DLF Cont. Pvt. Lmtd.


SEA VIEW VILLA PROJECT
Activity ID Activity Name Planned Duration Remaining Schedule % Start Finish Total Float Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Duration Complete
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
567d 482d 0% 19-Dec-19 A 10-Oct-21 -58d 10-Oct-21, Town house
Town house
87d 5d 0% 19-Dec-19 A 04-Apr-20 -58d 04-Apr-20, Approval
Approval
SAV10 start of prjec 0d 0d 0% 30-Mar-20 -58d start of prjec, 30-Mar-20

SAV20 Identify the constraints 4d 0d 100% 19-Dec-19 A 26-Dec-19 Identify the constraints
A

SAV30 Prepare documents 5d 0d 100% 19-Dec-19 A 29-Dec-19 Prepare documents


A

SAV40 Get approval 5d 5d 100% 26-Dec-19 A 04-Apr-20 -58d Get approval

SAV50 Prepare budget 0d 0d 100% 05-Jan-20 A 07-Jan-20 Prepare budget


A

25d 0d 0% 14-Jan-20 A 15-Mar-20 A 15-Mar-20 A, Foundation


Foundation
35d 25d 0% 16-Mar-20 A 25-Apr-20 -58d 25-Apr-20, Substrucrure envelop
Substrucrure envelop
33d 33d 0% 26-Apr-20 02-Jun-20 -58d 02-Jun-20, Shell superstructure
Shell superstructure
SAV100 Floor construction 10d 10d 0% 26-Apr-20 06-May-20 -58d Floor construction

SAV110 Roof construction 13d 13d 0% 07-May-20 21-May-20 -58d Roof construction

SAV120 Elevators 10d 10d 0% 23-May-20 02-Jun-20 -58d Elevators

17d 17d 0% 23-May-20 10-Jun-20 -58d 10-Jun-20, Shell exterior enclosure


Shell exterior enclosure
SAV130 Exterior wall 8d 8d 0% 23-May-20 31-May-20 -49d Exterior wall

SAV140 Corner 7d 7d 0% 03-Jun-20 10-Jun-20 -58d Corner

27d 27d 0% 11-Jun-20 12-Jul-20 -58d 12-Jul-20, Exterior glazing


Exterior glazing
SAV150 Fenestration 12d 12d 0% 11-Jun-20 24-Jun-20 -58d Fenestration

SAV160 Curtain wall system 15d 15d 0% 25-Jun-20 12-Jul-20 -58d Curtain wall system

30d 30d 0% 13-Jul-20 16-Aug-20 302d 16-Aug-20, Exterior door


Exterior door
SAV170 Entrance vestiblue 16d 16d 0% 13-Jul-20 30-Jul-20 -58d Entrance vestiblue

SAV180 Fire doors 14d 14d 0% 01-Aug-20 16-Aug-20 302d Fire doors

SAV190 Vents and areaways 4d 4d 0% 01-Aug-20 04-Aug-20 -58d Vents and areaways

38d 38d 0% 05-Aug-20 17-Sep-20 -58d 17-Sep-20, Shell enclosure roof


Shell enclosure roof
SAV200 Roof covering 15d 15d 0% 05-Aug-20 22-Aug-20 -58d Roof covering

SAV210 Insulation 10d 10d 0% 23-Aug-20 02-Sep-20 -58d Insulation

SAV220 Roof access 13d 13d 0% 03-Sep-20 17-Sep-20 -58d Roof access

112d 112d 0% 19-Sep-20 26-Jan-21 31d 26-Jan-21, Interior construction


Interior construction
SAV230 Entrance vestibule 20d 20d 0% 19-Sep-20 11-Oct-20 -58d Entrance vestibule

SAV240 Public lobby 14d 14d 0% 12-Oct-20 27-Oct-20 -58d Public lobby

SAV250 exit corridors 14d 14d 0% 28-Oct-20 12-Nov-20 -58d exit corridors

SAV260 Security office 7d 7d 0% 14-Nov-20 21-Nov-20 -58d Security office

SAV270 Mechanical and Electrical 14d 14d 0% 22-Nov-20 07-Dec-20 -58d Mechanical and Electrical equipment rooms
equipment rooms

SAV280 Janitor closet 5d 5d 0% 08-Dec-20 13-Dec-20 -58d Janitor closet

SAV290 Ventilation 5d 5d 0% 14-Dec-20 19-Dec-20 -58d Ventilation

SAV300 Arrange a space for 14d 14d 0% 20-Dec-20 04-Jan-21 -58d Arrange a space for system cabin
system cabin

SAV310 Electrical closets 5d 5d 0% 05-Jan-21 10-Jan-21 -58d Electrical closets

SAV320 Emergency egresstairs 14d 14d 0% 11-Jan-21 26-Jan-21 31d Emergency egresstairs

Actual Level of Effort


Primary Baseline
Milestone
summary
Page 1 of 4
Date Revision Checked Approved
Actual Work
Remaining Work 23-Oct-20 R00 Rahul Rahul
Critical Remaining Work
   
   
   

DLF Cont. Pvt. Lmtd.


SEA VIEW VILLA PROJECT
Activity ID Activity Name Planned Duration Remaining Schedule % Start Finish Total Float Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Duration Complete
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
24d 24d 0% 27-Jan-21 23-Feb-21 31d 23-Feb-21, Specialities
Specialities
SAV330 Building directory 14d 14d 0% 27-Jan-21 11-Feb-21 31d Building directory

SAV340 Floor identification 5d 5d 0% 13-Feb-21 17-Feb-21 31d Floor identification

SAV350 Room identification 5d 5d 0% 18-Feb-21 23-Feb-21 31d Room identification

62d 62d 0% 24-Feb-21 06-May-21 31d 06-May-21, interior finishes


interior finishes
SAV360 Main lobby 7d 7d 0% 24-Feb-21 03-Mar-21 31d Main lobby

SAV370 main elevator lobby 7d 7d 0% 04-Mar-21 11-Mar-21 31d main elevator lobby

SAV380 Upper floor elevator lobby 5d 5d 0% 13-Mar-21 17-Mar-21 31d Upper floor elevator lobby

SAV390 Public corridors 14d 14d 0% 18-Mar-21 03-Apr-21 31d Public corridors

SAV400 Security office 5d 5d 0% 04-Apr-21 08-Apr-21 31d Security office

SAV410 Building maintenance 5d 5d 0% 10-Apr-21 14-Apr-21 31d Building maintenance

SAV420 General storage 5d 5d 0% 15-Apr-21 20-Apr-21 31d General storage

SAV430 Electrical closet 14d 14d 0% 21-Apr-21 06-May-21 31d Electrical closet

45d 45d 0% 08-May-21 28-Jun-21 31d 28-Jun-21, Floors


Floors
SAV440 Entrance vestiblue 5d 5d 0% 08-May-21 12-May-21 31d Entrance vestiblue

SAV450 Main lobby 5d 5d 0% 13-May-21 18-May-21 31d Main lobby

SAV460 Main elevator lobby 5d 5d 0% 19-May-21 24-May-21 31d Main elevator lobby

SAV470 Upper floor elevator lobby 5d 5d 0% 25-May-21 30-May-21 31d Upper floor elevator lobby

SAV480 Public corridors 5d 5d 0% 31-May-21 05-Jun-21 31d Public corridors

SAV490 security office 5d 5d 0% 06-Jun-21 10-Jun-21 31d security office

SAV500 Building maintenance 5d 5d 0% 12-Jun-21 16-Jun-21 31d Building maintenance

SAV510 General storage 5d 5d 0% 17-Jun-21 22-Jun-21 31d General storage

SAV520 Electrical closets 5d 5d 0% 23-Jun-21 28-Jun-21 31d Electrical closets

45d 45d 0% 11-Jan-21 03-Mar-21 -47d 03-Mar-21, Ceiling


Ceiling
SAV530 Entrance vestiblue 7d 7d 0% 11-Jan-21 18-Jan-21 -58d Entrance vestiblue

SAV540 Main lobby 7d 7d 0% 19-Jan-21 26-Jan-21 -56d Main lobby

SAV550 Main elevatory lobby 7d 7d 0% 19-Jan-21 26-Jan-21 -58d Main elevatory lobby

SAV560 upper floor elevatory lobby 5d 5d 0% 27-Jan-21 01-Feb-21 -56d upper floor elevatory lobby

SAV570 Public corridors 7d 7d 0% 27-Jan-21 03-Feb-21 -58d Public corridors

SAV580 security office 5d 5d 0% 04-Feb-21 09-Feb-21 -58d security office

SAV590 Building maintenance 5d 5d 0% 10-Feb-21 15-Feb-21 -58d Building maintenance office


office

SAV600 General storage room 7d 7d 0% 16-Feb-21 23-Feb-21 -58d General storage room

SAV610 Electrical closet 14d 14d 0% 16-Feb-21 03-Mar-21 -47d Electrical closet

18d 18d 0% 24-Feb-21 16-Mar-21 -53d 16-Mar-21, Elevators


Elevators
SAV620 PUBLIC ELEVATORS 18d 18d 0% 24-Feb-21 16-Mar-21 -58d PUBLIC ELEVATORS

SAV630 SERVICE ELEVATORS 5d 5d 0% 04-Mar-21 09-Mar-21 -47d SERVICE ELEVATORS

26d 26d 0% 10-Mar-21 08-Apr-21 -58d 08-Apr-21, Plumbing


Plumbing
Actual Level of Effort
Primary Baseline
Milestone
summary
Page 2 of 4
Date Revision Checked Approved
Actual Work
Remaining Work 23-Oct-20 R00 Rahul Rahul
Critical Remaining Work
   
   
   

DLF Cont. Pvt. Lmtd.


SEA VIEW VILLA PROJECT
Activity ID Activity Name Planned Duration Remaining Schedule % Start Finish Total Float Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Duration Complete
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SAV640 DOMESTIC WATER 5d 5d 0% 17-Mar-21 22-Mar-21 -58d DOMESTIC WATER SUPPLY
SUPPLY

SAV650 STORM DRAINAGE AND 5d 5d 0% 10-Mar-21 15-Mar-21 -47d STORM DRAINAGE AND SEWERAGE SYSTEMS
SEWERAGE SYSTEMS

SAV660 DOMESTIC COLD WATER 5d 5d 0% 23-Mar-21 28-Mar-21 -58d DOMESTIC COLD WATER SYSTEM
SYSTEM

SAV670 DOMESTIC HOT WATER 5d 5d 0% 16-Mar-21 21-Mar-21 -47d DOMESTIC HOT WATER SYSTEM
SYSTEM

SAV680 SANITARY DRAINAGE 5d 5d 0% 29-Mar-21 03-Apr-21 -58d SANITARY DRAINAGE SYSTEMS


SYSTEMS

SAV690 DRINKING FOUNTAINS 5d 5d 0% 04-Apr-21 08-Apr-21 -58d DRINKING FOUNTAINS

20d 20d 0% 10-Apr-21 02-May-21 -58d 02-May-21, HVAC


HVAC
SAV700 DESIGN CONDITIONS 5d 5d 0% 10-Apr-21 14-Apr-21 -58d DESIGN CONDITIONS AND LOADS
AND LOADS

SAV710 ENERGY SUPPLY 5d 5d 0% 15-Apr-21 20-Apr-21 -58d ENERGY SUPPLY

SAV720 HEAT GENERATING 5d 5d 0% 21-Apr-21 26-Apr-21 -58d HEAT GENERATING SYSTEM


SYSTEM

SAV730 COOLING GENERATING 5d 5d 0% 27-Apr-21 02-May-21 -58d COOLING GENERATING SYSTEMS


SYSTEMS

9d 9d 0% 03-May-21 12-May-21 -58d 12-May-21, Air distribution system


Air distribution system
SAV740 VARIABLE AIR VOLUME 3d 3d 0% 03-May-21 05-May-21 -58d VARIABLE AIR VOLUME

SAV750 AIR HANDLING UNITS 3d 3d 0% 06-May-21 09-May-21 -58d AIR HANDLING UNITS

SAV760 EXHAUST AIR 3d 3d 0% 10-May-21 12-May-21 -58d EXHAUST AIR

10d 10d 0% 13-May-21 24-May-21 -58d 24-May-21, Fire protection system


Fire protection system
SAV770 FIRE SUPPRESSION 5d 5d 0% 13-May-21 18-May-21 -58d FIRE SUPPRESSION

SAV780 FIRE ALARM SYSTEM 5d 5d 0% 19-May-21 24-May-21 -58d FIRE ALARM SYSTEM

45d 45d 0% 25-May-21 15-Jul-21 -35d 15-Jul-21, Electrical


Electrical
SAV790 ELECTRICAL SERVICE 5d 5d 0% 25-May-21 30-May-21 -58d ELECTRICAL SERVICE

SAV800 GENERATOR UNIT 5d 5d 0% 31-May-21 05-Jun-21 -58d GENERATOR UNIT

SAV810 LIGHTING 5d 5d 0% 06-Jun-21 10-Jun-21 -58d LIGHTING

SAV820 ENTRANCE VESTIBULE 5d 5d 0% 12-Jun-21 16-Jun-21 -58d ENTRANCE VESTIBULE

SAV830 MAIN LOBBY 5d 5d 0% 17-Jun-21 22-Jun-21 -58d MAIN LOBBY

SAV840 MAIN ELEVATOR LOBBY 5d 5d 0% 23-Jun-21 28-Jun-21 -35d MAIN ELEVATOR LOBBY

SAV850 UPPER FLOOR 5d 5d 0% 23-Jun-21 28-Jun-21 -58d UPPER FLOOR ELEVATOR LOBBY
ELEVATOR LOBBY

SAV860 PUBLIC CORRIDORS 5d 5d 0% 29-Jun-21 04-Jul-21 -35d PUBLIC CORRIDORS

SAV870 SECURITY OFFICE 5d 5d 0% 29-Jun-21 04-Jul-21 -58d SECURITY OFFICE

SAV880 BUILDING MAINTENANCE 5d 5d 0% 05-Jul-21 10-Jul-21 -35d BUILDING MAINTENANCE OFFICE


OFFICE

SAV890 GENERAL STORAGE 5d 5d 0% 05-Jul-21 10-Jul-21 -58d GENERAL STORAGE ROOM


ROOM

SAV900 ELECTRICAL CLOSETS 5d 5d 0% 11-Jul-21 15-Jul-21 -35d ELECTRICAL CLOSETS

31d 31d 0% 11-Jul-21 15-Aug-21 -58d 15-Aug-21, FURNISHINGS


FURNISHINGS
SAV910 PUBLIC LOBBY 12d 12d 0% 11-Jul-21 24-Jul-21 -58d PUBLIC LOBBY

SAV920 CURTAINS 3d 3d 0% 17-Jul-21 19-Jul-21 -35d CURTAINS

SAV930 WINDOWS 19d 19d 0% 25-Jul-21 15-Aug-21 -58d WINDOWS

48d 48d 0% 16-Aug-21 10-Oct-21 -58d 10-Oct-21, BUILDING S


BUILDING SITE WORK
SAV940 WALKWAYS AND 24d 24d 0% 16-Aug-21 12-Sep-21 -58d WALKWAYS AND PLAZAS
PLAZAS

Actual Level of Effort


Primary Baseline
Milestone
summary
Page 3 of 4
Date Revision Checked Approved
Actual Work
Remaining Work 23-Oct-20 R00 Rahul Rahul
Critical Remaining Work
   
   
   

DLF Cont. Pvt. Lmtd.


SEA VIEW VILLA PROJECT
Activity ID Activity Name Planned Duration Remaining Schedule % Start Finish Total Float Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021
Duration Complete
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
SAV950 FOUNTAINS 14d 14d 0% 13-Sep-21 28-Sep-21 -58d FOUNTAINS

SAV960 VEGETATION 5d 5d 0% 29-Sep-21 04-Oct-21 -58d VEGETATION

SAV970 SITE LIGHTING 5d 5d 0% 05-Oct-21 10-Oct-21 -58d SITE LIGHTING

SAV980 FINISH THE PROJECT 0d 0d 0% 10-Oct-21 -58d FINISH THE PROJECT

Actual Level of Effort


Primary Baseline
Milestone
summary
Page 4 of 4
Date Revision Checked Approved
Actual Work
Remaining Work 23-Oct-20 R00 Rahul Rahul
Critical Remaining Work