Professional Documents
Culture Documents
Conceptual Delay Mitigation Model Using A Project Learning Approach in Practice
Conceptual Delay Mitigation Model Using A Project Learning Approach in Practice
To cite this article: Hamzah Abdul‐Rahman , Imran Ariff Yahya , Mohammed Ali Berawi & Low Wai Wah (2008) Conceptual
delay mitigation model using a project learning approach in practice, Construction Management and Economics, 26:1, 15-27,
DOI: 10.1080/01446190701744350
Taylor & Francis makes every effort to ensure the accuracy of all the information (the “Content”) contained
in the publications on our platform. However, Taylor & Francis, our agents, and our licensors make no
representations or warranties whatsoever as to the accuracy, completeness, or suitability for any purpose of the
Content. Any opinions and views expressed in this publication are the opinions and views of the authors, and
are not the views of or endorsed by Taylor & Francis. The accuracy of the Content should not be relied upon and
should be independently verified with primary sources of information. Taylor and Francis shall not be liable for
any losses, actions, claims, proceedings, demands, costs, expenses, damages, and other liabilities whatsoever
or howsoever caused arising directly or indirectly in connection with, in relation to or arising out of the use of
the Content.
This article may be used for research, teaching, and private study purposes. Any substantial or systematic
reproduction, redistribution, reselling, loan, sub-licensing, systematic supply, or distribution in any
form to anyone is expressly forbidden. Terms & Conditions of access and use can be found at http://
www.tandfonline.com/page/terms-and-conditions
Construction Management and Economics (January 2008) 26, 15–27
There is universal agreement that construction delay is a common phenomenon in the construction industry
worldwide. Poor or lack of project knowledge management continues to plague the construction industry,
especially in relation to project delays. Knowledge management is used to reduce the impact of construction
projects delay using a project learning approach. Three different phases of data collection were used for the
development of a delay mitigation model, namely preliminary survey, case studies and interviews survey. The
project learning approach contributes towards positive impacts on project schedule performance. Also, good
leadership and integrated commitment of all project parties are the principal impetus to improve the delay
phenomenon in the construction industry. The conceptual model incorporates knowledge on knowledge
management, project learning, lessons learned feedback and supervisory control principles. The results indicate
that the application of project learning is a way to align the project schedule performance to client and market
needs while maintaining the contractor’s core competency.
pose the biggest challenges on how to utilize appro- within and across projects in two different approaches,
priate existing knowledge in making decisions for namely: intra-project learning and inter-project learn-
current and future projects so that they can complete ing (Kotnour, 2000). Both approaches of project
within the specified time, cost and quality. learning offer a comprehensive view of learning from
Knowledge management plays an important role in projects in which the former stresses the capture and
the management of tacit knowledge (Robinson et al., use of real time knowledge and the latter focuses on the
2001; Berawi, 2004) and value achievement (Lee et al., reuse of learned experience and knowledge across
2005; Berawi and Woodhead, 2005). In the construc- projects.
tion industry, tacit knowledge significantly contributes Feedback is fundamental in a decision process as one
to the improvement of task performance, for instance the considers viable alternatives, compares them with
schedule performance. Appropriate knowledge manage- expectations, and adjusts efforts in the repetition of
ment could improve project methodologies and save the pre-decision, partial decision and post-decision
Downloaded by [University of Colorado - Health Science Library] at 01:14 26 December 2014
design time (see the study by Hari et al., 2005, which stages (Zeleny, 1982). To ensure an effective process in
links knowledge management with the possibilities of learning and knowledge management, feedback can
time reduction). Reduction of time in performance lead to the exploration and hunting of invisible or new
improvement can be achieved through the use of knowledge and the assessment of lessons learned within
knowledge management (Tserng and Lin, 2004) during the project (Berawi, 2006). This will subsequently help
the project period especially in critical delay events of the to reduce delay time in searching solutions, knowledge
construction phase (Chan and Kumaraswamy, 1997; and rework.
Abdul-Rahman et al., 2006a). Moreover, knowledge Supervisory control includes efforts by management
and information flow between the organization levels to increase the likelihood that individuals will act in
are outlined as important considerations in mitigating ways that will result in the achievement of organiza-
construction delay (Abdul-Rahman et al., 2006a). tional objectives (Stajkovic and Luthans, 2001). For a
Learning cannot be separated from and is no less construction project, which is fragmented in nature,
important than knowledge management (Lopez et al., supervisory control is important to maintain a contin-
2004; Keegan and Turner, 2001). Both learning and uous project learning process. As project learning is
knowledge management have always been the con- highly human oriented, supervisory control can pro-
nected elements in which knowledge management duce a positive impact during the project period.
encourages a structured and organized learning envir- Drawing on the previous studies, the relation
onment and vice versa. Learning in construction between the processes of knowledge management and
projects is thus important in governing the outcome learning management in delay management are
of a project especially in the reduction of project depicted in Figure 1.
duration (Arditi et al., 2001).
Previous studies
Knowledge management and learning process
Factors and effects of construction project delay have
Drawing on the implementation impact of knowledge captured considerable attention from researchers from
and learning on the project schedule performance, the various construction industries especially in the devel-
conceptual model of this study focuses on four oping countries as shown in Table 1. The findings of
concepts, namely: knowledge management, project these studies are that in practice, project delay factors
learning, lesson learned feedback loop and supervisory depend on the types of procurement methods, geo-
control. There exist comprehensive theories of the graphical area and types of projects. Rather than
knowledge management process (Scarbrough et al., focusing on the investigation of delay factors, it is
1999; Egbu, 1999; Tserng and Lin, 2004; Berawi, worthwhile to consider the major delay factor(s) and to
2004; Lee et al., 2005). The processes of knowledge study the mitigation methods.
management include knowledge identification, crea- Another prevailing research area is on the method of
tion, acquisition, transfer, sharing and exploitation delay analysis. For example, Bordoli and Baldwin
(Berawi, 2004; Lee et al., 2005). Fong (2003) argues (1998) proposed a systematic methodology for asses-
that collective project learning is central to the knowl- sing construction project delay that focuses on the
edge processes of knowledge sharing, knowledge project progress and detailed out six types of delay to
generation and knowledge integration. In other words, the construction works: date delay, total delay,
project learning is an important process in knowledge extended delay, additional delay, sequence delay and
management, especially in the project-based nature of progress delay. Another approach, known as delay
construction projects. Project learning is a set of actions analysis method using delay section (DAMUDS) deals
used by project teams to create and share knowledge with inadequate accounting of concurrent delay and
Delay mitigation 17
population owing to their involvement in various types Semi-structured interviews were performed with 15
of large scale construction projects. The sample was construction professionals from 12 contractor organi-
selected based on a simple random sampling method. zations for a period of five weeks from mid-May 2006.
Delay mitigation 19
The purpose of semi-structured interviews was to The questionnaire survey was administered by post
obtain comprehensive data on the nature of the and a covering letter was appended to explain the
problem. Participants ranged from top management problem being investigated and the objectives of the
to technical personnel, including one general manager, study. Descriptive statistics were selected in analysing
two project directors, four project managers, one the quantitative data. Quantitative data were analysed
contract manager, six quantity surveyors and one using chi-square (Freund and Simon, 1997; Spiegel
planning engineer. Interviews ran between 35 and and Stephens, 1999; Freund and Wilson, 2003)
120 minutes, and were conducted in a private and through a computer program (SPSS 13.0).
confidential one-to-one manner.
the project cycle. The identified project learn- Stage 2: case studies
ing enablers included environment, top man-
Project A
agement commitment, individual commitment
and relationship. Project A involved the construction and completion of
(3) Among the 12 contractor organizations, one three- to four-storey shop/offices. Industrialized
organization implements post project review to Building System (IBS) of hollow core slab was selected
capture and store lessons learned, bad and for its slab construction. A feasibility study of IBS
good practices from construction projects. utilization was performed prior to the start of the
(4) The reward system in terms of recognition and construction stage. The results of the feasibility study
promotion persists as the customary means of showed that the use of IBS was not encouraging except
retaining an individual’s knowledge in con- for slab elements. However, project A experienced a
struction organizations. delay for three and half months owing to discrepancies
(5) All the interviewees agreed that project learning and late approval of hollow core slab drawings.
implementation could lead to the improvement Eventually, construction of slab was changed to the
of project schedule performance. traditional approach to mitigate the impact of the delay
event. The main delay factor was due to the lack of
Based on the findings of the preliminary survey, it experience in IBS on the part of the contractor and the
can be inferred that: failure to incorporate learned experience and knowl-
(1) Conservative learning, that is face-to-face edge of previous projects into the feasibility study. The
human interaction, was widely used and learned experience and knowledge included potential
delay factors, non-technical problems and bad prac-
accepted at the project level. This indicates
tices. In project A, project learning best practices were
that effective human interaction needs to be put
identified as follows:
into the consideration.
(2) Human-related elements are important in (1) Before the beginning of each project activity,
maintaining and managing learning processes. relevant lessons learned of bad and good work
(3) Knowledge gained throughout the project practices of previous projects were extracted
development is poorly managed in the con- from a knowledge portal system and passed to
struction projects. This is because organiza- the relevant subcontractors. The learned
tions seldom recognize the importance of knowledge contains information on the techni-
managing project knowledge in a systematic cal working methods to secure the performance
and secure manner although the majority of of works.
interviewees recognized that knowledge is a (2) The contractor employed one experienced
valuable asset in improving project perfor- mechanical and electrical engineer and one
mance. In other words, project knowledge was experienced site agent with more than 30 years’
not given the right priority from the top experience on an annual contract basis.
management and many organizations resort to (3) Learned mistakes from previous projects were
insecure means of managing knowledge by used as a guide in decision making, for
merely retaining the experienced personnel in instance, planning on the sequence of project
organizations. activities.
(4) It is observed that more than half of the (4) Know-how and know-why were the type of
respondents perceived that learning should be knowledge shared during the project meeting
a subject of concern in the project environment. and individual inquiries.
22 Abdul-Rahman et al.
One of the significant bad practices of project learn- It is apparent that the enablers and barriers of project
ing was failure to integrate the knowledge of poten- learning include human relationships, top management
tial delay factors in decision making. The identified commitment, individual commitment, teamwork and
enablers and barriers of project learning included top openness.
management commitment, openness, and good and
timely feedback. Project C
Project C involved the construction and completion of
Project B new dies manufacturing plant. Project C is considered a
Project B involved the design, construction, comple- successful project as the project was successfully
tion, equipping, commissioning and maintenance of a completed on time. The best practices of project
proposed 76-bed hospital. Project B represents a learning identified include:
typical case in the current study as the project was
Downloaded by [University of Colorado - Health Science Library] at 01:14 26 December 2014
focused on the organizational policy; (b) the response to the importance of human elements in
use of project learning should not be limited to project learning, proper formal and informal super-
technical project knowledge but should be visory controls to secure effective interactive commu-
considered non-technical knowledge of mitigat- nication, both human to human and human to
ing a delay event, (c) a systematic and user technology, are essential. Moreover, supervisory con-
friendly system is important to capture the trol is necessary in ensuring project learning can be
lesson learning during the project period; (d) implemented in an effective manner.
good resource planning and a systematic flow of
lesson learning during the planning stage are
Conceptual framework of the delay mitigation
important in construction to prevent delay
model
events.
(4) The model is considered applicable in the Drawing on the results and the analysis of the data
Downloaded by [University of Colorado - Health Science Library] at 01:14 26 December 2014
learning meeting depends on the types of problems for the purpose of retrieving and referring. Examination
faced, the complexity of the problem and the accessi- of the project learning meeting should be conducted to
bility of the knowledge content. ensure that no important elements have been overlooked
Generalization using real life case studies is encour- which might have a negative impact on project schedule
aged as project parties can easily establish linkage or performance prior to the finalization of the decision.
connection between current and previous completed
projects. During the meeting, multi-way feedback Phase 3: knowledge exploitation
should be performed to improve the quality of new When performing the project activity, it is important for
knowledge and solutions. Relevant and important infor- relevant project parties explore the action taken in
mation and knowledge should be properly documented respect of the impact of the action taken on subsequent
activities and time performance. To exploit knowledge the application of project learning practice in construc-
during the construction stage of the project, project tion projects could prevent future project delay. The
parties need to track down potential problems, critical application of project learning thus should be managed
events and potential solutions which can affect the with due care and due diligence to grasp the maximum
project time goal. Any learned mistakes, learned value of project learning.
knowledge and principles of problem solving should The research has implications for both practitioners
be incorporated into the feedback report, attached to and academic researchers. For practitioners, this study
the project progress report and disseminated to pro- highlights the importance of project learning to
ject parties to form a real time feedback loop. A improve the level of competency of contractors for
real time feedback loop ensures that other project future projects. For academic researchers, there is a
parties are well informed, similar mistakes do not need to highlight and draw the practitioners’ attention
occur on the subsequent task, and it enables better to the significance of project learning in the develop-
Downloaded by [University of Colorado - Health Science Library] at 01:14 26 December 2014
informed decisions to be made for subsequent project ment of project performance competency. In addition,
activities. there is a need for researchers to look beyond the
construction project delay factors and employ a more
Phase 4: knowledge storage comprehensive and practical approach to deal with the
At the end of the project, knowledge gained throughout critical delay factors.
the project period must be filtered, compiled and stored It is suggested that further research on the proposed
in a standard template. The standard template should model be conducted as action research on a few
composed of milestone, action taken, types of delay, selected construction projects. Such research can
delay factors, learned mistake, bad practice, good improve the proposed delay mitigation model and
practice, and critical learned knowledge. These actions provide knowledge in field of delay mitigation. As
aim to avoid loss of valuable knowledge for reference in human elements play a critical role in the areas of
knowledge and learning, leadership and professional
future projects and to minimize the problem of
ethics serve as springboard for future studies on
information overload.
mitigating construction project delay using the project
learning approach.
Strength and limitation of the proposed
conceptual model
References
The strength of the model is the use of project
knowledge to improve delay factors due to lack of Abdul-Rahman, H., Berawi, M.A., Berawi, A.R.,
knowledge that will lead to the increase of time in Mohamed, O., Othman, M. and Yahya, I.A. (2006a)
searching for relevant knowledge, reinventing the wheel Delay mitigation in the Malaysian construction industry.
or other potential problems that can affect the time Journal of Construction Engineering and Management, 132(2),
performance. The potential shortcomings of this model 125–33.
are: (1) it is built on an unproved premise; (2) it is Abdul-Rahman, H., Mohamed, O., Othman, M. and
difficult to ensure accurate knowledge is disseminated Yahya, I.A. (2006b) Mitigation of delay during commis-
during the project period; (3) the model requires sioning of construction project using knowledge manage-
experienced personnel to perform the supervisory ment—contractors’ perception. Paper presented at the
Quantity Surveying National Convention, Sheraton
control; and (4) the process of the model tends to
Subang, Kuala Lumpur, Malaysia, 4–5 September.
cause overload of information especially in large and Ahmed, S.M., Azhar, S., Castillo, M. and Kappagantula, P.
complex projects. (2002) Construction Delays in Florida: An Empirical Study,
Report for the Department of Construction Management,
Florida International University.
Conclusions Aibinu, A.A. and Odeyinka, H.A. (2006) Construction delays
and their causative factors in Nigeria. Journal of Construction
Poor management of project knowledge in the con- Engineering and Management, 132(7), 667–77.
struction industry encourages difficulty of access to Al-Khalil, M.I. and Al-Ghafly, M. (1999) Important causes
of delay in public utility projects in Saudi Arabia.
valuable and quality knowledge in performing project
Construction Management and Economics, 17(5), 647–55.
tasks. This in turn will lead to repeated mistakes, slow Al-Momani, A.H. (2000) Construction delay: a quantitative
and wrong decision making, and as a consequence, it analysis. International Journal of Project Management, 18(1),
will lead to an increase in time and delay events. Case 51–9.
study findings showed that although the use of project Alaghbari, W., Kadir, M.R.A., Salim, A. and Emawati
learning practice cannot totally solve the delay event, (2007) The significant factors causing delay of building
26 Abdul-Rahman et al.
construction projects in Malaysia. Engineering, Construction Frimpong, Y., Oluwoye, J. and Crawford, L. (2003) Causes
and Architectural Management, 14(2), 192–206. of delay and cost overruns in construction of groundwater
Anuar-Othman, A., Torrance, J.V. and Abdul-Hamid, M. projects in a developing countries: Ghana as a case study.
(2006) Factors influencing the construction time of International Journal of Project Management, 21(5), 321–6.
engineering projects in Malaysia. Engineering, Construction Hammersley, M. and Gomm, R. (2000) Introduction, in
and Architectural Management, 13(5), 481–501. Gomm, R., Hammersley, M. and Foster, P. (eds) Case
Arditi, D. and Pattanakitchamroon, T. (2006) Selecting a Study Method, Sage Publications, London, pp. 1–16.
delay analysis method in resolving construction claims. Hari, S., Egbu, C. and Kumar, B. (2005) A knowledge capture
International Journal of Project Management, 24(2), 145–55. awareness tool: an empirical study on small and medium
Arditi, D., Akan, G.T. and Gurdamar, S. (1985) Reasons for enterprises in the construction industry. Engineering,
delays in public projects in Turkey. Construction Construction and Architectural Management, 12(6), 533–67.
Management and Economics, 3(2), 171–81. Hegazy, T. and Zhang, K. (2005) Daily windows delay
Arditi, D., Tokdemir, O.B. and Suh, K. (2001) Effect of analysis. Journal of Construction Engineering and
Downloaded by [University of Colorado - Health Science Library] at 01:14 26 December 2014
Mansfield, N.R., Ugwu, O.O. and Doran, T. (1994) Causes Sambasivan, M. and Yau, W.S. (2007) Causes and effects of
of delay and cost overruns in Nigerian construction delays in Malaysian construction industry. International
projects. International Journal of Project Management, Journal of Project Management (in press).
12(4), 254–60. Scarbrough, H., Swan, J. and Preston, J. (1999) Knowledge
Mezher, T.M. and Tawil, W. (1998) Causes of delays in the Management: A Literature Review, Institute of Personnel
construction industry in Lebanon. Engineering, Construction and Development, London.
and Architectural Management, 5(3), 252–60. Spiegel, M.R. and Stephens, L.J. (1999) Theory and Problems
Odeh, A.M. and Battaineh, H.T. (2002) Causes of construc- of Statistics, 3rd edn, Schaum’s Outline Series, McGraw-
tion delay: traditional contracts. International Journal of Hill, New York.
Project Management, 20(1), 67–73. Stajkovic, A.D. and Luthans, F. (2001) Differential effects of
Ogunlana, S.O., Promkuntong, K. and Jearkjirm, V. (1996) incentive motivators on work performance. Academy of
Construction delays in a fast-growing economy: comparing Management Journal, 44(3), 580–90.
Thailand with other economies. International Journal of Tserng, H.P. and Lin, Y.C. (2004) Developing an activity-
Downloaded by [University of Colorado - Health Science Library] at 01:14 26 December 2014
Project Management, 14(1), 37–45. based knowledge management system for contractors.
Robinson, H.S., Carrillo, P.M., Anumba, C.J. and Al- Automation in Construction, 13(6), 781–802.
Ghassani, A.M. (2001) Perceptions and barriers in Weisberg, H.F. and Bowen, B.D. (1977) An Introduction to
implementing knowledge management strategies in large Survey Research and Data Analysis, Weisberg, Herbert
construction organizations. Paper presented at the RICS Freeman and Company, San Francisco.
COBRA Conference 2001, Glasgow Caledonian Zeleny, M. (1982) Multiple Criteria Decision Making,
University, Glasgow, 3–5 September. McGraw-Hill Book Company, New York.
Rwelamila, P.D. and Hall, K.A. (1995) Total systems Zwikael, O., Cohen, Y. and Sadeh, A. (2006) Non-delay
intervention: an integrated approach to time, cost and scheduling as a managerial approach for managing
quality management. Construction Management and projects. International Journal of Project Management,
Economics, 13(3), 235–41. 24(4), 330–6.