Professional Documents
Culture Documents
Assignment 2 2021
Assignment 2 2021
Assignment 2 2021
Question 3
At a given construction site, there is a deep and homogenous deposit of sand and the water table
is 2m below the soil surface. The dry unit weight of sand is 𝛾𝑑𝑟𝑦 = 17 𝐾𝑁/𝑚3 and the saturated
unit weight of sand is 𝛾𝑠𝑎𝑡 = 20𝐾𝑁/𝑚3.
a) Calculate the total stress, effective stress and pore pressure at a depth of 5m below the
surface.
b) Plot (Sketch) the total stress, and the pore pressure distributions with depth for the entire
soil profile.
Question 4
A sheet piling system with its corresponding flow net is shown in the figure below.
a) Estimate the flow rate in 𝑚3 /𝑑𝑎𝑦 per 1m run of piling.
b) For the element A with L=1.5m, calculate the average velocity and effective vertical stress.
c) Determine the magnitude of the effective vertical stress ay the base and at the right hand
side of the sheet pile.
d) Calulate the factor of safety against quick condition, defined as the ratio of existing
hydraulic gradient along the downstream face of sheet pile to the critical hydraulic gradient
𝑘 = 0.02 𝑚𝑚/𝑠, 𝛾𝑠𝑎𝑡 = 20𝐾𝑁/𝑚3
Question 5
The following are the results of four drained, direct shear tests on a normally consolidated clay. Given:
• Size of specimen = 60 mm * 60 mm
• Height of specimen = 30 mm
Draw a graph for the shear stress at failure against the normal stress, and determine the drained
angle of friction from the graph.
Question 6
A consolidated-drained triaxial test was conducted on a normally consolidated clay. The results were as follows: