Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group

(https://www.kenziegroup.co.uk/)

NEWS

A CONCISE GUIDE TO UNDERSTANDING THE EOT


SUBCONTRACTOR CLAIMS PROCESS

Today’s construction industry is often challenged by the complexity, time constraints,


and expense of projects which are bound by contractual law. Even a minimal
departure from these contractual agreements can result in a significant loss of time
and money to all parties involved. Unfortunately, the responsibility for meeting the
constraints of time and cost falls squarely upon the shoulders of the general
contractor, who is ultimately responsible for meeting the stipulations within the
contract.

While most smaller projects, such as those involving the construction of a single
(https://www.kenziegroup.co.uk/construction-
residence or a small commercial building, can be completed within the terms set
claim-calculator/)
forth in the contract, larger building projects are often riddled with delays because of
the sheer number of subcontractors working on their portion of the project. For
RECENT POSTS
example, a general contractor may subcontract work out to electricians, plumbers, / DSU or BI Claim – it’s all about Cause and
welders, roofers, and other licensed professionals who are each responsible for the Effect! (https://www.kenziegroup.co.uk/dsu-or-
jobs they are contracted to undertake. bi-claim-cause-and-effect/)
Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 1/7
6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group

/ Six Reasons Why a DSU Delay Analysis Fails


(https://www.kenziegroup.co.uk/six-reasons-
why-dsu-delay-analysis-fails/)

/ Am I obliged to Spend Money To Mitigate a


Delay Caused by Others?
(https://www.kenziegroup.co.uk/obliged-
spend-money-mitigate-delay-caused-by-
others/)
/ If your baseline is flawed, you can forget
about demonstrating cause and effect!
(https://www.kenziegroup.co.uk/baseline-
flawed-forget-demonstrating-cause-effect/)
/ I Have a Programme included in my
Contract – so what?!
(https://www.kenziegroup.co.uk/programme-
included-contract-so-what/)

(HTTPS://FEED43.COM/ENGLANDWALESCONS
Sometimes, through no fault of a subcontractor, their work is delayed. What happens THE LATEST ENGLAND AND WALES
when they are unable to begin or complete their portion of the job timely and within CONSTRUCTION CLAIM DECISIONS IN
cost due to outside forces preventing them from working on schedule? At this point, 2018
that subcontractor will almost certainly want to file what is referred to as an Extension
(HTTP://WWW.BAILII.ORG/EW/CASES/EWHC/T
of Time (EOT) construction claims (https://www.kenziegroup.co.uk/services/expert-
construction-claims-consultants/), which needs to follow a very precise format. / Bombardier Transportation UK Ltd v
Following is a concise guide to understanding and filing this type of claim with the Merseytravel (No. 3: Costs) (Rev 1) [2018] EWHC
general contractor. 41 (TCC) (17 January 2018)
(http://www.bailii.org/ew/cases/EWHC/TCC/2018/41.html)
ACCEPTABLE REASONS FOR FILING AN EOT / Connect Plus (M25) Ltd v Highways England
Before filing for an Extension of Time, a subcontractor should refer to the guidelines Company Ltd [2018] EWHC 140 (TCC) (31
established by FIDIC, the International Federation of Consulting Engineers. This January 2018)
professional body establishes the rules and regulations to abide by which includes, (http://www.bailii.org/ew/cases/EWHC/TCC/2018/140.htm
but is not limited to, reasons and procedures for filing EOT claims. As per their / Contact (Print And Packaging) Ltd v
guidelines, a subcontractor can’t file for an Extension of Time if they were remiss in Travelers Insurance Co Ltd [2018] EWHC 83
carrying out their duties timely and within budget. That’s on them and they cannot (TCC) (23 January 2018)
expect to recover any losses which were incurred by their own dereliction of duties. (http://www.bailii.org/ew/cases/EWHC/TCC/2018/83.html

However, consider for a moment the domino effect. Since most jobs on a construction / Crown House Technologies Ltd v Cardiff
site are dependent on work that went on before their portion of the job commenced, Commissioning Ltd & Anor [2018] EWHC 54
an Extension of Time claim (https://www.kenziegroup.co.uk/extenstion-time-claim/) (TCC) (18 January 2018)
(http://www.bailii.org/ew/cases/EWHC/TCC/2018/54.html
Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 2/7
6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group
might be agreed if the subcontractor/s before them failed to meet time and cost / Fluor v Shanghai Zhenhua Heavy Industry
constraints. In the Building Service Subcontractor Claim, specific allowances are Co, Ltd [2018] EWHC 1 (TCC) (11 January 2018)
made for those times when delays resulted from such things as: (http://www.bailii.org/ew/cases/EWHC/TCC/2018/1.html)

Amended directives during a job.


Missing or incomplete blueprints and specs.
Previous time schedules not being met which their work is dependent upon.
The administration of alterations in plans.
Delays in the provision of utilities and facilities to be supplied by the contractor.

According to contract law, subcontractors have an obligation to compile and provide


explanations and documentation of claims. Each claim should be accompanied by
contractual references, factual causation, and quantification of the resulting impact
along with any and all documented evidence. This evidentiary documentation should
include such things as records of disruptions and delays, as well as records of
notification and any proposed contractor resolutions.

Statutory and case contract law stipulates which documents are to be used as proof
of a requested Extension of Time (EOT) and any costs incurred due to the EOT
Construction claim (https://www.kenziegroup.co.uk/services/expert-construction-
claims-consultants/) in question. In order to be granted an Extension of Time and be
compensated for any financial losses, a direct line of contributory events must be well
documented. For this reason, it would behove subcontractors to always be diligent in
maintaining complete and accurate records as a job progresses.

A FEW NOTES ON THE FIDIC BUILDING CONTRACT


Although this is a standard contract used in the construction industry around the
globe, the contract itself does not lay out the groundwork for determining liability
when an EOT claim is submitted. Rather, such contracts set out to define the role
each party to the contract is to play and then enumerate each party’s responsibilities.

Also, there is a standard procedure to be followed when submitting an EOT claim and
at that time, a subcontractor filing the claim should have any pertinent calculations at
hand. FIDIC guidelines state that best practices dictate that the subcontractor
seeking a compensatory measure should have very specific calculations on monetary
losses as well as the amount of time by which they were delayed. It can’t be said
enough that the contract as laid out by FIDIC in no way sets out to determine liability
but rather works as a set of guidelines to be followed when seeking extra time to
complete a job or compensation for losses incurred through no fault of their own.

SPECIFIC DETAILS OF A SUBCONTRACTOR’S EOT


CLAIM
Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 3/7
6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group
In addition to the very basic reasons for filing an EOT claim mentioned above, the
prescribed format should also include exact documentation of the following:

Initial delays resulting in total calendar days.


Delays resulting from previous Subcontractor duties known as site dependence
delays.
Delays resulting from the untimely issuance of approved drawings and
blueprints.
Delays resulting from pending RFIs (Request for Information).
Delays resulting from PVAs (Pending Variation Approvals).

Taking all of the above into consideration, it should be stated at this point that when a
new date of completion is agreed, it is assumed that the subcontractor filing the EOT
claim will not suffer any further delays. It is thus up to the general contractor to ensure
that everything is in line and completed prior to a continuance of work by the
subcontractor filing the claim.

ACTUAL PROLONGATION COST CLAIM TO BE FILED IN


ADDITION TO EOT CLAIM
When bidding a job, a general contractor must take into account any delays
(https://www.kenziegroup.co.uk/services/expert-construction-claims-
consultants/delay-analysis/) which should have been foreseeable. These are too
numerous to detail at this point but would include such things as an industry-wide
shortage of specific building materials, outside influences such as major repairs on
city or county utilities which may prove intermittent during a project of this scope,
and any other outside factors to be evaluated when setting forth the timeframe
under which they are asking to be contracted. The completion date is set by the
general contractor and from there, any and all subcontractors estimate dates of
completion based on the completion of work they are dependent upon.

This is where litigation often enters into the claims process. If the subcontractor feels
that the general contractor did not make a fair determination of the claim for
compensation as per stipulations in their subcontractor contract, the claim can (and
often does) end up in claims court. Sometimes being held up on one job prevents a
subcontractor from moving on to the next job they have contracted, causing losses
they are unable to prevent.

BASIC OUTLINE OF A SUBCONTRACTOR


CONTRACTUAL AGREEMENT
At this point, it should be evident just how important a subcontractor’s contract is.
While the basic format may vary from contractor to contractor or even between cities,
counties, states, and countries, the basic elements must be intact. Every
subcontractor contract should include such things as: Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 4/7
6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group
Parties agreeing to the contract, i.e. general contractor, subcontractor, client, etc.
General conditions.
Specific conditions.
The scope of work to be completed.
Time constraints/duration of the project with a completion

All documents are to be signed and dated by all parties agreeing to the terms and
conditions. Any revisions and amendments must likewise be agreed by all parties to
the contract, signed and dated.

WHO PAYS THE COST OF DELAYS?


You may be asking who is actually responsible for paying the cost of delays. There are
times when the general contractor is liable for delays if it can be shown that the party
responsible for delays was the general contractor. Sometimes it is one of many
subcontractors on a job and other times several subcontractors fell short of their
contractual agreement.

Think of this as a domino effect. One subcontractor sustains losses and files for an EOT
along with compensation for losses incurred. As a result of this subcontractor’s delay,
other subcontractors experience similar delays in time and costs, which continues
down the line. It can be a complex chain of events only determinable in a court of law.
For this reason, it is again reiterated just how important it is for the contractor and any
subcontractors to keep accurate documentation as the job progresses. Ultimate,
liability may depend on being able to pinpoint the exact point in time when the
delays began.

THE BOTTOM LINE


In the end, subcontractors are advised never to proceed with a job if they feel they will
not be in compliance with their contract. Whether it is through their own fault or the
fault of the general contractor or another subcontractor upon which their own work is
dependent, an EOT should be filed immediately. Each contractor and subcontractor is
legally responsible for being compliant with their contract. To proceed without being
granted an extension could cost you a considerable amount of profit. If you feel you
will be unable to meet time and cost constraints, file the appropriate requests for
amendments before being held liable for costly delays.

Facebook Comments

Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 5/7
6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group

0 Comments Sort by Oldest

Add a comment...

Facebook Comments plugin

GET YOUR FREE INITIAL CONSULTATION TODAY

Your Name (required)

NEED HELP RESOLVING A DISPUTE?

WE CAN HELP
Your Company (required)

As construction dispute resolution experts, we help corporate clients


and contractors get the result they need.

For free expert advice, simply fill out the form and one of our Your Company Email Address (required)

directors will call you back.

Your Company Telephone (required)

SUBMIT

 BACK TO NEWS (HTTPS://WWW.KENZIEGROUP.CO.UK/NEWS) Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 6/7
6/9/2021 A Concise Guide to Understanding the EOT Subcontractor Claims Process - Kenzie Group
next  (https://www.kenziegroup.co.uk/sloppy-work-damage-career/)
 previous (https://www.kenziegroup.co.uk/mirror-mirror-on-the-wall/)

Call us on

Stafford - 01785 747 600

London - 0203 751 6705

or email us (mailto:info@kenziegroup.co.uk)

Sign up for our news

(https://twitter.com/KenzieGroup)
(https://www.linkedin.com/company/kenzie-group-limited)

Privacy - Terms

https://www.kenziegroup.co.uk/a-concise-guide-to-understanding-the-eot-subcontractor-claims-process/ 7/7

You might also like