Revised Local Contractors Performance Report For The Month of February2020.
Revised Local Contractors Performance Report For The Month of February2020.
2 Metema - Abrajira 1,548,000,000.00 4.0 19-Oct-17 42.0 52.5 28.4 66.5 27.6 No
Bermog
Not qualified
10 Arbaminch-Belta Construction 564,572,728.82 3.0 12-Apr-10 92.5 115.6 118.7 95.7 95.70 100.0 100.0 1.0 0.0 100.00 Yes
for tendering
PLC
11 Dejen-Felegebirhan 575,946,453.32 3.0 3-Aug-11 80.8 101.0 103.0 97.5 100.0 Yes
12 Sawla-Maji, Contract 2: Laska Salyasish 692,496,973.93 3.0 5-Aug-11 79.1 98.9 102.9 89.5 100.0 Yes
Not qualified
Buhit-Dilyibza Road Upgrading Project, SATCON 87.73 78.9 5 4.5 83.36
13 951,231,102.56 4.0 25-Apr-11 92.1 115.1 106.3 97.8 80.7 No for tendering
Lot 2
14 Adura-Akobo and Adura-Burbe 1,165,860,248.87 3.0 16-Mar-09 121.6 152.1 131.6 64.6 66.3 No
1
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of February 2020
Reporting Period 29-Feb-20
Total
Time
contract 1.25 times Actual Aggregated Total
Revised Contract Time No. of Additional elapsed is
Mobilization period contract cumulative actual Average average
I. Contractor's Price Commencement Elapsed Expected Contracts expected beyond 5/4 Pass/ Non
Contract Name Period considered period progress to performance Expected expected
No. name (ETB) Date (Months) Progress under progress of the Performing
(months) for this (1.25* A) date (%) (%) progress progress
( C) consideration (%) contract
Evaluation (B) (G) (in %)
period
(A)
16 Efeson(Ataye)-MehalMeda 1,352,642,535.82 4.0 24-Apr-15 49.5 61.9 58.3 89.0 85.4 No
Omo-Maji Design and Build Road
17 772,077,818.33 3.0 20-Feb-17 40.5 50.6 36.3 62.5 42.8 No
Project Contract II:Sai-Maji
Yencomad 37.68 28.0 4 3 30.98 Pass
18 Melkasa-Sodere-Nuraera-Metehara 1,203,129,756.19 4.0 1-Jan-18 36.0 45.0 25.9 16.18 30.7 No
19 Adiarkay - Telmet 1,981,378,049.64 4.0 17-Jan-19 36.0 45.0 13.4 6.04 8.5 No
21 Degolo - Kelela 1,299,846,199.62 3.0 8-Apr-17 36.0 45.0 34.8 70.7 47.6 No
Sunshine 48.04 35.5 4 3 38.48 Pass
22 Debrebirhan - Ankober 1,083,570,868.24 6.0 23-Oct-18 24.0 30.0 16.2 30.8 27.7 No
25 Dima-Raad Bridge 865,811,042.92 6.0 16-Mar-15 58.1 72.6 59.5 97.8 55.0 No
30 Salayish-Omo 711,944,193.25 4.0 18-Jan-12 69.9 87.4 97.4 92.5 100.0 Yes
31 Debark- Buahit Road Project, Lot 1 699,465,650.00 4.0 4-Jul-11 72.8 91.0 104.0 85.6 100.0 Yes Not qualified
Akir 45.91 57.3 3.0 2.00 59.31
for tendering
Nekempt-Soge-Kamash-Koncho
32 1,327,447,854.94 4.0 17-Sep-18 40.8 51.0 17.4 - 11.9 No
Contract 3:km160-Koncho
2
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of February 2020
Reporting Period 29-Feb-20
Total
Time
contract 1.25 times Actual Aggregated Total
Revised Contract Time No. of Additional elapsed is
Mobilization period contract cumulative actual Average average
I. Contractor's Price Commencement Elapsed Expected Contracts expected beyond 5/4 Pass/ Non
Contract Name Period considered period progress to performance Expected expected
No. name (ETB) Date (Months) Progress under progress of the Performing
(months) for this (1.25* A) date (%) (%) progress progress
( C) consideration (%) contract
Evaluation (B) (G) (in %)
period
(A)
37 Fik-Hamero Lot I 819,129,220.55 3.00 2-May-17 36.0 45.0 34.0 70.4 46.1 No
Macro General
38 Adaba-Angetu 1,262,374,548.88 4.0 18-Nov-14 45.3 56.6 63.4 69.3 100.0 Yes Not qualified
Contractor and 38.07 43.2 3.0 2.00 45.19
for tendering
Trading
39 Warder - Kebridehar 1,814,123,577.90 4.0 10-Jun-19 48.0 60.0 8.7 1.7 2.3 No
41 Beles-Mekane Birhan Road Project 1,018,952,362.90 4.00 1-Nov-16 40.8 51.0 39.9 38.0 48.5 No
Taremaber-Meleya-Molale' Molale-
42 1,906,200,296.75 4.00 24-Dec-18 36.0 45.0 14.2 3.02 9.9 No
Sefemeda
Defence
43 Mekele-Dengolat-Samre-Finariwa Construction 1,594,387,610.14 3.00 1-Nov-16 41.9 52.4 39.9 52.9 46.8 No Not qualified
31.27 27.0 7.0 10.13 37.16
Enterprise for tendering
44 Adisheru-Dila -Samre (DCE) 2,114,048,067.84 4.00 9-May-19 36.0 45.0 9.7 3.16 4.3 No
Continuation of Ambo - Wolliso Road
45 1,264,907,396.11 3.00 26-Nov-19 30.0 37.5 3.1 - 0.1 No
Project
47 Debre Markos Town Road Upgrading Diriba Defersha 212,157,389.14 3.0 1-Jun-17 31.7 39.7 33.0 62.2 57.8 No
Not qualified
General 26.70 30.1 2.00 - 30.13
for tendering
Contractor
48 Kelela-Akesta 568,348,055.38 3.00 22-Jan-19 24.0 30.0 13.2 13.5 19.8 No
50 Sansusi -Tatek Kella 736,910,324.89 3.0 15-Nov-17 37.1 46.4 27.5 33.25 32.1 No
ASER
Construction 13.23 11.6 2.0 - 11.57 Pass
Construction Works of Asaita- Afambo – Plc
51 1,518,683,761.46 4.0 26-Aug-19 36.0 45.0 6.1 3.51 1.6 No
Djibouti Border Road Project
54 Babille-Fik Lot I 432,482,654.80 4.0 2-May-17 43.7 54.7 34.0 53.94 34.6 No
FAL 16.59 9.3 2.0 - 9.31 Pass
55 Debre Markos - Debre Elias 1,299,644,371.61 4.0 18-Sep-19 40.0 50.0 5.4 4.16 0.9 No
56 Babille-Fik Lot II 461,423,813.70 4.0 2-May-17 42.3 52.9 34.0 51.00 36.4 No
58 Babile-Fik Lot IV 461,624,969.90 4.0 30-May-17 37.4 46.7 33.0 75.47 42.0 No
Senan
59 Assosa-daleti Lot 1 Construction 228,630,902.66 3.0 7-Mar-17 36.0 45.0 35.8 55.75 55.75 49.6 49.6 1.0 - 49.62 No Pass
Plc
3
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of February 2020
Reporting Period 29-Feb-20
Total
Time
contract 1.25 times Actual Aggregated Total
Revised Contract Time No. of Additional elapsed is
Mobilization period contract cumulative actual Average average
I. Contractor's Price Commencement Elapsed Expected Contracts expected beyond 5/4 Pass/ Non
Contract Name Period considered period progress to performance Expected expected
No. name (ETB) Date (Months) Progress under progress of the Performing
(months) for this (1.25* A) date (%) (%) progress progress
( C) consideration (%) contract
Evaluation (B) (G) (in %)
period
(A)
63 Turmi -Omo 897,005,974.61 6.0 31-Aug-17 38.5 48.2 30.0 44.83 34.7 No
64 Azezo - Gonder Rama 871,565,791.41 2.0 14-Aug-18 27.6 34.4 18.5 25.40 27.4 No Not qualified
26.74 24.0 4.0 3.00 27.02
Robe -Gasera - Ginir (Contract 1: Robe - Construction for tendering
65 769,860,000.00 4.0 1-Nov-17 36.0 45.0 27.9 37.90 34.6 No
Gasera;
66 Bishoftu -Chefe Donsa-Sendafa 914,847,890.47 4.0 2-Sep-19 36.0 45.0 5.9 0.87 1.4 No
67 Turmi -Omo 897,005,974.61 6.0 31-Aug-17 38.5 48.2 30.0 44.83 34.7 No
71 Quyha -Maymekden 552,000,000.00 3.0 14-Jun-17 38.6 48.2 32.5 61.14 39.2 No
72 Maichew - Mehoni 378,614,038.16 3.0 29-Sep-17 35.6 44.5 29.0 56.94 37.3 No
73 Abomsa-Aseko-Dibu River Tekle Birhan 991,721,997.83 4.0 8-Nov-17 36.0 45.0 27.7 23.82 34.1 No
Ambaye Not qualified
74 Dibu River-Bedeyi-Cheleka 725,621,428.21 4.0 8-Nov-17 36.0 45.0 27.7 31.59 19.49 34.1 30.9 5.0 4.50 35.45 No
Construction for tendering
P.L.C
75 Robe-seru 993,181,495.37 4.0 18-Jan-19 36.0 45.0 13.4 2.25 8.4 No
Bishan Guracha (Tikur Wuha) -
76 589,395,779.03 4.0 9-Nov-17 26.9 33.7 27.7 2.29 55.6 No
Hawassa
Eshetu Lemma
Bole Junction - Weterdeno Horticulture Not qualified
78 Road 359,826,774.31 3.0 4-Oct-17 30.0 37.5 28.9 33.18 33.18 47.3 47.3 1.0 - 47.35 No
and Bole Abomsa for tendering
Contractor
79 Adiremet - Kulita -Adigoshu 953,000,000.00 4.0 26-Oct-17 36.0 45.0 28.1 48.60 34.9 No
Melcon
80 Rama-Chilla Construction 1,479,881,513.14 3.0 1-Apr-19 38.3 47.9 11.0 11.69 26.15 4.9 16.7 3.0 2.00 18.67 No Pass
Plc
81 Bahirdar – Tis Esat 767,050,000.00 No
82 Continuation of Werabe - Bojaber 795,000,000.00 4.0 1-Oct-19 36.0 45.0 5.0 5.62 0.7 No
83 Kunzila Horticulture Farm zebe Town Markan Trading 554,487,294.06 4.0 24-Jan-18 38.7 48.4 25.2 30.80 26.0 No
12.88 8.0 3.0 2.00 9.97 Pass
Plc
Jijiga-Gelesh- Deghamdo - Segege,Lot
84 768,698,951.11 4.0 22-Jul-19 36.0 45.0 7.3 7.46 2.5 No
4
Powercon Plc
in JV with
85 Ajire -Keraker Tesfaye 1,158,659,797.00 4.0 21-Sep-18 36.0 45.0 17.3 28.29 28.29 15.3 15.3 1.0 - 15.26 No Pass
Legesse
Construction
4
Engineering Procurement Directorate
Summary of Local Contractors' Performance Evaluation
Reporting Period End of February 2020
Reporting Period 29-Feb-20
Total
Time
contract 1.25 times Actual Aggregated Total
Revised Contract Time No. of Additional elapsed is
Mobilization period contract cumulative actual Average average
I. Contractor's Price Commencement Elapsed Expected Contracts expected beyond 5/4 Pass/ Non
Contract Name Period considered period progress to performance Expected expected
No. name (ETB) Date (Months) Progress under progress of the Performing
(months) for this (1.25* A) date (%) (%) progress progress
( C) consideration (%) contract
Evaluation (B) (G) (in %)
period
(A)
Cross Land
86 Oblo-Dermi 893,493,728.98 4.0 9-Oct-18 36.0 45.0 16.7 37.53 37.53 14.2 14.2 1.0 - 14.23 No Pass
Construction
Alemayehu
87 Edo-Serofta-Warqa 1,687,343,877.25 4.0 24-Jan-19 50.7 63.4 13.2 8.93 8.93 4.3 4.3 1.0 - 4.27 No Pass
Ketema GC
Zeluel
Yohannes GC in
Not qualified
89 Woldia Town Section Design and Build JV with Bokra 304,850,794.33 3.0 24-Feb-18 34.6 43.3 24.2 22.41 22.41 29.2 29.2 1.0 - 29.16 No
for tendering
Contruction and
Trading Plc
Samson
90 Dongoro-Kingi-Mekebilla 416,237,136.06 4.0 31-Jan-19 36.0 45.0 13.0 24.50 24.50 7.67 7.7 1.0 - 7.67 No Pass
Cherinet GC
1 2
Formula to be
Category of Contract Period Contractors who failed to complete projects after one fourth of the
used
contract period elapsed beyond the Contract period will be
First (1/3)rd 9(t1)
disqualified
Second(1/3)rd 9+29(t2)
last (1/3)rd 38+32(t3)
Beyond Contract period 70+30(t4)