Position __________________
Palfinger Operation
Discoverer India Rig SPECIFIC OJT
Module
Page 1 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
OBJECTIVES
Upon completion of this module, you should be able to:
1. Demonstrate a clear understanding of the role of operating the Palfinger crane in a safe,
incident free operation and competently.
TRAINING MATERIAL
The Palfinger Crane Operator OJT Module includes:
1. A mandatory task list, which is a list of jobs you must be able to perform;
2. A tool list, which is a list of supporting reference that will be available in the manual.
3. Review questions.
TRAINING PROCEDURE
The Palfinger Crane Operator OJT Module task list is the measure of progress in your training. As
you prove competence, your supervisor will sign off each specific task. Completion of the task list
is mandatory.
When you finish the requirements and signed by your supervisor hand your module to your
Supervisor to confirm completion.
If unable to complete during your hitch file in the filing cabinet on the rig floor and continue upon
your arrival of the following hitch.
On successful completion of the task list, your supervisor will fill sign the last page then forward to
the rig RSTC for signing off by the OIM then filed. The completed task list is to be kept on file at
the location of your work assignment.
Reference for Palfinger Crane manuals is with the Maintenance department and on the server –
Complete the information page at the end of the exercise before submitting
Page 2 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
General Topics
Page 3 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
5. Demonstrate normal crane shutdown procedures.
Crane Maintenance
Page 4 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
Crane Theory
200
ideal boom angle Max 4.6m 6.1m 8.0m 10.1m 12.3m 14.4 16.5m
E 5600kg 4520kg 3189kg 2280kg 1700kg 1340kg 1110kg 960kg
D 5750kg 4590kg 3260kg 2370kg 1800kg 1450kg 1210kg
C 5850kg 4680kg 3360kg 2480kg 1420kg 1570kg
B 6000KG 4780kg 3470kg 2600kg 2040kg
A 6100KG 4900kg 3600 2730kg
Page 5 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
Lifting Gear
Workbook Questions
1. What is the Maximum wind before stop operating the crane?
a.
What is the Minimum and Maximum operating temperatures for the crane?
a.
2. List 5 Defects that will require you to shut down crane operations
a.
b.
c.
d.
e.
f.
g.
h.
i.
Page 6 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
f.
g.
h.
i.
b.
c.
d.
e.
Swing Left
7. During loading activities, the crane operator must always have the at his
fingertips.
8. As long as a load is _ _, the operator must remain in contact with the _________
_____________ .
Page 7 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
a.
2. Lowering a heavy load from an extended boom configuration must be performed without
increasing the__________ ; otherwise the admissible load limit may be exceeded.
3. When working with a load, do not lower the main boom to full retraction since the
overload protection system does / does not function in that boom configuration.
4. Does this palfinger have overload protection?
5. What can happen if lowering a heavy load from and extended boom configuration while
increasing the outreach?
a.
6. When working with manual extensions, the admissible load of the manual extensions
determines the overall admissible load of the whole crane (see load chart), and that even if
they fully retract. (page 82)
Page 8 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
c.
d.
e.
f.
g.
h.
i.
j.
k.
Safety devices
8. What happens when the Emergency cut off valve is activated?
a.
____ _________ __________ immediately and press the emergency off switch until it
Test the function of the CUT-OFF button every time before working.
10. What functions are disabled if the pressure set for the overload valve is exceeded?
.......................................................................................... ___________
.......................................................................................... ___________
11. What actions can you take when the crane is in overload?
a.
b.
NOTE: To switch back the overload system it is necessary to push the peak – pressure
button a few seconds. Briefly press the release valve and lower the main boom.
Page 9 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
Additional equipment
12. Name 4 considerations in connection with load lifting gear
a.
b.
c.
d.
13. Explain pre-starting the crane checks and inspections that must always be carried out:
1.
2.
3.
4.
5.
14. What weight is required for a Lift plan or Permit to Work that is classed as a heavy lift?
a. .
16. What is the primary means of communication for the Banksman and crane operator?
a.
# Sequence Description
1.
Page 10 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
7
18. Describe the sequence for putting the crane in the Stored position
# Sequence Description
1.
2.
3.
4.
5.
a.
b.
c.
d.
e.
22. How can personnel be lowered from the basket if a hydraulic failure occurs?
Page 11 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
Candidate MUST complete10 lifts with the Palfinger which must be supervised by a competent
person. Each SUCCESSFUL lift will be signed off by the competent person observing the lift.
Description of lift:
Description of lift:
Description of lift:
Description of lift:
Description of lift:
Page 12 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
Candidate MUST complete10 lifts with the Palfinger which must be supervised by a competent
person. Each SUCCESSFUL lift will be signed off by the competent person observing the lift.
Description of lift:
Description of lift:
Description of lift:
Description of lift:
Description of lift:
Page 13 of 14
Palfinger Crane Operation Discoverer India Rig Specific OJT Module
Name : Unit :
To: RSTC
I certify that this training participant has completed to my satisfaction all of the mandatory tasks on
the Palfinger Crane Operator OJT Module task list for the Discoverer India. Also, this individual
has successfully completed the workbook exercises.
Signature: ____________________________________
Signature: ____________________________________
Signature: ____________________________________
Page 14 of 14