Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Vesting and Ownership of Plant on Dredging Projects: A Fair Remedy or a Relic of the Past?

15

DAVID KINLAN

VESTING AND OWNERSHIP OF PLANT ON


DREDGING PROJECTS: A FAIR REMEDY
OR A RELIC OF THE PAST?
ABSTRACT INTRODUCTION supplied for the permanent works will not
have the right to use the Contractor’s
Vesting of Plant refers to the transfer of The right of vesting or right to claim title of Equipment following termination unless
ownership or title of the Contractor’s ownership is generally used in construction there is a “Vesting of Plant” clause.
Equipment from the Contractor to the contracts when it applies to materials and
Employer for the period the Equipment goods supplied and delivered by the Vesting of plant refers to the transfer of
remains on the Site. It may even include the Contractor for incorporation into the Work. ownership or title of the Contractor’s
right to sell the Equipment to recover monies This is to enable the Employer to complete Equipment from the Contractor to the
as a debt due. The intention of a vesting the Works by using the materials and Employer for the period the Equipment
provision is that in the event of Contractor goods supplied in the event that the remains on the Site. It may even include
default or insolvency the Employer can retain Contractor’s employment is terminated. the right to sell the Equipment to recover
the Contractor’s Equipment in order to It is generally accepted that the materials monies as a debt due. The intention of a
complete the Works.Vesting of Plant clauses and goods change ownership when they vesting provision is that, in the event of
originated from the Institution of Civil are clearly identified as the property of the termination of the contract by the Employer
Engineers (ICE) Conditions of Contract and Employer upon delivery to the Work Site or for Contractor default or insolvency, the
its use has spread around the world. Despite upon payment by the Employer when they Employer can retain the Contractor’s
it falling out of favour in the United are incorporated into the permanent works, Equipment in order to complete the Works.
Kingdom, under FIDIC contracts and in other whichever comes first.
jurisdictions it can still be seen in a number
of countries’ standard conditions of contract However the position regarding the A BALANCED PERSPECTIVE
most notably in parts of the Middle East, Contractor’s Equipment deployed on the
Malaysia, Hong Kong and Australia. Work Site is different. The Employer whilst There are opposing interests with respect
gaining title to materials and goods of a vesting of plant clause. In the event of
Although there has been lobbying to remove the Contractor’s default and the
draconian vesting provisions from Above: International Contractors often work on projects subsequent termination of the contract
international contracts such as FIDIC, these far from home. FIDIC Blue Book’s Notes for Guidance then the Employer will wish to secure the
provisions have not been abandoned. The suggest that the Employer’s right to retain a completion of the Works by the quickest
question remains: Are such provisions a Contractor’s equipment may clash with the liquidator’s and most economically advantageous
workable contract solution for clients in right if insolvency arises. Referencing applicable laws in method. If the Employer is able to use it,
economically uncertain times or should both the country of the project and the Contractor’s then the Contractor’s Equipment is
they be consigned to history? country will be necessary. essential for this. The Employer would then
16 Terra et Aqua | Number 115 | June 2009

not be liable to pay the Contractor and the In the Dredging Handbook for Engineers
additional expenses incurred by the 2nd Edition, the authors question whether
Employer in completing the Works would the Employer would not be better advised
be chargeable to the Contractor. If the to increase the value of the performance
costs of execution and other expenses bond instead of resorting to a vesting of
incurred by the Employer were to exceed plant clause. In practice, a more important
the amount otherwise due to the provision is the Employer’s right not to
Contractor, then the Employer would be release a vessel from the work site until the
entitled to recover such excess amount as work related to that vessel has been
a debt due. completed.

In a vesting of plant situation, as the


Employer has title in the Contractor’s VESTING CLAUSES AROUND THE
Equipment, the Employer would be able to WORLD
sell the Contractor’s Equipment to recover
the debt. One of the obvious and The vesting of plant provision was first used
immediate problems of this arrangement is in the Institution of Civil Engineers (ICE)
that the Employer often does not have the Conditions of Contract as far back as 1945
expertise or insurance cover to operate and its use has spread around the world, Figure 2. Since the “rainbow suite” of contracts was
marine equipment and would more than particularly in Commonwealth Countries. never intended for dredging, the FIDIC Form of Contract
likely have to employ another contractor Use of the ICE Contracts was slowly for Dredging and Reclamation Works was developed,
to use the dredging equipment. replaced by the FIDIC (Fedération des tested and published in 2006.
Ingénieurs-Conseils) Contracts which were
The Contractor on the other hand has a largely based on the ICE 4th Edition.
significant capital investment in this the Contractor’s responsibility to operate
equipment which may be several times FIDIC Red Book versus ICE Contracts and maintain the same. Upon removal,
the value of the work to be undertaken. The first edition of the FIDIC Red Book for with the consent of the Engineer, the
Two questions are often asked: Should Construction was issued in 1957, the Contractor’s Equipment shall be deemed
the Contractor be required to complete second in 1969 and the Red Book 3rd to revest in the Contractor”.
the Works when the contract has been Edition was issued in 1977. The latter drew
terminated for default? And should the heavily on the experience of the ICE 5th International Applications
equipment be sold to recover a far Edition issued in 1973. The FIDIC Red Book Some countries such as Oman and Bahrain
minor debt? 3rd Edition largely took over as the basis took the FIDIC 3rd Edition and used it as
for use in international dredging and the template for their standard conditions
reclamation projects. The FIDIC Red Book of contract but without including the Part
3rd Edition departed from the ICE III amendments for dredging and
Contracts upon which it was based by reclamation works. This had the
including an optional Part III set of unfortunate result of re-instating the
particular conditions. This Part III was solely vesting of plant requirements. Dredging
meant for dredging and reclamation works contractors working in these countries are
and excluded the vesting of plant provisions faced with the potential of the vesting of
and the right for the Employer to sell the plant provisions being enforced in event of
Contractor’s Equipment (Figure 1). contractor default and would be expected
in all cases to qualify such tenders.
A typical Vesting of Plant Clause would be
as follows: Other countries such as Malaysia, which
“All Contractor’s Equipment owned by the used the former ICE Contracts as their
Contractor, or by any company in which template, incorporated the vesting of plant
Figure 1. Major port infrastructure projects require the the Contractor has a controlling interest, clause in their Public Works Contracts.
deployment of marine and land based equipment, such shall, when on Site, be deemed to be the However, with the privatisation of the port
as the various trailers seen here at work and the vertical property of the Employer. Provided always and infrastructure market, Employers
drains being installed for the development of a new that the vesting of such property shall not increasingly turned to either FIDIC or their
port. These may be owned, subcontracted and/or hired prejudice the right of the Contractor to the own drafted contracts and the vesting of
equipment. Should an Employer be entitled to sell the sole use of the Contractor’s Equipment for plant provisions were for the most part
Contractor’s equipment to settle any debt due? the purpose of the Works nor shall it affect largely discarded.
Vesting and Ownership of Plant on Dredging Projects: A Fair Remedy or a Relic of the Past? 17

DAVID KINLAN create a legal change of ownership in the Equipment shall, when brought on Site, be
(BSc. Quantity Surveying. MRICS) Contractor’s Equipment, rather that the deemed to be exclusively intended for the
worked as a Contracts Manager for Employer has a floating charge on the execution of the Works and the Contractor
Ballast Nedam Dredging, Ballast Ham Contractor’s Equipment if the Contractor shall not remove the same without the
Dredging and Van Oord between 1991 becomes insolvent. consent of the Engineer.
and 2008. From 1997 to 1999 he was
stationed on the Tanjung Pelepas Port, In the absence of registration in accordance FIDIC Red Book 4th Edition Clause 63.1
Malaysia. He has over twenty years with Part XII of the Companies Act 1985, provides that on termination the Employer or
experience with marine infrastructure such floating charge will be void against the another contractor employed by the
projects at both tender and execution Contractor’s administrator. The relevant Employer may use for completion so much
phase including dredging, reclamation, case is Smith (as Administrator of Cosslett of the Contractor’s Equipment as the
offshore and integrated civil engineering (Contractors) Ltd) v Bridgend County Employer may think proper. Clause 63.2
projects in worldwide and was involved Borough Council [2001] UKHL 58; [2002] provides that the Engineer shall on
with landmark capital works projects BLR 160) which went to the Court of termination certify the value of the
such as Chek Lap Kok Airport and the Appeal and was finally decided in the House Contractor’s Equipment.
Oresund Link. In 2008 he relocated to of Lords in 2001. The case demonstrates Dredging contractors working with FIDIC 4th
Brisbane, Australia and set up his own that whilst the right of the Employer to use Edition Part II Particular Conditions Clause
company to provide contractual support the Contractor’s Equipment to complete the 54.2 are faced with the potential of the
to Contractors and Clients both in Works following contract termination may more onerous part of the vesting of plant
Australia and the rest of the world. be legally enforceable, any right to sell the provisions being enforced in event of
Contractor’s Equipment to recover debt is Contractor default.
likely to fail.
FIDIC 4th Edition Part I General Conditions
Increasingly in the United Kingdom the Clause 54.5 provides that, in the event of
It is of interest to note that in Australia the Engineering & Construction Contract (ECC) is termination for Contractor’s default, the
Australian Standard General Conditions of being used for civil engineering projects. This Employer may then take over any hired
Contract both the AS 2124-1992 and the provides that on termination of the contract, equipment agreements and agrees to pay
later AS 4000-1997 have incorporated a the Employer may use any Equipment to the hire charges from the date of
vesting of plant procedure. In the event of which the Contractor has title to complete termination.
default of the Contractor, the Employer the Works. Title in equipment refers to a
may take work out of the hands of the legal right of possession or control. The ECC This gives some degree of protection to the
Contractor and perform that work and take Guidance Notes indicate that the Employer dredging vessel owner, as quite often the
possession of such Contractor’s Equipment can only use Equipment to which the registered vessel owner is a different entity
in order to do so. If the Contractor is Contractor has title, so that Equipment from, to that of the Contractor. This clause thus
indebted to the Employer then the for instance, subcontractors or hired ensures that payment will be made to the
Employer may retain the Contractor’s equipment would be exempted. owner if the Contractor’s Equipment is to
Equipment until the debt is satisfied, or, if be used to complete the Works.
the Contractor fails to pay the debt, the
Employer may sell the Contractor’s FIDIC’S USE OF THE VESTING OF The Rainbow Suite
Equipment. Similar provisions also exist in PLANT PROVISION In 1999 FIDIC introduced the new
the Hong Kong General Conditions of “rainbow suite” of contracts which
Contract for Civil Engineering Works 1999. In 1987 FIDIC updated its 3rd Edition Red included:
Book contract with the issue of the Red - a new Red Book Contract for
The principle of title and vesting of plant Book 4th Edition. Part III of the 3rd Edition Construction,
has undergone considerable transformation was discarded and the title and vesting of - a Yellow Book for Design-Build and
under the UK’s ICE Conditions of Contract. plant clause, although watered down, was - a Silver Book for EPC/Turnkey Work.
The pure vesting of Contractor’s Equipment brought back as an optional provision. In
included in the ICE 5th and 6th Editions has the 4th Edition Part II Particular Conditions The rainbow suite of contracts all follow
been discarded and was not used in Clause where vesting of the Contractor’s the same formatting and include identical
54 of the 7th Edition published in 1999. Equipment is required, Clause 54 termination clauses. The rainbow suite was
recommends wording similar to that of the never intended for dredging contracts.
UK Legal Judgment earlier ICE Contracts. Consequently, shortly thereafter in 2001 a
It has been held that the wording stating test edition blue form for dredging was
that the Contractor’s Equipment is deemed The wording of FIDIC Red Book 4th Edition issued, with the first Blue Book edition
to be property of the Employer does not Clause 54.1 provides that all Contractor’s subsequently issued in 2006 (Figure 2).
18 Terra et Aqua | Number 115 | June 2009

Since the issue of the vesting of plant in right of the liquidator or receiver to realize REFERENCES
relation to marine dredging vessels was no the assets of an insolvent Contractor.
longer an issue to the writers of the Reference to the applicable laws, both in Australian Standard AS 2124-1992, General
rainbow suite, not unexpectedly, vesting of the country of the project and in the Conditions of Contract. Standards Australia
plant crept back into the new rainbow insolvent Contractor’s country, would be Publishers.
suite. In addition, there were no provisions necessary”.
which dealt with the Employer being able Bray, R N, Bates, A D and Land, J M (1995).
to take over hire agreements. Clause 15.2 Dredging A Handbook for Engineers 2nd Edition.
provides that following termination the CONCLUSIONS Arnold Publishing. p. 323.
Employer may complete the Works and/or
arrange for any other entities to do so. Vesting of Plant provisions have come a Corbett, E C (1991). FIDIC 4th: A Practical Legal
long way since their initial use in the ICE Guide: a Commentary on the International
Although it does not clearly state that the Conditions of Contract and their later Construction Contract.
Employer or other entities may use the adoption by FIDIC. Smith v. Bridgend
Contractor’s own or hired equipment, it County Borough Council demonstrates that Dolmans, Constantijn (2001). Terra et Aqua, “A
does say that the Employer shall then give whilst the right of the Employer to use the Contract for ‘Just Digging a Hole’”, pp. 3-10.
notice that the Contractor’s Equipment will Contractor’s Equipment to complete the
be released to the Contractor at or near the Works following contract termination is a Eggleston, Brian (2001). The ICE Conditions of
Site. The presumption is that the Employer contract requirement and is legally Contract, Seventh Edition. Wiley-Blackwell
only releases the Contractor’s Equipment enforceable, any right to sell the Publishers.
when the Works are completed. Contractor’s equipment to recover debt is
likely to fail. FIDIC (1987). Conditions of Contract for Works
There is no express right regarding of Civil Engineering Construction, Fourth Edition.
Employer’s use of the Contractor’s The dredging industry has urged the
Equipment, and if the Employer did use the removal of the more draconian vesting FIDIC (2006). Form of Contract for Dredging and
Equipment there is no provision for provisions from international contracts such Reclamation Works. Agreement, General
payment by the Employer for such use of as FIDIC. Nonetheless, dredging contractors Conditions, Rules for Adjudication and Notes for
the Contractor’s Equipment after should remain vigilant that vesting Guidance.
termination. It then goes on to provide that provisions still exist in the construction
if a payment due is not made to the market and that payment for use of Glover, Jeremy, Thomas, Christopher and
Employer then the Employer may sell the Contractor’s Equipment following Hughes, Simon (2006). Understanding the New
Equipment to recover the payment. termination is not dealt with in either the FIDIC Red Book: a Clause-by-Clause Commentary.
new FIDIC rainbow suite nor included in Sweet & Maxwell Publishers. UK.
The Blue Book for Dredging the more recent Form of Contract for
In 2006 FIDIC issued the long awaited Form Dredging and Reclamation Works. Goudsmit. JJ “A first impression of the 4th
of Contract for Dredging and Reclamation edition of the FIDIC Conditions of Contract”.
Works (the Blue Book in the rainbow suite). Employers who are concerned as to the Terra et Aqua, No. 36.
In it Clause 12.1 provides that in event of possibility of contractor default or
Contractor’s default the Contractor shall insolvency are advised to review either their Institution of Civil Engineers (1973).
demobilise from the Site, but leave behind own or standard termination clauses and ICE Conditions of Contract, Fifth Edition.
any Contractor’s Equipment which the consider recourse to other forms of London, UK.
Employer instructs is to be used until the contract security as they will not be entitled
completion of the Works. to sell the Contractor’s equipment in order Institution of Civil Engineers (1995). The
to recover a debt due. Engineering and Construction Contract: a NEC
There is no provision that the Employer can Document: Guidance Notes. London, UK.
sell the Contractor’s Equipment in order to Employers are also advised to consider
recover a debt due nor is there any wording similar to FIDIC 4th Edition Clause House of Lords Judgment Index http://www.
arrangement to pay hire charges from the 54.5 to secure that any hired equipment publications.parliament.uk/pa/ld200102/
date of termination. may be used to complete the Works ldjudgmt/jd011108/smith-1.htm
following termination of the Contract for
In the Blue Book Notes for Guidance (12.3) contractor’s default. Contractors will also Murdoch, John and Hughes, Will. (2008).
it states in respect of insolvency (FIDIC benefit from such wording as there is an Construction Contracts: Law and Management.
2006, p. 33): arrangement whereby the Contractor’s Taylor & Francis Publishers. UK, USA and
“The right of the Employer to retain the Equipment will be paid for should the Canada.
Contractor’s Equipment may clash with the Employer use it.

You might also like