Sea View Villa Project: DLF Cont. Pvt. LMTD
Sea View Villa Project: DLF Cont. Pvt. LMTD
Sea View Villa Project: DLF Cont. Pvt. LMTD
SAV20 Identify the constraints 4d 0d 100% 19-Dec-19 A 26-Dec-19 Identify the constraints
A
SAV110 Roof construction 13d 13d 0% 07-May-20 21-May-20 -58d Roof construction
SAV160 Curtain wall system 15d 15d 0% 25-Jun-20 12-Jul-20 -58d Curtain wall system
SAV180 Fire doors 14d 14d 0% 01-Aug-20 16-Aug-20 302d Fire doors
SAV190 Vents and areaways 4d 4d 0% 01-Aug-20 04-Aug-20 -58d Vents and areaways
SAV220 Roof access 13d 13d 0% 03-Sep-20 17-Sep-20 -58d Roof access
SAV240 Public lobby 14d 14d 0% 12-Oct-20 27-Oct-20 -58d Public lobby
SAV250 exit corridors 14d 14d 0% 28-Oct-20 12-Nov-20 -58d exit corridors
SAV270 Mechanical and Electrical 14d 14d 0% 22-Nov-20 07-Dec-20 -58d Mechanical and Electrical equipment rooms
equipment rooms
SAV300 Arrange a space for 14d 14d 0% 20-Dec-20 04-Jan-21 -58d Arrange a space for system cabin
system cabin
SAV320 Emergency egresstairs 14d 14d 0% 11-Jan-21 26-Jan-21 31d Emergency egresstairs
SAV370 main elevator lobby 7d 7d 0% 04-Mar-21 11-Mar-21 31d main elevator lobby
SAV380 Upper floor elevator lobby 5d 5d 0% 13-Mar-21 17-Mar-21 31d Upper floor elevator lobby
SAV390 Public corridors 14d 14d 0% 18-Mar-21 03-Apr-21 31d Public corridors
SAV430 Electrical closet 14d 14d 0% 21-Apr-21 06-May-21 31d Electrical closet
SAV460 Main elevator lobby 5d 5d 0% 19-May-21 24-May-21 31d Main elevator lobby
SAV470 Upper floor elevator lobby 5d 5d 0% 25-May-21 30-May-21 31d Upper floor elevator lobby
SAV550 Main elevatory lobby 7d 7d 0% 19-Jan-21 26-Jan-21 -58d Main elevatory lobby
SAV560 upper floor elevatory lobby 5d 5d 0% 27-Jan-21 01-Feb-21 -56d upper floor elevatory lobby
SAV600 General storage room 7d 7d 0% 16-Feb-21 23-Feb-21 -58d General storage room
SAV610 Electrical closet 14d 14d 0% 16-Feb-21 03-Mar-21 -47d Electrical closet
SAV650 STORM DRAINAGE AND 5d 5d 0% 10-Mar-21 15-Mar-21 -47d STORM DRAINAGE AND SEWERAGE SYSTEMS
SEWERAGE SYSTEMS
SAV660 DOMESTIC COLD WATER 5d 5d 0% 23-Mar-21 28-Mar-21 -58d DOMESTIC COLD WATER SYSTEM
SYSTEM
SAV670 DOMESTIC HOT WATER 5d 5d 0% 16-Mar-21 21-Mar-21 -47d DOMESTIC HOT WATER SYSTEM
SYSTEM
SAV750 AIR HANDLING UNITS 3d 3d 0% 06-May-21 09-May-21 -58d AIR HANDLING UNITS
SAV780 FIRE ALARM SYSTEM 5d 5d 0% 19-May-21 24-May-21 -58d FIRE ALARM SYSTEM
SAV840 MAIN ELEVATOR LOBBY 5d 5d 0% 23-Jun-21 28-Jun-21 -35d MAIN ELEVATOR LOBBY
SAV850 UPPER FLOOR 5d 5d 0% 23-Jun-21 28-Jun-21 -58d UPPER FLOOR ELEVATOR LOBBY
ELEVATOR LOBBY