Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 1

Tariffs and Subsidies in Zimbabwe’s Reforming Electricity


Industry: Steering a Utility through Turbulent Timesi

Engineer S.E. Mangwengwende


Chief Executive
Zimbabwe Electricity Supply Authority
P.O. Box 377, HARARE, Zimbabwe
Phone: 263-11607301, 2634-301690
Email: mangwe@ecoweb.co.zw

Abstract

In 1991, the Government of Zimbabwe adopted a public enterprise reform strategy


as part of a World Bank driven Economic Structural Adjustment Programme
(ESAP). For the electricity sector, the Government adopted a two-pronged
programme of reform – a performance improvement programme (PIP) for the
national utility, the Zimbabwe Electricity Supply Authority (ZESA), and a legal
and regulatory reform programme for the electricity sector in general. Ten years
later, significant success has been achieved in improving the utility’s performance
in technical operations and customer service. However, there has been very little
progress on the legal and regulatory front. This has adversely affected the utility’s
financial performance, as well as frustrating the Government’s efforts in attracting
private sector investment. The centrality of the tariff question reflects the
importance of the customer or end-user to the power sector reform process. This
article outlines the power sector reform experiences in Zimbabwe with special
focus on the tariff question. The paper suggests, from the perspective of a utility
executive, reasons for the mixed results at ZESA, and lessons for other countries in
the region undertaking similar reforms.

Keywords electricity tariffs, PSR, Zimbabwe

1. Brief Background on {Insert brief country profile:


Zimbabwe’s Electricity Zimbabwe}
Sector
Table 1 Power Stations in
The Zimbabwe Electricity Supply Zimbabwe
Authority (ZESA) provides the bulk
of electricity generated, transmitted, The five power stations are only
distributed and supplied in capable of meeting a maximum
Zimbabwe (see brief country profile). demand of 1,600 MW. Given
It is a statutory corporation Zimbabwe’s current maximum
established by an Act of Parliament – demand of around 2,034 MW
(the Electricity Act of 1985). A (ZESA, 1999), compared to the
Board of Directors, appointed by the limited internal generation capacity,
Minister in charge of energy, is the country has to rely on imports to
responsible for the management of satisfy its power requirements (Table
ZESA. 2).

Zimbabwe’s electricity sector Table 2 Zimbabwe’s Power


comprises of five power stations with Imports
a total installed capacity of 1,961
MW (Table 1) (Bhagavan (ed), 1999)
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 2

The 220kV interconnection with 2001 are Z$28 billion (US$510


Botswana is used more as an million) and Z$4.9 billion (US$89
emergency support line for that million), respectively. The debt
country, since Botswana is also collection performance since the
dependent on power imports to mid-1990’s has been fairly good,
satisfy demand. Between 150 and with receivables being 30 to 40 days
500 MW can be supplied from South revenue (ZESA, 1999). The level of
Africa, depending on the loading on profitability has, however, not been
the Cahora Bassa line (ZESA, 1996). sufficient for the organisation to
Zambia, which is interconnected at embark on major generation
330 kV at Kariba, also serves as the expansion projects.
interconnection for the Democratic
Republic of Zambia (DRC), which 1.2 Current Challenges
has a 220kV, 250MW
interconnection into the Zambian The current challenges facing ZESA
grid (ZESA, 1992). While the are the need to sustain and improve
interconnection with Zambia can financial profitability, to resolve
carry up to 700 MW, supply is chronic cash flow problems and to
currently limited to an average of 100 expand electrification, especially in
to 200 MW due to generation rural areas. The macro-economic and
constraints in Zambia (Table 2). regulatory regime is at present
unfavourable, with the former
In summary, the energy sent out from characterised by recurring fiscal
Zimbabwe’s five power stations is deficits - resulting in high inflation,
about 7,090 GWh, which represents unstable exchange rates, scarcity of
just over 65.61% of annual demand foreign currency and negative
of over 12,500 GWh. The balance of economic growth.
33.39% is supplied from imports
(ZESA, 1999). The present legal and regulatory
framework does not support
ZESA’s total annual energy sales are sustainable financial performance,
just under 11,000 GWh (10,779 because pricing and operational
GWh in 1999 and 10,685 GWh in decisions are susceptible to political
2000). This level of sales reflects influence. During the electricity price
total system losses of about 12.8% of controls of 1998 and 1999, the
energy sent out (ZESA, 1999). The organisation had net losses of Z$6.6
number of customers supplied is billion and Z$1.7 billion, respectively
nearly 500,000, and the level of (ZESA, 1998).
electrification is 40%. Eighty per
cent of the urban dwellers and below The Zimbabwean Cabinet recently
20% of the rural population have approved a White paper, which
access to electricity (Kayo, 2001; recommended that a new Electricity
AFREPREN, 2001). The major users Act be designed to establish an
of power are industrial and independent regulatory authority and
commercial operations (55%), facilitate the unbundling and
mining and agriculture (25%) and privatisation of ZESA. The challenge
households (20%) (Zesa, 2000). is to translate this approval into
actual legislation, followed by the
1.1 Financial Performance implementation of the necessary
institutional changes.
The total annual revenues and net
surplus for the year ending December
2000 were Z$20.437 billion (US$433 2. Initial Reforms after
million) and Z$3.038 billion (US$65 Independence
million), respectively (Kayo, 2001).
The corresponding non-audited
figures for the year ending December
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 3

At independence in 1980, Zimbabwe reduced the adverse impact of the


inherited a power sector comprising power shortages as electricity
six publicly owned utilities: demand eased.
• Central African Power
Corporation (CAPC), jointly By 1991, it became evident to the
owned by the Governments of Government, the consumers and the
Zimbabwe and Zambia, and general public that ZESA had not
responsible for generation and lived up to the initial expectations.
transmission of power to the While ZESA had succeeded in
two countries from the Kariba rationalising the tariff structure and
Hydroelectric Scheme. establishing a streamlined
• Electricity Supply management and planning process
Commission (ESC), which for the power sector, the earlier
was responsible for coal-fired envisaged economies of scale and
generation at Hwange and growth were not forthcoming. As
Munyati, (table 1) as well as economic growth started to pick up
the distribution of power in 1992/1993, power rationing had to
throughout Zimbabwe, outside be introduced - triggering the present
the four main cities. reform process.
• Four municipal electricity
undertakings owned by the A two-pronged strategy of reform
cities of Harare, Bulawayo, was adopted – a performance
Gweru and Mutare - improvement programme for ZESA
responsible for providing and a legal and regulatory framework
power to the cities and their for the electricity sector in general.
environs. This article confines itself to the PIP.

2.1 Formation of ZESA 2.3 ZESA’s Performance


Improvement Programme
An Electricity Act passed in 1985 led (PIP)
to the amalgamation of the five
Zimbabwean-owned utilities and the The Government and the Board of
Zimbabwean-based generation and ZESA initiated the performance
transmission facilities of the CAPC improvement programme (PIP) with
into the present-day Zimbabwe the appointment of a new Chief
Electricity Supply Authority (ZESA) Executive in December 1992, placing
(Government of Zimbabwe, 1986). the latter and all senior managers on
The amalgamation was to streamline a performance contract.
the administration of the electricity Concurrently, Electricité de France
sector through the Ministry (EDF) was engaged to work with the
responsible for energy, to achieve new management team to develop a
efficiencies through economies of programme to improve the
scale and to remove duplication of performance of the organisation in
functions among the utilities. the key areas of technical operations,
customer service, financial
2.2 Shortcomings of ZESA performance and human resources
management.
Within three years of its
establishment, ZESA was running at A two-year programme, covering the
a financial loss (ZESA, 1997). A fiscal years July 1993 to June 1994
brain drain of skilled staff ensued, and July 1994 to June 1995, was
resulting in the rural electrification developed and approved by the
programme virtually grinding to a Board and Government, with a
halt, power shortages and frequent ministerial directive to the Board to
system breakdowns. However, the implement and make regular reports
slow down in the economy, from the to the Minister on the PIP. The
late 80s to the beginning of the 90s, favourable results of the programme
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 4

were later used as the basis for The elimination of electricity


formulating a five-year corporate rationing and frequent load-shedding
business plan for the period July were undertaken to achieve customer
1995 to June 2000. satisfaction. This was achieved by
signing new import contracts with
The following eight strategic issues ZESCO of Zambia and SNEL of the
and objectives were initially used to Democratic Republic of the Congo,
define performance targets: building the 400 kV interconnections
to South Africa (1994/95) and to
(a) Quality Standards - focus on Cahora Bassa (1996/97) and
achieving world-class developing a customer charter to help
performance. frontline employees in customer
(b) Product Quality - focus on service (ZESA, 1996; AFREPREN,
elimination of supply problems 2001). Refurbishment and
(c) Service Quality - focus on reinforcement of the transmission
honouring promises to and distribution networks helped to
customers reduce the frequency and duration of
(d) Profitability - to consistently power outages.
achieve profit targets
(e) Growth - to achieve total 2.5 Liquidity and Profitability
electrification
(f) Corporate Image - to achieve Improving cash collection and
world class utility image seeking government approvals for
(g) Employee Satisfaction - to cost-reflective tariffs were the key
attract and retain skills strategies employed to maximise
(h) Autonomy - to empower the revenue. Receivables were reduced
individual and the utility from an average of 99 days in 1993
to about 30 days at present.
Later, the following six strategic
issues and objectives became the Cash flow and profitability, however,
basis of performance measurement at remained below target. Tariffs were
both corporate and individual level: only adjusted in response to an actual
financial crisis notwithstanding prior
(a) Customer Satisfaction - warnings. The legacy of belated tariff
customer-driven product and increases is reflected in the perennial
service quality liquidity problems, which ZESA has
(b) Liquidity and Profitability - faced over the years. Financial
focus on both cash and profit deficits were financed through short-
(c) Growth - focus on total term borrowings. When tariff
electrification increases were granted, profitability
(d) Employee Satisfaction - recovered almost overnight but took
attraction and retention of several months for the cash flows to
skills recover because of the heavy short-
(e) Corporate Image - responsible term debt service requirements.
corporate citizenship
(f) Innovation - striving to be With this ad hoc tariff setting
better, faster, cheaper always approach, getting approvals for
tariffs that reflect prospective
Appendix A provides a summary of investment costs proved impossible.
the key technical and financial results ZESA, therefore, failed to finance the
and performance indicators for major generation expansion
ZESA, over the period 1990/91 to programme that had been envisaged.
2000/01.
The payment of dividends was a
2.4 Customer Satisfaction premature and ill-advised action that
made it impossible for ZESA to
sustain profitability and growth.
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 5

Additionally, the power sector getting customer and Government


reform agenda was removed from support for tariff approvals.
Government priorities.
2.9 Innovation
2.6 Growth
Research and Development
The high rate of urban electrification programmes, business process re-
was underpinned by a marked engineering and the application of
increase in the number of new information technologies were the
customers - from 6,496 in 1993 to initiatives used to find better, faster
more than 25,000 a year by the late and cheaper ways of achieving all the
1990’s (ZESA, 1999). The revived above strategic objectives.
rural electrification programme was Computerisation facilitated
subsequently based on more improvements in billing and revenue
sustainable financing mechanisms - collection including financial
1% levy on customer bills and reporting management
schemes for mobilising community
contributions (Kayo, 2001). Whereas ZESA proactively assisted
the previous rural electrification Government with the drafting of the
programme serviced 80 rural centres, Electricity White Paper and the new
the levy and the community Electricity and Rural Electrification
contribution schemes assisted in Bills.
servicing over 400 rural centres
between 1997 and June 2001 (Dube,
2001). 3. Analysis of the Successes
and Failures of the PIP
2.7 Employee Satisfaction
The successes of the PIP and
The review of the remuneration of Corporate Business Plan relate to
the staff, including performance those issues, which were achievable
bonuses for meritorious within the legal and regulatory
achievements motivated them. The framework established by the
staff strength was reduced from Electricity Act of 1985. That Act had
10,500 to 7,955, with the actual not anticipated the radical reforms of
number of staff in service being the Economic Structural Adjustment
6,983 as at December 2000 (ZESA, Programme (ESAP) era involving the
1999). However, the failure to make unbundling and privatisation of the
progress on the legal and regulatory electricity industry.
front has begun to erode gains in
employee satisfaction, due to The ESAP reforms entailed a
increasing political interference on significant change in the oversight
issues affecting employees. role of Government. From owning,
managing and regulating the day-to-
2.8 Corporate Image day operations of the electricity
sector, the Government was expected
An open door policy for the media to focus only on overall energy
and the creation of customer advisory policy issues. ESAP represented a
committees helped to engender and significant departure from socialism -
maintain a positive image of ZESA the fundamental political ideology of
among the key stakeholders. Most of the ruling party.
the positive media stories on ZESA
were derived from a fortnightly In contrast, the existing electricity
newsletter that was established. legislation was designed along the
strong state control socialist
The major benefit of maintaining a ideology. The Electricity Act of 1985
positive corporate image was in established a board of directors with
very little power - implementing
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 6

ministerial directives. On corporate Period from mid-1995 to mid 1997:


governance, the Board in the The next Minister of Energy decided
Electricity Act of 1985 was another to maintain the management
layer of management, with the approach of his predecessor.
Minister being the de facto Board. However, he was reluctant to
increase prices in his first year, but
In practice, the performance of ZESA granted a 26% increase in 1996.
reflects the performance of the ZESA continued to prosper (Kayo,
Minister in charge. The financial 2001).
results and performance indicators in
Tables A3 and A4 of Appendix A Period from mid 1997 to early 2000:
correlate very well with the actions Soon after a new Minister was
of the Ministers who were in charge appointed, there was a series of
of energy. This is elaborated in the devaluations of the Zimbabwe dollar
next section: starting in November, 1997. The
Period up to mid-1992: The Minister effect of the devaluations was to
did not approve proposals to review reduce the tariff in US$ terms from
tariffs, because, for political reasons, 0.041 in October 1997 to 0.017 by
he wanted both the Board and the October 1998 (Kayo, 2001). There
then Chief Executive to resign. The were food riots as devaluation-
Minister, though a prominent induced price escalations took effect
businessman, was politically on essential commodities. The
outspoken as a staunch proponent of political climate was tense.
socialism and did not support the
ESAP price deregulation policies. Predictably, requests by ZESA for
After a cumulative increase in tariff reviews were not immediately
inflation of 98%, without tariff granted, until an inadequate 20%
reviews, he only allowed a 21.7% tariff adjustment was allowed in
increase in 1991 (ZESA, 1992). The October 1998. Consequently, ZESA
result of the Minister’s term of office had its largest ever-financial deficit
was a succession of years of financial of Z$6.6 billion for the year ending
losses for ZESA. He succeeded only December 1998 (ZESA, 1998).
in getting rid of the Board and Chief
Executive and in appointing his own A series of quarterly price
Board. He was subsequently adjustments of 15% were allowed
removed from the Cabinet. during the first three quarters of
1999. From October 1999, the
Period from mid-1992 to mid- 1995: quarterly adjustments were increased
A new Minister came in and adopted to 20%. In August 1999, the Minister
a more business-like approach. He allowed the introduction of an
did not change the Board, but automatic tariff adjustment formula
supported it in its management for non-domestic customers.
restructuring exercise and the Adjustments were to be made for
performance improvement movements in inflation, exchange
programme. During his tenure of rates and fuel prices. These measures
office, average electricity prices were resulted in a significant improvement
increased by 77.1% in 1992, 76.3% in financial performance for the year
in 1993 and 20% in 1994 (Appendix 1999 when a reduced deficit of Z$1.7
A3). The turnaround in performance billion was achieved. A timely tariff
of ZESA during this period is very review at the end of 1997 or early in
clear from the financial and 1998 would have avoided all the
operational results, starting with a losses.
surplus of Z$36.8 million for the year
ending June 30th1993 - reversing a The financial crisis had a positive
three-year trend of financial losses. effect in that the Minister was
persuaded to make progress in
drafting a White Paper for the reform
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 7

of the electricity sector. To the authority and, perhaps, a final


Minister, the attractive aspect of the solution to the tariff question in
reform proposals was the delegation Zimbabwe.
of the politically sensitive task of
tariff-setting to the proposed
regulatory authority. 4. The Tariff Question: The
Rhetoric and the Reality
Period early 2000 to present: There
have been three Ministers of Energy In 1986, the Government
in the short period between February commissioned consultants to
2000 and the beginning of 2002. The undertake a tariff policy-study. The
rapid turnover of Ministers has consultants recommended that the
disrupted progress of the long-run marginal cost (LRMC)
implementation of the Electricity principle be adopted. The long run
White Paper. ZESA is once again marginal cost required to support this
facing an uncertain financial future development programme has been
as tariff reviews are being deferred estimated at between 6 to 7 US
for political reasons. c/kWh, depending on the trade off
between import dependency and self-
While the first Minister allowed the sufficiency (AFREPREN, 2001).
tariff formula principle to be
extended to domestic customers in When the original LRMC
the first quarter in 2000, the next recommendation was made, the
Minister cancelled the scheduled average tariff in Zimbabwe was 2.47
20% quarterly increases for October US c/kWh. Adjusting tariffs to
and deferred the December 2000 LRMC level would have implied an
adjustment to January 2001. During increase of over 200%. The
2001, the only tariff adjustments Government was not prepared to
allowed were those due to implement the recommendation
movements in the tariff formula without a second opinion. Another
variables. The result was that revenue study was done in 1988 by different
for 2001, estimated at Z$28 billion, is consultants who reached essentially
12.5% less than the budgetary target the same conclusions as their
of Z$32 billion (ZESA, 1999). predecessors. While the Government
did not implement the
There is an unhealthy increase in recommendations, it did adopt the
staff turnover at the skilled and principle of LRMC as its official
managerial levels. During the first tariff policy.
quarter of 2001, political influence
resulted in the loss of the entire When ESAP was introduced in 1991,
executive management team, which the Ministry of Finance agreed with
had been responsible for the the World Bank on a phased
successful performance improvement programme of tariff adjustments with
programme. Soon afterwards, the the objective of attaining LRMC
Minister was replaced in a Cabinet levels by 1995/96. The target was
reshuffle. later moved to 2000 after several
revisions and updates to the System
A positive development is that the Development Plans. However, the
current Minister has now taken firm successive Ministers of Energy did
steps towards implementing the not implement the LRMC tariff
White Paper. Cabinet approval in programme.
September 2001 for the White Paper
has set in motion the legislative
process, which should be completed 5. Consequences of Failure
early in 2002. Hopefully, the new to Implement LRMC
Act would lead to the rapid Tariffs
establishment of a regulatory
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 8

The major casualty of the failure to Letter of Intent to YTL Corporation


raise tariffs to LRMC levels was the of Malaysia for the privatisation and
System Development Plan. Options expansion of the Hwange Power
for generation expansion for Station. The letter provided for the
Zimbabwe which were identified sale of the existing power plant to a
then, and which are still being joint venture between YTL (51%)
considered today, were the and ZESA (49%). The joint venture
following: was then expected to finance the
extension of the plant by two 300
• Extension of existing power MW units on a non-recourse project
stations: The options identified finance basis. The existing power
were an extra 300 MW at Kariba plant was valued at US$627 million,
costing an estimated US$200 while the expansion required US$550
million and an extra 600 MW at million (Clark and Mark, 2000;
Hwange costing an estimated Botbol, 2001).
US$660 million (Daniel, 2001;
Dube, 1998). In order for the joint venture to
• New power stations: The options undertake this level of investment
which have been studied and obtain a 20% return on
extensively were an 800 MW investment, it was estimated that the
hydroelectric scheme at Batoka average retail tariff would have to be
on the Zambezi estimated to cost immediately raised to 5 US c/kWh
US$1 100 million and a 1,400 and then to 6.2 US c/kWh by 2000.
MW coal-fired plant at Gokwe Compared to the average retail tariff
North estimated to cost US1,600 of 2.97 US c/kWh in 1996, the
million (Clark and Mark, 2000; proposed tariff increases were
Botbol, 2001). considered to be too high by the
Imports from the Southern African Government (Kayo, 2001).
Power Pool: Existing surplus power,
expected to last up to 2007, is YTL then came up with another
estimated at 1,100 MW, with 600 proposal to pay US$184 million for
MW coming from South Africa, 300 the existing plant, which was
MW from the DRC and 200 MW consistent with the existing tariffs.
from Zambia. After 2007, the amount The expansion project was to be
available for import would depend on deferred until the Government was
new power station developments in prepared to grant the necessary tariff
these and other neighbouring increases to LRMC levels. Having
countries. Hitherto, none of the gone public on the US$627 million
planned projects have taken off, with as being the fair value for the
the exception of interconnection existing plant, the Government could
projects for imports. Consequent to not accept the massive price discount
the high turnover of Ministers of to US$184 million. The negotiations
Energy, the link between LRMC were, therefore, called off in March
tariff levels and the financial 2000 without finalising an agreement
feasibility of new generation projects (Botbol, 2001).
became more and more blurred. This
was vividly demonstrated by the 5.2 Failed Gokwe North Project
failed attempts at privatising Hwange
Power station and getting private In April 1997, Government signed a
sector investment for Gokwe North Letter of Intent with National Power
project. and Rio Tinto of UK for the phased
development of a 1,400 MW coal-
5.1 Failed Hwange Privatisation fired power plant at Gokwe North.
and Expansion Project The expected cost of the
development was US$1,600 million
On September 15th 1996, the including finance charges. The
Government of Zimbabwe issued a viability of the project was
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 9

conditional on a commitment to transparent and predictable tariff-


achieve LRMC tariff levels by the setting process.
year of commissioning of the first
unit. Again the Government was 6.1 Automatic Tariff-Adjustment
unable to fulfil this commitment, Formula
with the project failing to procure
financial support. Negotiations were It is evident from the historical
also abandoned in early 2000 (Clark analysis of the Ministerial decisions
and Mark, 2000; Botbol, 2001). on tariffs that the tariff-setting
process was fundamentally flawed.
Notwithstanding the existence of a
6. Tariff Reform is an formal policy on tariff-setting, tariffs
Essential Pre-Requisite tended to be increased only in
for Privatisation response to actual financial crises. In
January 1999, ZESA decided to
The unmistakable conclusion from develop an automatic tariff-
these failed privatisation attempts adjustment formula, as a way of
was the need for tariff reforms to divorcing the tariff-setting process
precede any attempts at privatisation. from politics. The Electricity Act
It was, however, important to isolate empowered ZESA to have negotiated
the two key issues in tariff reform – tariffs for special customers whose
the tariff setting process and the tariff operations were incompatible with
level needed to support investment. the standard tariffs.

Setting the tariff level on the basis of One of the special tariff customers, a
reversing financial losses has not ferrochrome mining and smelting
been a difficult exercise as both the company, had a commodity-linked
customers and the Ministers have tariff formula, which had been
been able to appreciate the need for developed to assist the customer in
tariff adjustments under such weathering periods of reduced metal
circumstances. The problem is prices. In return, ZESA would
attributed to requests to adjust tariffs receive the benefit of increases in
to meet future expenditure. This is ferrochrome prices by charging more
the rationale for the LRMC, when the market recovered. The
theoretically the official tariff policy tariff was denominated in US dollars,
of the Government. the currency of the ferrochrome
markets. The devaluation of the
Asking for tariff levels to be adjusted Zimbabwe dollar at the end of 1997
to LRMC levels, in the absence of an and during 1998 led to a substantial
investment programme, failed to increase in revenue from this
solicit a sympathetic response from customer.
Ministers. With hindsight, this was
good because the experience with the An analysis of the customer base was
directive for dividend payments undertaken in order to investigate the
would have meant that the additional possibility of applying a similar tariff
revenue from LRMC tariff levels was to other customers. The customer
not likely to have been put aside for base of ZESA during the 1990s
development. By failing to adjust revealed the revenue and
tariffs when required to support the consumption statistics shown in
Hwange and Gokwe North Table 3.
investment projects, Zimbabwe lost
two golden opportunities of finally Table 3 ZESA Customer Base
resolving the tariff question. The next
section deals with Zimbabwe’s The statistics indicated that 88% of
experience and proposed plan to the total number of customers was
establish a politically neutral, domestic and yet consumed 20% of
total energy demanded, and
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 10

contributed 15% of total revenue. Monthly revenue jumped from


Their ability to influence ministerial Z$600 million to over Z$1 billion
decisions on tariffs was therefore out within the first two months of
of proportion to their commercial introducing the formula. By
significance to ZESA (Kayo, 2001; December 1999, ZESA reported a net
ZESA, 1992-99). deficit of Z$1.7 billion, a huge
improvement from the Z$6.6 billion
ZESA took the decision to classify deficit recorded a year earlier (ZESA,
all the non-domestic consumers as 1999).
special customers who would be
charged on a tariff formula basis. The incident-free and successful
Following the precedent with the application of the formula to non-
dozen or so customers who were domestic customers, as well as the
already on specially negotiated Minister’s support, inspired the
tariffs, the tariff formula was going development of another formula for
to be subject to agreement between domestic customers. It was decided
the customers and ZESA without the to use the Consumer Price Index as
need for formal approval by the the main variable because it would
Minister. lead to a more gradual adjustment in
prices than was the case with the
Meetings were held between ZESA formula for the non-domestic
and customer representatives using customers. The formula for the
the consumer advisory committees domestic customers was
set up as part of the PIP strategy of implemented from the first quarter of
enhancing the corporate image. The 2000. The financial performance for
committees were educated on the the year ending December 2000
cost structure of ZESA as well as the became one of the best for ZESA –
concept of the LRMC and its link to revenues exceeded Z$20 billion with
new investment. The customer net surplus being Z$3 billion (Kayo,
representatives, being business 2001; AFREPREN, 2001).
people, were able to appreciate the
fact that ZESA was able to control 6.2 Subsidies
only 10% of the cost variables, while
a massive 71% of the costs were While the tariff adjustment formulas
influenced by movements in the helped to raise the average tariff
exchange rate. Fuel costs and levels, it did not address the problem
domestic inflation accounted for 8% of untargeted subsidies, implicit in
and 11% respectively. the tariff structure. The LRMC study
recommendations advocated for the
Once the customer representatives removal of any cross subsidies in
were convinced on the soundness of order to achieve economic efficiency.
the tariff formula approach they, in In adopting the LRMC principle as
turn, went to educate their members the official tariff policy, the
with assistance from the staff of Government did not, however, adopt
ZESA’s regional offices. By mid- any explicit subsidy policy. The
1999 almost all the non-domestic policy emerged implicitly in
customers had been communicated Ministerial decisions on tariff
with and queries and suggestions adjustments.
from the customers had been dealt
with. It was decided to implement the Over the years, ZESA had been
tariff formula with effect from submitting requests for tariff
August 1st, 1999 after giving formal adjustments, which attempted to
written notice to each customer. match the tariff class to the cost of
supplying that class. On this basis,
The result of the formula was a the highest energy cost would have
dramatic improvement in the been charged to the domestic
financial performance of ZESA. category. The Ministers generally
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 11

rejected such proposals, preferring to


have the non-domestic customers to 7.1 Lifeline Tariffs
carry the higher unit charges in order
to keep electricity affordable to A study by ZESA on the use of
domestic customers. The large, electricity by the domestic category
generally agri-related or other showed that there are four different
industries deemed strategic, were sub-groups. The first is the very low-
also able to make direct appeals to income group that uses an average of
Government for concessionary 50 kWh per month principally for
tariffs. The implicit subsidy policy, lighting and power for radios.
which therefore developed resulted in Heating and cooking needs are met
the domestic and some large by using other fuels. The second, and
customers paying less than the cost the largest of the domestic groups,
of providing supply. The bulk of the uses an average of 300 kWh for
subsidies were provided by the lighting and power, as well as for
small- to medium-scale commercial, cooking using a one- or two-plate
mining and industrial customers. stove without an oven. The next
These categories included group uses an average of 1,000 kWh
supermarkets, which were always per month and has heavier heating
seen as being able to absorb large needs for three- to four-plate cookers
tariff increases by reason of their with ovens. This group also has
ability to immediately pass on the refrigerators and geysers. The fourth
costs to their customers. Table 4 on group with an average consumption
results from revenue and cost studies above 1,000 kWh is a mixed one
illustrates the extent of the cross comprising very high-income
subsidies. families (ZESA, 2000).
Table 4 Revenue to Cost To take account of these different
Analysis groups, the domestic-metered tariff
was made into a four-block tariff (see
Clearly, there is a mismatch between table 5). The tariff level for the first
the cost and revenues for the two blocks is based on an assessment
domestic and large agricultural and of ability to pay and comparison with
special customers. The adjustment of the cost of alternative fuels. Ability
tariff levels only served to exacerbate to pay is taken as a monthly bill,
the mismatch as can be seen from the which is about 5%, and not more
revenue to cost figures for the year than 10% of the take home pay.
2000, when compared to 1999.
The next two blocks have a tariff,
which is more than double the lower
7. Tariff Rationalisation blocks in order to remove the subsidy
benefit from the high-income groups.
There is a limit on the level of The last block has unit charges,
subsidy that can be carried by the which are higher than commercial
small- and medium-scale non- rates.
domestic categories. As the
automatic tariff adjustment formula Table 5 Domestic Tariff
began to create frequent upward Categories in
tariff increases, the customer groups Zimbabwe
carrying the subsidy burden started to
make representations for tariff 7.2 Special Agricultural Tariff
rationalisation. ZESA initiated the
process of tariff rationalisation by The process of consultation on the
restructuring the domestic tariff in tariff formula revealed that
order to protect the low-income agricultural customers on a two-part
groups but reducing the subsidy from energy and demand tariff who use
the high-income groups. electricity for irrigation were
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 12

disadvantaged during the rainy developing the Electricity White


season. The two-part tariff is Paper involved the setting up of a
designed to penalise customers with working group dedicated to tariff
high capacity installations, which are rationalisation and reform to work
poorly used. During the rainy season, together with two other groups - one
farmers sometimes have no need to on legislation and the other on
irrigate, except for few days in a ZESA’s unbundling and
month. The tariff would punish them privatisation. Consequently, the new
for such use, which is outside their draft legislation, which emerged
control. To mitigate this, an upper from the working groups, revolved
limit on charges was introduced for around financial and tariff issues.
this group of customers. This
requires the subsidised groups to The main focus of the new Electricity
provide the difference in revenue. Act is on the regulation of standards
of service and the prices charged for
7.3 Tariff Rationalisation those services. This is in sharp
Benefits contrast to the Act of 1985 whose
focus was on the establishment and
The customers have welcomed the management of ZESA. The adverse
modest tariff rationalisation that has impact of politics on the tariff-setting
been implemented. This has allowed process has influenced the elaborate
significant jumps in tariff levels to be measures provided in the legislation
made without adverse impact on to ensure the independence of the
revenue collection. Since the Regulatory Commission. To further
introduction of the tariff formula in minimise political influence in tariff-
Zimbabwe, average electricity prices setting, the commission itself will
have risen from 87 Zc/kWh (2.26 US comprise of professionals with
c/kWh) to 267 Zc/kWh (4.9 US stakeholder involvement.
c/kWh). Simultaneously, the average
amount of outstanding revenue has 8.1 Implementation Hurdles
remained within 30 to 40 days for all
tariff categories. Total system losses If implemented in accordance with
have risen by less than 1%, mostly the spirit of the new law, there is no
due to technical losses, as a result of doubt that the tariff question will be
the rapid growth in the rural finally resolved and the much needed
electrification network. new investment and growth in the
electricity sector will be achieved.

8. Implications of the Tariff One hurdle to overcome is the bad


Question for Power precedent, which has been set in
Sector Reform Zimbabwe’s Telecommunications
sector. The new Telecommunications
The Power Sector reform agenda in Regulatory Authority in Zimbabwe is
Zimbabwe has been profoundly a statutory body appointed and
influenced by experiences with the controlled by the responsible
tariff-setting and review process Minister. Experience in the
described above. electricity sector has shown that
performance becomes unpredictable
The Government’s main objectives when power is concentrated in the
for the power sector reforms are to hands of a single individual.
improve efficiency of service-
delivery, to expand electrification, Another hurdle to overcome is the
especially in the rural areas, and to macro-economic policy, which is not
relieve the Treasury of the burden of aligned with the fundamental free
financing electricity infrastructure. market ideology implicit in the
To emphasise the importance of the proposed power sector reform
tariff question, the process of programme.
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 13

At present the Government’s macro- Gokwe North to go ahead before the


economic policy is based on socialist regulatory and tariff questions had
principles of state ownership and been answered.
state control. These are principles,
which are no longer in favour with Important lessons which have been
the international financial and donor learnt in Zimbabwe that are useful
community. The domestic financial for other countries in the region
markets have no capacity to support embarking on Power Sector Reform
the major investments required by (PSR) can be summarised as follows:
the electricity sector. The (a) Begin with the electricity
Government will, therefore, sooner customer in mind: By linking
or later, need to realign its economic tariff increases with significant
policies with those of the performance improvements,
international capital markets. ZESA was able to generate a
lot of customer goodwill.
Power sector reforms must,
9. Conclusions and Lessons therefore, focus on providing
from the Zimbabwe quality service to the customer
Experience and the end-user. The positive
performance by ZESA in debt
Many countries in sub-Saharan collection and in restricting
Africa, as is the case worldwide, non-technical losses to a
have embarked on power sector minimum is an indicator of
reforms without adequate attention customer satisfaction.
being paid to the tariff question.
Even developed countries have made (b) Better use of local
elementary mistakes in this respect. management skills can achieve
Recently the State of California significant performance
experienced power blackouts and improvements at low cost:
utility bankruptcies because of Immediate improvements in
defective tariff policies. Retail tariffs customer service can be
were controlled, while freeing up achieved with modest changes
wholesale market prices. Not in management. Most of the
surprisingly, it did not take long performance improvements in
before utilities experienced massive ZESA were achieved by
financial losses because the making better use of existing
controlled retail tariffs could not management in both the utility
cover the costs of purchasing power and the Ministry.
on the wholesale market - where (c) Regulatory and Tariff Reform
prices were changing freely. The must precede privatisation:
utilities failed to purchase power and Whenever there is a significant
the State Government was forced to gap between electricity prices
intervene to avoid a total shutdown and investment cost, it is
of the system. imprudent to seek private
sector investment on a non-
In Zimbabwe, the power sector recourse project finance basis.
reform process is still ongoing. Existing assets will not be able
Progress has been constrained by the to fetch prices that reflect their
failure to establish a predictable and worth. Financial markets will
sustainable tariff-setting process. not consider new project
However, the slow progress and finance unless there is a
some failures have not been predictable and sustainable
completely without positive results. revenue stream sufficient to
Because the tariff is the only source cover the financing costs. Levy
of revenue for non-recourse project on customers’ bills and
finance, it would have been schemes for mobilising
disastrous for the Hwange and community contributions are
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 14

important for improving (f) End with the customer in


electrification services to the mind: Subsidies are necessary,
poor communities. because cost and ability to pay
are not always matched. It is
(d) It is far easier to set tariff important to analyse the
levels in response to sunk costs consumption patterns and
than in preparation for future incomes of consumers in order
costs: Marginal cost pricing to design a tariff structure,
may be economically efficient, which satisfies different
but it is a difficult concept to customer groups. A properly
implement. As soon as ZESA structured tariff will allow
started to record positive net cost-reflective tariffs to be
surpluses, and before the tariff charged without compromising
levels were sufficient to meet the utility’s ability to collect
future investment cash and to control losses.
requirements, the Government
decided to take 50% of the
surpluses as a cash dividend. 10. References
In addition, opportunities to
achieve long-run marginal cost Bhagavan (Ed) (1999): ‘Reforming
levels were missed with the the Power Sector in Africa’
failed privatisation projects at Zed Books Ltd, London,
Hwange and Gokwe North. United Kingdom
These were specific AFREPREN (2000): ‘Country
investment programmes, Reports: Energy Sector
which would have absorbed Reform Theme Group’
the additional revenues from AFREPREN General
long-run marginal cost prices, Assembly, 12th-16th November
thereby avoiding any 2000, Afrepren/FWD, Nairobi,
misallocation. Kenya
Karekezi, S Kimani, J Wangeci, J
(e) Power sector reform must be (Eds) (2001): Occasional Paper
compatible with No. 5: Power Sector Reform in
macroeconomic policy: Africa, Proceedings of a
Contemporary power sector Regional Policy Seminar,
reforms are founded in the free AFREPREN/FWD, Nairobi,
market ideology. Most of the Kenya
developing countries are Government of Zimbabwe (1996):
emerging from decades of ‘Electricity Act: Chapter 13:
socialist experiments. 05’ Revised Edition,
Focussing on tariff reform as a Government Printers Harare
priority helps to confront and Zimbabwe
deal with the ideological issues Government of Zimbabwe, (1999)
before going far with the Draft Electricity White Paper
power sector reforms. In Electricity Sector Reform in
Zimbabwe, socialist thinking Zimbabwe. Government of
influences the Government’s Zimbabwe, Harare, Zimbabwe.
macroeconomic policies. Government of Zimbabwe, (1985)
Before much progress can be Zimbabwe Electricity Act
achieved in power sector (1985) No.6. Government of
reforms, it is essential that the Zimbabwe, Harare, Zimbabwe.
Government resolve the tariff Kayo D. (2000): ‘Country Validation
question, which is in fact Data: Data and Statistics’
linked to macroeconomic (October 2000) (January 2001)
policy. AFREPREN/FWD, Nairobi,
Kenya
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 15

Kayo D. (2001): Journal Article ‘The Zimbabwe Electricity Supply


Power Sector in Zimbabwe: Authority [ZESA] (2000)
Increasing Electrification and Tariff Structure, ZESA, Harare
Strengthening Local
Participation’ First Draft, (1st
February 2001) Harare, 11. Selected Bibliography
Zimbabwe
Kayo, D., (2001). ‘Power Sector Botbol M. (1998-2001): African
Reform in Zimbabwe’ in Energy and Mining, Indigo
AFREPREN Occasional Paper Publications group, Paris,
No 10: Proceedings of a France
Regional Policy Seminar on Clark M. and Marks J (2000):
Power Sector Reforms in Africa, African Power Projects:
AFREPREN, Nairobi. Financial Times Energy,
Mangwengwende, S.E., (2000). Financial Times Business
‘Experiences in Power Sector Limited, London WIP 9LL
Reform in Zimbabwe’, in Central Statistical Office (1999):
AFREPREN Occasional Paper Quarterly Digest of Statistics,
No 5: Proceedings of a June 1999, Central Statistical
Regional Policy Seminar on Office, Harare, Zimbabwe
Power Sector Reforms in Daniel M. (2001): Global Private
Africa, AFREPREN, Nairobi. Power: Financial Times March
Zimbabwe Electricity Supply 2001, Financial Times Energy,
Authority [ZESA] (1992) London, United Kingdom
Annual Report. ZESA, Harare Dube I. (1998): Reform and
Zimbabwe Electricity Supply Restructuring of the Power
Authority [ZESA], (1993.) Sector: Privatization the Question
Annual Report. ZESA, Harare of Zimbabwe, Afrepren/FWD,
Zimbabwe Electricity Supply Nairobi, Kenya
Authority [ZESA)] (1994) Dube I. (2000): Country Validation
Annual Report. ZESA, Harare Data: Zimbabwe Statistics
Zimbabwe Electricity Supply Validation, October 2000 -
Authority [ZESA] (1995) January 2001, Afrepren/FWD,
‘Annual Report’. ZESA, Nairobi, Kenya
Harare EIU (1991-2000): Zimbabwe:
Zimbabwe Electricity Supply Country Profile: The
Authority [ZESA] (1996) Economist Intelligence Unit,
Annual Report. ZESA, Harare London SW1Y 4LR, United
Zimbabwe Electricity Supply Kingdom
Authority [ZESA] (1997) Zimbabwe Electricity Supply
Annual Report. ZESA, Harare Authority (ZESA), 1999. Load
Zimbabwe Electricity Supply Forecast, ZESA, Harare
Authority [ZESA] (1998) Zimbabwe Electricity Supply
Annual Report. ZESA, Harare Authority [ZESA] (2000)
Zimbabwe Electricity Supply Long Run Marginal Cost
Authority [ZESA] (1999) Study, ZESA, Harare
Annual Report. ZESA, Harare Zimbabwe Electricity Supply
Zimbabwe Electricity Supply Authority [ZESA] (2000)
Authority [ZESA] (1995) Project Appraisal Manual,
Corporate Business Plan: (June ZESA, Harare
1995) to (June 2000) Outlook Zimbabwe Electricity Supply
to (2015) ZESA, Harare, Authority [ZESA] (2000)
Zimbabwe Project Costing Guidelines,
Zimbabwe Electricity Supply ZESA, Harare
Authority [ZESA] (2000) Zimbabwe Electricity Supply
Tariff Review, ZESA, Harare Authority [ZESA] (2000)
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 16

Rural Electrification Report, Zimbabwe Electricity Supply


ZESA, Harare Authority [ZESA] (1992)
Zimbabwe Electricity Supply Survey on Domestic Energy
Authority (ZESA), 2000. Use, ZESA, Harare
Statistical Metering Data,
ZESA, Harare
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 17

Table 1 Power Stations in Zimbabwe

Station Name Plant Type Nameplate Capacity Available


(MW) Capacity (MW)
Kariba Hydro-electric 666 470
Hwange Coal-fired 920 800
Harare Coal-fired 135 60
Bulawayo Coal-fired 120 90
Munyati Coal-fired 120 60
Total 1 961 1 620
Source: ZESA, 1999
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 18

Table 2 Zimbabwe’s Power Imports

Country Interconnection Maximum Capacity Available Capacity


Voltage (kV) (MW) (MW)
Mozambique 400 500 500
South Africa 400 500 150 - 500
Zambia 330 700 100-200
D.R. Congo 220 (to Zambia) 250 150
Botswana 220 100 Nil

Source: ZESA, 1993, 1996 and 1999


Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 19

Table 3 ZESA Customer Base

Customer category Consumption (% of Revenue (% of Numbers (% of


total GWh) Total $) Tot)
Agriculture 10 15 2.3
Mining 15 15 0.2
Domestic 20 15 88.0
Industry 40 35 0.5
Commerce 15 20 9.0
Total 100 100 100

Source: ZESA 1999


Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 20

Table 4 Revenue to Cost Analysis

Cost
Tariff Category (% of Total) Revenue to Cost Ratio (%)

1999 2000
Domestic, Load LImited 27.9 51.0 76.2
Domestic, metered 6.2 34.9 56.2
Public Lighting 0.8 89.5 139.5
Low capacity, industrial and mining 1.4 145.9 226.2
Low capacity, commercial 8.8 144.4 222.4
Low capacity agricultural 9.5 107.1 125.4
High capacity, industrial and Mining 17.1 151.3 180.0
High capacity, commercial 3.6 194.1 216.8
High capacity, agricultural 3.9 92.5 97.7
Sub-transmission 12.6 90.9 103.3
Sub-transmission, special 8.1 42.3 54.7

Source: Kayo, 2000


Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 21

Table 5 Domestic Tariff Categories in Zimbabwe

Zimbabwe Dollars US Dollars


Fixed Charge 133.7 2.43
First 50 kWh 1.42 0.025
51-300 kWh 1.57 0.028
301 – 1,000 kWh 3.68 0.066
Above 1,000kWh 3.82 0.069

Source: ZESA, 2002


Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 22

Appendix A Zimbabwe Electricity Supply Authority

Performance statistics and indicators -1990/91 to 2000/01

A1. TECHNICAL PERFORMANCE

Year Maximum Energy Sent Energy Sold Electrification


Demand (MW) Out (GWh) (GWh) Access (%)
1990 1 572 9 694 8 852 <20
1991 1 608 10 068 8 992 20
1992 1 458 10 264 9 248 28
1993 1 546 8 682 7 731 29
1994 1 590 9 544 8 412 31
1995 1 617 10 123 9 022 32
1996 1 792 10 495 9 341 34
1997 1 885 11 311 10 088 35
1998 * 1 950 17 516 15 534 36
1999 2 034 12 363 10 779 39
2000 1 986 12 105 10 658 40

* Figures relate to 18 months ending December 31, the new financial year-end.
Prior figures are for 12 months periods ending June 30th.
Source: Kayo, 2001; ZESA, 1999
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 23

A2. TECHNICAL PERFORMANCE (continued)

Year Transmission Distribution Total Average Time Generation


Losses (%) Losses (%) System for New Plant
Losses Connections Availability
(%) (Days) * (%) **
1991 4.0 7.0 10.7 n/a n/a
1992 3.6 6.5 9.9 n/a n/a
1993 4.4 6.9 11.0 n/a n/a
1994 3.6 8.5 11.9 n/a n/a
1995 3.5 7.5 10.7 150 n/a
1996 2.8 8.2 10.8 53 75.3
1997 2.8 8.4 10.8 34 75.0
1998 2.7 8.0 11.3 30 70.2
1999 3.4 8.9 12.8 35 65.8
2000 4.2 9.8 13.3 23 72.5

Source: Kayo, 2001; ZESA, 1999

* Assumes infrastructure in place. The figures not available (n/a) are for periods when
this performance measure was not used.
** The declining availability figures are for periods of power station refurbishment
projects, made possible by interconnection projects, which provided replacement
power through imports.
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 24

A3. FINANCIAL PERFORMANCE


Year Total Average Exchange Total Average
Revenue Price Rate (Z$: Revenue Price (US
(Z$) (Zimbabwe US$) (US$) cents/kWh)
cents/kWh)
1990 525.2 5.68 2.268 231.0 2.64
1991 657.1 6.55 2.639 249.0 2.51
1992 989.1 11.60 5.051 195.8 1.81
1993 1 464.5 20.50 5.482 267.2 3.26
1994 2 139.6 24.61 8.540 250.5 2.88
1995 2 436.1 24.61 8.380 290.7 3.25
1996 3 050.4 31.01 9.400 324.5 2.97
1997 3 858.1 38.21 10.963 351.9 3.13
1998 8 253.3 53.1 37.851 218.0 1.33
1999 9 756.8 90.5 38.519 253.3 2.26
2000 20 437.1 191.7 47.230 432.7 3.85
2001 28 075.7 267.3 55.000 510.0 4.90
(estimates)

Source: Kayo, 2001; ZESA, 1999

• Figures for 1998 are for 18 months period ending December 31st, the new financial
year end. Prior figures are for financial years ending June 30th.
• Long run marginal cost (LRMC) target is 6 – 7 US c/kWh has never been achieved
despite official policy.
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 25

FINANCIAL PERFORMANCE (continued)

Year Net Net Self Debt Debtors Current


Surplus Surplus Financing Service (Days) ratio
(Z$) (US$) Ratio (% Coverage
Capex.) Ratio
Target Target 1.5 Target 45 Target
40% 1.5 -2.0
1991 (63.5) (24.1) (102) 0.76 74 0.98
1992 (73.1) (14.5) (28) 1.29 85 1.09
1993 36.8 6.7 27 1.30 99 1.38
1994 84.9 9.9 31 0.88 61 1.80
1995 83.6 10.0 47 1.00 50 1.30
1996 94.4 10.0 38 1.30 56 1.10
1997 104.8 9.6 38 1.36 37 0.89
1998 (6 587.8) (174.1) n/a 1.55 32 0.99
1999 (1 697.8) (44.1) n/a 1.06 32 0.58
2000 3 080.1 65.2 n/a 1.89 33 0.58
2001 4 916.3 89.4 n/a n/a n/a n/a

• Note the missed current ratio target, which indicates the perennial liquidity
problem as a result of the reactive approach to tariff reviews. Profitability responds
much faster to tariff increases than cash flow.
• Figures for 2001 are estimates.

Source: Kayo, 2001; ZESA, 1999


Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 26

Brief Country Profile: Zimbabwe

Zimbabwe

Zimbabwe: Selected Indicators

• Population (million): 12.1 (2000)


• Area (km2): 391,000
• Capital City: Harare
• GDP Growth Rate (%): -6.1 (2000)
• GNP per Capita (US$): 688 (2000)
• Official Exchange Rate: Z$ 55.5 = 1 US$ (Feb, 2002)
• Parallel Market Exchange Rate: Z$ 300 = 1 US$ (Feb, 2002)
• Economic Activities: Agriculture, mining, manufacturing,
commerce, forestry
• Energy Sources: Coal, imported petroleum, solar, biomass, hydro
• Installed Capacity (MW): 1961 (2001)
• Electricity Consumption per Capita (kWh): 874 (2000)
• Electricity Generation (GWh): 12,105 (2000)

Sources: Business in Africa (2001); AFREPREN (2001); World Bank (2000);


World Bank (2001); OECD/IEA (2001); Time Inc. (2002); ZESA (2001); EIU
(2001
Tariffs and subsidies in Zimbabwe’s reforming electricity industry / Energy Policy 27

Endnotes

i
The views expressed herein are those of the author and are not necessarily the

same as the official position of the Government of Zimbabwe or o f the Zimbabwe

Electricity Supply Authority

You might also like