materials being placed as refilling, while acceptable at the time when approved, become
unacceptable to the Engineer due to exposure to weather conditions or due to flooding or have
become puddle, soft or segregated during the progress of work, the Contractor shall at his own
expense remove such damaged, softened or segregated materials and replace it with fresh
approved materials. To permit the proper consolidation of back fill into the voids behind trench
sheeting and supports, trench sheeting shall be withdrawn gradually as back fill progresses in depth
and along the trench. On no account shall any excavated materials be dozed back when refilling
trenches in roads and no back filling shall be carried out unless, in the opinion of the Engineer,
sufficient mechanical rammers are in operation on that portion of the work.
Where directed by the Engineer, trench excavation shall be refilled with granular materials or
concrete in accordance with the Drawings or/and direction of the Engineer.
Except where welded steel pipelines or self anchoring joints are used, thrust blocks are required
wherever the pipeline changes direction, diameter, terminates or is expected to develop a thrust,
e.g. at a valve or at unstable soil conditions.
Pipe Installation
The items provided for pipe in the Bill of Quantities shall cover all things necessary to provide, take
over, where expressly stated, install, test and disinfect the pipe including storing, transporting,
excavation and back filling (other than with granular fill or concrete) to the depths shown on the
Drawings for underground pipes; laying, cutting, jointing, reinstatement in all surfaces; connection to
existing mains; and all other things necessary for pipe installation not measured separately under
other items in the Bill of Quantities. For pipe work within buildings or fixed to structures the rates
shall include for all necessary supports, hangers, clamps and the like.
Measurement shall be made per linear metre along the centreline of the pipe.
Valve Chambers
Payment for air valve, washout, washout hydrant, sluice valve, butterfly valve and hydrant chambers
shall be made at a unit rate for each chamber constructed.
With the exception of the items listed below, the unit rate shall include for all the Contractor's
obligations necessary to complete the chambers in accordance with the Drawings including, but not
limited to, excavation, concrete, brickwork, pipe work, fittings, valve, hydrant, joint material and
associated pipe work, surface box and PVC drain pipe.
PW3-Sec-7 (Tech. Spec.) 73
Concrete Encasement and Thrust Blocks
Items are provided in the Bill of Quantities for concrete encasement to be paid per linear meter for
each pipe size. Thrust blocks shall be measured for payment per cubic meter placed to the limits
shown on the Drawings.
The Contractor shall submit for the Engineer's approval details of his proposed methods and
programme for testing (including details of test equipment) and shall arrange for all tests to be
witnessed by the Engineer or other person appointed by the Engineer.
The Contractor shall provide all things necessary for carrying out testing and cleaning including
pumps, gauges, piped connections, stop ends and all other temporary works.
The Contractor shall remain responsible for the care of the Works during testing and cleaning of the
pipeline.
Where the refilling of trench excavation has not been completed before pressure testing is ready to
start, the Engineer, may nevertheless allow testing to proceed provided that sufficient refill material
is placed to restrain pipe movement under test and that all thrust blocks are complete and mature.
Before pressure testing is started, the Contractor shall recheck pipes and valves for cleanliness and
shall recheck the operation of all valves. The open ends of the pipeline (or sections thereof) shall
normally be closed by blank flanges or end caps additionally secured where necessary by
temporary struts and wedges. All anchor and thrust blocks shall have been completed and all pipe
straps and other devices intended to prevent the movement of pipes shall have been securely
fastened.
Since valves cannot be guaranteed to be perfectly drop-tight, testing against closed valves which
are connected to an existing public water supply shall be prohibited, because of the danger of
contamination; testing against other closed valves (including air valves) not so connected, may be
attempted if desired, provided the valves are suitably anchored against thrust. No claims
whatsoever will be entertained on account of leaking valves, or any other difficulties in closing off
lengths of pipe work for testing, which shall be entirely at the Contractor's expense.
Sections of pipelines shall be tested with partial back filling in lengths not exceeding 500 m. The
Contractor shall ensure that the pipe is adequately restrained and that all thrust blocks are in place
and have reached working strength.
The pipe (or section thereof) shall be filled with water and all air removed as far as possible. The
pipe shall be tightly plugged after spelling the air. The pressure shall then be raised by pumping in
water until the specified test pressure is reached and shall be maintained at this pressure by further
pumping until it is steady. The pipe shall then be left under pressure for twenty four (24) hours after
which pumping shall resume in order to restore the specified test pressure.
The test pressure for two hours shall be such that the test head plus gravity head at any point in the
pipeline shall be as shown on the Test Pressure Schedule in Table 5.1.
Test Pressure
Pipeline kg/cm2 m
Raw & Treated Water Transmission Pipe 10 100
During all testing, the trench in general and the joint pockets in particular shall be kept clear of water
and should the trench become unstable due to work or leaking on testing or re-testing it shall be
excavated to solid ground and made up with lean mix concrete or such other material as the
Engineer may direct, all at the Contractor's expense. Should a test fail, the Contractor shall at his
own expense replace defective pipes or fittings or make good leaking joints or otherwise rectify
defective work. Cleaning, inspection and testing shall then be repeated, until the work is to the
Engineer's satisfaction.
The Contractor shall be liable to the Employer for any damage caused to the pipe or to pumps and
other equipment of the Employer as a result of foreign matter of any kind not having been cleaned
out of the pipeline before it is handed over to the Employer.
2. A stock disinfecting solution shall be prepared by mixing for not less than five (5) minutes, in
a clean container, Chlorosene (30% available chlorine) and potable water in the proportion of 10
parts of powder to 100 parts water by weight. After mixing, the solution shall stand for a further
five (5) minutes after which the clear supernatant liquid shall be decanted into clean container.
Stock solutions shall be made up fresh daily.
3. The pipe to be disinfected shall be filled with potable water t the same time as the stock
solution is added through a convenient air valve in such quantities (to be determined by the
PW3-Sec-7 (Tech. Spec.) 77
Engineer) as will result in a final solution containing 25 ppm free chlorine in the pipe line. Care
shall be taken to ensure that the stock solution is added at a constant rate, starting when water
is fed into the main and ending as soon as the main is full.
4. Every pipe charged with disinfecting solution shall stand for twenty-four (24) hours, after
which a sample shall be taken at a washout valve by the Contractor in the presence of the
Engineer’s Representative, from whom the sampling bottle shall be obtained. If the sample does
not show at least 2ppm free chlorine, disinfection shall be repeated. If the sample is satisfactory,
the pipe shall be emptied, flushed out and filled with treated water and allowed to stand for one
(1) hour.
5. The Contractor shall take adequate care and safety measures so that the highly
concentrated chlorinated water for disinfection is not consumed by any person, livestock, etc.
Prior to disinfection of a section of network, people of the surrounding area shall be warned of
the fatal effect of consumption of chlorinated water through wide publicity conducted with the
assistance of KWASA and concerned Ward Heads. The testing and flushing out schedule
should be made known to the people of the area.
After disinfection, the water in the pipeline shall be discharged to a nearby drain or depression
or as directed by the Engineer and this will follow continuous flushing out of the pipeline with
fresh potable water. In order to avoid any accident or health hazard, the Contractor shall be
vigilant and watchful that the flushed out water is not consumed by human being, livestock or
animals.
6. Two (2) further samples shall then be taken as before, one for a further determination of free
chlorine and the other, in a sterilized bottle, bottle, for bacteriological analysis. If the free
chlorine determination shows more than 4 ppm free chlorine the main shall be flushed out
again. If the bacteriological analysis is unsatisfactory, disinfection and sampling shall be
repeated until satisfactory results are obtained before the main is commissioned.
7. The Contractor shall provide all equipment, materials and testing apparatus etc. as may be
necessary for the effective disinfection of all pipelines.
Work to be undertaken in this clause shall include, but are not limited to:-
Supply and installation of pumping equipment in Intake Pump Station including Delivery
Pipes & Fittings.
Supply and installation of pumping equipment in Surface Water Treatment Plant
including Delivery Pipes & Fittings.
Supply and installation of Filter influent, & filter effluent Pipes, Backwash and sludge
drainage pipes & fittings
Supply and installation of Sluice Valves, Check Valves, Flow Meter, Pressure Gauge, Air
Valves and other accessories as required.
Testing and commissioning of Mechanical Equipment
All machinery, accessories and other equipment to be used in the mechanical installation work shall
be new and of the highest quality to the best modern practices, sound workmanship, robust in
design and of a grade and quality suitable for the purpose and the climatic conditions at the location.
All equipment shall be of approved types, supplied by approved manufacturers.
All manufactured items shall be the product of manufacturers regularly engaged in producing works
of the types specified and be constructed and finished by the same manufacturer.
All manufactured items shall be free from imperfections and defects which may impair their
durability and serviceability or affect their appearance.
Before installation and purchasing of any machinery, accessories and equipment, catalogues
related to type and model no. and warranty certificate (s) from the manufacturer (s) shall be
presented to the Engineer. As per decision of the Engineer, the Contractor shall take
necessary steps for the execution of the testing and inspection of the materials mentioned
herein, prior to purchase and installation.
All requirements as specified in other sections of the Technical Specification shall apply to
this section where applicable.
The equipment to be furnished shall be new and shall be a standard product of a manufacturer
experienced in the design, fabrication and construction of that equipment. The manufacturer shall
demonstrate to the Engineer from operating installations of equal or larger capacity utilizing
equipment such as herein, that all the mechanical features and appurtenances of the equipment will
operated satisfactorily for the purposes intended.
1. Factory tests are required for all mechanical equipment and assemblies to be supplied by
the Contractor. The Contractor shall perform factory tests in accordance with tile relevant
British Standards or other such standards approved by the Engineer.
2. Tests at the Manufacturer's works shall be accompanied with test certificates showing all
the relevant information and details relating to the test.
1. The Engineer or his representative may inspect fabricated mechanical equipment at the
factory. The Contractor shall notify the engineer in sufficient time so that factory inspection
can be arranged.
2. Factory inspection may be made after the manufactures have performed satisfactory
checks, adjustments, tests, and operations.
3. Approval of equipment at the factory only allows the manufacturer to ship the equipment to
the site, and does not constitute a final acceptance.
l. On mechanical equipment, a factory primer and high quality oil-resistant backed industrial
enamel paint are to be applied.
2. Surfaces that are inaccessible after assembly are to be painted otherwise protected by a
method, which shall provide protection for the life of the equipment.
1. The Contractor shall guarantee all equipment in accordance with the condition of contract.
Before purchasing and installation of any machinery, accessories and equipment, the
Contractor shall provide three complete sets of catalogues related to type and model number,
drawings and instructions required for operation and maintenance of all items of equipment
and instrumentation furnished. These shall include instructions for lubrication, repair and
servicing, parts lists and all other pertinent information available from the equipment
manufacturers.
Brand names are used herein merely to describe the nature of the described equipment and
not used to endorse or indicate a preference for a particular product or manufacturer. Goods,
which have similar characteristics and provide performance in quality at least equal to those
specified, are acceptable.
After installation of the mechanical machines and accessories, the contractor shall prepare as
build drawings together with specification and data covering performance and materials of
construction.
9.3.2 Submittals
The Contractor shall submit complete information including fabrication, assembly, foundation, and
installation data together with detailed specifications and performance information covering
materials of construction, power drive assembly, parts, devices, wiring diagrams, and all other
accessories of the pumping equipment furnished. The submittals shall include, but not be limited to
the following:
A. Pump data including pump cross-sectional drawing with part identification list and MOC
B. Motor data, including:
Manufacturer.
Motor construction details
Minimum guaranteed efficiency at full load, 3/4 load, and 1/2 load.
Power factor at full load, 3/4 load, and 1/2 load.
Locked rotor current.
Motor speed.
Dimensions, weights and mounting details of motors
E. Certificates of compliance.
Motor shall be, squirrel cage induction type and shall operate at 3 phase, 50 HZ, AC supply of 380-
440 volts with sufficient tolerance upto 340 volts. The contractor shall propose the power rating of
the motor which shall provide sufficient allowance that at this low voltage the motor shall not get
overload throughout the working range of the pump. Motor speed shall not exceed 1500 rpm.
The stator coils shall easily rewind able. There should be smooth access to the windings to facilitate
checking and locating of any fault and replacing defective coils without distributing the full winding. A
complete stator unit, if required, should be easily and instantaneously replaceable by a new one.
The stator body shall be shot blasted and painted with epoxy coating for corrosion resistance. The
rotor shall be brazed with silver brazing alloy for better performance and be painted for corrosion
resistance. The rotor shaft shall be dynamically balanced at high speed.
The motor shall be rated to comply with BS 4999 or equivalent. Winding shall be designed to give a
reasonable even temperature distribution, free from hot spots.
The coupling shall be rigid sleeve made of stainless steel non-slip type with matching groove, collar
& key.
The material of motor casing shall be made of Cast Iron. The material for Motor casing shall be free
from pitting or any defect.
v. Accessories to be provided
Each pump shall be furnished with, but not limited to the following accessories:
Couplings with guard : One (1) set
Bed plate (common or individual) : One (1) set
Compound and pressure gauge : Complete set
Flange adapter with tie rods for discharge pipe : Complete set
Foundation bolts and nuts : One (1) set
Air vent and others piping : One (1) set
Suction reducer and delivery enlarger with flange : Complete set
Special tools for maintenance as recommended by : One (1) set
the Manufacturer or as instructed by the Engineer
vi Spare Parts
The Contractor shall provide the following spare parts for each unit of pump, and supply other items
as recommended by the Manufacturer as spares for 5 years operation.
3 A leak detector shall be furnished to detect water in the stator chamber for motors over 15 kW.
The sensor shall utilize a float switch and controls shall be arranged to open a normally closed
contact for remote monitoring and stop the pump.
4 A bearing temperature monitor shall be furnished for the lower bearing arranged to open a
normally closed contact for remote monitoring and stop the pump. The set temperature of the
temperature monitor shall be as recommended by the manufacturer.
Motors shall have high efficiency. Motors with the following minimum efficiencies, at full load shall
be provided:
The motors shall be sized so that the brake power does not exceed 90 percent of the full load
nameplate power unless otherwise indicated in the driven equipment specifications.
The motor must be able to accelerate the driven machine from zero to full speed at 90 percent of
rated voltage without overheating.
The maximum temperature by resistance for each of the various parts of the motor shall not exceed
the values of the NEMA MG1-1.65 Class B insulation system as indicated in NEMA MG 1-12.42.
Each assembled pump shall be tested at the manufacturer/supplier test bench to determine the
following characteristics in accordance with the latest Hydraulic Institute Standards (BHRI-British
Hydraulic Research Institute)
1. head-capacity curve,
2. power curve,
3. efficiency curve.
Random test at least one for each type pump unit shall be carried out in
Manufacturer/Supplier/BUET Test Bench in presence of the purchaser’s representative. All
cost including witness of purchaser representative or charge for BUET test including
transportation, loading, unloading etc. shall be borne by the contractor.
Tests at the Test Bench shall be accompanied with test certificates showing all the relevant
information and details relating to the test.
Same dimension shall be applied for concerned bends, tees & other fittings.
The pipe shall be suitable for a minimum test pressure of 15 bar. Straight pipe shall be supplied to a
standard length of not less than 3 metres. The term "short piece" for pipes will mean as required to
fulfill site condition. The pipes and specials shall, before installation, be internally coated with tar
epoxy resin and externally with bitumen reinforced with an inner layer of fibre glass tissue except for
the pipe work exposed.
Flanged joints to BS standard shall be made, unless specified otherwise, with rubber joint rings and
steel bolts and nuts which shall include two washers per bolt, joint rings shall be made from 1/8 inch
thick rubber to BS 3063 reinforced with fabric in accordance with BS 1787 of such width as to cover
the machined face of the joint inside the bolt holes.
They shall be of such physical properties as to be capable of forming permanent watertight joints
against pressures up to the maximum test pressure. The use of jointing paste or grease will not be
permitted. The bores of abutting pipes or fittings shall be concentric and no jointing material is to be
left protruding into the bore.
All nuts shall first be tightened by hand and nuts on opposite sides of the joint circumference shall
then be alternately and progressively tightened with a spanner so as to ensure even pressure all
round the joint.
Welded Joints
All welding works shall be done with proper welding rods having about 2.5 kg/cm 2 tensile strength.
The welders must have enough experience for high pressure welding. Shims can be used for proper
penetration of metals during welding. Base plants joints shall be placed face to face for butt-welding.
Continuous single run welding must not be done to avoid deforming and wrapping due to over-heat.
Subsequent runs shall be done after thoroughly cleaning, chipping and grinding the previous
welding. Penetrated side must be finished with the disc grinder and a light welding will give the final
finish. The steel pipes and fittings shall be of welded quality.
Welding of joints in steel pipes shall be carried out manually by the metal-arc process complying
generally with the requirements of BS 1856 and BS 4515. Welding shall be carried out only by
welders approved by the Engineer. All fillet welds shall have a throat thickness of not less than 0.7
times the thickness of the pipe to be welded.
If deflection at a welded joint is permitted by the Engineer it shall not exceed the angle specified by
the manufacturer. Spare parts to be welded shall have loose scale, slag, rust and other foreign
matter removed by means of a mechanical brush and solvent and shall be left clean and dry. All
scale and slag shall be removed from each weld run when it is completed. Pipes manufactured with
PW3-Sec-7 (Tech. Spec.) 88
longitudinal or spiral welds shall be lined up before jointing so that these welds are at least 15
degree apart around the joint circumference.
Flanges and internal retaining rings shall be jointed to pipe ends by two circumferential fillet welds
having a throat thickness not less than 0.7 times the thickness of the pipe.
Before commencing any welding work on site, the Contractor shall submit to the Engineer for
approval details of the plant, materials and method he proposes to employ.
The pipes shall be accurately installed to the line, levels, grades and positions specified in the
drawings.
Pipes shall be laid in accordance with CP312 for pipes specified. The programme for pipe laying
shall be submitted to and approved by the Engineer before the commencement of the works. Any
subsequent change in program shall also be approved by the Engineer.
9.5.1 General
A. All valves shall be new and shall be suitable for use with water temperature up to 50 o C and in
climatic and soil conditions encountered in the country of installation. Valves shall be of the
same pressure rating as the adjoining pipe, but with a minimum rating of 10 bar. Valves shall be
supplied complete with flanges, gaskets and stainless steel nuts, bolts, and washers. Flange
gaskets shall be of the metal reinforced type. Nuts, bolts, screws and fittings shall be of
stainless steel with 2 washers per bolt. Bolt length shall be such that after the joints are made-
up, the bolt protrudes through the nut but not more than 12 mm.
B. Marking of valves shall include the; manufacturing standard; manufacturer’s name or trademark;
nominal diameter (N.D.) in mm; pressure rating in bars; an individual serial number which
relates directly to the manufacturer’s test certificate; and month and year of manufacture.
C. All gate and butterfly valves shall be clockwise closing and the direction of opening and closing
shall be clearly marked. Position indicators shall be provided on all gate and butterfly valves and
shall have adjustable end limit stops at both open and closed and positions to prevent damage
by excessive operating force. The maximum effort required to operate the valve against the
maximum unbalanced head applied at the circumference of the handwheel or end of the tee-key
shall not exceed 15 kg and where necessary gearing shall be provided as specified to achieve
this. Hand wheels shall be provided for all valves when installed above ground, when operation
is within reach. Valves installed deeper than 300 mm shall be provided with an extension
spindle and Tee-key. Valves installed out of reach above ground shall be provided with chain
drive or remote control drive as shown or specified.
D. All gate and butterfly valves shall be designed to provide 100 percent water tight shut off at all
specified pressures and suitable for installation of electrical actuators when required. Line
valves of 300 mm diameter and smaller shall be double flanged gate valves, unless otherwise
indicated. Butterfly valves shall be used as line valves for sizes larger than 300 mm diameter
and shall be flanged. Where flanges are required they shall be drilled to PN 10 unless specified
or directed otherwise.
C. Single orifice air valve shall be of screw down type and of 25/50 mm size. Valves shall be
supplied with gunmetal cock, gunmetal strap and stainless steel pipe.
A. Valves shall be installed and commissioned in accordance with manufacturer’s instructions. The
Contractor shall co-ordinate the valve requirements with those of the actuators and
instrumentation to ensure compatibility of control interfacing and operations.
B. All valves shall be tested to the appropriate test pressure at the manufacturer’s works, and shall
be supported by a test certificate from the manufacturer. Work tests on all valves shall
witnessed by an approved independent testing agency at no extra cost to the Employer. The
Contractor shall supply the original manufacturer’s test certificate endorsed by the approved
independent testing agency for each valve supplied. The certificate shall relate to the individual
number cast on each valve and shall give the date of test. The manufacturer shall factory test
each valve for performance, leakage and hydrostatic pressure in accordance with AWWA C500.
Scope
The water meters will be used to record the discharge of water from deep the tube wells having
same characteristics as mentioned for tube well pumps.
Standard to be used
All materials and workmanship shall comply with the latest provision of BS/ISO or equivalent
standard.
Registers shall record up to maximum 9,999,999.99 cubic metres. The meter recording device
should be such that after recording full capacity it automatically reverts to zero. Whole cubic meters
are to be indicated in black and fractions of cubic meters in red. The unit symbol m 3 should be
shown either on the dial or in the immediate vicinity of the digital indicator.
Each meter shall be equipped with a tamper proof device consisting of a seal wire and lead seal
which must be broken in order to remove the register box.
Performance Requirements
Each water meter shall be designed for high flow accuracy and have a proven performance record
with registration error not exceeding ±2% and ±5% when tested with water at 30 0C at normal test
flow limit and the minimum test flow rate respectively. The following are probable assumed flow
dimensions:
Meter Size (mm) Maximum Continuous Minimum Maximum Permissible Head Loss
Designed Flow Flow
150 mm 150 m3/hr 15 m3/hr Not to exceed 1 metre at 200 m3hr
250 mm 500 m3/hr 25 m3/hr Not to exceed 1.75 metres at 500
m3/hr
300 mm 750 m3/hr 40 m3/hr Not to exceed 2.0 metres at 750
m3/hr
Painting
All external and internal ferrous metal surfaces, except machined and bearing surfaces, shall be
painted for corrosion resistance. Other parts which are not recommended for painting should have
corrosion resistant coating suitable for tropical humid weather. A quantity of cleaning solvent,
sufficient to remove the factory applied coating shall be furnished. They should be properly
packaged and labeled before shipment.
The inspection and tests shall be carried out by the Supplier at no extra cost to the Purchaser
However, inspection agent’s charges for inspection and testing shall be borne by the Purchaser.
The Supplier shall submit satisfactory test certificate for the water meters in addition to the above
tests prior to dispatching the Goods.
Stored Goods shall be properly watched at all times. Any article found to be faulty shall not be
accepted.
9.7.1 Standards
All tests shall be performed in accordance with the latest Hydraulic Institute Standards.
ii) Each pump performance shall be documented by obtaining concurrent readings showing
motor voltage, current, pump head and discharge. Readings shall be documented for at
least four pumping conditions to ascertain the actual pumping curve.
iii) One test shall be at shut off head. Each power load to the motor shall be checked for
proper current balance.
Each assembled pump and drive listed herein shall be tested after installation to
determine the following characteristics at the maximum speed at which the pumps are to
be operated.
i). Head-Capacity Curve
ii) Brake Horsepower Curve
iii) Efficiency Curve
2. The adequacy of all pipe hangers and supports and valve supports shall comply with the
specified requirements.
3. The Contractor shall rectify all detects found and all associated costs shall be borne solely
by the Contractor.
9.7.4 Requirement
1. In the event that the goods do not meet the specified requirements, the goods or
component part of the goods, shall be replaced or modified by the manufacturer to meet the
requirements of the Specifications and shall be retested in accordance with the provisions of
the Specifications.
2. In the event of retesting, all costs of the retesting including costs for additional witnessing
shall be borne by the Contractor.
Pumping equipment installation and all work in connection therewith shall be valued by the
measurement of only such items as are included in the bill of quantities. The cost of
equipment’s not itemized in the bill of quantities shall be deemed to be included elsewhere in
the Contract rates to cover the all Contractor's obligations under the Contract.
Beddings shall not be carried out until steel works has been finally leveled and connected, the
stanchions meanwhile being supported on steel packing.
Immediately before grouting, the space underneath the steel should be thoroughly cleaned and
freed from water. Bedding should be done using cement grouts, mortar or fine concrete, depending
on the space to be filled.
10.4 Welding
Before fabrication, all steel shall be thoroughly wire brushed, cleaned of all scale, rust, grease and
thoroughly straightened by approved methods that will not injure the materials being worked on.
Welding shall be continuous along the entire line of contact except where tack or intermittent
welding is permitted. Where exposed, welds shall be cleaned of flux and ground smooth. Welding
shall be performed by experienced tradesmen, and made with electrodes conforming to BS 639.
All structural welds shall be continuous and shall be properly sized to develop the full strength of the
smaller of the two members being joined. The Engineer shall have to write the limit of the thickness
of each weld head pass.
10.10 Aluminium
All aluminum plate, pipe and structural shapes shall conform to ASTM B-209, B-221 and/or B-308
for 6061 -T6 alloy or equivalent, unless otherwise noted. All aluminum bearing on or embedded in
concrete shall have one coat of zinc chromatic primer.
10.11 Galvanizing
Iron and steel galvanizing shall be done in accordance with ASTM A-123 or equivalent with an
average coating weight of 600 gm per sq.m and not less than 560 gm per sq.m. Repair to
galvanized coating damaged during erection or fabrication shall be done using specified toughing
material.
10.13 Measurement
Metalwork and all work in connection therewith shall be valued by the measurement of only such
items as are included in the Bill of Quantities. The cost of metal work not itemized in Bill of
Quantities shall be deemed to be included in the contract rates to cover all the Contractor’s
obligations under the contract.
11.2 Materials
11.2.1 General
All paints to be used for the painting system shall be obtained from one manufacturer. Paint shall be
supplied in sealed containers of not more than 5 liters capacity and these shall be used in strict
order of delivery. The paint shall be adequate in all respects for the intended purpose and shall be
obtained from the manufacturer ready for the use specified.
Paint shall he stored in sealed containers in a lock-up store where it is not exposed to extreme
temperature. Any special storage conditions recommended by the manufacturer shall be observed.
Paint not used within the shelf life period specified on the containers, or within 18 months of the date
of manufacture, shall be replaced.
At the end of a working period, paint with a limited pot life or any two pack primers etc. shall be
discarded. Other types of paint shall be returned to the store and kept in sealed containers.
Red lead pigment in the dry form or as a paste in oil shall conform to ASTM D 83. The 97% grade
shall he specified for dry pigment.
In mixing for paint, raw linseed oil (ASTM D 234) may be replaced with boiled linseed oil (ASTM D
260) to the extent of 50% of the total oil content.
Flue paint, preferably, shall be factory mixed. As an alternative the pigment shall he furnished in the
form of red lead paste.
11.2.3 Undercoat
The undercoat shall be red lead paint as specified above, tinted light brown with lamp black in an
amount not exceeding 1/32 kilogram per litre of linseed oil. I)ry film thickness shah be 50 micron.
(A) General
Surfaces of metal to be painted shall he thoroughly cleaned, removing rust, loose mill scale, dirt, oil
or grease and other foreign substances. Unless cleaning is to he done by sand blasting. all weld
areas, before cleaning is begun, shall he neutralized with a proper chemical, after which they shall
he thoroughly rinsed with water.
The removal of rust, scale and dirt shall be done by the use of metal brushes, scrapers, chisels, or
hammers or other effective means. Oil and grease shall be removed by this use of gasoline or
benzene. Bristle or wood fiber brushes shall be used for removing loose dirt.
Steelwork shall be mechanically cleaned using power driven tools such as grinding discs, chipping
hammers and needle guns, followed by steel wire brushing, washing and dusting to remove all
loosened material. Excessive burnishing of the metal through prolonged application of rotary wire
brushes shall be avoided. Any visible peaks and ridges produced by the use of mechanical cleaning
tools shall be removed.
(D) Sandblasting
The sandblasting shall remove all loose mill scale and other substances down to the bare metal.
Special attention shall he given to cleaning of corners & angles. Before painting, sand adhering to
the steel in corners and elsewhere shall be removed. Cleaning shall he approved by the Engineer
prior to any painting, which shall be done within 2 hours and before rust forms.
1) Oil, grease and similar adherent matter shall he removed by washing with a suitable solvent.
Excess solvent shall be wiped from the work before proceeding with subsequent operations.
2) The surface to be painted shall be cleaned and dehydrated (free of occluded moisture) by the
passage of oxyacetylene flames which shall have an oxygen to acetylene ratio of at least one.
The inner cones of these flames shall have a ratio of length to port diameter of at least 8 and
shall be not more than 3.7 mm centre to centre. The oxyacetylene flames shall he traversed
over the surfaces of the steel in such manner and at such speed that the surfaces are
dehydrated, and dirt, rust, loose scale in the form of blisters or scabs, and similar foreign matter
are freed by the rapid intense heating by the flames. The flames shall not be traversed so slowly
that loose scale or other foreign matter is fused to the surface of the steel. The number
arrangement and manipulation of the flames shall be such that all parts of surfaces to be
painted are adequately cleaned and dehydrated.
3) Promptly after the application of the flames, the surfaces of the steel shall be wire brushed,
hand scraped wherever necessary, and then swept and dusted to remove all free materials and
foreign particles. Compressed air shall not he used for this operation.
4) Paint shall be applied within 2 hours after the steel has been cleaned and while the temperature
of the steel is still above that of the surrounding atmosphere, so that there will be no re-
condensation of moisture on the cleaned surfaces.
The color shall be as specified or determined by the Engineer. The coats shall be sufficiently
different in color to permit detection of incomplete application.
Material painted under cover in damp weather shall remain under cover until dry or winter weather
conditions permit its exposure in the open. Painting shall not be done when the metal is hot enough
to cause the paint to blister and produce a porous paint film.
11.3.5 Application
(A) General
Painting shall be done in a neat and workmanlike manner. Paint may be applied with hand brushes
or by spraying except that aluminum paint preferably shah be applied by spraying. By either
method, the coating of paint applied shall be smoothly and uniformly spread so that no excess paint
collects at any Point. If work done by spraying is not satisfactory to hue Engineer, hand brushing
shall be required.
(B) Brushing
When brushes are used, the paint shall be so manipulated under the brush as to produce a smooth,
uniform, even coating in close contact with flue metal or with previously applied paint, and shall be
worked into all corners and crevices.
(C) Spraying
Power spraying equipment shall apply the paint in a fine, even spray without the addition of any
thinner. Paint, when applied with spray equipment, shall be immediately followed by brushing when
necessary to secure uniform coverage and to eliminate wrinkling, blistering and airholes.
11.4 Measurement
The quantity of work done under this section shall be measured in square meters to include
all painting required on each structure or structural unit.
Manufacturing and (or) Assembling and Supply of Transformers, Lightning Arresters, Drop-
out fuses, LT/HT Panels, PFI Plants, Motor Control Panels and Accessories
Supply and installation of all Equipment required for the Sub-Station and Motor Control
Centre
Supply and Installation of Cables between the equipment of sub-station and pump motors in
underground /Cable Trench/Surface through Conduits
Installation of Earthings
Arrangement for inspection of the Electrical Installations and taking approval of Licensee
Board
Obtaining sanction of required load (Demand Note) from Power Supply Authority (PDB/REB)
with the assistance of local DPHE and Pourashava.
Deposition of Security money in the Bank
Arrangement of power supply to the Pumping Plant
Testing and Commissioning of the sub-station as well as pumping Plant
Supply of spares and Maintenance of the sub-station for at least one year.
12.2.1 General
All machinery, accessories and other equipment to be used in the electrical installation work shall be
new and of
The highest quality to the best modern practices
sound workmanship, robust in design and of a grade and quality suitable for the purpose
and he climatic conditions at the location.
approved types, supplied by approved manufacturers
All electrical materials and equipment shall comply in all respects (design, properties, qualities,
testing, etc.) as a minimum with the latest International Electro-technical Commission
recommendations and/or the latest British Standards. Should there be and difference between the
IEC/BS and this Specification, then the most stringent requirements shall apply.
Component parts of similar use and rating shall be interchangeable with each other.
All manufactured items shall be the product of manufacturers regularly engaged in producing works
of the types specified and be constructed and finished by the same manufacturer.
All manufactured items shall be free from imperfections and defects which may impair their
durability and serviceability or affect their appearance.
Before installation and purchasing of any machinery, accessories and equipment, catalogues
related to type and model no and warranty certificate (s) from the manufacturer (s) shall be
presented to the Engineer. As per decision of the Engineer, the Contractor shall take necessary
steps for the execution of the testing and inspection of the above mentioned materials, prior to
purchase and installation.
To maintain quality of electrical equipment & related accessories the contractor shall follow the
instructions below :
A. Manufacturer’s Qualifications
The Contractor shall provide, for the approval of the Engineer, the equipment/material, country of
origin, together with clear evidence to demonstrate that it has been successfully manufactured at
that facility and has been installed and operating successfully, in a number of similar projects in type
B. Factory Tests
Factory tests are required for all electrical equipment and assemblies to be supplied by the
Contractor. The Contractor shall perform factory tests in accordance with the relevant British
Standards or other such standards approved by the Engineer.
Test at the manufacturer’s works shall be accompanied with test certificates showing all the relevant
information and details relating to the test. Three (3) copies of test certificates signed by the
manufacturer’s representative shall be submitted to the Engineer.
C. Factory Inspection
The Engineer or his representative may inspect fabricated electrical equipment at the factory. The
Contractor shall notify the Engineer in sufficient time so that factory inspection can be arranged.
Factory inspection may be made after the manufactures has performed satisfactory checks,
adjustments, tests, and operations. Approval of equipment at the factory only allows the
manufacturer to ship the equipment to the site, and does not constitute a final acceptance.
Protection against impact, abrasion discoloration and other damage are to be ensured. Damages
are to be repaired as directed and approved by the manufacturer.
E. Factory Painting
On electrical equipment, drives, starters, control panels and similar self-contained or enclosed
components, a factory primer and high quality oil-resistant backed industrial enamel finish are to be
applied. Surfaces that are inaccessible after assembly are to be painted otherwise protected by a
method which provide protection for the life of the equipment.
12.2.5 Workmanship
The entire work provided in this specification shall be constructed and finished in every respect in a
workmanlike and substantial manner. The Contractor shall provide the system in accordance with the
best trade practice and to the satisfaction of the Engineer.
Keep others fully informed as to the shape, size and position of all openings required for apparatus
and give full information sufficiently in advance of the work so that all openings may be built in
advance. Provide and install all sleeves, supports, etc., hereinafter specified or required.
Obtain detailed information from the manufacturers of apparatus as to the proper method of installing
and connecting same. Obtain all information from others which may be necessary to facilitate work
and the completion of the whole project.
Provide the services of an experienced foreman, who shall be continuously in charge of the erection of
the electrical work, together with all necessary skilled workmen, helpers and labors required to
properly unload, transfer, erect and connect up, adjust, start, operate and test the system.
Before installing any work, verify that it does not interfere with clearance required for other work.
Notice of adverse conditions shall be forwarded in writing to the Engineer before any work in question
is installed. If notification is not made, and work installed causes interference with the contemplated
design, make such changes in his work as directed by the Engineer to permit the installation of all
work of the project, at no additional cost to the Employer.
Should part of the equipment be subcontracted to another manufacturer, the Contractor shall ensure
that the Engineer is authorized to inspect, examine and test the equipment in the premises of the Sub-
Contractor.
These inspection, examinations and tests shall not relieve the Contractor in any case from this
contractual responsibility and commitments.
The Contractor shall notify the Engineer in writing at least 15 days beforehand of the date and place at
which any equipment shall be available for tests to be made according to the provisions of the
Contract. Should the Engineer not have appeared at the place indicated within ten days following the
date indicated by the Contractor, the latter shall proceed with the tests and it shall be deemed that
they had been witnessed by the Engineer. The Contractor shall send the Engineer duly certified
copies of the results of the tests.
The Engineer shall notify the Contractor of his intentions to attend the test 24 hours beforehand.
Should the Contract provide for tests to be made in the premises of the Contractor or any Sub-
Contractors or suppliers. The Contractor shall afford any assistance, labour materials, electricity, fuel
supplies, equipment and instrument required and which can be reasonably requested for these tests.
Testing
On completion of the entire electrical installation work or any separate or distinct part thereof, notify
the Engineer, in writing, that the complete part of the electrical work is ready for inspection. Before
doing so, perform initial trial tests. Test, correct, adjust, balance, regulate, etc., the section concerned
PW3-Sec-7 (Tech. Spec.) 104
as necessary until required conditions are obtained.
The inspection of the Contractors work shall be carried out in the presence of the Engineer and in
accordance with the requirements of Section 'E' of the IEE 'Regulations for Electrical Equipment of
Buildings' and shall comprise of but not limited to :
a. Verification of polarity
b. Effectiveness of earthing
c. Insulation resistance test
d. Test of ring circuit continuity
e. Phase rotation
f. Operation tests of relays, interlocks and any other protective and control device to ensure
correct functioning.
The results and readings obtained shall be equal or better than the requirements of the IEE and the
supply authority regulations and these shall be recorded on forms similar to the ones described in the
IEE Regulations.
Supply all instruments and tools required for carrying out the tests.
Follow-up and make all necessary arrangements with the supply authority for the purpose of providing
permanent electricity supply. Also provide all facilities and attendance to the supply authority for any
other tests carried out before energising the installation.
12.5.4 Tappings
Adjustable tappings shall be provided on the primary windings for variation from +7.5% to
-7.5% in 2.5% steps.
Tapping control shall be by means of a manual, externally operated, off-circuit tapping
switch complete with tap mechanical tap position indicator.
Locking facilities shall be provided for the switch such that the lock can be inserted only
when the switch is in a definite tap position.
The tap changing selector shall be located below the oil level inside the tank and the
selector operating rod shall be external outside the tank.
12.5.5 Construction
The core shall be constructed from cold rolled steel laminations manufactured to BS 6404.
The aminations shall be insulated from each other by means of a suitable temperature
resistant oil proof coating.
The windings design and construction shall provide adequately designed and located
coolant flow ducts so that possible hot spots are eliminated. Windings shall be braced to
withstand dynamic stress due to short circuit conditions. Full details shall be provided of
arrangements for taking up or eliminating coil shrinkage during service.
The core and winding shall be designed so that the iron loss is at a minimum but the ratio of
copper loss to iron loss shall be in accordance with an economic design and the
manufacturer shall state the ratio used.
The arrangement of internal connections shall be such that the transformer core and
windings may be lifted bodily from the tank without disturbing the cable boxes or
insulators.
The transformer tanks shall be constructed from high grade steel with electrically welded
seams. The structure of the tank shall enable it to be handled whilst filled with oil and shall
be pressure tested to 70 kN/m2.
Tank shall be mounted on a hot dip GI Angle Frame fixed to the Standard SPC Pole.
The tank shall incorporate lifting eyes suitable for the mass of the transformer and oil.
The tanks shall be provided with external cooling tubes or fins to provide natural cooling
under the climatic conditions.
12.5.7 Fittings
In addition to the standard fittings as per BS 171, the transformer shall be fitted with the following:
12.5.8 Earthing
The transformers shall be connected to the earth bars installed inside the substation.
All metallic enclosures, tanks, fittings and accessories must be bonded together and
connected to the earth bar.
The transformer secondary winding star point/neutral shall be connected to earth.
12.5.10 Testing
A. Type and routine tests shall be carried out in accordance with BS 171/IEC 76.
D. Type Tests
1. Temperature rise test on the transformer.
2. Impulse withstand test on the transformer shall be applied on the HV winding leg only and
shall be in accordance with BS 923 and BS 171.
E. Short circuit test need not be performed if already performed on a transformer of the same
rating and similar construction. Type test result shall be made available.
12.6.2 Submittals
Full specifications of the enclosures and the components of the switchgear, switchboards, PFI
Plants and motor control centres, with relevant sheets of manufacturer’s catalogues.
The Main Low Tension Switchboards shall be of Indoor construction, purpose made,
floor standing, dead front, totally enclosed, cellular cubicle type, dust protected, vermin proof
PW3-Sec-7 (Tech. Spec.) 108
and of clean and modern appearance containing the main components shown on the
Drawings and/or specified.
The switchboards shall be fabricated, assembled, wired, checked, tested and
coordinated at the factory by one manufacturer using the same make for all internal
switchgear components and shall be constructed in accordance with BS 5486; Part 1 or IEC
439.
The Normal Components, Fittings and Accessories required for safe and proper
operation of switchgear shall be provided, whether specifically mentioned herein or not.
1) The panel board shall be fabricated from 2mm thick (min) sheet steel pressed or rolled to
shape and neatly finished and free from any joints or sharp edges. It shall be metal clad,
totally enclosed, dust and vermin-proof and self-supporting suitable for floor mounting. Size,
rating arrangements shall be as indicated on the Drawings.
2) The switchboard shall consist of standard cubicles assembled together on continuous base
channels to form a rigid in line flush fronted free standing continuous switchboard assembly.
Frames are constructed from 2.0mm thick (minimum) folded sheet steel strengthened
wherever necessary. The cubicle shall be sufficiently rigid to withstand all operating forces
without deformation or damage.
3) The switchboards shall be totally enclosed, all hinged doors, covers shall be gasketed to
provide protection against dust.
4) Cabinet shall have adequate means of lifting and shall be capable of being rolled or moved
into the installation position and bolted directly to the floor.
5) The switchboards shall be provided with suitable cable glands to suit the type, size and
number of cables as indicated on the Drawings. The cable glands or bracket where required
shall be adequately mounted inside the switchboard. The switchboards shall be provided
with the proper cable fixing clamps and terminal lugs for incoming and outgoing cables as
well as earth bonding connections.
6) After fabrication, steel work shall be cleaned, zinc sprayed and stove enamelled with one
prime coat, two under-coats and one finishing coat, the surface being rubbed down after
each coat.
7) Finished color: light grey or as approved by the Engineer.
8) The enclosure shall be constructed with a degree of protection at least equal to IP 54.
C. Labels.
1. All the components in the switchboards shall be identified by means of white labels of an
approved design engraved with 5mm black lettering adequately describing the function of
the unit to which it is attached and shall be secured by screws to the outside of each item.
Special outlets and equipment shall be fitted with labels in a similar manner. Labels secured
by adhesive are not acceptable.
2 All labels shall be engraved in both Bengali and English and shall be approved by the
Engineer.
D. Switchboard Wiring.
1 Switchboards shall be furnished completely wired including all cleats and terminal blocks.
2 Control and instrument wiring shall be made with a standard switchboard colour coded cable
with fire resistant braid. No cable sizes smaller than 2.5 sq.mm shall be used.
3 The wiring on instrument panels shall have flexible connections to the terminal blocks.
4 The end of every wire shall be numbered with the number as stated in the control circuit
wiring diagram of the manufacturer, also number the terminal blocks.
5 A sufficient number of terminal connections including 15% spare terminals shall be provided
for all control and instrument wiring.
6 Wiring within the switchboard shall be distinctly colored throughout and marked with ferrules
at each end for identification. The letters and numbers used shall correspond with the switch
board wiring diagram.
PW3-Sec-7 (Tech. Spec.) 109
The wiring color code shall be as follows:
E. Safety Measures.
All terminals, connectors, relays and other components which may remain or become energized
when front access doors are open shall be adequately screened. It shall not be possible to obtain
access to adjacent cubicles when any door is opened. Circuit breakers shall be provided with
suitable means to prevent unauthorised and accidental operations. Interlocks to prevent dangerous
operations shall be provided wherever necessary. High voltage parts shall be protected to prevent
accidental human contact. Warning signs of durable type fixed on visible place shall be provided on
high voltage parts. Earthing of metal parts shall be provided.
F Panel Lighting
Each cubicle, where a door is required to be opened for access, shall be provided with
fluorescent lighting which shall be automatically switched on when the panel door is opened.
G Annunciation
Audible and visual annunciation for each panel shall be provided. The audible annunciation for
minor fault and major fault shall be differentiated by separate tones.
Each panel shall be provided with lamp testing switch and re-setting facility.
I. Lamp Indication.
A pilot lamp for each panel shall be provided. The lamp shall light up when the input cable is live
irrespective of the position of the circuit breaker in the panel.
Indicator lamps shall be not less than 20 mm diameter and shall be of the projecting type so that
they can be seen from the front and the side of the switch board. They shall be visible under bright
sun light conditions. The lamps shall be under –run to give long life or higher voltage lamps shall be
used. Alternatively the lamps shall be transformer operated.
1 The busbars shall be electro-tinned hard drawn, high conductivity 99.9 percent purity,
suitably sleeved for phase identification to BS 158.
2 All busbars shall extend through the length of the board with same cross section throughout
unless indicated otherwise.
3 A Copper Earth Busbar sized at least 50 percent of the phase busbars shall be provided
along the full length of the board.
4 Busbars shall be adequately supported by porcelain or moulded insulators spaced on
suitable centres so that the complete assembly can withstand the maximum mechanical
stresses to which it may be subjected to under fault conditions.
5 Busbars shall be housed in separate adequately ventilated compartment which shall not
contain any wiring or apparatus other than that required for connections for busbars.
6 Busbars shall be housed in separate adequately ventilated compartment which shall not
1 Shall have a combination of thermal and magnetic tripping giving an inverse time delay
protection against sustained overloads and instantaneous tripping under heavy overloads
and short circuits.
2 Breakers shall have a quick make, quick break over-centre switching mechanism that is
mechanically trip free from the handle so that contacts cannot be held closed against short
circuits and abnormal current.
3 Tripping due to overload or short circuits shall be clearly indicated by the handle assuming a
position mid-way between the manual ON and OFF position.
4 Latch surfaces shall be polished.
5 Poles shall be constructed to open, close and trip simultaneously.
6 Ampere ratings shall be clearly visible.
7 Breakers shall be completely enclosed in a moulded case to IEC No. 157 - 1A, suitable for
installation inside switchboards.
8 Non-interchangeable trip breakers shall have the trip unit sealed.
9 Breakers with earth leakage relay protection shall be provided with shunt trips.
10 Frame sizes shall be as per manufacturer’s standard size and as approved by the Engineer.
11 The magnetic trip shall be adjustable type for rating 200 Amp. and above.
These shall be suitable for the type of load they feed. They shall be fault rated so that fuse backup
protection is not required. They shall be rated in accordance with BS EN 60898. They shall include
the following minimum features:
M Fuses
The fuse shall either include a suitable fuse carrier or it shall be capable of isolation. If the fuse
carrier is included it shall be such that when it is being withdrawn normally or when it is completely
withdrawn the operator is completely protected from accidental contact with any live metal of its fuse
link fuse contacts and fixed contacts.
If the fuse is capable of isolation it shall be so interlocked with the switch that isolation is complete
before the fuse enclosure can be opened further. The switch shall be prevented from closing wshile
the fuse-cover is open.
1 The relay shall comprise a core balance transformer, tripping mechanism and reset testing
buttons.
2 The relay shall operate within 0.2 sec, when the fault current exceeds specified sensitivity as
detailed on the Drawings.
3 The relay shall be connected to the load side and the testing device shall be connected to
the supply side.
4 The relay shall withstand available short circuit. In case of using with the MCCB’s integrated
E/L Relay in MCCB can be accepted.
5 Audible and visual alarm earth leakage relay shall be provided where specified on the
PW3-Sec-7 (Tech. Spec.) 111
Drawings.
a) Similar in construction to Earth Leakage Relay except it operates an audible and visual
alarm located in the board and remotely positioned in lieu of shunt trip of the breakers.
b) Audible Alarm shall be of sufficient level and may be cancelled by suitable reset button
but visual indicator shall remain ON until fault is Cleared.
O Measuring Instruments
The Measuring Instruments shall include ammeters, voltmeters, kWh meters, selector switches and
associated accessories as indicated on the Drawings and described herein as follows:
1 Ammeter, Voltmeter and Power Factor Meter.
a) The measuring instruments shall be moving iron vane type, flush pattern with dust and
moisture proof enclosure. Anti-glare glass front, anti-parallax scales and white faces with
black numerals and marking shall be used. All instruments shall be of long scale 240
Degree with full load indicating approximately at 180°.
b) The dial size shall be 10 x 10 sq.cm.
c) Accuracy shall be one percent of full scale values.
d) Moving elements shall be provided with zero adjustments located at face of dial.
e) The Ammeter shall be capable of withstanding twice of rated current for 10 minutes and
overload sustained under fault conditions without damage or loss of accuracy.
f) Voltmeter shall have a measuring range from 0 to 500 V and shall withstand twice the
rated full scale voltage for 1.0 minute without damage.
g) Three Ammeters shall be provided to read the current of each phase, as indicated on
the Drawings/BOQ.
h) Three voltmeters shall be provided to read the voltages for B-R, R-Y and Y-B positions.
2 Current Transformers.
a) Current transformers shall be of the bar primary type, air cooled and suitably insulated.
The current transformers shall be of Class C accuracy for indication and Class CM
accuracy for metering purposes.
b) Current transformers shall be rated not less than 5 VA and shall have thermal and
mechanical rating at least equal to those of the main circuit breakers.
3 KWh Meters.
a) The kWh meters shall be suitable for operation on 415/240 Volt, 3 phase, 4 wire, 50 Hz
supply and shall conform to BS 37 Part 1 and BS 5685.
b) The meters shall be dust-proof and vermin proof, protected from corrosion due to high
humidity and compensated against the effect of temperature up to 55°C.
c) The meters shall maintain their accuracy over many years service under the project site
climatic conditions. The counter shall be of the cycle meter type with six figures, the
lowest figure being unit. Pointer type counters are not acceptable.
d) The meter cover and cases shall be of metal.
e) Meters shall not have less than 5mm diameter terminal holes and shall be operated
through three current transformers and the counter of the meter should be calibrated to
read the primary kWh.
f) All meters shall be handed over to the supply authority for calibration prior to final
installation and connection.
All incoming and outgoing cables shall be provided with cable dividing and sealing boxes or cable
glands suitable to the type of cable specified.
All Panel board or switchboards shall, unless other wise specified, be provided with bottom cable
entry.
Each cubicle shall be suitable for cable access for all incoming and out going cables. This access
shall be so arranged that cables can be installed directly to their respective terminations without
being threaded through another compartment.
i) One black fluted rubber safety mat running the length of the switch
board/panel board.
ii) Pairs rubber gloves according to rated voltage switchboard.
iii) One “treatment for electric shock” metal enamel instruction plate suitable
for screen attachment, written in English and Bengali
iv) Operating handles, tools, spares and lubricants specified elsewhere.
General
Power factor improvement equipment shall be provided in LV feeder panels.
Correction shall be automatic and be capable of correcting the power factor to within the
range 0.9 lagging to unity as required by the design.
Individual power factor capacitors shall be provided for the larger motorized drives,
as indicated on the single line diagrams.
All capacitors must be arranged so that they are connected to the LV feeder panels
in stages. These stages shall be sized to prevent system over-voltage during light loads
conditions.
Capacitors
Capacitors shall comply with BS 1650 and shall be of a dry metalised film construction,
containing no liquid and must have low losses (typically 0.5 W/kVAr).
Each capacitor shall be housed in a sealed container and be fitted with a fail-safe, pressure
sensitive disconnect device.
Each capacitor shall be equipped with suitable discharge resistors to reduce the voltage to
less than 50 V in one minute, or less, after supply disconnection.
A. The switching of capacitor units on each section of switchgear must be controlled by a single
relay.
C. Switching contactors must have a minimum duty category AC4 to BS 5424 and a minimum
current rating of 1.3 x the current consumed by the capacitor bank. (See BS 1650).
12.7.1 General
This Section is to include the supply, installation and commissioning of all wires and cable systems
in accordance with the Specifications and Drawings. Cables shall be supplied by an approved
manufacturer and where possible the same manufacturer shall be used for all cables. All cables
shall deliver with cable ends effectively sealed. When a cable is cut from a drum both cable ends
shall be immediately seated to prevent ingress of moisture.
A If cable sizes are not indicated on Drawings or in schedules, determine the correct size based
on current rating, voltage drop and short circuit current, as relevant, after taking into
consideration:
1 type of cable and wire
2 ambient conditions
3 method of installation
4 the disposition of each cable relative to other cables.
B Calculate voltage drop and current ratings based on information given in supply authority’s
regulations or IEE Regulations, whichever are more stringent.
A Each drum length of cable shall be allotted a distinct and separate reference number. This
number shall appear on the test certificates covering the respective length of cable and shall
also be clearly marked on the cable drum.
B the Contractor shall advise the Engineer upon delivery to site of each drum length, quoting the
reference number, the test certificates shall be handed to the Engineer for examination and
approval.
C All cables shall be delivered to site with the manufacturer’s seals, labels or other proof of origin
intact. These labels and seals shall not be removed until the cable is required for use and shall
be retained for inspection by the Engineer.
D The Contractor shall be responsible for the off-loading and handling of the cables on site, and
shall ensure that cables are delivered to site on drums and properly protected against
mechanical damage. Where lengths are cut from cables, the open cable ends shall be sealed.
B All conductors shall have good fatigue resistance and not subject to breaks due to nicks or cuts
when terminating.
12.7.5 Cables
A Unless otherwise specified, cables and wires of the following specified voltage ratings shall be
used as indicated.
1 8700/15000V rated cables :11000V equipment circuits
2 600/1000V rated cables :Main and sub-main distribution panels, motor
control centers, circuits serving process equipment
3 450/750V rated cables :Final sub-circuit supplies for lighting, socket outlets, etc.
4 250V rated cables :Extra low voltage wiring, communication circuits where
the maximum voltage is 50V.
5 All multicore cables shall be 600/1000V rated.
6 450/750V rated cables :Clock system cables.
B General
1 Conductors shall be high conductivity copper, to BS 6360/IEC 228 unless otherwise
indicated.
2 Copper conductors shall be stranded for 2.5 mm2 and over.
3 Signal control cables shall have solid conductors.
4 Flexible cords shall have fine stranded conductors.
5 Conductor sizes shall be metric. Conductors with cross sectional areas smaller than those
specified will not be accepted.
6 Insulation for each conductor shall be color coded or otherwise identified as required by the
Regulations. Color coding shall be maintained throughout the installation.
7 The current carrying capacity of conductors has been determined in accordance with the
specified regulations, the specified type of insulation and the expected conditions of
installation.
8 All cables shall be as far as practicable, of one manufacturer only. All cables shall comply
with the relevant IEC/BS.
C PVC insulated steel wire armoured and PVC over sheathed (PVC/SWA/PVC) cable.
1 Multicore PVC/SWA/PVC cable, 600/1000V grade, to BS 6346
F Instrumentation Cables
1 To BS 5308 part 2, 300/500 V grade.
2 All instrument cables shall include a single wire armor with overall PVC sheath and shall
include an overall screen of copper braid or aluminium foil.
3 Shielded Twisted Pair. Cables shall be color coded individually screened twisted pair,
multicore, 0.9 mm2 copper conductor, PVC insulated, galvanized steel wire armored with
overall PVC outer sheath.
4 Unshielded Twisted Pair. Cable shall be color coded twisted pair, multicore, 0.9 mm 2 copper
conductor, PVC insulated, galvanized steel wire armored with overall PVC outer sheath.
5 Coaxial Cable. Shall be suitable for local area network conforming to IEEE 802.3 10 Base
2. Thinnet coaxial trunk cable, 20 AWG (19 x 32). 50 ohm characteristic impedance,
capacitance 83 pF/m.
6 Unshielded Twisted Pair (LAN). Cable shall be suitable for all local area network and
structured cabling systems that require 100 ohm impedance, UTP cabling.
12.7.6 Sundries
A Joints
1 For conductors up to 16 mm2 barrel type connectors with pinching screws, the whole
shielded in porcelain or hard resistant materials are not permitted.
2 For conductors exceeding 16 mm2 to be made with bakelite shrouds.
B Jointing Boxes
1 For use where intermediate joints are necessary on MICC mains cable and shall be suitably
sized galvanized malleable iron adaptable box with glands and fixed base mechanical
clamping connectors of approved design. For external use the jointing box shall be
enclosed in a second galvanized box with glands.
2 For use on plastics and elastomer insulated cables of a type recommended by cable
manufacturers having an inner box with provision for making a watertight seal into inner
sheaths of cables, and an outer cast iron box with provision for making a watertight seal to
cable outer sheaths, clamping cable armour and bending the armour across the joint.
Where applicable suitable connections shall be provided to ensure electrical continuity of the
cable screen is maintained.
C Compression Glands
PW3-Sec-7 (Tech. Spec.) 116
For terminating plastic or synthetic cables to switchgear, switchboards, motor control centre and
other equipment to BS 6121 and to approval.
D Cable Terminations
1 For plastics or synthetic rubber insulated cable with suitable brass compression glands,
unless otherwise recommended by cable manufacturer. Glands for armoured or screened
cables shall have suitable clamps therefore.
2 External compression glands shall have close fitting PVC shrouds.
3 Earthing for armouring and metallic sheaths shall have suitable brass or copper clamps, and
copper strip conductor of selection not less than MEW Regulations or requirements and not
less than 2.5 sq.mm.
4 Cables forming part of a LAN or structured cable system shall be terminated to floor plates
or wall sockets compatible with the media interface connector specified for the particular
network being used.
E Cable Sockets
1 Shall be correct size for type of cable.
2 Shall be sweating type, or an approved crimping type used with an approved crimping tool.
3 Sweating sockets for conductors 70 sq.mm and over : machined cast brass.
F Fire Barriers
1 Shall be purpose made, comprising a rigid fixed frame with adjustable seals and a suitable
clamping device.
2 In fire compartment separation walls and floors thyey shall be same standard of fire
resistance as wall or floor.
G Cable covers shall be to BS 2484. Concrete covers exceeding 300mm wide shall be reinforced.
I Solder shall be an alloy of lead and tin to BS 219 grade F or H, unless otherwise recommended
by cable manufacturer.
J Cable sealing compounds shall be to BS 1858 and be approved by cable manufacturer; shall be
tropical grade and shall be an oil-resisting compound where the difference in level between
cable ends exceeds 6m.
A General
B Bending radious shall be as large as possible and not allow cable to bend to a radius less than
that specified in IEE Regulations, relevant British Standard, or manufacturer’s recommendation,
whichever is largest.
C Underground Cables
1 Lay in concrete encased pipe ducts/Under Ceramic Cable Cover.
2 Cable duct size shall be as specified in the Drawings.
3 Run cables at least 300mm clear of other services, whether the latter run parallel or
transversely to cable trench.
4 Run cables below intersecting piped services, unless the cable would be at a depth
exceeding 2m, in which case seek instructions.
E Jointing
1 Joints in wires and cables shall be avoided wherever possible. Joints in flexible cables and
cords are not permitted. Where joints are unavoidable they shall be permanently accessible
and made only in junction boxes.
2 Leave at least 150mm of free conductor at each outlet, switch point and pull box for the
making up of joints or the connecting of fixtures and devices, except where conductors are
intended to loop without joints through lamp holders, socket outlets and the like.
3 Complete joints and termination in the shortest time without interruption.
4 Do not commence jointing and terminations without approval, except where the work is in a
dry, weather-proof place.
5 Do not make joints in wet or dirty conditions.
6 Make outdoor joints under a suitable tent or shelter.
7 Fill joints with compound filling in stages to allow the material to flow. Do not allow
compound to cool to the point where re-heating is necessary.
8 Ensure sealing compounds are pouring at the correct temperature. Check compound level
and top up if necessary, after cooling.
9 Make intermediate joints on plastic and elastomer insulated cables in a joint box. Arrange
to have each joint inspected by the Engineer before closing and filling.
10 On external joints on MICC cable fill outer box with jointing compound.
11 Joint cables in straight through joints and main cables in tees and other branching joints
core to core.
F Cable Terminations
1 Take cable cores through the termination box directly to equipment terminals, without
crosses, unless impracticable and make off with sweated cast brass or hydraulically crimped
sockets.
2 Sweat cable core solid 25 mm on each side of compound level and over-tape the exposed
core insulation with two layers of PVC or other approved tape in appropriate phase colour,
PW3-Sec-7 (Tech. Spec.) 118
half-lapping the tape.
3 Plumb the cable sheath to the brass wiping gland, neatly lay back the armour wires over the
gland and fix with an amour clamp effectively bonded to earth.
4 Cut back tape of tape armoured cables neatly below the wiped gland, thoroughly clean,
secure with a suitable armour clamp and bond to the body of the terminating box with two
soft copper tapes at least 70 mm2 aggregate cross section.
5 Equipment to which cables are connected shall have blank, undrilled gland plates. Drill
holes necessary for fitting glands.
Cable trays shall be made of perforated hot dipped galvanised steel of thickness not less than 1.6
mm with upturned flanges on both sides. The tray width shall be as appropriate to accommodate all
the cables in the same run. Cable supports shall be steel brackets fixed to ceiling, wall or slab in the
manner as approved by the Engineer. Cable support spacing shall be 1.0m.
Subject to determination by tests at site, the earth electrodes shall be provided as mentioned in
BOQ each comprising a conductor system by vertical GI pipe of 38 mm dia 18 m long (or as per
field requirement) with 6.5mm dia hole at every 150mm interval. To make main earthing connection
between main earthing electrode and earth terminal, a 10mm x125mm x150mm copper junction
plate with ‘0’ or 1/0 SWG wire by jointing with proper soldering the wire to the bus and passing the
wire through the 38mm dia GI pipe and copper rod making a 10mm hole centrally to the copper rod
by bending, binding and soldering the assemblies should be done. The two electrodes shall be
physically arranged and spaced to be electrically independent and leads from each shall be brought
to a common concrete disconnection chamber set in the ground, or to a main earth busbar when
specified. Two bolted copper links shall be provided in the disconnection chamber to enable each
electrode to be disconnected from the system for test purposes. Each electrode shall be capable of
providing an effective earth of resistance not greater than value specified, with the second
disconnected.
All excavation of trenches for the installation of the earth electrodes and the disconnection chamber
will be carried out by the Contractor.
The Contractor shall be responsible for the supervision of the back-filling of the trenches and the
setting and alignment of the disconnection and inspection chambers. After the earth installation has
been completed the contractor shall demonstrate to the Engineer that the resistance of the
electrodes to earth and continuity of the earth network are within the limits specified. Any additional
earth electrodes and test instruments required for the tests shall be provided by the Contractor.
Marker posts and plates shall be provided to mark the position of the electrodes and buried
connections. The markers shall be similar to those provided for cable routes
An earth continuity conductor shall be provided between all electrical & mechanical equipment,
exposed steelworks and the like as required to meet the requirement of BS Code of practice CP
1013 – Earthing. This can be as follows:
2. Where the distributor is an armoured cable the metal sheath and/or armouring of the cable,
it shall be securely bonded at each end to the metal work of the apparatus or to an earth
bar. Particular care shall be taken to ensure continuity across items of apparatus situated
with a cable run and should the design of such item of apparatus not provide adequate and
lasting continuity through its structural body, then additional earthing clips and conductors
shall be provided to independently bond the cable sheaths together. Similarly additional
earthing clips shall be provided to bond the cable sheaths/armour to any piece of apparatus
PW3-Sec-7 (Tech. Spec.) 119
fitted with a special earth Terminal. Any additional earthing clips shall be fitted within the
apparatus wherever possible.
3. Where the distribution system is PVC single cable in conduit, a separate conductor shall be
installed. Where under special circumstances rigid of flexible conductor is corporated into
the Contract works, an external earth conductor shall be securely bonded to the terminating
or intermediate
5. Where the distribution system is PVCs sections shall be made using an approved earth link.
Lightning Protection
Lightning air terminals and down conductors for lightning air terminals shall be provided and shall be
min of 15 mm diameter tinned copper (air termination rod) 0.8 metre long with top spike. Roof
conductors and down conductors shall be of PVC sheath 3 x 20 mm copper tape or copper
conductor size 50 mm2 PVC color to be approved by the Engineer. However copper tape may be
used.
Air termination rods shall be securely anchored and welded. Down conductors shall be run along
the outer surface of the wall or column of the building. Down conductors shall be as short as
possible protected and directly connected to earth pit. Anchoring bolts shall be used to hold roof
conductors and down conductors in firm position. Lightning conductor connectors shall be provided
for conductor splice connections and conductor terminal connections. The connectors shall be
heavy duty, cast metal and shall have hex-head screws in the bodies and holes in the tongues for
bolts. Handrail and structures in the vicinity of the lightning protection system, if any, shall be
bonded to the system by 50 mm2 PVC sheath copper.
Suitable concrete earth pit and cover supplied by the same lightning protection system manufacture
shall be provided.
Testing
Testing earth electrode resistance by earth resistance tester.
The resistance of the earth electrode shall not exceed 2.0 ohm.
Install additional earth electrodes if these figures are not met.
The general layout for all lighting fittings, general purpose power outlets, ceiling fans, exhaust fans
etc. are shown on the drawings. The positions are given to indicate approximate location only. The
exact positions for ceiling fittings shall comply with the ceiling grid liners and panels. Other positions
shall be verified with the Engineer on site.
Light Fittings
The types of light fittings for the work are shown on the drawings. The contractor shall be
responsible for the supply and installation of the all the various types of lighting fittings. Lighting
fittings shall be complete with starters, chokes, sockets, power factor correcting capacitors tubes,
lamps, shades, reflectors, etc.. The Contractor shall be also be responsible for the replacement of
all the consumable components of the fittings within the warranty period.
Each surface mounted lighting fitting shall terminate at a standard junction box having entries to
conduit and shall include connectors of adequate capacity and size for the connection of the number
of wires at that point.
Each fitting mounted on suspended ceiling shall have the standard mounting brackets or clips for
the type of ceiling in question. The fittings shall include the necessary connectors and heat resistant
cable for connection between the fittings and the terminal box. All suspended fittings shall be
PW3-Sec-7 (Tech. Spec.) 120
suitable for servicing and maintenance from the underside of the fittings.
Fittings installed directly to the underside of the non-fireproof ceiling shall be provided with a 12 mm
gap between the fittings and the ceiling for ventilation.
All light fittings shall be provided with earthing terminal which shall be connected to the earth
continuity lead of the final sub-circuit. Fittings for external use shall be weatherproof and insect
proof.
Switches
Sub-circuit switches unless otherwise stated shall be single pole quick make and slow break type
with solid silver alloy contacts and totally enclosed switch action for flush mounting as required and
shall be suitable for indoor and outdoor use. The switches shall be housed in standard galvanized
steel boxes complete with conduit knockouts. The switches may be single or multi-gang as required.
Switches in mechanical plant rooms shall be metal clad type and suitable for flush or surface
mounting as required. Switches for External use shall be Waterproof
Switches shall be rated at 5A depending on the connected load on the final sub-circuit. For inductive
loads switch rating shall be twice the steady current of loads.
Switch based outlet sockets shall be to BS 2814 single pole 13A three pins switched shuttered
outlets and shall be flush mounted type. Switches shall be quick make slow break type with solid
silver alloy contacts having totally enclosed switch action. Outlet sockets shall be flush mounted in
galvanised steels boxes to BS 1299 and 1363 with conduit knockouts.
Each 15A outlet sockets shall be mounted at 300mm above finished floor level or 1.5 m high for use
above a counter or work bench. Where they are above a work bench or counter, the height may be
adjusted by 100 mm.
Socket Outlets 5A
Switch based outlet sockets shall be to BS 2814 single pole 5A two pins switched shuttered outlets
and shall be flush mounted type. Switches shall be quick make slow break type with solid silver alloy
contacts totally enclosed switch action.
Plugs
Each 15A outlet sockets shall be complete with an ivory finish moulded plug to BS 1363 complete
with colour coded fuse to BS 1362. Plugs shall be supplied complete with fuse and handed to the
Engineer on the issue of the practical completion certificate of the installation.
Lamps
Lamps shall be furnished and installed in all lighting fixtures covered under the Contract.
Lamps used for temporary lighting services shall not be used in the final lamping of fixture
units.
Lamps for permanent installation shall not be placed in the fixtures until so directed by the
Engineer, and this shall be directly before the building areas are handed over.
Installation of Material
All wiring, conduits, conduit boxes, drawing-in boxes, junction boxes, saddles, brackets etc. required
for the completion of the sub-circuit installation and wiring shall be included in this work. Generally,
PVC insulated copper conductors shall be used for the wiring of lighting and general purpose outlets
and in concealed conduits.
12.10 Measurement
General
This work shall consist of the application of cement plaster to masonry and all other surfaces shown
on the Drawings or ordered by the Engineer.
Materials
Cement mortar for plastering shall conform to the general requirements given in Clause 6.3. Sand,
having a FM of at least 1.5, shall be screened and washed prior to use to remove all deleterious
material.
Construction Methods
The surfaces to be plastered shall be cleaned of all dust and mud by brushing and scraping. All
loose flakes of brick, mortar, or stone shall be removed with a trowel, or a hammer and chisel. Bricks
to be plastered shall be thoroughly wetted and maintained wet for at least 24 hours before any
plaster is placed on them.
The average thickness of the final layer of plaster shall be not less than the specified thickness by
more than 3 mm. In local depressions were the masonry surface requires more than 20 mm of
plaster, an initial leveling layer of plaster shall be applied and allowed to set for 24 hours prior to
applying the final surface. The leveling layer shall be left rough and grooved by trowel cuts to
ensure a good bond with the final layer.
The mortar for the final layer of plaster shall be applied in a fairly wet condition as a rough layer of
approximately the required thickness. The evenness of the layer shall be continuously checked
using a wooden straight edge. When the plaster has achieved its initial set and feels firm under the
finger tips, the surface shall be smoothed using a wooden float. Where required by the Engineer,
the plaster surface shall be finished using a steel float or trowel and a light application of water as
required to seal the surface. The masonry surfaces shall then be thoroughly wetted, and kept wet
for at least seven days. During this period it shall be suitably protected from all damages.
Mortar stricken off the plastered surface shall not be reused. Such work using reused plaster shall
be rejected and redone to the satisfaction of the Engineer at the Contractor's expense.
All plastered surfaces shall be absolutely plane and free of joint patches or laps. Corners and edges
shall be finished as shown on the Drawings or as otherwise directed by the Engineer. The plaster
shall be cured for a minimum of 7 days.
A coat of neat cement finish approximately 1.5 mm thick shall be applied where shown on the
Drawings or otherwise directed. The cement shall be applied by hand and brushed while the plaster
is still fresh. It shall be finished smooth with steel trowels and brought to the desired polish. Marks of
any kind shall be removed to the satisfaction of the Engineer.
Any cracks which appear on the surface as well as all portions which sound hollow when tapped,
are found to be soft, or are otherwise defective shall be cut out in a rectangular shape and redone
as directed by the Engineer.
Surface to receive white wash or colour wash shall be thoroughly cleaned with clean water and
freed from all foreign matters. Defects shall be repaired for a smooth, finished surface. White wash
or colour wash shall be applied to surfaces in two coats over a priming coat. It shall be applied
vertically and horizontally in alternate applications. The final coat shall be applied vertically. Each
coat shall be perfectly dry before the succeeding coat is applied over it. In case of coloured wash,
the priming coat shall be white. The final coat shall be perfectly smooth and free from any mark of
the brush.
Care shall be taken to protect hardware, doors, windows, floor etc. against spreading of paints. After
white washing all unwanted paint marks and drips shall be removed thoroughly at contractor’s
expenses.
Painting of wood works window, frames and grills, can be done when it is absolutely dry. Before
applying paint the wood surface must be thoroughly cleaned and all projections are removed. The
wood works should be brought to smooth by applying sand paper of different grades. Synthetic
enamel paints shall be used. the paint must be approved by the Engineer before application.
Varnishing to be applied is either oil varnish or spirit varnish as directed by the Engineer.
The wood works include the cost of fittings in position after sawing, dressing, planning, working,
jointing etc. complete with necessary shoe plates, bolts, screws, spikes straps wall ties, clamps,
tarring of hidden portion in contact with masonry etc. Door and window frames shall be properly
framed and morticed together.
b)Door Shutters
The type of door shutter shall be stated in the schedule of items. Wood for door shall be of best
quality well seasoned shilkorai, gamari or similar solid wood. Finished thickness of the door leaf
shall be 37mm.
3mm thick glass panes should be fitted to glazed windows. The glass should not touch the wood
work of the frame. Glass shall be secured by nails with wooden frame and finally putty should be
applied making sloping from the inner side towards the outer edge.
Pressure pipes should not be completely encased by concrete. Where pipes must be completely
encased, they should be totally wrapped in a 6 mm thick compressible wrapping.
The thrust faces of all blocks shall be cast directly against sound faces of excavations and the
shape and size of the blocks shall be determined by the Engineer having regard to the nature of the
ground and the load or thrust to be imposed upon it.
For pressure testing to be carried out, minimum 7 (seven) days has to elapse since the last concrete
thrust block or support was cast.
The road restoration work in single layer brick flat soling and/or herringbone bond bricks, shall be
completed as per design and drawings and as directed by the Engineer. If any damage or
settlement occurs in the restored portion before and during the maintenance period, the Contractor
shall be liable to repair immediately at his own cost.
First class bricks shall be laid in a single layer on edge with the shortest and longest sides horizontal
in a herringbone pattern true to the lines, grades, levels dimensions and cross sections shown on
the Drawings and as required by the Engineer to produce a smooth running surface for vehicular
travel. Workmanship shall be of paramount importance. All bricks shall be laid so that they are
tightly interlocked and the tops of adjacent bricks should be flush with each other. The edge of the
layer shall be made with cut bricks to produce a line which is compatible with brick edging. The
joints shall be thoroughly filled with local sand brushed in and completed layer shall be sprinkled
liberally with water.
Any deviation of more than 5 mm between adjacent bricks, or any deviation throughout the
alignment which is in excess of 15 mm above or 10 mm below the specified grades shall be
removed and re-laid at the Contractor’s own cost. Any deviation in excess of 12 mm from a straight
edge 3 meters long applied to the surface parallel to the centre-line or a template laid transversely
shall be corrected by removal, reshaping and relaying at the Contractor’s own cost.
First class brick-on-end edging shall be constructed with bricks laid with their longest side vertical
and shortest side perpendicular to the road including necessary excavation, filling and ramming to
the satisfaction of the Engineer. The completed work shall be true to the lines, levels and grades as
indicated on the Drawings. Interstices between brick edging and adjacent paving or soling shall be
PW3-Sec-7 (Tech. Spec.) 126
filled by brushing in local fine sand washing in the sand with water until all voids are completely filled
General
This work shall consist of the construction of brick soling for the construction of walkways and to
improve foundation condition of soft soils in accordance with the lines and levels shown on the
Drawings or ordered by the Engineer.
Brick soling with mortared joints shall be considered to be brick masonry as described in 6.4.
Materials
Brick for brick soling comply with Clause 6.2.
Sand filler shall consist of sound, clean, free draining fine sand having FM of 0.8 as approved by the
Engineer.
Construction Methods
All works to be covered by brick soling shall be compacted and trimmed to the lines and levels
shown on the Drawings. For roads, the sand sub-base course shall be prepared to the corrected
profile, grade, and camber, and compacted to the satisfaction of the Engineers before the bricks are
placed.
Bricks shall be hand laid with each brick touching the adjacent brick and laid flat or on edge in a
herringbone bond unless otherwise directed. The bonds shall have their joints broken in both
longitudinal and transverse directions. Immediately after the bricks are placed, all gaps shall be
blinded with sand by spreading and brushing until the gaps are filled. Water shall be poured freely
on the entire surface so that the sand enters and completely fills the interstices.
For single layers of flat brick soling, the interstices shall be filled with sand at 0.085 m 3/m2. For brick
on edge payment in a single layer herringbone bond, the interstices shall be filled with sand at 0.12
m3/m2.
When a layer of brick on edge pavement in a herring bone bond is to be placed over the initial layer
of flat brick soling, one layer of 12 mm thick sand cushioning shall be placed between the two
layers.
Local deviations in the finished brick soling surface shall no be allowed. They shall be rectified to
the satisfaction of the Engineer.
Defects present in the finished construction shall be rectified at the Contractor's expenses. The
entire defective soling shall be dismantled to the full depth and reconstructed to the satisfaction of
the Engineer. In no case shall filling the depressions with filler material be permitted.
Measurement and payment
All measurements will be made according to the lines, levels and thicknesses shown on the
Drawings or ordered by the Engineer. Brick soling shall be measured per square meter. Brick
edging shall be measured per liner meter.
Payment for brick soling shall be full compensation for all costs involved in the construction of the
specified work, including the transportation of all materials, equipment, tools, incidental charges and
labour required to carry out the work.
The water retaining structure under the section includes coagulation, flocculation & sedimentation
basins, sand filters and clear water reservoir. The contractor shall carry out testing of all above water
retaining structures for water tightness and disinfect only the storage reservoirs after successful
PW3-Sec-7 (Tech. Spec.) 127
testing.
During the test any visible leakages should be marked and drop in water level recorded including
evaporation. All leakages shall be located and repaired and test repeated at no extra cost to the
Employer until the water tightness is ensured.
On the eighth day a shallow watertight GI evaporation tray of 0.40 square meter area filled with 75
mm depth of water shall be placed floating in the tank. The water level shall be recorded and the
test continued for the next 7 days. Readings of the water levels in the reservoir and the tray shall be
recorded every 24 hours during the test period. If the water level in the tank falls or signs of
leakages occur during the test period, the Contractor shall mark the location of the defects. When
the test period is over, the tank shall be emptied and all defects shall be rectified.
After rectification of the defects, the reservoir / tank shall be refilled and the test repeated at no extra
cost to the Employer until the tank is water tight to the satisfaction of the Engineer. In case the fall of
water level (minus the fall accounted for by evaporation) in the tank during the test period does not
exceed 12 mm, the tank shall be deemed to be water tight.
13.9.4 Disinfection
After satisfactory test, the reservoir / tank shall be thoroughly scoured in order to remove whatever
debris and dirt may remain therein. The reservoir / tank shall than be disinfected by at least 50 ppm
chlorine for a period of at least 24 hours. At the end of this period samples of water shall be
collected and tested for residual chlorine. All samples shall have a free residual chlorine of not less
than 0.2 ppm. If any sample gives a free chlorine residual figure smaller than 0.2 ppm. The reservoir
/ tank shall be scoured and the disinfection repeated until the above requirement is fulfilled.
Disinfection shall be carried out to the entire satisfaction of the Engineer. Workmen engaged in the
reservoir shall have a valid certificate from the health Officer showing that they are medically fit for
carrying out the said work and free from water borne diseases.
The cost of testing and Disinfection, including provision of water and all other associated works shall
be deemed to be included in the contract rates for testing and disinfection.
13.10.1 Commissioning
After completion of all construction and installation works as described in these Specifications, the
whole plant shall be commissioned as per agreed date with the engineer. The contractor shall
supervise the working condition of the plant for one week and during that period provide all
necessary engineering and technical supervision continuously to effect any adjustment that
may be necessary. During full commissioning period the entire treatment plant has to run under the
supervision of the Contractor to the complete satisfaction of the Engineer for 7 days.
The trial run shall concern the entire plant, and shall at least cover the following aspects as far as
not yet covered elsewhere in these Specifications: